CLC Rec and Dining Combined Specs.pdf
PDF 5 MB Posted
- Solicitation number
- 36C24226B0049
About this file
This is a specification document for the renovation of the CLC (Community Living Center) Recreation and Dining Area at James J. Peters VA Medical Center in Bronx, New York (Project #526-14-115). The project comprises 100% construction documents and includes three primary bid items: General Construction, Electrical Work, and Mechanical Work.
The scope encompasses complete demolition and renovation of Building 106's recreation and dining facilities across four phased construction stages (Phase I through IV), with work including structural modifications, mechanical and HVAC systems, plumbing and sanitary installations, electrical and telecommunications systems, fire protection systems, and interior finishes such as flooring, ceiling, wall coverings, and painting. The facility must remain operational 24/7 during construction, requiring the contractor to develop a detailed phasing plan with interim life safety measures, coordinate work to minimize disruption to medical center operations, maintain existing utility services, and implement comprehensive infection control and dust containment procedures. Key administrative requirements include submission of an Accident Prevention Plan 15 calendar days before the preconstruction conference, Activity Hazard Analyses for each work phase, designation of a Site Safety and Health Officer and Competent Persons, OSHA 30-hour training certification for safety personnel, photographic documentation with interactive digital indexing throughout construction, as-built drawings in electronic format, maintenance and operating manuals for all equipment, and formal operator training by factory-trained representatives. The contractor must also obtain security clearance, comply with VA security protocols including badge requirements and key control procedures, provide construction and safety signage, and maintain performance documentation including testing, commissioning plans, and final elevation photographs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S02 Buy American Certificate blank.pdf | ||
| WAGE RATES_NY_BRONX_5.26.2026.pdf | ||
| 526-14-115_ALL SHEETS.pdf | ||
| S02 852.219-75 Limitation on Subcontracting Jan 2023- Blank.docx | DOCX document | |
| 013200 Construction Documentation.docx | DOCX document | |
| 36C24226B0049_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
SPECIFICATIONS
For “Renovate CLC Recreation and Dining Area”
Project Number 526-14-115
100% Construction Documents
For
James J. Peters VA Medical Center
At
Bronx, NY
James J. Peters VAMC
Renovate CLC Recreation and Dining
Area, Building 106
#526-14-115
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
00 01 10 Table of Contents
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 06-15
01 33 23 Shop Drawings, Product Data, and Samples 07-15
01 35 26 Safety Requirements 10-14
01 42 19 Reference Standards 07-15
01 45 29 Testing Laboratory Services 06-15
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 02-15
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 10-12
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 09-11
04 05 16 Masonry Grouting 09-11
04 20 00 Unit Masonry 02-15
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-12
05 21 00 Steel Joist Framing 03-10
05 31 00 Steel Decking 10-12
05 50 00 Metal Fabrications 07-14
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 05-15
06 16 63 Cementitious Sheathing 05-12
06 20 00 Finish Carpentry 06-13
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 06-12
07 22 00 Roof and Deck Insulation 10-10
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 05-15
07 60 00 Flashing and Sheet Metal 07-14
07 81 00 Applied Fireproofing 05-15
07 84 00 Firestopping 05-15
07 92 00 Joint Sealants 05-15
07 95 13 Expansion Joint Cover Assemblies 05-15
DIVISION 08 - OPENINGS
Renovate CLC Recreation and Dining
00 01 10-2
08 11 13 Hollow Metal Doors and Frames 01-13
08 14 00 Interior Wood Doors 09-15
08 41 13 Aluminum-Framed Entrances and Storefronts 05-15
08 42 29 Sliding Automatic Entrances
08 71 00 Door Hardware 02-15
08 71 13 Automatic Door Operators
08 80 00 Glazing 09-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 22 16 Non-Structural Metal Framing 10-14
09 29 00 Gypsum Board 11-14
09 30 13 Ceramic/Porcelain Tiling 09-15
09 51 00 Acoustical Ceilings 12-13
09 65 13 Resilient Base and Accessories 10-11
09 65 19 Resilient Tile Flooring 05-15
09 68 00 Carpeting 10-15
09 72 16 Vinyl-Coated Fabric Wall Covering 10-15
09 91 00 Painting 10-15
DIVISION 10 – SPECIALTIES
10 11 23 Tackboards 05-15
10 21 13 Toilet Compartments 09-15
10 26 00 Wall and Door Protection 09-15
10 28 00 Toilet, Bath, and Laundry Accessories 09-15
10 44 13 Fire Extinguisher Cabinets 08-14
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 09-15
12 32 00 Manufactured Wood Casework 09-15
12 36 00 Countertops 09-15
DIVISION 21- FIRE SUPPRESSION
21 05 11 Common Work Results for Fire Suppression 11-09
21 13 13 Wet-Pipe Sprinkler Systems 05-08
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-14
22 05 23 General-Duty Valves for Plumbing Piping 07-14
22 07 11 Plumbing Insulation 05-11
22 11 00 Facility Water Distribution 01-14
22 13 00 Facility Sanitary and Vent Piping 07-14
22 40 00 Plumbing Fixtures 01-14
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-15
23 05 12 General Motor Requirements for HVAC Equipment 11-10
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
02-15
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 07 11 HVAC Insulation 02-15
Renovate CLC Recreation and Dining
00 01 10-3
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 09-12
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 02-15
23 36 00 Air Terminal Units 02-15
23 37 00 Air Outlets and Inlets 02-15
23 82 16 Air Coils 04-11
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 12-12
26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13
26 05 26 Grounding and Bonding for Electrical Systems 12-12
26 05 33 Raceway and Boxes for Electrical Systems 05-14
26 09 23 Lighting Controls 05-14
26 24 16 Panelboards 05-14
26 27 26 Wiring Devices 08-14
26 29 11 Motor Controllers 08-14
26 29 21 Enclosed Switches and Circuit Breakers 12-12
26 43 13 Surge Protective Device 12-12
26 51 00 Interior Lighting 08-14
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 11-09
27 05 33 Raceways and Boxes for Communications Systems 12-05
27 10 00 Structured Cabling 12-05
27 41 31 Master Antenna Television Equipment and Systems 06-13
27 51 16 Public Address and Mass Notification Systems 06-13
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 13 53 Security Access Detection 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 05-13
32 14 16 Brick Unit Paving 04-10
James J. Peters VAMC Renovate CLC Recreation and Dining Area
Bronx, NY Project #526-14-115
07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI001 COVER SHEET
GI002 ABBREVIATIONS AND SYMBOLS
GI101 FIRST FLOOR LIFE SAFETY PLAN
GI102 FIRST FLOOR INFECTION AND DUST CONTROL PLAN
GI103 FIRST PHASING PLAN
CIVIL
CS101 CIVIL SITE PLAN AND DETAILS
STRUCTURAL
S001 STRUCTURAL GENERAL NOTES
S002 STRUCTURAL GENERAL DETAILS
S101 STRUCTURAL FOUNDATION AND FRAMING PLAN
S201 STRUCTURAL DETAILS
ARCHITECTURAL
AD101 FIRST FLOOR DEMOLITION PLAN
AD102 FIRST FLOOR DEMOLITION REFLECTED CEILING PLAN
AD501 DEMOLITION EXTERIOR ELEVATION
AD601 DEMOLITION EXTERIOR WALL SECTIONS
AE101 FIRST FLOOR PLAN
AE102 FIRST FLOOR REFLECTED CEILING PLAN
AE103 ROOF PLAN
AE301 FIRST FLOOR EQUIPMENT PLAN
AE501 EXTERIOR ELEVATIONS
AE502 INTERIOR ELEVATIONS
AE503 INTERIOR ELEVATIONS
AE601 EXTERIOR WALL SECTIONS
AE701 PARTITION SCHEDULES
AE702 DOOR AND WINDOW TYPES, DETAILS AND SCHEDULE
AE801 DETAILS AND SECTIONS
INTERIORS
AI101 FIRST FLOOR FINISH FLOOR PLAN
AI601 FINISH FLOOR SCHEDULE AND LEGEND
FIRE ALARM
FA001 FIRE ALARM LEGEND, GENERAL NOTES, AND ABBREVIATIONS
FA101 FIRE ALARM PLAN - FIRST FLOOR
FA102 FIRE ALARM PLAN - FIRST FLOOR
FIRE PROTECTION
FX101 FIRE PROTECTION PLAN - FIRST FLOOR
07-01-15
00 01 15 - 2
MECHANICAL
M-001 MECHANICAL ABBREVIATIONS, SYMBOLS, AND GENERAL NOTES
MD101 MECHANICAL HVAC AND PIPING DEMOLITION PLAN - FIRST FLOOR
MD102 MECHANICAL HVAC AND PIPING DEMOLITION PLAN - FIRST FLOOR
MD103 MECHANICAL HVAC AND PIPING DEMOLITION PLAN - SECOND FLOOR
MD104 MECHANICAL HVAC AND PIPING DEMOLITION PLAN - PENTHOUSE
MH101 MECHANICAL HVAC PLAN - FIRST FLOOR
MH102 MECHANICAL HVAC PLAN - FIRST FLOOR
MH103 MECHANICAL HVAC PLAN - SECOND FLOOR
MH104 MECHANICAL HVAC PLAN - PENTHOUSE
MH301 MECHANICAL HVAC SECTION
MH501 MECHANICAL HVAC DETAILS
MH601 MECHANICAL HVAC SCHEDULES
MP101 MECHANICAL PIPING PLAN - FIRST FLOOR
MP102 MECHANICAL PIPING PLAN - FIRST FLOOR
PLUMBING
P-001 PLUMBING ABBREVIATIONS, SYMBOLS, AND GENERAL NOTES
PD101 PLUMBING AND SANITARY/VENT DEMOLITION PLAN - FIRST FLOOR
PD102 PLUMBING AND SANITARY/VENT DEMOLITION PLAN - FIRST FLOOR
PP101 PLUMBING PLAN - FIRST FLOOR
PP102 PLUMBING PLAN - FIRST FLOOR
PP501 PLUMBING DETAILS AND SCHEDULES
PS101 SANITARY/VENT PLAN - FIRST FLOOR
PS102 SANITARY/VENT PLAN - FIRST FLOOR
ELECTRICAL
E-001 ELECTRICAL ABBREVIATIONS, SYMBOLS, AND GENERAL NOTES
E-501 ELECTRICAL DETAILS
E-901 ELECTRICAL PHOTOGRAPHS
ED101 ELECTRICAL DEMOLITION PLAN - FIRST FLOOR
ED102 ELECTRICAL DEMOLITION PLAN - FIRST FLOOR
EL101 ELECTRICAL LIGHTING PLAN - FIRST FLOOR
EL102 ELECTRICAL LIGHTING PLAN - FIRST FLOOR
EL501 ELECTRICAL LIGHTING DETAILS
EL502 LIGHTING SCHEDULES
EP101 ELECTRICAL POWER PLAN - FIRST FLOOR
EP102 ELECTRICAL POWER PLAN - FIRST FLOOR
EP601 ELECTRICAL PANEL SCHEDULES
EM101 ELECTRICAL EQUIPMENT PLAN - FIRST FLOOR
EM102 ELECTRICAL EQUIPMENT PLAN - FIRST FLOOR
EM601 ELECTRICAL EQUIPMENT SCHEDULES
ET101 ELECTRICAL TELECOMMUNICATIONS PLAN - FIRST FLOOR
ET102 ELECTRICAL TELECOMMUNICATIONS PLAN - FIRST FLOOR
ET501 ELECTRICAL TELECOMMUNICATIONS DETAILS
EY101 ELECTRICAL SYSTEMS PLAN - FIRST FLOOR
EY102 ELECTRICAL SYSTEMS PLAN - FIRST FLOOR
--END-
06-01-15 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 USE OF ROADWAYS
1.16 CONTRACTING OFFICER’S REPRESENTATIVE'S FIELD OFFICE
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.18 TEMPORARY USE OF EXISTING ELEVATORS
1.19 TEMPORARY USE OF NEW ELEVATORS
1.20 TEMPORARY TOILETS
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
1.22 NEW TELEPHONE EQUIPMENT
1.23 TESTS
1.24 INSTRUCTIONS
1.25 GOVERNMENT-FURNISHED PROPERTY
1.26 RELOCATED ITEMS
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.28 CONSTRUCTION SIGN
1.29 SAFETY SIGN
1.30 PHOTOGRAPHIC DOCUMENTATION
1.31 FINAL ELEVATION DIGITAL IMAGES
06-01-15
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the Project No. 526-14-115, Renovate CLC Recreation and Dining Area, James J. Peters VAMC, Bronx, NY as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
COR
C. Offices of Paradigm Engineers and Constructors, Louisville, KY as
Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the Contracting Officer’s Representative (COR) in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the Contracting Officer’s Representative
(COR).
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, drainage, necessary removal of existing structures and construction and certain other items.
ITEM II, Electrical Work: Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project as required by the drawings and specifications.
06-01-15
01 00 00 -2
ITEM III, Mechanical Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project as required by the drawings and specifications.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense,
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Guards:
1. The General Contractor will not be required to provide guards during the construction.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
06-01-15
01 00 00 -3
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours
06-01-15
01 00 00 -4 before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the Contracting Officer’s Representative (COR).
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not
06-01-15
01 00 00 -5 permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by Contracting Officer’s Representative (COR).
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To insure such executions, Contractor shall furnish the Contracting
Officer’s Representative (COR) with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the Contracting Officer’s Representative (COR) two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to the Medical Center Director, Contracting Officer’s Representative (COR) and Contractor, as follows:
Phase I: General demolition and construction of the existing Sun Room as prescribed on sheet GI103 (First Floor Phasing Plan) of the
Construction Documents.
Phase II: General demolition and construction of the existing Men and
Women Restrooms as prescribed on sheet GI103 (First Floor
Phasing Plan) of the Construction Documents.
06-01-15
01 00 00 -6
Phase III: General demolition and construction of the existing CLC Room as prescribed on sheet GI103 (First Floor Phasing Plan) of the
Construction Documents.
Phase IV: General construction of the existing CLC Room as prescribed on sheet GI103 (First Floor Phasing Plan) of the Construction
Documents.
H. Building No.106 will be occupied during performance of work; but immediate areas of alterations will be vacated.
1. Certain areas of Building No. 106 will be occupied by Medical Center personnel for various periods as listed below:
AREA PERIOD
(First Floor) 0 a.m. to 0 p.m.
(Second Floor) 0 a.m. to 0 p.m.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by Contracting
Officer’s Representative (COR).
06-01-15
01 00 00 -7
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Contracting Officer’s
Representative (COR).
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of Contracting Officer’s
Representative (COR). Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval.
Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS
INSTALLATIONS for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
Contracting Officer’s Representative (COR) in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least
06-01-15
01 00 00 -8 inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the Contracting Officer’s Representative
(COR).
5. In case of a contract construction emergency, service will be interrupted on approval of Contracting Officer’s Representative
(COR). Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the
Contracting Officer’s Representative (COR).
N. Coordinate the work for this contract with other construction operations as directed by Contracting Officer’s Representative (COR).
This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
06-01-15
01 00 00 -9
1.7 ALTERATIONS (NOT USED)
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by Contracting Officer’s Representative (COR).
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract
06-01-15
01 00 00 -10 or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
Contracting Officer’s Representative (COR). Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Contracting Officer’s Representative (COR) before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA (NOT USED)
1.12 PROFESSIONAL SURVEYING SERVICES (NOT USED)
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
06-01-15
01 00 00 -11
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, that are reasonably necessary to properly assure that location, orientation, and elevations established for are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the Contracting Officer’s Representative (COR) before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.
Furnish such certification to the Contracting Officer’s Representative
(COR) before any major items of concrete work are placed. In addition, 06-01-15
01 00 00 -12 the Contractor shall also furnish to the Contracting Officer’s
Representative (COR) certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to Contracting
Officer’s Representative (COR).
F. Upon completion of the work, the Contractor shall furnish the
Contracting Officer’s Representative, (COR)one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the Contracting Officer’s Representative's (COR) review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the Contracting
Officer’s Representative (COR) within 15 calendar days after each completed phase and after the acceptance of the project by the
Contracting Officer’s Representative (COR).
D. Paragraphs A, B, & C shall also apply to all shop drawings.
06-01-15
01 00 00 -13
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the Contracting Officer’s
Representative (COR) such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.16 CONTRACTING OFFICER’S REPRESENTATIVE'S FIELD OFFICE (NOT USED)
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by Contracting
Officer’s Representative (COR) in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the Contracting Officer’s Representative
(COR) will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again
06-01-15
01 00 00 -14 immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.18 TEMPORARY USE OF EXISTING ELEVATORS (NOT USED)
1.19 TEMPORARY USE OF NEW ELEVATORS (NOT USED)
1.20 TEMPORARY TOILETS
A. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by the Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to
06-01-15
01 00 00 -15 the Government. The Contractor shall carefully conserve any utilities furnished without charge.
1.22 NEW TELEPHONE EQUIPMENT
The contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA.
1.23 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental
06-01-15
01 00 00 -16 conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.24 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the Contracting Officer’s
Representative (COR) coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item.
Emphasis shall be placed on the use of special tools and instruments.
The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until
06-01-15
01 00 00 -17 instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the Contracting Officer’s Representative COR and shall be considered concluded only when the Contracting Officer’s Representative (COR)is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the Contracting Officer’s Representative (COR), does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.25 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the
Government-furnished property shown on the drawings.
B. Equipment furnished by Government to be installed by Contractor will be furnished to Contractor at the Medical Center.
C. Storage space for equipment will be provided by the Government and the
Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Medical Center.
D. Notify Contracting Officer in writing, 60 days in advance, of date on which Contractor will be prepared to receive equipment furnished by
Government. Arrangements will then be made by the Government for delivery of equipment.
1. Immediately upon delivery of equipment, Contractor shall arrange for a joint inspection thereof with a representative of the Government.
At such time the Contractor shall acknowledge receipt of equipment described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.
2. Contractor thereafter is responsible for such equipment until such time as acceptance of contract work is made by the Government.
E. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices, complete with all fittings, fastenings, and appliances necessary for connections to respective services installed
06-01-15
01 00 00 -18 under contract. All fittings and appliances (i.e., couplings, ells, tees, nipples, piping, conduits, cables, and the like) necessary to make the connection between the Government furnished equipment item and the utility stub-up shall be furnished and installed by the contractor at no additional cost to the Government.
F. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.
G. Furnish supervision of installation of equipment at construction site by qualified factory trained technicians regularly employed by the equipment manufacturer.
1.26 RELOCATED ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing items indicated by symbol "R" or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the Contracting Officer’s Representative (COR).
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT (NOT USED)
1.28 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the Contracting Officer’s
Representative (COR). All wood members shall be of framing lumber.
Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm
(4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet)
06-01-15
01 00 00 -19 above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of…