CIRCUIT SPECIFICATIONS: QB138
1. TELECOMM PROVIDER MUST PROVIDE TOTAL FIBER MILES AND ROUND TRIP DELAY (RTD) FROM THE
CUSTOMER "A" LOCATION TO THE CUSTOMER "Z" LOCATION. THE RTD SHALL BE LESS THAN OR EQUAL
TO 10 MILLISECONDS TO EFFECTIVELY SUPPORT THE GOVERNMENT’S MISSION. THE GOVERNMENT
ACCEPTING AUTHORITY WILL CONFIRM THE RTD DURING THE TURN-UP AND TEST PHASE AND IF IT
DOES NOT ALIGN WITH THE CONTRACTORS PROPOSAL, DISA IE161 WILL NOTIFY DITCO IMMEDIATELY IN
WRITING
2. THIS REQUIREMENT MUST BE ENGINEERED AND PROVISIONED TOTALLY DIVERSE END TO END TO THE
GOVERNMENT'S SERVICE DELIVERY POINTS (SDP'S) FROM TSR RU30JUL206721; MEANING THAT THE
PHYSICAL PATHS ARE TOTALLY SEPARATE INCLUDING MAN HOLES, CONDUIT, (CENTRAL OFFICE
LOCATIONS), AND FIBER BUILDS. ADDITIONALLY, AS A MINIMUM MUST HAVE 50 METERS PHYSICAL
SEPARATION FROM RU30JUL206721.
**THE 50 METER SEPARATION IS WAIVED INSIDE BLDG 761 FOR THE FT SNELLING LOCATION.***
3. THE VENDOR MUST PROVIDE LIGHT LEVEL READINGS (SIGNAL STRENGTH IN DBM) ON THE XTENSION
FROM COMMERCIAL POP TO THE GOVERNMENT SERVICE DELIVERY POINT (SDP) AT THE "A" AND "Z"
LOCATION PRIOR TO CIRCUIT TURN OVER TO THE GOVERNMENT ENSURING LEVELS ARE WITHIN SPECS.
LIGHT LEVELS MUST BE ADJUSTED TO -3 TO -9 DBM.
4. VENDOR MUST CONDUCT WALK-THROUGH SITE SURVEY PRIOR TO INSTALLATION AT THE "A" AND "Z"
LOCATIONS.
5. THE VENDOR MUST CONTACT DISA GOC IP BACKBONE ENGINEERING AND IMPLEMENTATION GROUP
UPON RECEIPT OF A VALID TSO TO ESTABLISH THE COORDINATION AND ACTIVATION PROCESS. PHONE:
(C) 618-418-8627, (D) 418-8627.
6. THE PROVIDER MUST CONDUCT A SATISFACTORY 24-HOUR TEST FROM THE DROP SIDE OF THEIR OR
LOCAL EXCHANGE CARRIERS FDP INSTALLED IN THEIR EQUIPMENT SUITE AT THE "A" LOCATION TO
THEIR OR LOCAL EXCHANGE CARRIERS FDP INSTALLED IN THEIR EQUIPMENT SUITE AT THE "Z" OCATION
AND MUST INCLUDE THE EXTENSION BETWEEN THE COMMERCIAL DEMARC AND THE GOVERNMENT'S
SDP. VENDOR MUST ENSURE TEST SETS ARE PLACED AT THE DROP SIDE AT THE "A" LOCATION AND AT
THE "Z" LOCATION. TESTING MUST BE SATISFACTORY PRIOR TO TURN OVER TO THE GOVERNMENT FOR
ACCEPTANCE TESTING
1. CIRCUIT REQUIRES THE FOLLOWING PARAMETERS:
(A) VENDOR PROVIDED 10GB ETHERNET IP BACKBONE CIRCUIT BETWEEN THE DISA IE1 PROVIDED
JUNIPER MX-240 ROUTER (UJEWFSO040)
(B) FIBER TERMINATION: FRAME FORMAT: 10GB ETHERNET (OPTICAL HANDOFF-10GB ETHERNET-LAN-
PHY-SINGLE MODE FIBER), 1310NM. "SC" OR "LC" CONNECTORS AS DETERMINED BY SITE SURVEY.
NOTE: WHEN EXTENDED REACH OPTICS ARE USED THAT CHANGE THE TX/RX WAVELENGTH OF THE
OPTIC, THE VENDOR WILL NOTIFY THE GOVERNMENT 30 DAYS PRIOR TO DELIVERY
(C) COMMITTED INFORMATION RATE (CIR): 10GB
(D) ETHERNET FRAME SIZE WILL BE CONFIGURED TO SUPPORT MAXIMUM TRANSMISSION UNIT (MTU)
OF 9000 OCTETS (BYTES) JUMBO FRAMES.
(E) NO NETWORK INTERFACE UNIT, DEDICATED PATH
GFE CLOCKING: VENDOR ESFU (OR EQUIVALENT) NOT TO BE ENGINEERED INTO CIRCUIT.
(F) TESTING CRITERIA: VENDOR MUST TEST THE CIRCUIT FOR 24 HOURS IAW THE FULL ITU-T.Y.1564
BENCH MARKING METHODOLOGY FOR NETWORK INTERCONNECT DEVICES STANDARD, AND AT THE
COMMITTED INFORMATION RATE (CIR) IAW ITU-T-Y.1564. NOTE: ETHERNET FRAME SIZE DESIGNATOR
'H' (MTU) IS EQUAL TO 9000 BYTES
(G) LINE MUST REMAIN FULLY OPERATIONAL AND AVAILABLE TO USERS 24 HOURS A DAY, SEVEN DAYS
PER WEEK, MONTHLY PERFORMANCE OF 99.5% AVAILABILITY OR BETTER
(H) 1 HOUR RESPONSE TIME TO RESPOND TO CUSTOMER UPON RECIEPT OF TROUBLE.
(I) VENDOR REQUIRED TO HAVE CIRCUIT VISIBILITY TO ASSIST IN ANY CIRCUIT OUTAGES.
(J) VENDOR MUST HAVE A 24X7 NETWORK OPERATIONS CENTER.
(K) TELECOMM PROVIDER MUST MAINTAIN OPERATIONS, MAINTENANCE AND ADMINISTRATION
MONITORING OF ETHERNET CIRCUIT.
TEST & ACCEPTANCE INSTRUCTIONS:
1. VENDOR MUST PROVIDE:
A. VENDOR WINNING AWARD IS RESPONSIBLE FOR INSTALLATION AND MAINTENANCE OF THE SERVICE
IAW THE UNIQUE INSTALLATION FACTORS.
B. INSIDE WIRING IS AUTHORIZED IAW THE UNIQUE INSTALLATION FACTORS.
C. VENDOR MUST COORDINATE SITE VISIT WITH POC'S 72 HOURS IN ADVANCE PRIOR TO REQUIRING
ACCESS TO FACILITIES AT BOTH USER LOCATIONS.
2. ALL EQUIPMENT AND CIRCUIT PROBLEMS WILL BE REPORTED BY PHONE TO THE DISA GOC IP
BACKBONE ENGINEERING AND IMPLEMENTATION GROUP.
MINIMUM TECHNICAL SPECIFICATIONS: SPECIFIC FORMAT TO BE USED IS: LINE RATE: 10.3125
GIGABITS/S, +- 100 PPM LINE CODE: OPTICAL
1. TEST AND ACCEPTANCE: CIRCUITS SHALL PASS A FULLY DOCUMENTED SATISFACTORY 72 HOUR SOAK
TEST BY DISA GOC.
TESTING MUST BE SATISFACTORY PRIOR TO TURN OVER TO THE GOVERNMENT FOR ACCEPTANCE
TESTING. THE VENDOR MUST TEST THE CIRCUIT FOR 24 HOURS IAW THE FULL ITU-T.Y.1564 BENCH
MARKING METHODOLOGY FOR NETWORK INTERCONNECT DEVICES STANDARD, AND AT THE
COMMITTED INFORMATION RATE (CIR) IAW ITU-T-Y.1564.
2. ERROR PERFORMANCE: ERROR PERFORMANCE SHALL BE BETTER THAN THE FOLLOWING
PARAMETER THRESHOLDS TO BE ACCEPTABLE: AVAILABILITY SHALL BE GREATER THAN 99.5% OR BETTER. FRAME LOSS SHALL BE EQUAL TO ZERO WHEN TESTING AT 10 GIGABIT HIGHEST FRAME RATE, AND SHALL MEET ITU-T-Y.1564 STANDARDS.
3. JITTER SHALL BE LESS THAN 3 MSEC. DELAY SHALL BE BETTER THAN 10 MSEC.
4. MEAN TIME TO LOSS OF BIT COUNT INTEGRITY (MTTLBCI) SHALL BE GREATER THAN 24 HOURS.
5. ROUND TRIP DELAY (RTD) FOR THIS DISA TRANSPORT TRUNK WILL BE MEASURED IN MILLISECONDS
FROM THE CUSTOMER'S SERVICE DELIVERY POINT (SDP) SITE-A TO THE CUSTOMER'S SERVICE
DELIVERY POINT (SDP) SITE-Z. THE RTD SHALL BE LESS THAN OR EQUAL TO 10 MILLISECONDS TO
FFECTIVELY SUPPORT THE GOVERNMENT'S MISSION. THE GOVERNMENT ACCEPTING AUTHORITY
WILL CONFIRM THE RTD DURING THE TURN-UP AND TEST PHASE AND IF IT DOES NOT ALIGN WITH THE
CONTRACTORS PROPOSAL, DISA IE161 WILL NOTIFY DITCO IMMEDIATELY IN WRITING.