City Hall Security Upgrades.pdf

PDF 14 MB Posted

Attached to
Security Upgrades at City Hall
Solicitation number
IFB #2026-07 Bid
Issued by
Stanly County, Alliance Town, North Carolina

About this file

Summary

This is a Construction Document and Bidding Package for the City of Albemarle, North Carolina, for the Albemarle City Hall Renovation project located at 144 N. 2nd Street, Albemarle, NC 28001. The project encompasses interior renovation of office spaces to enhance security and functionality across two floors, including reconfiguration of architectural layouts to accommodate new offices, reception areas, conference rooms, and customer service spaces, along with modifications to mechanical, electrical, and fire protection systems. The work is divided into two phases: Phase One covering Economic Development and Planning Department areas, and Phase Two covering Administration and Public Utilities areas, with all construction confined to the interior and the exterior completely out of scope. A Non-Mandatory Pre-Bid Conference and Site Visit is scheduled for July 9, 2026, at 2:30 PM at Albemarle City Hall. Sealed bids will be received until 2:00 PM local time on August 6, 2026, in the Ray Allen Community Room, Room 118. The bidder deadline for submitting written questions is 5:00 PM local time on July 23, 2026. The successful bidder must complete all work within 180 calendar days from the Notice to Proceed, with liquidated damages assessed at $250.00 per calendar day for delays beyond the substantial completion date. The contract is structured as a single prime, lump sum agreement.

Bidders are required to hold their proposed bid price for 90 days following bid opening and must submit bid security in the amount of 5 percent of the total bid price in the form of a bid bond, cash, cashier's check, or certified check. The Base Bid Price must include a 10 percent owner contingency allowance, with any unused contingency funds to be returned to the Owner via deduct change order. All bidders must be properly licensed contractors in North Carolina and must provide Performance and Payment Bonds for the contract. Minimum insurance requirements include Workers' Compensation with Employers Liability of $100,000 per injury and $500,000 policy limit, Commercial General Liability of $1,000,000 each occurrence and $2,000,000 general aggregate, and Business Auto Policy of $1,000,000 combined single limit. Bidders are required to submit non-collusion affidavits, Equal Opportunity Employment affidavits, and Minority Business Enterprise participation documentation. The project is funded by the City of Albemarle, with construction documents prepared by Creech & Associates, PLLC, and mechanical, electrical, plumbing, and fire protection design provided by Optima Engineering, PA.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL – CONSTRUCTION DOCUMENTS

ALBEMARLE CITY HALL RENOVATION

144 N. 2ND ST. ALBEMARLE, NC 28001

Albemarle, North Carolina

Architect Project No. 2026-07

OWNER

Albemarle City Hall Renovation

144 N. 2ND ST.

Albemarle, NORTH CAROLINA 28801

ARCHITECTS

CREECH & ASSOCIATES, PLLC

1000 W. MOREHEAD ST, SUITE 120

CHARLOTTE, NORTH CAROLINA 28208

PHONE: (704) 376.6000

CONSULTANTS

MECHANICAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION

OPTIMA ENGINEERING. PA

1927 SOUTH TRYON STREET

CHARLOTTE, NORTH CAROLINA 28203

PHONE: 704.338.1292

CONSTRUCTION DOCUMENTS 05/14/2026

© 2026

DOCUMENT 00 01 10 - TABLE OF CONTENTS

Creech & Associates 1 Albemarle City Hall Renovation Project #2022-050 00 01 10 100% Construction Documents – 05-14-2026

PROJECT MANUAL – 100% CONSTRUCTION DOCUMENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 01 Project Title Page

00 01 10 Table of Contents 00 11 13 Advertisement For BID

00 11 16 Invitation To BID 00 31 00 Available Project Information

00 41 13 BID Form Stipulated Sum

00 43 13.16 BID Form Checklist 00 43 28 Tax Rebate Forms

00 52 00 Agreement Forms 00 62 00 Certificate Of Insurance

00 72 00 General Conditions of the Contract for Construction (AIA A201 – 2017)

DIVISION 01 – GENERAL REQUIREMENTS

01 10 00 Summary 01 26 00 Contract Modifications Procedures

01 29 00 Payment Procedures 01 31 00 Project Management and Coordination

01 32 00 Construction Progress Documentation

01 33 00 Submittal Procedures 01 40 00 Quality Requirements

01 42 00 References 01 50 00 Temporary Facilities and Controls

01 60 00 Product Requirements

01 73 00 Execution 01 73 29 Cutting and Patching

01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures

01 78 23 Operation and Maintenance Data

01 78 39 Project Record Documents 01 79 00 Demonstration and Training

DIVISION 02 – EXISTING CONDITIONS

02 41 19 Selective Demolition

DIVISION 03 – CONCRETE (NOT USED)

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS (NOT USED)

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 10 53 Miscellaneous Rough Carpentry

06 16 00 Sheathing 06 40 23 Interior Architectural Woodwork

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames

DOCUMENT 00 01 10 - TABLE OF CONTENTS

Creech & Associates 2 Albemarle City Hall Renovation Project #2022-050 00 01 10 100% Construction Documents – 05-14-2026

08 14 16 Flush Wood Doors

08 41 13 Aluminum-Framed Entrances and Storefronts

08 56 53 Security Windows 08 71 00 Door Hardware

08 80 00 Glazing 08 83 00 Mirrors

08 90 00 Louvers and Vents

DIVISION 09 - FINISHES

09 29 00 Gypsum Board Assemblies 09 51 13 Acoustical Panel Ceilings

09 65 13 Resilient Base And Accessories 09 65 19 Resilient Tile Flooring

09 67 23 Resinous Flooring

09 68 13 Tile Carpeting 09 84 13 Fixed Sound-Absorptive Panels

09 91 00 Painting

DIVISION 10 - SPECIALTIES

10 14 00 Signage

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 - FURNISHINGS

12 36 00 Countertops

DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)

DIVISION 21 - FIRE SUPPRESSION (NOT USED)

DIVISION 22 – PLUMBING (NOT USED)

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING (NOT USED)

DIVISION 26 – ELECTRICAL (NOT USED)

DIVISION 27 – COMMUNICATIONS (NOT USED)

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY (NOT USED)

DIVISION 31 – EARTHWORK (NOT USED)

DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)

END OF TABLE OF CONTENTS

DOCUMENT 00 11 13 - ADVERTISEMENT FOR BID

Project #2026-07 00 11 13 100% Construction Documents 05-14-2026

CITY OF ALBEMARLE, NORTH CAROLINA

ADVERTISEMENT FOR BID

IFB #2026-07 Bid

Albemarle City Hall Security Upgrades

Sealed Bids for City Hall Security Upgrades will be received by the City of Albemarle until 2:00 PM local time on

August 6, 2026, in the Ray Allen Community Room, Room 118, at the Albemarle City Hall 144 N 2ND ST, Albemarle, NC 28001. Late bids will not be accepted.

If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED – 2026-07” and “BID ENCLOSED –

2026-07 Bid Bond” and shall be addressed to 144 N. 2ND ST., Albemarle, NC 28801, Attn: Matt Smith.

A Non-Mandatory Pre-Bid Conference and Site Visit will be held on July 9, 2026, at 2:30 PM local time at the

Albemarle City Hall 144 N. 2ND ST, Albemarle, NC 28001. Please check in and remain in the lobby of the rear entrance outside the council chamber.

Scope of Work: Renovation of interior office spaces for security upgrades. Work takes place entirely on the interior, with the exterior being completely out of scope.

The Work shall be completed in two phases, one being the Economic Development and Planning Department areas and the second phase being the Administration and Public Utilities areas. The Work includes coordinating with

Albemarle City Hall for access, security, and shut downs.

All questions about the meaning or intent of the Bidding Documents are to be submitted in writing to the architect via email at jcrawford@creech-design.com. Deadline for questions is 5:00 PM local time on July 23, 2026.

Questions will be addressed via Addenda no later than 7 days prior to bid date.

The Issuing Office for the Bidding Documents is:

Creech & Associate

1000 W. Morehead St., Suite 120

Charlotte, NC 28208

Attn: John Crawford, AIA

For any question concerning the project, please contact:

John Crawford jcrawford@creech-design.com

Bidding Documents will be available in electronic format on the city’s website. The link will allow you to download the documents as well as any addenda that may be issued throughout the bidding process.

Bids will be received for a single prime, lump sum Contract.

Bidders must have a license to do work as a contractor in the State of North Carolina, as set forth under Article 1 chapter 87 of the North Carolina General statutes. The bidder’s North Carolina Contractor license number shall be designated on the outside of the sealed envelope containing the Bid.

Bidders are required to provide a non-collusion affidavit, as set forth in the bidding documents.

DOCUMENT 00 11 13 - ADVERTISEMENT FOR BID

Project #2026-07 00 11 13 100% Construction Documents 05-14-2026

As provided by statute, a deposit of cash, cashier’s check or certified check on some bank or trust company insured by the Federal Deposit insurance Company, or a bid bond executed by corporate surety licensed under the laws of

North Carolina to execute such bonds in the amount of 5% of the bid must accompany each bid. The payee shall be

“City of Albemarle”. Said deposit shall guarantee that the Agreement will be entered into by the successful bidder if award is made. Such deposit may be held by the city until the successful bidder has executed and delivered all required Contract documents to Albemarle City Hall.

Bidders should note the provisions of the Supplementary instruction to bidders contained in the Bid Documents regarding minority participation. The City of Albemarle encourages good faith effort outreach. Bidders shall submit a completed identification of Minority Participation form and an Affidavit A & Affidavit B, or an Affidavit C, as applicable along with their Bid.

The Owner reserves the right to reject any or all bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid and Bidder whom they find, after reasonable inquiry and evaluation, to not be responsible. Owner may also reject the Bid and Bidder if the Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities and technicalities not involving price, time, or changes in the Work and to negotiate, as allowed by law, contract terms with the Successful Bidder.

END OF DOCUMENT 00 11 13

DOCUMENT 00 11 16 – INVITATION TO BID

Project #2026-07 00 11 16 100% Construction Documents 05-14-2026

1.

1.1 PROJECT INFORMATION

A. Notice to Bidders: Bidders are invited to submit bids for Project as described in this document.

1.2 Related Sections:

A. 00 11 13 Advertisement for Bids

B. 00 21 00 Instructions to Bidders

C. 00 25 00 Pre Bid Meetings

D. 00 41 13 Bid Form – Stipulated Sum

E. 00 43 13.16 Bid Form Checklist

F. 00 43 13 Bid Security Form

G. 00 43 39.13 Guidelines for Recruitment and Selection of Minority Business

H. 00 45 19 Non-Collusion Affidavit

I. 00 45 36 Equal Opportunity Employment Affidavit

J. 00 45 39 MBE Provisions Affidavit

1.3 Project Identification:

1. Name: Albemarle City Hall Renovation

2. Location:

a. 144 N. 2ND ST. Albemarle, NC 28001.

3. Designer: Creech & Associates

a. Creech & Associates, 1000 W. Morehead Street Suite 120, Charlotte, NC 28208

(704) 376-6000

4. Owner: Albemarle City Hall

a. The Owner designates persona as its representative and a Point of Contact for this Bid.

Bidders shall restrict all contact and direct all questions regarding this Bid, including responses. Questions regarding terms and conditions, and technical specifications, to the Procurement Point of Contact listed below in writing (via email) no later than July 23, 2026, at 5:00pm.

b. Owner’s Point of Contact:

Matt Smith, Asst. Finance Director City of Albemarle

144 N. 2nd Street Albemarle, NC 28001 704.438-0980 Mjsmith@albemarlenc.gov

1.4 SUMMARY

A. Renovation of interior spaces at the offices and reading area. Work takes place entirely on the interior, with the exterior being completely out of scope.

B. Architect Identification:

1. Project Designer: Creech & Associates

2. Owner: Albemarle City Hall, NC.

C. The project will be constructed in one phase.

D. Construction Contract: Bids will be received for the following work:

1.5 BID SUBMITTAL AND OPENING

A. Owner will receive sealed bids until the bid time and date at the location indicated within the section 00 11 13 Advertisement for Bidders for Bid IFB# 2026-07 Bid.

DOCUMENT 00 11 16 – INVITATION TO BID

Project #2026-07 00 11 16 100% Construction Documents 05-14-2026

1.6 BID SECURITY

A. Bid security shall be submitted with each bid in the amount of 5 percent of the bid amount. No bids may be withdrawn for a period of 90 days after opening. Owner reserves the right to reject any and all bids to waive informalities and irregularities.

1.7 DOCUMENTS

A. Online Procurement and Contracting Documents. Complete sets of Bidding Documents can be obtained from the Issuing Office as described within the section 00 11 13 Advertisement for

Bidders for Bid IFB# 2026-07 Bid.

1.8 Time of completion and liquidated damages

A. Bidders shall begin the Work on receipt of Notice to proceed and shall complete the Work within 180 calendar days. Work is subject to liquidated damages of $250.00 per day.

1.9 BIDDERS QUALIFICATIONS

A. Bidders must be properly licensed under the laws governing their respective trades and be able to obtain insurance and bonds required for the Work. A Performance and Payment Bond and Insurance in a form acceptable to Owner will be required of the successful Bidder.

END OF DOCUMENT 00 11 16

DOCUMENT 00 31 00 - AVAILABLE PROJECT INFORMATION

Project #2022-050 00 31 00 100% Construction Documents – 05-14-2026

1.1 SUMMARY

A. This Document with its referenced attachments is part of the Bidding Requirements for this Project and is not part of the Contract Documents. It includes the following:

1. Geotechnical Data.

1.2 PROJECT CONDITIONS

A. Geotechnical Data:

1. Subsurface investigation reports have been prepared by an independent agency and are attached to this Document.

2. These reports were obtained by the Owner for reference purposes only and are not a part of the Contract Documents. Test boring records are included for bidders’ convenience and information but are not a warranty of subsurface conditions.

3. Prior to construction, Contractor may make his own subsurface investigation to satisfy themselves as to the site and subsurface conditions, but such subsurface investigations shall be performed only under time schedules and arrangements approved in advance by the Architect.

1.3 ATTACHMENTS

A.

B.

END OF DOCUMENT 00 31 00

DOCUMENT 00 41 13 – BID FORM STIPULATED SUM

Project #2026-07 00 41 13 100% Construction Documents 05-14-2026

BID INFORMATION

Name of Bidder:

Date:

Project Name: Albemarle City Hall Renovation

Owner: Albemarle

Owner Project Number: IFB #2026-07

Designer: Creech and Associates

Designer Project Number: 2026-07

CERTIFICATIONS OF BASE BID

The undersigned Bidder, hereby declares that he has carefully investigated the scope of work and having thoroughly familiarized himself with the Contract Documents relative hereto, and has read all special provisions furnished prior to the opening of the bids; that he has satisfied himself relative to the work to be performed.

The bidder further declares that he and his sub-contractors have fully complied with NCGS 64, Article 2 in regards to E-Verification as required by N.C. General Statute 143-129(j). The bidder agrees to hold the proposed bid price for 90 days.

The bidder proposes and agrees if this proposal is accepted, to contract with the City of Albemarle, in the form of contract specified, to provide all necessary labor, equipment, materials, machinery, tools, apparatus, transportation, services, fees, permits, etc., to complete the construction of Albemarle City Hall Renovation, all in accordance with the aforementioned Contract Documents to the full and entire satisfaction of the City of Albemarle, with definite understanding that no money will be allowed for extra work except as set forth in the General Conditions and the Contract Documents for the lump sum of:

Provide 10% of base bid price as an owner contingency allowance and provide a Total Base Bid Price. Any funds not used from this allowance will be returned to the Owner by deduct change order.

A) BASE BID PRICE:

Dollars ($ ).

B) OWNERS CONTINGENCY:

C) TOTAL BASE BID PRICE WITH OWNER CONTENGENCY (A+B=C):

SUB-CONTRACTOR LIST:

The following shall execute subcontracts with the Bidder for the portion of the work indicated:

Project #2026-07 00 41 13 100% Construction Documents 05-14-2026

Electrical Sub-Contractor (Name & License No.):

License No.

Mechanical Sub-Contractor (Name & License No.):

Fire Protection Sub-Contractor (Name & License No.):

TIME OF COMPLETION

The undersigned Bidder proposes and agrees hereby to commence the Work of the Contract Documents on a date specified in a written Notice to Proceed to be issued by Architect and shall fully complete the Work within __________________ calendar days. This is not the deciding factor but may be considered in the final decision.

LIQUIDATED DAMAGES:

The undersigned further agrees, stipulates, and fixes as Liquidated Damages if delayed, but not as a penalty, the sum of Two Hundred and Fifty Dollars ($250.00) per calendar week that the undersigned together with the undersigned’s surety shall pay the Owner for each calendar day or part thereof that expires after the date specified for the substantial completion of the work and until the Work is Substantially complete. By bidding, the undersigned hereby agrees to be responsible for liquidated damages.

BID SECURITY:

Accompanying this proposal is a bid security five percent (5%) of the Total Bid Price Sum in accordance with Instructions to Bidders in the form of (check one):

⬜ Bid Bond (AIA Document A310-2010), or

⬜ Cash, or

⬜ Cashier’s Check, or Certified Check.

RECIEPT OF ADDENDA:

The undersigned acknowledges receipt of the following addenda which will be considered as part of the contract Documents:

Addendum No. Dated Addendum No. Dated

MBE INORMATION:

Acknowledgement and submittal of MBE information is included with this Proposal: ⬜ Yes ⬜ No

CONTRACTOR’S LICENSE:

The undersigned further states that it is a duly licensed contractor for the proposed work in the State of North Carolina, and that all fees, permits, etc. pursuant to submitting this proposal have been paid in full.

ACKNOWLEDGEMENT AND REPRESENTATIONS:

If notice of acceptance of this bid is given to the undersigned within 90 days after the date of opening of bids, or any time thereafter before this bid is withdrawn, the undersigned will execute and deliver an Agreement in the prescribed form promptly after is has been presented to him for signature. Certificates of Insurance and

Creech & Associates 3 Albemarle City Hall Renovation Project #2026-07 00 41 13 100% Construction Documents 05-14-2026

Performance and Payment bonds shall be furnished to the Owner at the execution of this agreement and as required by North Carolina General Statutes.

Upon request of the Owner, the undersigned bidder agrees to submit evidence in affidavit form of applicable experience, adequate financial resources, work in hand capacity, adequate organization, and acceptable past performance. Submittal will be in the form of AIA Document A305 Contractor’s Qualification Statement.

Bidder’s qualifications information shall be considered confidential.

The undersigned bidder certifies the neither he/she, nor any official, agent or employee has entered into any agreement, participated in any collusion, or otherwise taken any action which is in restraint of free competitive bidding in conjunction with this bid. The person signing this bid form represents that he/she has full authority and representative capacity to execute this Bid Form in the capacity indicated below.

The undersigned agrees that in the case of failure on his part to execute the said contract and the bond within ten (10) consecutive calendar days after written notice being given of the award of contract, the certified check, cash or bid bond accompanying this bid shall be paid into the funs of the Owner’s account set aside for the Project, as liquidated damages for such failure; otherwise, the certified check, cash or bid bond accompanying the Proposal shall be returned to the undersigned.

The undersigned bidder agrees that they are expected to act as Project Expediter and coordinate work of all other contractors.

The firm signing this bid and registered under that name is legally qualified to perform all work included in the scope of the contract as determined by the State of North Carolina, in granting the registration.

PROPOSAL SIGNATURE:

Respectfully submitted this day of , 20 .

(Name of firm or corporation making bid)

By:

Signature and Typed Name

Title:

Address of Bidder:

Bidders N.C. Contractor License No.

Type of License:

Limitations:

Attest:

By:

Title:

END OF DOCUMENT 00 41 13

DOCUMENT 00 43 13.16 – BID FORM CHECKLIST

Project #2022-050 00 43 13.16 100% Construction Documents 05-14-2026

1.1 Bid Form Checklist

A. Submit this form as a cover sheet to your Bid.

B. Attach the noted documents to your Bid.

C. Checklist:

⬜ 00 43 13 Bid Form

⬜ Contractor’s Name and License Number Completed

⬜ Total Base Bid Price includes Base bid plus 10% of Base Bid Price

⬜ Subcontractors listed

⬜ Bid Security is Recognized

⬜ Addenda Recognized with Date

⬜ Contractor information has been Attest

⬜ 00 43 13.13 Bid Security

⬜ AIA A310-2010

⬜ Cashier’s or Certified Check

⬜ 00 45 19 Non-Collusion Affidavit

⬜ 00 45 36 Equal Opportunity Employment Affidavit

⬜ 00 45 39 HUB Minority Forms

⬜ Identification of HUB Certified/ Minority Business Participation (this form is require with the Affidavits or Bid cannot be accepted)

⬜ Affidavit A

⬜ Affidavit B

⬜ Affidavit C

⬜ 00 52 00 Agreement Form

END OF DOCUMENT 00 43 13.16

DOCUMENT 00 43 28 – TAX REBATE FORMS

Creech & Associates 1 Albemarle City Hall Renovations Project #2026-07 00 43 28 100% Construction Documents 05-14-2026

Instructions for Completing

Certificate for North Carolina Sales Tax Form

City of Albemrle may apply for a refund of all sales and/or use taxes paid in North Carolina by the County’s contractors on purchases of building materials, supplies, fixtures and equipment which become a part of or are annexed to any building or structure being erected, altered or repaired under contract with the County. Contractors shall include and must pay all other taxes imposed by governmental authorities which are applicable to the contract work. Examples of property on which sales and use tax has been paid by the contractor and for which the contractor will not be reimbursed by the County are scaffolding, forms for concrete, fuel for the operation of machinery and equipment, tools, equipment repair parts and equipment rentals, blueprints, etc, or any other items which do not become a part of or are not annexed to the building or structure being erected, altered, or repaired.

Please submit with this form invoices (or copies of invoices) from vendors covering the items purchased. This form should still be submitted as “0” if no sales tax was paid for the period covered.

Requests for sales tax reimbursements should be filed with each request for contract payment.

Project or Contract Number: The name of the project, or the County Contract Number.

Date: The date the form was completed.

Trade: Your trade, e.g., electrical, plumbing, concrete contractor, etc.

Contractor: The name of your company.

Invoice Date: The date the materials were purchased.

Invoice Number: The vendor's invoice number.

Name of Vendor: The vendor's name.

Description of Materials: The type of materials purchased, e.g., concrete, nails, roofing material, etc.

Item Cost: The cost of the item(s) before any taxes are added.

State Tax: The North Carolina State tax, currently 4.75% of the item cost.

County Tax: The County tax, currently 2.25% of the item cost.

Total Invoice: The sum of the Item Cost, State Tax, and County Tax.

County Name: County where material was purchased and sales tax paid, e.g., Stanly, Cabarrus, Anson, etc. The owner or an officer of the company must certify that the statement is correct. The signature should also be notarized.

Creech & Associates 2 Albemarle City Hall Renovations Project #2026-07 00 43 28 100% Construction Documents 05-14-2026

Page ______ of ______.

Certificate for North Carolina Sales Tax Trade: ________________________________________________________________________

Contractor: _____________________________________________________________________

Project or Contract Number: _______________________________________________________

Date: _________________________________________________________________________

Invoice Date

Invoice Number Name of Vendor Description of Materials Item Cost State Tax

County Tax

Total Invoice

County Name

Totals:

NOTE: Last page must be the certified page.

Page _____of _____.

Project #2022-050 00 01 10 100% Construction Documents 05-14-2026

Certificate for North Carolina Sales Tax Trade: ________________________________________________________________________

Contractor: _____________________________________________________________________

Project or Contract Number: _______________________________________________________

Date: _________________________________________________________________________

Invoice Date

Invoice Number Name of Vendor Description of Materials Item Cost State Tax

County Tax

Total Invoice

County Name

Totals:

This is to certify that the above materials purchased on the invoices listed were used in the construction of the ________________________________________ and that the Sales Tax listed (State and County) is not included on the monthly estimate for contract payment or any other certificate for North Carolina sales tax.

Further, that the items listed are annexed to, affixed to, or in some manner have become a part of the building or structure being erected, altered or repaired.

Certified to be correct by:_____________________________________________________ Owner or Officer of Company

Sworn to and Subscribed before me this _______day of_________________20_______

________________________________________ (SEAL)

Notary Public

My Commission Expires:___________________

DOCUMENT 00 52 00 - AGREEMENT FORMS

Project #2022-050 00 52 00 100% Construction Documents – 05-14-2026

1.1 FORM OF AGREEMENT

A. The following form of Owner/Contractor Agreement shall be utilized for the Project:

1. AIA Document A102, Owner-Contractor Agreement Form, Cost of the Work Plus a Fee, 2017 Edition.

END OF DOCUMENT 00 52 00

DOCUMENT 00 62 00 – CERTIFICATE OF INSURANCE

Creech & Associates 1 Albemarle City Hall Renovations Project #2026-07 00 62 00 100% Construction Documents 05-14-2026

1.1

The City of Albemarle frequently deems it necessary to utilize the services of outside entities (contractors) to assist in performing the work of the City. It is a part of the City’s risk management policy to impose certain minimum standards for insurance, hold harmless, indemnification and safety requirements upon contractors performing work on behalf of the City. These requirements are set forth to protect the City and its contractors and are a benefit to both.

In order to be a contractor eligible of performing work as called upon by the City, contractors must agree and meet the following requirements:

I. INSURANCE PROVISIONS

All contractors must carry the following minimum liability insurance requirements:

A. Worker’s Compensation –Shall cover all employees and shall have Employers

Liability insurance in the amount of $100,000 bodily injury, $100,000 bodily injury by disease and $500,000 bodily injury by disease policy limit. Coverage shall be provided for duration of project.

B. Commercial General Liability – Coverage shall be a minimum of $1,000,000 each occurrence $2,000,000 general aggregate, and $2,000,000 products-completed operation aggregate limit.

C. Business Auto Policy – Coverage shall be a minimum of $1,000,000 combined single limit for any one accident or loss. Policies and limits shall be required when vehicles are directly utilized in the contracted services provided to the City.

D. Professional (Errors and Omissions) Liability – A minimum of $1,000,000 per employee/per occurrence of Professional Liability Insurance shall be required for all contractors performing service type activities (architectural, engineering and consulting services).

E. Additional Insurance Requirements:

1. The City shall reserve the right to require additional insurance coverages for specialty operations and/or higher limits of liability for projects where the City is exposed to significantly higher liability risks (such as explosion/collapse/underground (XCU) coverage or builder’s risk).

2. Coverages shall remain in effect at least until the completion of the contracted project and at any time when the contractor may be correcting, replacing or removing any defective work.

3. The City of Albemarle shall be given thirty days notice prior to the expiration of a certificate of insurance and failure to provide such notice shall impose no liability on the City, its agents or representatives.

4. It shall be the responsibility of the contractor to ensure that all subcontractors comply with the requirements of this policy.

II. ADDITIONAL INSURED STATUS/CERTIFICATE OF INSURANCE

The City of Albemarle shall be endorsed as an additional insured on the applicable liability insurance policies with the exception of professional liability policies.

Two certificates shall be provided by the agent or broker that produced the policy denoting compliance with the above requirements including additional insured status for the City. Certificates of insurance shall be provided prior to the awarding of any contract; and such certificate shall include provisions that the insurance shall not be cancelled, allowed to expire or be materially changed without giving the City thirty days advance written notice.

III. INDEMNIFICATION AND HOLD HARMLESS

The contractor shall indemnify and hold harmless the City of Albemarle, its officers, agents and employees from and against all loss, cost, damages, expense and liability caused by an accident or other occurrence resulting in bodily injury, including death and disease to any person or damage or destruction of property either real or personal, arising directly or indirectly from operations, products, or services rendered or purchased under the contract.

IV. BONDS

A performance bond and a when necessary laborers’ and materialmen’s bonds for the full amount of the contract is required for construction contracts of $300,000 or more and for contracts of $50,000 or more when one or more of the contracts is in conjunction with a project exceeding $300,000.

V. SAFETY REGULATIONS

All contractors shall comply with all applicable Occupational Safety and Health Administration (OSHA) requirements for General Industry and Construction Standards. Depending on the scope of work to be performed the City may require compliance with specific OSHA standards.

It shall be the responsibility for the contractor to provide adequate supervision for all contract employees and to ensure that these employees follow all applicable OSHA and general safety guidelines. The contractor is responsible for ensuring contract employees follow proper safety procedures. The contractor shall remedy the situation immediately or provide evidence to the City that the condition is necessary for the completion of the project and does not unduly jeopardize people or property.

I hereby understand and agree to comply with the terms of this policy.

Authorized Representative Attest

Date

DOCUMENT 00 62 00 – CERTIFICATE OF INSURANCE

Creech & Associates 3 Albemarle City Hall Renovations Project #2026-07 00 62 00 100% Construction Documents 05-14-2026

END OF DOCUMENT 00 62 00

DOCUMENT 00 72 00 - GENERAL CONDITIONS

Project #2022-050 00 72 00 100% Construction Documents – 05-14-2026

1.1 GENERAL CONDITIONS

A. General Conditions for the Project are AIA Document A201-2017 General Conditions of the Contract for Construction.

B. The above document is hereby incorporated into this Project Manual by reference.

C. Copies of AIA standard forms may be obtained from:

1. American Institute of Architects, Charlotte, NC: 704.377.3610.

END OF DOCUMENT 00 72 00

SECTION 01 10 00 - SUMMARY

Project #2022-050 01 10 00 100% Construction Documents – 05-14-2026

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Type of Contract.

3. Work schedule and sequence.

4. Use of premises.

5. Work restrictions.

6. Specification formats and conventions.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

Project Identification: Albemarle City Hall Renovation Project Location: 144 N 2nd St, Albemarle, North Carolina

1. Owner: Albemarle, North Carolina.

B. Architect Identification: The Contract Documents, dated May 14, 2026, were prepared for Project by Creech & Associates, 1000 West Morehead Street, Suite 120, Charlotte, NC 28208.

C. Construction Manager Identification: The Owner has selected the following organization to serve as Construction Manager for the Project:

1.4 The scope of work involves the interior renovation of the Albemarle City Hall to enhance its functionality across two floors. The renovation will involve reconfiguring the architectural layout to accommodate new offices, reception areas, a conference room, and customer service spaces. In addition to the architectural changes, the project will require modifications to the mechanical, electrical and fire protection systems to support the updated layout and functions. All construction activities will be confined to the interior, with no work planned for the building’s exterior.

1.5 CONTRACTS

A. Project will be constructed under a general construction contract.

1.6 WORK SCHEDULE AND SEQUENCE

A. The Work shall be conducted in two phases with phase two staring immediately after first phase completition, with the date of Substantial Completion to be as indicated in the Agreement.

1.7 USE OF PREMISES

A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

1. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Deliveries: Provide representative to receive all materials and offload at the job site. The Owner will refuse all deliveries to other locations.

SECTION 01 10 00 - SUMMARY

Project #2022-050 01 10 00 100% Construction Documents – 05-14-2026

C. Personnel Identification: All construction personnel in occupied portions of the facility must wear Contractor-furnished identification badges at all times. Personnel without proper identification are subject to removal from the site by the Owner.

D. Safety and Security: Comply with Owner’s requirements related to security and fire drills and alerts.

E. Burning/Welding Operations: Comply with Owner’s requirements related to Burning and Welding permits.

Coordinate turning off of fire/smoke detection systems in affected areas. Contractor shall be responsible for Fire Department response fees related to construction operations.

F. Smoking: No smoking is allowed on the premises, except within 20 feet of the Contractor’s job office trailer or as otherwise designated by Owner’s representative.

G. Use of Site: Limit use of premises to indicated areas within the Contract limits. Do not disturb portions of Project site beyond areas in which the Work is indicated.

a. Limits: Confine constructions operations to areas indicated on Civil Drawings.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 9:00 p.m., Monday through Friday, except otherwise indicated.

1. Weekend Hours:

a. Saturday Hours: 8:00 a.m. to 6:00 p.m.

b. Sunday Hours: 1:00 p.m. to 6:00 p.m.

2. Early Morning Hours: Restrict noisy work until after 7:00 a.m.

1.9 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the 33-division format and CSI/CSC's "MasterFormat" numbering system.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred, as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract

Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications.

Requirements expressed in the imperative mood are to be performed by Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 10 00

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

Project #2022-050 01 26 00 100% Construction Documents – 05-14-2026

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

1.3 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions."

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by Architect are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

2. Within 20 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the

Contract Time.

B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change.

1. Include a statement outlining reasons for the change and the effect of the change on the

Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract

Time.

5. Comply with requirements in Division 01 Section "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.

C. Proposal Request Form: Use AIA Document G709.

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

Project #2022-050 01 26 00 100% Construction Documents – 05-14-2026

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the

Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 26 00

SECTION 01 29 00 - PAYMENT PROCEDURES

Project #2022-050 01 29 00 100% Construction Documents – 05-14-2026

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with Continuation Sheets.

b. Submittals Schedule.

c. Contractor's Construction Schedule.

2. Submit the Schedule of Values to Architect at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

3. Subschedules: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values correlated with each phase of payment.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name and location.

b. Name of Architect.

c. Architect's project number.

d. Contractor's name and address.

e. Date of submittal.

2. Submit draft of AIA Document G703 Continuation Sheets.

3. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed:

a. Related Specification Section or Division.

b. Description of the Work.

c. Name of subcontractor.

d. Name of manufacturer or fabricator.

e. Name of supplier.

f. Change Orders (numbers) that affect value.

g. Dollar value.

1) Percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.

4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate.

Include separate line items under required principal subcontracts for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training in the amount of 5 percent of the Contract Sum.

5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

Project #2022-050 01 29 00 100% Construction Documents – 05-14-2026

6. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site. If specified, include evidence of insurance or bonded warehousing.

7. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

8. Allowances: Provide a separate line item in the Schedule of Values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.

9. Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

10. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the

Contract Sum.

1.4 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is the 15th day of each month, unless otherwise specified in the Agreement. The period covered by each Application for Payment starts on the day following the end of the preceding period and ends 15 days before the date for each progress payment.

C. Payment Application Forms: Use AIA Document G702 and AIA Document G703 Continuation Sheets as form for Applications for Payment.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule.

Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

E. Transmittal: Submit 4 signed and notarized original copies of each Application for Payment to

Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

F. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of Values.

3. Contractor's Construction Schedule (preliminary if not final).

4. Products list (preliminary if not final).

Project #2022-050 01 29 00 100% Construction Documents – 05-14-2026

5. Schedule of unit prices.

6. Submittals Schedule (preliminary if not final).

7. List of Contractor's staff assignments.

8. List of Contractor's principal consultants.

9. Copies of building permits.

10. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

11. Initial progress report.

12. Report of preconstruction conference.

13. Certificates of insurance and insurance policies.

H. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial

Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

I. Submittals that must precede or coincide with submittal of Application for Payment at Substantial Completion include the following:

1. Operation and Maintenance Data final submittal.

J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."

5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."

6. AIA Document G707, "Consent of Surety to Final Payment."

7. Evidence that claims have been settled.

8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

9. Final, liquidated damages settlement statement.

END OF SECTION 01 29 00

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

Project #2022-050 01 31 00 100% Construction Documents – 05-14-2026

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General Project coordination procedures.

2. Coordination Drawings.

3. Requests for Information.

4. Project meetings.

B. See Division 01 Section "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.3 COORDINATION

A. Coordination: Coordinate construction operations included in various Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for…