Inconel shielding, exhaust lagging blankets and associated parts
Solicitation number
70Z08026S17001B00
Issued by

About this file

This is a CLIN (Contract Line Item Number) and Pricing List for exhaust insulation blankets, lagging systems, and associated Inconel shielding components for 87-foot patrol boat (87 WPB) vessels operated by the U.S. Coast Guard. The document establishes pricing for five ordering periods, with identical line items and quantities recurring across each period. All items are sourced from Advanced Thermal Products, Inc. (ATP) under a sole-source procurement arrangement.

The contract encompasses 13 CLINs per ordering period, including exhaust insulation blanket kits, complete exhaust lagging systems, and modular exhaust components (MDE and SSDG configurations) for both port and starboard sides of the vessels. Estimated annual quantities range from 1 to 6 units per CLIN, with delivery required within 90 days of receiving each delivery order. Unit of issue designations include KT (kit), EA (each), and SE (set). The document does not provide specific unit pricing or total estimated annual amounts, indicating these fields remain to be completed. This pricing list supports the Coast Guard's requirement to maintain and replace critical thermal management systems across its 87 WPB fleet over the five-year contract period.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Order PR 1

SUPPLIES/SERVICES FOR:
1st Ordering Period
CLINNSNPART NUMBERDESCRIPTIONEST. ANNUAL QTYU/IDELIVERY SCHEDULE
10012990-01-674-51031117CG87-MW11EXHAUST INSULATION BLANKET PORT006KT90 Days after Receipt of Delivery Order
10022990-01-674-91881117CG87-MW12INSULATION SET EXHAUST STBD004KT90 Days after Receipt of Delivery Order
10032990-01-F11-2236114CG87-KIT87WPB COMPLETE EXHAUST LAGGING005KT90 Days after Receipt of Delivery Order
10042990-01-F11-2230114CG87-MW1MDE STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
10052990-01-660-4276114CG87-MW10EXHAUST INSULATIONBLANKET PORT001SE90 Days after Receipt of Delivery Order
10062990-01-F11-2231114CG87-MW2MDE PORT SIDE EXHAUST INCONEL001EA90 Days after Receipt of Delivery Order
10072990-01-F11-2232114CG87-MW3MDE STSBD SIDE TURBO EXHAUST I001EA90 Days after Receipt of Delivery Order
10082990-01-F11-2233114CG87-MW4MDE PORT SIDE TURBO EXHAUST IN001EA90 Days after Receipt of Delivery Order
10092990-01-F11-2234114CG87-MW5MDE STBD SIDE EXHAUST SECONDARY004EA90 Days after Receipt of Delivery Order
10102990-01-F11-2235114CG87-MW6MDE PORT SIDE EXHAUST SECONDARY005EA90 Days after Receipt of Delivery Order
10112990-01-F11-2228114CG87-MW7SSDG STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
10122990-01-F11-2229114CG87-MW8SSDG PORT SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
10132990-01-660-4272114CG87-MW9EXHAUST INSULATIONBLANKET STBD001SE90 Days after Receipt of Delivery Order

Total Estimated Annual Amount

Order PR 2

SUPPLIES/SERVICES FOR:
2nd Ordering Period
CLINNSNPART NUMBERDESCRIPTIONEST. ANNUAL QTYU/IDELIVERY SCHEDULE
20012990-01-674-51031117CG87-MW11EXHAUST INSULATION BLANKET PORT006KT90 Days after Receipt of Delivery Order
20022990-01-674-91881117CG87-MW12INSULATION SET EXHAUST STBD004KT90 Days after Receipt of Delivery Order
20032990-01-F11-2236114CG87-KIT87WPB COMPLETE EXHAUST LAGGING005KT90 Days after Receipt of Delivery Order
20042990-01-F11-2230114CG87-MW1MDE STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
20052990-01-660-4276114CG87-MW10EXHAUST INSULATIONBLANKET PORT001SE90 Days after Receipt of Delivery Order
20062990-01-F11-2231114CG87-MW2MDE PORT SIDE EXHAUST INCONEL001EA90 Days after Receipt of Delivery Order
20072990-01-F11-2232114CG87-MW3MDE STSBD SIDE TURBO EXHAUST I001EA90 Days after Receipt of Delivery Order
20082990-01-F11-2233114CG87-MW4MDE PORT SIDE TURBO EXHAUST IN001EA90 Days after Receipt of Delivery Order
20092990-01-F11-2234114CG87-MW5MDE STBD SIDE EXHAUST SECONDARY004EA90 Days after Receipt of Delivery Order
20102990-01-F11-2235114CG87-MW6MDE PORT SIDE EXHAUST SECONDARY005EA90 Days after Receipt of Delivery Order
20112990-01-F11-2228114CG87-MW7SSDG STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
20122990-01-F11-2229114CG87-MW8SSDG PORT SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
20132990-01-660-4272114CG87-MW9EXHAUST INSULATIONBLANKET STBD001SE90 Days after Receipt of Delivery Order

Total Estimated Annual Amount

Order PR 3

SUPPLIES/SERVICES FOR:
3rd Ordering Period
CLINNSNPART NUMBERDESCRIPTIONEST. ANNUAL QTYU/IDELIVERY SCHEDULE
30012990-01-674-51031117CG87-MW11EXHAUST INSULATION BLANKET PORT006KT90 Days after Receipt of Delivery Order
30022990-01-674-91881117CG87-MW12INSULATION SET EXHAUST STBD004KT90 Days after Receipt of Delivery Order
30032990-01-F11-2236114CG87-KIT87WPB COMPLETE EXHAUST LAGGING005KT90 Days after Receipt of Delivery Order
30042990-01-F11-2230114CG87-MW1MDE STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
30052990-01-660-4276114CG87-MW10EXHAUST INSULATIONBLANKET PORT001SE90 Days after Receipt of Delivery Order
30062990-01-F11-2231114CG87-MW2MDE PORT SIDE EXHAUST INCONEL001EA90 Days after Receipt of Delivery Order
30072990-01-F11-2232114CG87-MW3MDE STSBD SIDE TURBO EXHAUST I001EA90 Days after Receipt of Delivery Order
30082990-01-F11-2233114CG87-MW4MDE PORT SIDE TURBO EXHAUST IN001EA90 Days after Receipt of Delivery Order
30092990-01-F11-2234114CG87-MW5MDE STBD SIDE EXHAUST SECONDARY004EA90 Days after Receipt of Delivery Order
30102990-01-F11-2235114CG87-MW6MDE PORT SIDE EXHAUST SECONDARY005EA90 Days after Receipt of Delivery Order
30112990-01-F11-2228114CG87-MW7SSDG STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
30122990-01-F11-2229114CG87-MW8SSDG PORT SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
30132990-01-660-4272114CG87-MW9EXHAUST INSULATIONBLANKET STBD001SE90 Days after Receipt of Delivery Order

Total Estimated Annual Amount

Order PR 4

SUPPLIES/SERVICES FOR:
4th Ordering Period
CLINNSNPART NUMBERDESCRIPTIONEST. ANNUAL QTYU/IDELIVERY SCHEDULE
40012990-01-674-51031117CG87-MW11EXHAUST INSULATION BLANKET PORT006KT90 Days after Receipt of Delivery Order
40022990-01-674-91881117CG87-MW12INSULATION SET EXHAUST STBD004KT90 Days after Receipt of Delivery Order
40032990-01-F11-2236114CG87-KIT87WPB COMPLETE EXHAUST LAGGING005KT90 Days after Receipt of Delivery Order
40042990-01-F11-2230114CG87-MW1MDE STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
40052990-01-660-4276114CG87-MW10EXHAUST INSULATIONBLANKET PORT001SE90 Days after Receipt of Delivery Order
40062990-01-F11-2231114CG87-MW2MDE PORT SIDE EXHAUST INCONEL001EA90 Days after Receipt of Delivery Order
40072990-01-F11-2232114CG87-MW3MDE STSBD SIDE TURBO EXHAUST I001EA90 Days after Receipt of Delivery Order
40082990-01-F11-2233114CG87-MW4MDE PORT SIDE TURBO EXHAUST IN001EA90 Days after Receipt of Delivery Order
40092990-01-F11-2234114CG87-MW5MDE STBD SIDE EXHAUST SECONDARY004EA90 Days after Receipt of Delivery Order
40102990-01-F11-2235114CG87-MW6MDE PORT SIDE EXHAUST SECONDARY005EA90 Days after Receipt of Delivery Order
40112990-01-F11-2228114CG87-MW7SSDG STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
40122990-01-F11-2229114CG87-MW8SSDG PORT SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
40132990-01-660-4272114CG87-MW9EXHAUST INSULATIONBLANKET STBD001SE90 Days after Receipt of Delivery Order

Total Estimated Annual Amount

Order PR 5

SUPPLIES/SERVICES FOR:
5th Ordering Period
CLINNSNPART NUMBERDESCRIPTIONEST. ANNUAL QTYU/IDELIVERY SCHEDULE
50012990-01-674-51031117CG87-MW11EXHAUST INSULATION BLANKET PORT006KT90 Days after Receipt of Delivery Order
50022990-01-674-91881117CG87-MW12INSULATION SET EXHAUST STBD004KT90 Days after Receipt of Delivery Order
50032990-01-F11-2236114CG87-KIT87WPB COMPLETE EXHAUST LAGGING005KT90 Days after Receipt of Delivery Order
50042990-01-F11-2230114CG87-MW1MDE STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
50052990-01-660-4276114CG87-MW10EXHAUST INSULATIONBLANKET PORT001SE90 Days after Receipt of Delivery Order
50062990-01-F11-2231114CG87-MW2MDE PORT SIDE EXHAUST INCONEL001EA90 Days after Receipt of Delivery Order
50072990-01-F11-2232114CG87-MW3MDE STSBD SIDE TURBO EXHAUST I001EA90 Days after Receipt of Delivery Order
50082990-01-F11-2233114CG87-MW4MDE PORT SIDE TURBO EXHAUST IN001EA90 Days after Receipt of Delivery Order
50092990-01-F11-2234114CG87-MW5MDE STBD SIDE EXHAUST SECONDARY004EA90 Days after Receipt of Delivery Order
50102990-01-F11-2235114CG87-MW6MDE PORT SIDE EXHAUST SECONDARY005EA90 Days after Receipt of Delivery Order
50112990-01-F11-2228114CG87-MW7SSDG STBD SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
50122990-01-F11-2229114CG87-MW8SSDG PORT SIDE EXHAUST LAGGING002EA90 Days after Receipt of Delivery Order
50132990-01-660-4272114CG87-MW9EXHAUST INSULATIONBLANKET STBD001SE90 Days after Receipt of Delivery Order

Total Estimated Annual Amount