This document contains a bid abstract for a federal contract opportunity to construct a boat shed on the Chicago Sanitary Ship Canal. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Chicago as number W912P6-20-C-0030. Seven contractors submitted bids by the deadline of September 18, 2020. The base work included mobilization, site improvements, construction of a pre-engineered storage building, utility coordination, and bonding. Three option periods provided additional details for interior partitions, plumbing facilities, fencing, and a temporary generator. Bid prices ranged from $1,607,000 to $2,481,631. The contract was awarded to Cora Jane Contractors LLC for $1,607,000 on September 30, 2020. The boat shed will be located on the Chicago Sanitary Ship Canal to serve as an electric fish dispersal barrier.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P6-20-B-0012 Fish Barrier Boat Shed 18 SEP 2020, 1500 hours 5 Amendments

CLIN SLIN DESCRIPTION Qty U/M Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount

0001 Base Work 0001 AA Mobilization 1 job $22,000.00 $22,000.00 50,000.00$ 50,000.00$ 10,321.00$ 10,321.00$ 54,979.00$ 54,979.00$ 50,000.00$ 50,000.00$ 130,000.00$ 130,000.00$ 45,000.00$ 45,000.00$ 417,289.00$ 417,289.00$ 0001 AB Demobilization 1 job $14,300.00 $14,300.00 20,000.00$ 20,000.00$ 10,231.00$ 10,231.00$ 33,229.00$ 33,229.00$ 10,000.00$ 10,000.00$ 18,250.00$ 18,250.00$ 10,000.00$ 10,000.00$ 5,084.00$ 5,084.00$ 0001 AC Site Improvements 1 job $14,100.00 $14,100.00 100,000.00$ 100,000.00$ 77,913.00$ 77,913.00$ 135,728.00$ 135,728.00$ 62,652.00$ 62,652.00$ 65,000.00$ 65,000.00$ 630,000.00$ 630,000.00$ 39,373.00$ 39,373.00$ 0001 AD Pre-Engineered Storage Building 1 job $1,069,300.00 $1,069,300.00 849,500.00$ 948,500.00$ 1,384,244.00$ 1,384,244.00$ 1,149,143.00$ 1,149,143.00$ 1,357,914.00$ 1,357,914.00$ 1,041,000.00$ 1,041,000.00$ 885,000.00$ 885,000.00$ 885,797.00$ 885,797.00$ 0001 AE Gravel Road 500 LF $148.60 $74,300.00 55.00$ 27,500.00$ 181.41$ 90,706.00$ $41.1020 20,551.00$ 50.00$ 25,000.00$ 140.00$ 70,000.00$ 136.00$ 68,000.00$ 61.46$ 30,730.00$ 0001 AF Utility Coordination 1 job $7,700.00 $7,700.00 10,000.00$ 10,000.00$ 42,785.00$ 42,785.00$ 2,500.00$ 2,500.00$ 5,000.00$ 5,000.00$ 24,000.00$ 24,000.00$ 50,000.00$ 50,000.00$ 1,120.00$ 1,120.00$ 0001 AG External Electrical 1 job $16,700.00 $16,700.00 10,000.00$ 10,000.00$ 127,205.00$ 127,205.00$ 9,016.00$ 9,016.00$ 57,500.00$ 57,500.00$ 10,000.00$ 10,000.00$ 50,000.00$ 50,000.00$ 2,800.00$ 2,800.00$ 0001 AH Performance and Payment Bond 1 lot $10,000.00 $10,000.00 11,000.00$ 11,000.00$ 29,163.00$ 29,163.00$ 6,439.00$ 6,439.00$ 19,490.00$ 19,490.00$ 18,500.00$ 18,500.00$ 36,000.00$ 36,000.00$ 16,000.00$ 16,000.00$

SUBTOTAL $1,228,400.00 1,177,000.00$ 1,772,568.00$ 1,411,585.00$ 1,587,556.00$ 1,376,750.00$ 1,774,000.00$ 1,398,193.00$ Option 1

0002 AA Demising Partitions 1 job $78,800.00 $78,800.00 59,500.00$ 59,500.00$ 80,092.00$ 80,092.00$ 66,319.00$ 66,319.00$ 40,000.00$ 40,000.00$ 60,000.00$ 60,000.00$ 109,000.00$ 109,000.00$ 65,408.00$ 65,408.00$ 0002 AB Bathroom Facilities 1 job $27,200.00 $27,200.00 8,000.00$ 8,000.00$ 56,700.00$ 56,700.00$ 6,050.00$ 6,050.00$ 27,870.00$ 27,870.00$ 45,000.00$ 45,000.00$ 59,500.00$ 59,500.00$ 5,600.00$ 5,600.00$ 0002 AC Slop Tub 1 job $4,300.00 $4,300.00 4,000.00$ 4,000.00$ 2,520.00$ 2,520.00$ 1,300.00$ 1,300.00$ 3,000.00$ 3,000.00$ 2,500.00$ 2,500.00$ 2,200.00$ 2,200.00$ 2,240.00$ 2,240.00$ 0002 AD Floor Drains 1 job $69,500.00 $69,500.00 4,000.00$ 4,000.00$ 10,080.00$ 10,080.00$ 11,400.00$ 11,400.00$ 9,000.00$ 9,000.00$ 7,500.00$ 7,500.00$ 8,800.00$ 8,800.00$ 16,800.00$ 16,800.00$ 0002 AE Boat Washout Station 1 job $115,000.00 $115,000.00 45,000.00$ 45,000.00$ 76,860.00$ 76,860.00$ 38,455.00$ 38,455.00$ 60,000.00$ 60,000.00$ 45,000.00$ 45,000.00$ 10,000.00$ 10,000.00$ 113,405.00$ 113,405.00$ 0002 AF Epoxy Floor Sealant 1 job $10,700.00 $10,700.00 50,000.00$ 50,000.00$ 52,731.00$ 52,731.00$ 33,200.00$ 33,200.00$ 48,000.00$ 48,000.00$ 38,500.00$ 38,500.00$ 50,000.00$ 50,000.00$ 37,184.00$ 37,184.00$ 0002 AG Septic Tank 1 job $26,800.00 $26,800.00 8,000.00$ 8,000.00$ 63,000.00$ 63,000.00$ 21,900.00$ 21,900.00$ 11,136.00$ 11,136.00$ 20,000.00$ 20,000.00$ 55,000.00$ 55,000.00$ 56,000.00$ 56,000.00$ 0002 AH Portable Water Storage Tank 1 job $33,700.00 $33,700.00 5,000.00$ 5,000.00$ 17,640.00$ 17,640.00$ 9,150.00$ 9,150.00$ 15,000.00$ 15,000.00$ 20,000.00$ 20,000.00$ 15,400.00$ 15,400.00$ 22,400.00$ 22,400.00$

0002 AJ

Bond 1.00 lot $1,300.00 $1,300.00 1,500.00 1,500.00 3,150.00 3,150.00 1,690.00 1,690.00 4,280.00 4,280.00 1,700.00 1,700.00 7,000.00 7,000.00 3,500.00 3,500.00

SUBTOTAL $367,300.00 185,000.00$ 362,773.00$ 189,464.00$ 218,286.00$ 240,200.00$ 316,900.00$ 322,537.00$ 0003 Option 2 - Fencing Work 0003 AA Existing Fence Demolition 1 job $10,000.00 $10,000.00 42,500.00$ 38,430.00$ 38,430.00$ 4,500.00$ 4,500.00$ 10,000.00$ 10,000.00$ 4,500.00$ 4,500.00$ 12,000.00$ 12,000.00$ 22,702.00$ 22,702.00$ 0003 AB New Non-Conductive Fence 900 LF $473.00 $425,700.00 90.00$ 81,000.00$ 63.00$ 56,700.00$ 78.388889$ 70,550.00$ 75.00$ 67,500.00$ 50.00$ 45,000.00$ 218.89$ 197,000.00$ 87.30$ 78,570.00$

0003 AC

Bond 1 lot $3,000.00 $3,000.00 1,500.00$ 2,940.00$ 2,940.00$ 675.00$ 675.00$ 1,550.00$ 1,550.00$ 400.00$ 400.00$ 5,970.00$ 5,970.00$ 900.00$ 900.00$

SUBTOTAL $438,700.00 125,000.00$ 98,070.00$ 75,725.00$ 79,050.00$ 49,900.00$ 214,970.00$ 102,172.00$ Option 3

0004 AA Temporary Generator 25 WKS $6,468.00 $161,700.00 4,740.00$ 118,500.00$ 9,828.00$ 245,700.00$ 1,600.00$ 40,000.00$ 4,400.00$ 110,000.00$ 5,115.00$ 127,875.00$ 3,000.00$ 75,000.00$ 11,195.52$ 279,888.00$

0004 AB

Bond 1 lot $2,000.00 $2,000.00 1,500.00$ 1,500.00$ 2,520.00$ 2,520.00$ 360.00$ 360.00$ 2,200.00$ 2,200.00$ 650.00$ 650.00$ 2,250.00$ 2,250.00$ 2,500.00$ 2,500.00$

SUBTOTAL $163,700.00 120,000.00$ 248,220.00$ 40,360.00$ 112,200.00$ 128,525.00$ 77,250.00$ 282,388.00$

TOTAL PRICE 2,198,100.00$ 1,607,000.00$ 2,481,631.00$ 1,717,134.00$ 1,997,092.00$ 1,795,375.00$ 2,383,120.00$ 2,105,290.00$

SAM active/WOSB SAM active/WOSB

19W132 Marino Court 1121 E. Main St., Ste. 220 9101 S. Baltimore Ave

SAM active/ WOSB Chicago, IL 60656 SAM active/WOSB

Itasca, IL 60143 SAM active/WOSB JV SAM active/WOSB JV

St. Charles, IL 60174 Chicago, IL 60617 SAM active/WOSB

Schwartz Excavating 7023 Willow Springs Rd., Ste 103

Countryside, IL 60525 3321 State Route 31

Direct Steel 8604 W. Catalpa Ave, Ste 907

Foundation Mechanics

Crystal Lake, IL 60012 Chicago, IL 60607 Bid opening date/time:

Solicitation No.:

Title: JA Watts Inc.

940 W. Adams St., Ste 400 Batir Partners JV CCC HoldingsCora Jane Contractors JV

IGE

CERTIFICATION:

I CERTIFY that all the bids recorded on this abstract of bids were opened and read and received in response to the above named Solicitation Number.

NAME AND TITLE OF CERTIFYING OFFICE

REGINA G. BLAIR, DISTRICT CHIEF OF CONTRACTING

SIGNATURE:___________________________________

DATE: ____________________________

Bid Abstract

2020-09-29T09:57:27-0500
BLAIR.REGINA.GAIL.1120858889

File details come from the government source that posted it. Updated .