CITY_OF_KISSIMMEE__Haven_on_Vine__Electrical_System_Upgrade.pdf
PDF 193 KB Posted
- Solicitation number
- RFQ No. 6
- Issued by
- Polk County, Lake Harbor CDP, Florida
About this file
This is a Request for Quotations (RFQ No. 6) issued by the City of Kissimmee for a complete electrical system upgrade at Haven on Vine Apartments, a four-unit residential building located at 1815 W. Vine Street in Kissimmee, Florida. The scope of work encompasses demolition, installation, testing, labeling, and final inspection of a new electrical service system, including secondary underground service conductors, a five-position meter center with four individual residential meters, four 125-amp load centers with 100-amp main disconnects, complete apartment rewiring, life safety devices (smoke detectors, AFCI breakers, GFCI receptacles, and tamper-resistant receptacles), HVAC electrical connections, exterior electrical work including a photocell and communication bonding block, and comprehensive testing and commissioning. Electronic quotations are due Wednesday, July 8, 2026, and must be submitted to facilities.proposals@kissimmee.gov. The successful contractor shall execute an agreement immediately upon award, coordinate utility service requirements with Kissimmee Utility Authority, obtain all required permits, mobilize during the second week of July 2026, and complete work in accordance with a submitted construction schedule.
The project is federally funded and requires Davis-Bacon prevailing wage compliance under General Decision Number FL20250078 and Build America, Buy America (BABA) compliance. Quotations must be submitted as a lump sum price and include the proposed project schedule, earliest mobilization date, warranty information, material lead times, and confirmation of federal compliance. Qualified contractors must hold a current Florida electrical contractor license, provide a certificate of insurance, submit three references for similar multifamily electrical service upgrade projects, and include project superintendent information. The contractor shall provide manufacturer warranties on all equipment and a minimum one-year workmanship warranty. The City reserves the right to reject any or all quotations, request clarification, negotiate pricing, and award the project based on best overall value rather than lowest price.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATIONS (RFQ No. 6)
HAVEN ON VINE APARTMENTS
ELECTRICAL SYSTEM UPGRADE
One (1) Four-Unit Apartment Building
1. PURPOSE
The City of Kissimmee is requesting written quotations from qualified electrical contractors to furnish all labor, materials, supervision, equipment, permits, coordination, testing, and incidentals necessary to complete the electrical service upgrade for one (1) four-unit apartment building at the Haven on Vine Apartments. (Apartment Unit - Building #D Only).
The building consists of four (4) dwelling units, with two (2) units located on the first floor and two (2) units located on the second floor.
This project is federally funded and is subject to Davis-Bacon Prevailing Wage Requirements and Build America, Buy America (BABA) requirements.
2. QUOTATION DUE DATE
Wednesday, July 8, 2026
Electronic quotations shall be submitted to:
facilities.proposals@kissimmee.gov
3. PROJECT LOCATION
Haven on Vine Apartments mailto:facilities.proposals@kissimmee.gov
1815 W. Vine Street
Kissimmee, Florida 34741
4. PROJECT SCHEDULE
The successful contractor shall:
• Execute an agreement immediately upon award.
• Coordinate utility service requirements with Kissimmee Utility Authority (KUA).
• Obtain all required permits.
• Mobilize during the second week of July 2026.
• Complete the work in accordance with the submitted construction schedule.
5. SCOPE OF WORK
The Contractor shall furnish all labor, supervision, materials, equipment, permits, testing, inspections, utility coordination, and incidentals necessary to provide a complete electrical service upgrade for one (1) four-unit apartment building.
The work shall include all demolition, installation, testing, labeling, startup, and final inspection necessary to provide a complete and operational electrical system.
ELECTRICAL SERVICE
Provide and install a complete new electrical service from the existing utility transformer to the apartment building.
The work shall include:
• Secondary underground service conductors.
• Underground conduit system.
• Building service entrance.
• Complete service raceway system.
• Grounding and bonding.
• Utility coordination.
• Final energization.
METERING
Provide and install:
• One (1) five-position meter center.
• Four (4) individual residential electric meters.
• One (1) house meter position for common electrical loads.
Coordinate final meter installation with the serving utility.
ELECTRICAL PANELS
• Four (4) new 125-amp rated load centers (one per apartment).
• Four (4) new 100-amp main disconnects.
• Complete circuit identification and labeling.
APARTMENT REWIRING
Each apartment shall receive complete electrical rewiring as required to provide a code-compliant installation.
The work shall include:
• New branch circuit wiring.
• Reuse of existing conduit where practical.
• New grounding conductors.
• New home runs where required.
• New breakers.
• Circuit balancing.
• Complete reconnection of existing electrical equipment.
LIFE SAFETY DEVICES
Provide and install code-required:
• Smoke detectors.
• AFCI breakers.
• GFCI receptacles.
• Tamper-resistant receptacles.
HVAC ELECTRICAL
Provide complete electrical connections for:
• Air Handling Unit (AHU).
• Condensing Unit (CU).
• Dedicated breakers.
• Disconnects where required.
• Wiring sized in accordance with equipment nameplate requirements.
EXTERIOR ELECTRICAL
• One (1) photocell for exterior lighting.
• New ground rods.
• Communication bonding block.
• All required grounding and bonding.
DEMOLITION
The Contractor shall:
• Remove obsolete electrical equipment.
• Remove abandoned wiring where required.
• Remove existing panels, meters, disconnects, and associated equipment to accommodate the new installation.
• Dispose of all demolished materials in accordance with applicable regulations.
APPROXIMATE QUANTITIES
The following quantities are provided for bidding purposes only.
Description Quantity
Four (4) Apartment Units 1 Building
New 125-Amp Load Centers 4 EA
New 100-Amp Main Disconnects 4 EA
Five-Position Meter Center 1 EA
Residential Meter Positions 4 EA
House Meter Position 1 EA
Secondary Underground Electrical Service from Transformer 1 Complete System
Underground Conduit System 1 Complete System
Apartment Electrical Rewiring 4 Units
Surge Protection Devices 4 EA
Smoke Detectors As Required by Code
AFCI Breakers As Required by Code
GFCI Receptacles As Required by Code
Tamper-Resistant Receptacles As Required by Code
AHU Electrical Connections 4 EA
Condensing Unit Electrical Connections 4 EA
Photocell 1 EA
Ground Rods As Required by Code
Communication Bonding Block 1 EA
TESTING AND COMMISSIONING
• Perform all required electrical testing.
• Verify proper grounding and bonding.
• Test all branch circuits.
• Coordinate final inspections.
• Coordinate utility energization.
• Label all electrical panels and disconnects.
• Demonstrate proper system operation to the Owner.
CLEANUP
• Maintain a clean and safe worksite.
• Remove all debris daily.
• Dispose of demolished materials properly.
• Restore disturbed finishes associated with the electrical work.
• Leave the project site in a clean condition.
6. WARRANTY
The Contractor shall provide:
• Manufacturer warranties on all equipment.
• Minimum one-year workmanship warranty.
• Warranty documentation at project closeout.
7. FEDERAL REQUIREMENTS
This project is federally funded.
The selected contractor shall comply with:
• Davis-Bacon Prevailing Wage Requirements.
• Build America, Buy America (BABA).
• 2 CFR Part 200.
• Equal Employment Opportunity requirements.
• Certified Payroll reporting.
• Debarment and Suspension requirements.
• All applicable federal contract provisions.
Supporting documentation shall be submitted prior to commencement of work.
8. CONTRACTOR QUALIFICATIONS
The Contractor shall provide:
• Current Florida Electrical Contractor License.
• Certificate of Insurance.
• Three references for similar multifamily electrical service upgrade projects.
• Proposed project schedule.
• Project Superintendent information.
9. QUOTATION REQUIREMENTS
The quotation shall include:
• Lump Sum Price.
• Proposed project schedule.
• Earliest available mobilization date.
• Warranty information.
• Material lead times.
• Confirmation of Davis-Bacon and BABA compliance.
• Confirmation that all utility coordination with KUA is included.
10. CITY RESERVATIONS
The City reserves the right to reject any or all quotations, request clarification of any proposal, negotiate pricing where appropriate, and award the project to the contractor determined to provide the best overall value to the City.
The City is not obligated to accept the lowest quotation.
ATTACHMENTS
Attachment A – Electrical System Schedule
Attachment B – Building Electrical Layout
Attachment C – Davis-Bacon Wage Determination
Attachment D – Build America, Buy America (BABA) Requirements
Attachment E – Existing Site Electrical Plan (if available)
Attachment F – Contractor Quote Form
| REQUEST FOR QUOTATIONS (RFQ No. 6) |
| HAVEN ON VINE APARTMENTS |
| ELECTRICAL SYSTEM UPGRADE |
| One (1) Four-Unit Apartment Building |
| 1. PURPOSE |
| 2. QUOTATION DUE DATE |
| 3. PROJECT LOCATION |
| 4. PROJECT SCHEDULE |
| 5. SCOPE OF WORK |
| ELECTRICAL SERVICE |
| METERING |
| ELECTRICAL PANELS |
| APARTMENT REWIRING |
| LIFE SAFETY DEVICES |
| HVAC ELECTRICAL |
| EXTERIOR ELECTRICAL |
| DEMOLITION |
| APPROXIMATE QUANTITIES |
| TESTING AND COMMISSIONING |
| CLEANUP |
| 6. WARRANTY |
| 7. FEDERAL REQUIREMENTS |
| 8. CONTRACTOR QUALIFICATIONS |
| 9. QUOTATION REQUIREMENTS |
| 10. CITY RESERVATIONS |
| ATTACHMENTS |
File details come from the government source that posted it. Updated .