This is a Request for Information (RFI) issued by the United States Coast Guard seeking market research on qualified U.S.-based Vessel Construction Managers (VCMs) and shipyards capable of supporting the design, construction, testing, and delivery of an 8,000 long-ton capacity floating drydock (FDD) before calendar year 2030. The Government anticipates awarding a Firm-Fixed-Price contract to a prime VCM who will partner with a qualified domestic shipyard. The FDD must be constructed and launched as a fully assembled, monolithic single-section unit in compliance with domestic-content and Made in America requirements, with construction to occur under American Bureau of Shipping (ABS) survey and classification based on a Government-furnished contract design.

The RFI specifies estimated FDD characteristics including 516 feet overall length, 124.04 feet width, 5,930 long tons lightweight, and 8,000 long tons rated lift capacity. The key construction constraint prohibits sectional construction, launching in sections, or post-launch assembly using splice plates. The Government's notional acquisition schedule includes Draft RFP release in January 2027, Industry Day in February 2027, RFP release in June 2027, contract award in November 2027, construction period from January 2028 through October 2029, and delivery to USCG Yard in Baltimore, Maryland by December 2029. Responses are due by 2:00 PM ET on Wednesday, December 2, 2026, submitted via email to Contracting Officer Christopher Katz and Contract Specialists Liessel Ampie and Karyn Waters. The RFI requests information on VCM experience, shipyard selection approach, rough-order-of-magnitude pricing, production design and ABS classification procedures, transportation and delivery plans, risks, warranty terms, and shipyard capabilities including build area, waterfront access, launching capability, and schedule availability. NAICS Code 336611 (Ship Building and Repairing) and PSC Code 1950 (Floating Dry Docks) apply.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES COAST GUARD

REQUEST FOR INFORMATION (RFI)

Title: Request for Information: U.S. Shipyard and Vessel Construction Manager Capability for Floating

Drydock Construction

RFI Number: CG-SEA-C11-FDD-RFI-2027

Date Issued: 18NOV2026

Response Due Date: 02DEC2026

Point of Contact

Program Manager: Annie Simon, Email: Anne-Marie.Simon@uscg.mil

Contracting Officer: Christopher Katz, Email: Christopher.A.Katz2@uscg.mil

Contract Specialists: Liessel Ampie, Email: Liessel.Ampie@uscg.mil

Karyn Waters, Email: Karyn.L.Waters@uscg.mil

NAICS Code: 336611, Ship Building and Repairing

PSC Code: 1950, Floating Dry Docks

THIS IS A REQUEST FOR INFORMATION (RFI) ONLY. THIS RFI IS ISSUED SOLELY

FOR INFORMATION AND PLANNING PURPOSES AND DOES NOT CONSTITUTE A

SOLICITATION. RESPONSES TO THIS NOTICE ARE NOT OFFERS AND CANNOT BE

ACCEPTED BY THE GOVERNMENT TO FORM A BINDING CONTRACT.

1. Description

The United States Coast Guard (USCG) Surface Domain Assistant Commandant and Program Executive Office Surface Acquisitions, is conducting market research to identify qualified U.S.-based shipyards and Vessel Construction Managers (VCMs) capable of supporting the detailed production design, construction, testing, and delivery of a new 8,000 long-ton capacity floating drydock (FDD) before calendar year 2030. The Government anticipates awarding a Firm-Fixed- Price contract through a prime VCM, who will partner with a qualified domestic shipyard to execute the build under American Bureau of Shipping (ABS) survey and classification based on a Government-furnished contract design. To meet rigorous structural and operational standards, the FDD must be constructed and launched as a fully assembled, monolithic single-section unit in full compliance with applicable domestic-content and Made in America requirements.

2. Purpose

The USCG seeks information from:

1. VCMs capable of managing FDD construction, including shipyard proposal coordination, subcontractor integration, quality oversight, transportation, delivery, warranty administration, and associated project risk management.

2. U.S. shipyards capable of constructing and launching the FDD as a fully assembled, one-piece unit.

3. Program Overview

The Government anticipates awarding a fixed-price commercial contract to a single VCM. The selected VCM would propose a confirmed U.S. shipyard as part of its proposal.

A contract design and specification package are currently under development with the USCG’s Design Agent. The design will be reviewed by ABS and will be provided with the Request for Proposal (RFP). The selected VCM is to oversee the shipyard’s development of the production-level design, including a three-dimensional model and detailed production drawings, based on the Government-furnished design and specification.

The FDD shall be built under ABS survey and is required to achieve ABS classification.

Construction must occur in the United States and comply with applicable domestic-content and Made in America requirements. Respondents should independently review and account for all applicable statutory and regulatory requirements.

4. Estimated Floating Drydock Characteristics

The following characteristics are provided for market research purposes and are subject to refinement during design development. For access to preliminary general arrangement drawings, please contact the contracting officer.

Characteristic Estimated Requirement

Overall length 516 feet, including communications bridge in closed position and end fender

Overall width 124.04 feet, including mooring tees and pedestrian gangway platform

Pontoon dimensions 492 feet long × 114 feet wide × 52 feet high

Pontoon depth 12.5 feet at centerline; 12 feet at sides

Wingwalls 12 feet wide each

Dock lightweight, including blocks 5,930 long tons

Estimated steel weight 4,845 long tons at current design maturity

Frame spacing 2 feet

Rated lift capacity 8,000 long tons

Configuration One-piece; non-self-propelled

Classification ABS

Electrical power Shore-supplied electric power

Ballast system 16 ballast tanks, each with a 35-horsepower submersible pump and associated valves

Additional tanks Four centerline void tanks and cross-connect tunnel

Maintenance pit 36 feet × 40.67 feet × 4 feet deep

Other systems/features

Industrial wastewater collection system; dry firemain system; control house; communications bridge at inshore end consisting of two sections;

fixed mooring system with three guides and three grippers; vessel-handling trolley system with two tracks and six trolleys

Access infrastructure 122-foot pedestrian gangway; 56-foot × 16.5-foot vehicle bridge

5. Key Construction Constraint

The FDD must be constructed and launched as a fully assembled, single-section drydock.

The Government does not anticipate accepting an approach in which the dock is:

• Constructed in separate sections and assembled afloat;

• Launched in sections and subsequently connected; or

• Assembled after launch using splice plates or similar connections.

6. Notional Acquisition Schedule

The Government’s current planning milestones are:

Milestone Estimated Date

Draft RFP January 2027

Industry Day for shipyards and VCMs February 2027

RFP release June 2027

Contract award November 2027

Anticipated construction period January 2028–October 2029

Delivery to USCG Yard, Baltimore, Maryland December 2029

*These dates are planning estimates only and may change.

7. Requested Information: Vessel Construction Managers

The following questions are primarily for VCMs. Shipyards may provide comments as applicable.

1. Interest and Relevant Experience

• Confirm the company’s interest in competing for this requirement.

• The USCG is planning to include a mandatory experience requirement for VCMs to have managed the construction of documented vessel that was delivered within the last 7 years.

The vessel must be of comparable size, scope or complexity to the FDD. Provide evidence to support this requirement.

2. VCM’s Shipyard Selection and Teaming Approach

• The USCG is planning to include a mandatory requirement for the VCM’s proposal to include a subcontracted U.S. shipyard capable of building and launching the FDD in a one-piece configuration. Describe how your company would identify, evaluate, and secure a qualified shipyard before proposal submission.

• Identify how the relationship/agreement between the VCM and the shipyard could be secured and documented and how construction will be included as a firm fixed price in the proposal.

• Identify risks, challenges or concerns associated with the VCM/shipyard partnership and any contractual considerations for the prime contract.

3. Rough-Order-of-Magnitude Cost and Payment Approach

• Provide a non-binding ROM price for any costs outside of construction and a general breakdown to provide insight into VCM services (for the duration of the project), transportation and temporary storage. Identify the assumed scope, principal cost drivers, exclusions, contingencies, and other estimate assumptions.

• Identify any preferences for commercial payment schedules or CLIN structure and the basis for the recommendation.

4. Production Design and ABS Classification

• Describe how your company would integrate the USCG Design Agent as the post-design support and production-design validation agent. Identify risks, challenges or concerns associated with the VCM/USCG Design Agent relationship for design consultation.

• Describe how your company would arrange or manage design reviews, design changes and issue resolution.

• Describe how your company will ensure ABS classification can be achieved and how you will complete operational testing/verification.

5. Transportation, Delivery, Installation and Storage

• The VCM will be required to transport, deliver and install the non-self-propelled FDD at the USCG Yard in Baltimore, MD. Describe how you would plan and manage transportation, delivery and installation at the USCG Yard.

• Describe any geographical considerations that would influence shipyard selection.

• Describe how you would manage and oversee temporary storage, preservation, maintenance, security and insurance if site readiness or acceptance is delayed.

• Identify significant transportation, delivery, or storage risks and recommended mitigations.

6. Risks, Warranty, and Other Feedback

• Identify primary areas of concern that may impose risk and recommended mitigations.

• Describe standard warranty terms and conditions the VCM would anticipate offering.

• Provide any additional feedback that your company would like to share.

8. Requested Information: U.S. Shipyards

The following questions are primarily for U.S. shipyards. VCMs may provide comments as applicable.

1. Interest, Capability, and Schedule Availability

• Confirm your company’s interest in supporting this requirement.

• Confirm your company’s capability to construct, handle and launch the FDD as a fully assembled, one-piece unit. Include available build area, facilities, waterfront access, lifting or transfer capability, launch method, and any dimensional or weight limitations.

• Identify any anticipated subcontracted work or offsite fabrication and explain how it would support the required construction approach.

• Considering current workload, facilities, labor, and material availability, state whether your company could support the anticipated construction period of January 2028 through October 2029.

• Schedule is of high importance to align with strategic major cutter capability upgrades for waterfront construction and dredging. Identify the earliest practical construction start date and estimated overall construction duration given the planned contract award date.

2. Rough-Order-of-Magnitude Cost

• Provide a non-binding ROM price or price range for FDD construction.

• Identify the principal assumptions, exclusions, schedule assumptions, escalation considerations, and major cost drivers supporting the estimate.

• Identify information that would be needed to develop a more refined estimate.

• Identify approximate hours and personnel required to complete construction and operational testing.

3. Relevant Experience and Workforce

• Describe relevant experience building floating drydocks, large marine structures, barges, vessels, or projects of similar size and complexity. For relevant projects, provide the project type, approximate size, customer type, and completion status or delivery date.

• Provide a high-level description of available engineering, production, trade, and subcontractor capacity.

4. VCM Teaming and Contracting Considerations

• State how the shipyard would establish agreements or contracts in support of this requirement. Identify nature of teaming to one or multiple VCMs and identify any associated concerns.

• Describe any experience working under a VCM-led construction model.

• Identify considerations or concerns the Government should address in structuring the relationship among the Government, VCM, shipyard, and design support agent.

5. Risks, Warranty, and Other Feedback

• Identify primary areas of concern that may impose risk and recommended mitigations.

• Describe standard warranty terms and conditions the shipyard would anticipate offering.

• Provide any additional feedback that your company would like to share.

9. Recommended Response Instructions

• Response format: PDF, no page limit.

• Submission deadline: Wednesday, 02 December 2026 by 2:00pm ET.

• Submission method: Responses via email to the Contracting Officer, Christopher Katz at Christopher.A.Katz2@uscg and to the Contract Specialists Liessel Ampie and Karyn Waters at Liessel.Ampie@uscg.mil and Karyn.L.Waters@uscg.mil.

• Point of contact: Include name, title, business email, telephone number, company name, facility location(s), business size in NAICS 336611 and CAGE/UEI, if available.

• Proprietary information: Clearly mark proprietary or business-sensitive information.

The Government will handle submissions in accordance with applicable law and policy but cannot guarantee that all information will be exempt from disclosure.

• Industry Day: Interested parties should indicate whether they intend to participate in the anticipated February 2027 Industry Day.

10. System for Award Management Registration

Interested parties, including entities not currently doing business with the Federal Government, should ensure they are registered in the System for Award Management (SAM) at SAM.gov.

Registration instructions are available through the Federal Service Desk (https://www.fsd.gov/gsafsd_sp/en/entity-registration-how-do-i-register-a-new-entity-or-obtain-a-new-unique?id=kb_article_view&sysparm_article=KB0038643). Firms requiring assistance with SAM registration may also contact Liessel Ampie at Liessel.Ampie@uscg.mil.

mailto:Christopher.A.Katz2@uscg mailto:Liessel.Ampie@uscg.mil mailto:Karyn.L.Waters@uscg.mil https://www.fsd.gov/gsafsd_sp/en/entity-registration-how-do-i-register-a-new-entity-or-obtain-a-new-unique?id=kb_article_view&sysparm_article=KB0038643 https://www.fsd.gov/gsafsd_sp/en/entity-registration-how-do-i-register-a-new-entity-or-obtain-a-new-unique?id=kb_article_view&sysparm_article=KB0038643 mailto:Liessel.Ampie@uscg.mil

File details come from the government source that posted it. Updated .