This is a Statement of Work (SOW) for the supply and delivery of Spirax Sarco steam trap components for the USCGC HEALY (WAGB 20), a U.S. Coast Guard icebreaker. The contract, identified as PR #52000PR260027750, was last updated on April 2, 2026.

The SOW specifies four required parts to be supplied: 18 units of Spirax Sarco Universal Connectors (Model PC20, ½" IPS with blowdown, Part #67980); 12 units of Spirax Sarco Model UFT32-4.5 Universal Float & Thermostatic Steam Traps in stainless steel rated at PMO65 PSI (Part #1465300); 6 units of Spirax Sarco Model UBP32 Universal Balanced Pressure Thermostatic Steam Traps in stainless steel with Near to Steam Capsule 7F rated at PMO 464 PSI (Part #1270900); and 1 unit of Spirax Sarco Model VB-VS Combination Vacuum Breaker Balanced Pressure Air Vent 1/2" NPT (Part #72147). These components are essential for the ship's steam heating system, which enables extended operations and scientific research capabilities in Arctic climates. All items must be delivered to SFLC PE Staff in Seattle, Washington (1519 Alaskan Way S., Seattle, WA 98134, ATTN: HEALY DS FY27). Inquiries regarding this SOW should be directed to Derek Raymond at derek.k.raymond@uscg.mil.

View the file

Other files

File Type Posted
FAR CLAUSES FOR SUPPLY.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PR #: 52000PR260027750

STATEMENT OF WORK

LAST UPDATED: 04/02/2026 PAGE 1/1

STATEMENT OF WORK (SOW)

FOR

CGC Healy Spirax Sarco Steam Traps

1.0 SCOPE

This contract specifically addresses supply and delivery of multiple steam traps throughout USCGC HEALY (WAGB 20), providing steam for heating the ship, supporting HEALY’s ability to operate for extended periods and perform scientific research in Arctic climates. Timely completion of this maintenance is critical to ensure the cutter remains fully operational and can successfully execute all assigned missions.

2.0 OBJECTIVE

The objective of this contract is for the supply and delivery of the stated items to the stated address below.

3.0 REQUIRED PARTS

Qty Part # Description

18 67980 Spirax Sarco Universal Connector, Model PC20, ½” IPS with blowdown

12 1465300

Spirax Sarco Model UFT32-4.5 Universal Float & Thermostatic Steam Trap, Stainless Steel, PMO65

PSI

6 1270900

Spirax Sarco Model UBP32 Universal Balanced Pressure Thermostatic Steam Trap, Stainless Steel, with Near to Steam Capsule 7F PMO 464

PSI

1 72147

Spirax Sarco Model VB-VS Combination Vacuum Breaker Balanced Pressure Air Vent 1/2” NPT

4.0 LOGISTICS

SFLC PE Staff - LCDR Josh Martin

ATTN: HEALY DS FY27

1519 Alaskan Way S.

Seattle, WA 98134

Please contact Derek Raymond at derek.k.raymond@uscg.mil with questions regarding this SOW.