CIRCUIT SPECIFICATIONS:

1. TELECOMM PROVIDER MUST PROVIDE TOTAL FIBER MILES AND ROUND TRIP DELAY (RTD) FROM THE

CUSTOMER "A" LOCATION TO THE CUSTOMER "Z" LOCATION. THE RTD SHALL BE LESS THAN OR EQUAL

TO 15 MILLISECONDS TO EFFECTIVELY SUPPORT THE GOVERNMENT’S MISSION. THE GOVERNMENT

ACCEPTING AUTHORITY WILL CONFIRM THE RTD DURING THE TURN-UP AND TEST PHASE AND IF IT

DOES NOT ALIGN WITH THE CONTRACTORS PROPOSAL, DISA IE161 WILL NOTIFY DITCO IMMEDIATELY IN

WRITING

2 THIS REQUIREMENT MUST BE ENGINEERED AND PROVISIONED TOTALLY DIVERSE END TO END TO THE

GOVERNMENT'S SERVICE DELIVERY POINTS (SDP'S) FROM TSR RU30JUL206722; MEANING THAT THE

PHYSICAL PATHS ARE TOTALLY SEPARATE INCLUDING MAN HOLES, CONDUIT, (CENTRAL OFFICE

LOCATIONS), AND FIBER BUILDS. ADDITIONALLY, AS A MINIMUM MUST HAVE 50 METERS PHYSICAL

SEPARATION FROM RU30JUL206722.

***THE 50 METER SEPARATION IS WAIVED INSIDE BLDG 761 FOR THE FT SNELLING LOCATION.***

3. THE VENDOR MUST PROVIDE LIGHT LEVEL READINGS (SIGNAL STRENGTH IN DBM) ON THE

EXTENSION FROM COMMERCIAL POP TO THE GOVERNMENT SERVICE DELIVERY POINT (SDP) AT THE "A"

AND "Z" LOCATION PRIOR TO CIRCUIT TURN OVER TO THE GOVERNMENT ENSURING LEVELS ARE

WITHIN SPECS. LIGHT LEVELS MUST BE ADJUSTED TO -3 TO -9 DBM.

4. VENDOR MUST CONDUCT WALK-THROUGH SITE SURVEY PRIOR TO INSTALLATION AT THE "A" AND "Z"

LOCATIONS.

5. THE VENDOR MUST CONTACT DISA GOC IP BACKBONE ENGINEERING AND IMPLEMENTATION GROUP

UPON RECEIPT OF A VALID TSO TO ESTABLISH THE COORDINATION AND ACTIVATION PROCESS. PHONE:

(C) 618-418-8627, (D) 418-8627.

6. THE PROVIDER MUST CONDUCT A SATISFACTORY 24-HOUR TEST FROM THE DROP SIDE OF THEIR OR

LOCAL EXCHANGE CARRIERS FDP INSTALLED IN THEIR EQUIPMENT SUITE AT THE "A" LOCATION TO

THEIR OR LOCAL EXCHANGE CARRIERS FDP INSTALLED IN THEIR EQUIPMENT SUITE AT THE "Z"

LOCATION AND MUST INCLUDE THE EXTENSION BETWEEN THE COMMERCIAL DEMARC AND THE

GOVERNMENT'S SDP. VENDOR MUST ENSURE TEST SETS ARE PLACED AT THE DROP SIDE AT THE "A"

LOCATION AND AT THE "Z" LOCATION. TESTING MUST BE SATISFACTORY PRIOR TO TURN OVER TO THE

GOVERNMENT FOR ACCEPTANCE TESTING.

CIRCUIT REQUIRES THE FOLLOWING PARAMETERS:

A. FIBER TERMINATION: FRAME FORMAT: 10GB ETHERNET (OPTICAL HANDOFF-10GB ETHERNET-LAN-

PHY-SINGLE MODE FIBER), 1310NM. "SC" OR "LC" CONNECTORS AS DETERMINED BY SITE SURVEY.

NOTE: WHEN EXTENDED REACH OPTICS ARE USED THAT CHANGE THE TX/RX WAVELENGTH OF THE

OPTIC, THE VENDOR WILL NOTIFY THE GOVERNMENT 30 DAYS PRIOR TO DELIVERY.

B. COMMITTED INFORMATION RATE (CIR): 10GB

C. ETHERNET FRAME SIZE WILL BE CONFIGURED TO SUPPORT MAXIMUM TRANSMISSION UNIT (MTU)

OF 9000 OCTETS (BYTES) JUMBO FRAMES.

D. NO NETWORK INTERFACE UNIT, DEDICATED PATH

E. GFE CLOCKING: VENDOR ESFU (OR EQUIVALENT) NOT TO BE ENGINEERED INTO CIRCUIT.

F. TESTING CRITERIA: VENDOR MUST TEST THE CIRCUIT FOR 24 HOURS IAW THE FULL ITU-T.Y.1564

BENCH MARKING METHODOLOGY FOR NETWORK INTERCONNECT DEVICES STANDARD, AND AT THE

COMMITTED INFORMATION RATE (CIR) IAW ITU-T-Y.1564. NOTE: ETHERNET FRAME SIZE DESIGNATOR

'H' (MTU) IS EQUAL TO 9000 BYTES.

G. LINE MUST REMAIN FULLY OPERATIONAL AND AVAILABLE TO USERS 24 HOURS A DAY, SEVEN DAYS

PER WEEK, MONTHLY PERFORMANCE OF 99.5% AVAILABILITY OR BETTER.

H. 1 HOUR RESPONSE TIME TO RESPOND TO CUSTOMER UPON RECIEPT OF TROUBLE.

I. VENDOR REQUIRED TO HAVE CIRCUIT VISIBILITY TO ASSIST IN ANY CIRCUIT OUTAGES.

J. VENDOR MUST HAVE A 24X7 NETWORK OPERATIONS CENTER.

K. TELECOMM PROVIDER MUST MAINTAIN OPERATIONS, MAINTENANCE AND ADMINISTRATION

MONITORING OF ETHERNET CIRCUIT.

TEST & ACCEPTANCE INSTRUCTIONS:

1. VENDOR MUST PROVIDE:

A. VENDOR WINNING AWARD IS RESPONSIBLE FOR INSTALLATION AND MAINTENANCE OF THE SERVICE

IAW THE UNIQUE INSTALLATION FACTORS.

B. INSIDE WIRING IS AUTHORIZED IAW THE UNIQUE INSTALLATION FACTORS.

C. VENDOR MUST COORDINATE SITE VISIT WITH POC'S 72 HOURS IN ADVANCE PRIOR TO REQUIRING

ACCESS TO FACILITIES AT BOTH USER LOCATIONS.

2. ALL EQUIPMENT AND CIRCUIT PROBLEMS WILL BE REPORTED BY PHONE TO THE DISA GOC IP

BACKBONE ENGINEERING AND IMPLEMENTATION GROUP, SCOTT AFB, IL. PRIMARY: (C) 618-418-9950,

(D) 418-9950 TOLL FREE: 855-868-9950.

MINIMUM TECHNICAL SPECIFICATIONS: SPECIFIC FORMAT TO BE USED IS: LINE RATE: 10.3125

GIGABITS/S, +- 100 PPM LINE CODE: OPTICAL

1. TEST AND ACCEPTANCE: CIRCUITS SHALL PASS A FULLY DOCUMENTED SATISFACTORY 72 HOUR SOAK

TEST BY DISA GOC.

TESTING MUST BE SATISFACTORY PRIOR TO TURN OVER TO THE GOVERNMENT FOR ACCEPTANCE

TESTING. THE VENDOR MUST TEST THE CIRCUIT FOR 24 HOURS IAW THE FULL ITU-T.Y.1564 BENCH

MARKING METHODOLOGY FOR NETWORK INTERCONNECT DEVICES STANDARD, AND AT THE

COMMITTED INFORMATION RATE (CIR) IAW ITU-T-Y.1564.

2. ERROR PERFORMANCE: ERROR PERFORMANCE SHALL BE BETTER THAN THE FOLLOWING

PARAMETER THRESHOLDS TO BE ACCEPTABLE: AVAILABILITY SHALL BE GREATER THAN 99.5% OR

BETTER. FRAME LOSS SHALL BE EQUAL TO ZERO WHEN TESTING AT 10 GIGABIT HIGHEST FRAME RATE, AND SHALL MEET ITU-T-Y.1564 STANDARDS.

3. MEAN TIME TO LOSS OF BIT COUNT INTEGRITY (MTTLBCI) SHALL BE GREATER THAN 24 HOURS.

4 ROUND TRIP DELAY (RTD) FOR THIS DISA TRANSPORT TRUNK WILL BE MEASURED IN MILLISECONDS

FROM THE CUSTOMER'S SERVICE DELIVERY POINT (SDP) SITE-A TO THE CUSTOMER'S SERVICE

DELIVERY POINT (SDP) SITE-Z. THE RTD SHALL BE LESS THAN OR EQUAL TO 15 MILLISECONDS TO

EFFECTIVELY SUPPORT THE GOVERNMENT'S MISSION. THE GOVERNMENT ACCEPTING AUTHORITY

WILL CONFIRM THE RTD DURING THE TURN-UP AND TEST PHASE AND IF IT DOES NOT ALIGN WITH THE

CONTRACTORS PROPOSAL, DISA IE161 WILL NOTIFY DITCO IMMEDIATELY IN WRITING.

5. ROUND TRIP DELAY VARIANCE (JITTER) SHALL BE NO MORE THAN 3MS. DELAY SHALL BE BETTER THAN

10 MSEC.