CIS NOI CMGC 20220603.pdf
PDF 241 KB Posted
- Attached to
- Tuna, Light Meat in Water
- Solicitation number
- S-29100-00002807
- Issued by
- Marion County, Oregon
About this file
This is a Notice of Intent to Award issued by CIS (Collaboration Center for Integrated Services) dated June 3, 2022, regarding the selection of a Construction Management/General Contractor for the CIS Collaboration Center project located at 15875 Boones Ferry Road, Lake Oswego, Oregon. The selection committee received proposals from six general contracting firms: Bremik Construction, Inc., Fortis Construction, Inc., Pence Construction LLC, Triplett Wellman, Inc., Howard S. Wright (a Balfour Beatty Company), and P & C Construction Co. CIS intends to enter into negotiations with the top-ranked firm, Bremik Construction, Inc., to provide construction management and general contractor services for the new collaboration center project.
The notice does not specify detailed contract pricing terms, set-asides, or specific contract duration information in the document provided. However, the document indicates that the selection process has been completed and negotiations will proceed with the selected firm. For additional information regarding the committee's decision and project details, inquiries should be directed to Gerry Mulrooney at gmulrooney@planbconsult.net or (971) 256-9112.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Tuna~1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice of Intent to Award a Contract
Construction Management/General Contractor Services
CIS
15875 Boones Ferry Road, #1469 Lake Oswego, OR 97035
(503) 763-3800
To:
From:
June 3, 2022
General Contractors for New CIS Collaboration Center
CIS
Re: Status of Selection Project – CIS Collaboration Center – Construction Management/General Contractor Services
CIS has completed its selection process regarding professional services for the above named project.
It has been our objective to select the most qualified firm to provide these services through this selection process. The committee received proposals from the following companies:
• Bremik Construction, Inc.
• Fortis Construction, Inc.
• Pence Construction LLC
• Triplett Wellman, Inc.
• Howard S. Wright, a Balfour Beatty Company
• P & C Construction Co
It is our intention to enter into negotiations with the top-ranked firm, Bremik Construction, Inc.
If you have any questions about the committee’s decision, please contact Gerry Mulrooney at gmulrooney@planbconsult.net or (971) 256-9112 for additional details.
Sincerely, The CIS Collaboration Center Selection Committee mailto:gmulrooney@planbconsult.net