Chapel Building Photos.pdf
PDF 527 KB Posted
- Solicitation number
- RFQ - 171 - 240000000322
- Issued by
- Jackson County, Michigan
About this file
The document provided contains pre-design photos of the Chapel Building at the Parnall Correctional Facility Phase 400 project in Michigan. The file details various aspects of the existing chapel building, including the roof slope, construction materials, and electrical components. The related state and local contract opportunity is for the Parnall CF - Bldgs 16 and 53 Roof Restoration, which is being managed by the Michigan Department of General Services Administration (GSA). The contract seeks bids for the roof restoration work, with a deadline for bid submissions of 2:00 pm. The contract specifications and requirements are provided through SIGMA VSS, the State of Michigan's procurement platform, and all questions should be directed to the designated contract specialist.
The contract opportunity does not provide details on pricing terms, set-asides, incumbent contractors, funding sources, or other salient commercial information. The focus of the document is on the technical details of the existing chapel building and the requirements for the roof restoration project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Parnall Correctional Facility Phase 400 – Pre-Design Photos
Appendix A– Chapel Building Roof Photos
Report No. M2163.01-032 Date 3-30-23 Page 1 of 2
1. Chapel Building. General View. Shingles with 9 inch per foot roof slope.
2. Chapel Building. Typical north and south door overhang.
3. Chapel Building. Double tongue in groove wood plank decking. Measured at ~2 5/8” thick. Glulam beams supporting plank are approximately 13 feet on center.
4. Chapel Building. Double tongue in groove wood deck,
5.5 inches side to side.
5. Chapel Building. Near the SE corner there is a reglet cut into stone. This condition only happens for about ten feet of wall.
6. Chapel Building. The low sloped roof ties into the shingles at this one edge.
Photographs 1-6
Parnall Correctional Facility Phase 400 – Pre-Design Photos
Appendix A– Chapel Building Roof Photos
Report No. M2163.01-032 Date 3-30-23 Page 2 of 2
7. Chapel Building. The rake edge is 6 inches in size.
8. Chapel Building. When measured from back side the bottom of the double tongue in groove is 3 inches above the rake.
9. Chapel Building. Inside view. Wood Glulam beams at
13 feet on center. The double tongue and groove wood is directly on the Glulam Beams. There is no soffit or ridge venting provided. No insulation in roof system.
10. Chapel Building. Somehow electrical service is within the roof system. The assumption is that a channel cut was made on the top side of the double tongue in groove to lay conduit for the lights.
11. Chapel Building. Close up view of 5/8” to 3/4” conduit coming down from the deck.
12. Chapel Building. View of steeple. The bottom portion of the steeple appears to be a metal flashing shroud that can be removed and replaced in like kind following reroofing.
Photographs 7-12