Cedar_Springs_LiftStations_Sewer_Pumps_Specs_SOW_FINAL.docx
DOCX document 91 KB Posted
- Attached to
- Cedar Springs Sewer Lift Stations Construction
- Solicitation number
- 1240LT24Q0049
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to replace the sewer pumps and motors at two Cedar Springs lift station locations. The project requires removing a total of four existing sewer pumps and motors, and installing four new sewer pumps and motors. The work includes all necessary electrical and plumbing connections, as well as replacing the existing control panel weather-proof boxes. The project location is in the Flaming Gorge Ranger District of the Ashley National Forest in Utah. The contract duration is 150 calendar days for materials procurement and on-site work. Key submittals include construction schedule, quality control plan, and operation and maintenance manuals. Testing requirements include system pressure testing and demonstrating proper pump operation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1240LT24Q0049 a1.pdf | ||
| 1240LT24Q0049.pdf | ||
| Project Site Map.docx | DOCX document | |
| Daggett County Utah Wage Determination.txt | TXT text file | |
| ATTACHMENT_4_UpperLiftStation_PumpData.pdf | ||
| PHOTO_LOG_PDF.pdf | ||
| ATTACHMENT_3_UpperLiftStation_PumpCurve.pdf | ||
| ATTACHMENT_1_LowerLiftStation_PumpCurve.pdf | ||
| ATTACHMENT_2_LowerLiftStation_PumpData.pdf | ||
| Cedar_Springs_LiftStations_Sewer.Pumps.SOI_FINAL.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
SEWER PUMPS, MOTORS, VALVES REPLACEMENT -
CEDAR SPRINGS LIFT STATIONS
03/22/2024 – FINAL
SCOPE OF CONTRACT
This project work includes:
Remove a total of four (4) existing sewer pumps & motors & valve combinations, from two (2) existing lift station vaults at two (2) locations about ¼ mile apart.
Provide & install a total of four (4) new sewer pumps & motors & valve combinations at these two (2) vault locations.
Work to include all electrical and plumbing connections and appurtenances.
Work to include re-securing the existing control panel weather-proof boxes to the existing exterior supports; to include replacing the old, weathered wood with new wood of equal dimension and construction, and provide new anchoring hardware to secure the control panel weather-proof boxes to the new wood support panels (see attached PHOTO LOG).
See attached PHOTO LOG for photos and brief explanations of both the Lower Lift Station site and the Upper Lift Station site.
Work as described above and in attached Schedule of Items.
Existing pumps for removal/disposal are:
FloWay Pumps VTP, both 6 Stage and 3 Stage Pumps, both 10’-0” and 8’-0” OAL; with US Electrical Motors 1-phase 230V 15.0HP and 7.5 HP.
Provide & install four (4) new pumps & motors shall be:
0. Intended for Sewer Applications.
Lower Lift Station:
Semi-Open Impellers, Vertical Turbine
TYPE 6JOLL, 6 STAGE, 125 GPM
10’-0 ¾” O.A.L.
15 hp, 3450 RPM, 3 Phase, 230/460 V
SEE ATTACHMENTS
Upper Lift Station:
Semi-Open Impellers, Vertical Turbine
TYPE 6JOLL, 3 STAGE, 100 GPM
8’-0 ¾” O.A.L.
7.5 hp, 3450 RPM, 3 Phase, 230/460 V
SEE ATTACHMENTS
Pump and Motor shall meet the Dimensions, Specifications, and Pump Curve attached. Attachments are for the existing FlowWay Pumps and Motors that are to be removed and replaced (Attachments), or approved equal.
Provide & Install a new combination of 4-inch Swing Check Valve and a new 4-inch Gate Valve Wheel Operated, at both the Lower Lift Station and Upper Lift Station, at each of the Four(4) Pumps.
PROJECT LOCATION
The project is located in the Flaming Gorge Ranger District of the Ashley National Forest, Daggett County, Utah, approx. Latitude 40°, 54’, 36” N, Longitude109°, 26’, 53” W. It is located approximately 40 miles North of Vernal, UT and 33 miles South of Manila, UT.
The project may be accessed from US Highway 191. Then followed by Forest Road 183 (Cedar Springs Marina Road).
Forest Road 183 (Cedar Springs Marina Road) is a asphalt paved, 2 lane road. The distance on Cedar Springs Road is approximately ¼ mile to Upper Lift Station and another ¼ mile to Lower Lift Station.
Then followed by 2-track Access Road at both Upper Lift Station and Lower Lift Station, for a distance of approximately 200 feet at each site (see photos).
SITE INFORMATION AND LIMITATIONS
The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
Contractor will provide all materials and labor necessary to protect vegetation, trees, and ground whether wet or dry, from excessive damage during construction activities.
All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
Water is not available at the site for construction purposes. No other utilities are available at the site for construction purposes.
WORK CAMPS, STAGING AND STORAGE AREAS
Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers on site.
Overnight camping is not allowed on site.
INSPECTION OF WORKSITE
The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
START DATE
Summer 2024 Procurements; Fall 2024 On Site Replacement
CONTRACT TIME
150 Calendar Days; for materials procurements and on-site work
SPECIFICATIONS
The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
Section 011250 - Measurement and Payment Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 024100 - Waste Material Disposal Section 024102 - Removal And Disposal Of Structures And Obstructions Section 221103 - Plumbing Appurtenances Section 221310 - Packaged Sewer Pumps and Motors Systems Section 260500 - Common Work Results For Electrical Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 262726 - Wiring Devices
END OF SECTION C
April 202421
USDA FOREST SERVICE, R-4
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 011250 - MEASUREMENT AND PAYMENT
1. GENERAL
SUMMARY
Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
DETERMINATION OF QUANTITIES
The following measurements and calculations shall be used to determine contract quantities for payment.
For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
UNITS OF MEASUREMENT
Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
Acre: Make longitudinal and transverse measurements for area computations horizontally.
50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
Cubic Yard (CY): A measurement computed by one of the following methods:
Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
Each (EA): One complete unit, which may consist of one or more parts.
Gallons (GAL): The quantity shall be measured by any of the following methods:
Measured volume in container.
Metered volume by approved metering system.
Commercially package volume.
Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
Linear Foot (LF): Measurement of work along its length from point-to-point; parallel to the base or foundation. Do not measure overlaps.
Lump Sum (LS): One complete unit.
Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
Square Foot (SF): Measured on a plane parallel to the surface being measured.
Square Yard (SY): Measured on a plane parallel to the surface being measured.
Ton: Measured as a short ton consisting of 2,000 pounds.
METHOD OF MEASUREMENT
One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
As a result of changes in the work authorized by the CO.
As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PRODUCTS (NOT APPLICABLE)
EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
MEASUREMENT AND PAYMENT 011250-3
USDA FOREST SERVICE, R-4
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 011900 - MOBILIZATION
1. GENERAL
SUMMARY
This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
MEASUREMENT AND PAYMENT
The measurement shall be lump sum for mobilization. Payment shall be as follows:
Bond premiums will be reimbursed after receipt of the evidence of payment.
50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
Progress payments for mobilization and preparatory work shall be subject to retainage.
PRODUCTS (NOT USED)
EXECUTION (NOT USED)
END OF SECTION 011900
MOBILIZATION 011900-1
USDA FOREST SERVICE, R-4
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 013300 - SUBMITTAL PROCEDURES
1. GENERAL
SUMMARY
This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
See other specification section within this package for additional requirements on submittal.
SUBMITTAL PROCEDURES
Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
If intermediate submittal is necessary, process it in same manner as initial submittal.
Allow 14 days for processing each re-submittal.
No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
Identification: Place a permanent label or title block on each submittal for identification.
Indicate name of firm or entity that prepared each submittal on label or title block.
Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
Include the following information on label for processing and recording action taken:
Project name.
Date.
Name and address of Contractor.
Name of manufacturer.
Unique identifier, including revision number.
Number and title of appropriate Specification Section.
Drawing number and detail references, as appropriate.
If more than one item is shown on submittal sheet, identify item.
Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
MEASUREMENT AND PAYMENT
No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PRODUCTS
ACTION SUBMITTALS – (Submittals requiring CO approval) General: Prepare and submit Action Submittals required by individual Specification Sections.
Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
Mark each copy of each submittal to show which products and options are applicable.
Include the following information, as applicable:
Manufacturer's written recommendations.
Manufacturer's product specifications.
Manufacturer's installation instructions.
Manufacturer's catalog cuts.
Wiring diagrams showing factory-installed wiring.
Compliance with recognized trade association standards.
Compliance with recognized testing agency standards.
Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
Preparation: Include the following information, as applicable:
Dimensions.
Identification of products.
Fabrication and installation drawings.
Roughing-in and setting diagrams.
Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
Notation of dimensions established by field measurement.
Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
Samples: Prepare physical units of materials or products, including the following:
Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval) General: Prepare and submit Informational Submittals required by other Specification Sections.
Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
EXECUTION
GENERAL
Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
Submittals not required by the Contract Documents will not be reviewed and may be discarded.
Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
Requests for substitutions will only be considered if contractor submits the following:
Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution. Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive – additional submittals may be required by specific specifications:
TABLE 013000-1
| Spec. Section |
| Section Title |
| Subsection |
| Required Submittal |
| 013300 |
| Submittal Procedures |
| 2.1D |
| Construction Schedule |
| 014100 |
| Quality Control |
| 1.3 A |
| Contractor Quality Control Plan |
| 014100 |
| Quality Control |
| 1.3 D |
| As-Built Red-Line Drawings |
| 221103 |
| Plumbing Appurtenances |
| 1.2A |
| Product Data |
| 221103 |
| Plumbing Appurtenances |
| 1.2B |
| Operation & Maintenance Data |
| 221310 |
| Packaged Sewer Pumps and Motors |
| 1.4A |
| Product Data |
| 221310 |
| Packaged Sewer Pumps and Motors |
| 1.4B |
| Shop Drawings |
END OF SECTION 013300
SUBMITTAL PROCEDURES 013300-5
USDA FOREST SERVICE, R-4
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 014100 - QUALITY CONTROL
1. GENERAL
SUMMARY
This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
QUALITY CONTROL
The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
Testing agency will re-test and re-inspect corrected work.
Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
SUBMITTALS
Contractor Quality Control Plan Permits, Licenses, and Certificates Test and Inspection Reports As-Built Drawings
MEASUREMENT AND PAYMENT
No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PRODUCTS (Not Applicable)
EXECUTION
QUALITY CONTROL SYSTEM
General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
CONTRACTOR QUALITY CONTROL PLAN
At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
The Government reserves the right to require changes in the plan during the contract period as necessary.
No change in the approved plan may be made without written concurrence by the Contracting Officer.
At a minimum, the plan shall include the following:
A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
Methods of performing, documenting, and enforcing quality control of all work.
Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
TEST AND INSPECTION REPORTS
Submit three copies of complete test results no later than three calendar days after the test was performed.
Submit failing test results and proposed remedial actions within four hours of noted deficiency.
Testing and Inspection Reports shall include the following:
Date of issue.
Project title and number.
Name, address, and telephone number of testing agency.
Dates and locations of samples, tests, or inspections.
Names of individuals performing tests and inspections.
Reference Specification Section(s).
Complete test or inspection data.
Test and inspection results and an interpretation of test results.
Ambient conditions at time sample was taken, tested, or inspected.
Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
Name and signature of laboratory inspector.
Recommendations on retesting and reinspecting.
PERMITS, LICENSES, AND CERTIFICATES
For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
AS-BUILT DRAWINGS
The Contractor shall maintain a set of the contract drawings depicting as-built conditions. These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
| 221300 |
| 3.10 |
| Pressurized Sewer Pressure Test |
| See Spec. |
| 221300 |
| 3.11B |
| Leakage Test |
| Until Passing |
| 221300 |
| 3.11C |
| System Test |
| Until Passing |
END OF SECTION 014100
QUALITY CONTROL 014100-3
USDA FOREST SERVICE, R-4
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 024100 - WASTE MATERIAL DISPOSAL
1. GENERAL
SUMMARY
This Section includes the loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.
MEASUREMENT AND PAYMENT
There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.
PRODUCTS – NOT APPLICABLE
EXECUTION
WASTE MATERIAL TO BE HAULED TO A DISPOSAL AREA
All excavated material not used in the construction of embankments or backfilling of trenches, or other excess material resulting from the excavation and embankment operation shall be hauled to a disposal area.
All unsuitable excavated material and oversize boulders shall be hauled to a disposal area.
All stumps, slash and other clearing and grubbing debris shall be hauled to a disposal area.
Disposal Area: All waste material above shall be hauled to the disposal area on Government property as designated by the Contracting Officer.
Waste material shall be piled and compacted to form a dense layer.
The size and shape of the piled waste material shall be designated by the Contracting Officer.
The piled material shall be covered with soil to a uniform depth of six inches minimum and sloped to 2:1 or flatter.
The disposal site shall be left suitable for seeding.
WASTE MATERIAL TO BE HAULED TO A LANDFILL
All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed off of Government property in an approved landfill.
The contractor is responsible for all costs and permits associated with landfill disposal.
The Government is not responsible for waste material upon its departure from the project site.
END OF SECTION 024100
WASTE MATERIAL DISPOSAL 024100-2
USDA FOREST SERVICE, R-4
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 221103 - PLUMBING APPURTENANCES
1. GENERAL
SUMMARY
This section includes piping, fittings, valves, gauges, backflow preventers, flowmeters and other plumbing devices within utility boxes or at other designated locations.
Related sections include the following:
Section 133402 “Utility Box.”
Section 260500 “Common Work Results for Electrical.”
SUBMITTALS
Product Data: For the following:
Air and vacuum valves.
Check valves Flow meters.
Operation and Maintenance Data: To be used in emergency, operation, and maintenance manuals. Include the data for the following:
Air and vacuum valves.
Check valves Flow meters.
MINIMUM SYSTEM REQUIREMENTS
Unless otherwise noted, the minimum working pressure for piping and specialty valves and devices shall be 160 psig.
MEASUREMENT AND PAYMENT
There will be no separate measurement or payment for work in this Section. Plumbing Appurtenances is considered incidental to other items of work shown in the Schedule of Items.
PRODUCTS
GENERAL
All plumbing appurtenances shall be new and unused, of the type, pressure rating or class, and size specified and as show on the Drawings.
FLOW METER
Description: Electromagnetic flow meter, with no moving parts, Class 1, Division 1, NEMA 4X/6P enclosure, CSA Certified, suitable for operation at 6100’, with flanged ends.
Size: 3-inch.
Pressure Rating: 150 psig.
Model: M4000 as manufactured by Badger Meter, Inc. or an approved equal.
PLUG VALVE
Description: Eccentric plug valve, with flanged ends.
Size: 3-inch.
Pressure Rating: 175 psig.
Model: #5803RN as manufactured by Val-matic Valve and Manufacturing Corp. or an approved equal.
CHECK VALVE
Description: Swing-flex check valve, full flow body type, ANSI/AWWA C508, with flanged ends.
Size: 3-inch.
Pressure Rating: 250 psig.
Model: Model #503A as manufactured by Val-matic Valve and Manufacturing Corp. or an approved equal.
WASTEWATER COMBINATION AIR VALVE
Description: AWWA C512, with flanged ends and exterior universal alkyd primer, suitable for use with wastewater.
Size: 3-inch.
Pressure Rating: 150 psig.
Model: Series 800 or 48A/300 as manufactured by Val-Matic Valve and Manufacturing Corp. or an approved equal.
PIPE AND FITTINGS
Ductile Iron: According to Section 221300 “Onsite Wastewater Treatment Systems.”
ELECTRICAL DISTRIBUTION SYSTEM
According to Section 260500 “Common Work Results for Electrical.”
SUPPORTS FOR PIPES AND APPURTENANCES
Description: Galvanized steel framing system, pipe clamps and hangers.
Manufacturer: Unistrut Corporation or an approved equal.
EXECUTION
INSTALLATION
Install piping, fittings, valves, gauges, flow meters and other plumbing devices within utility boxes or at other locations according to the manufacturer’s written instructions and as indicated on the Drawings. Install so water can be drained from each appurtenance for winterization of the system.
COMBINATION AIR VALVE FOR PIPELINES INSTALLATION
Install combination air valve as shown on the Drawings. Support the air valve using pipe supports as specified in Part 2.
END OF SECTION 221103
PLUMBING APPURTENANCES 221103-3
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 221310 - PACKAGED SEWER PUMPS & MOTORS SYSTEMS
1. GENERAL
SUMMARY
The pumps and motors shall be the latest standard product of a supplier regularly engaged and having at least 5 years of experience in the production of packaged submersible pump systems. The equipment supplied under this section shall be manufactured and supplied by a single source supplier, capable of producing a complete pre-engineered, packaged, submersible, sewage pump system. The single supplier shall be responsible for all mechanical, structural, electrical and communication components, as well as on site supervision of the start-up services, training, submittals, operation and maintenance manuals, and all warranties related to the materials, equipment and the entire pumping system.
This Section includes the following:
Pipe, valves and fittings.
Wet Well.
Pumps.
Pump Controls and Disconnect Panel.
Related Sections include the following:
Section 024100 “Waste Material Disposal.”
Section 033020 “Concrete From Package Dry Mix For Minor Structures.”
Section 221300 “Onsite Wastewater Treatment Systems.”
Section 260500 “Common Work Results for Electrical.”
Section 312000 “Earthwork.”
DEFINITIONS
GSP: Galvanized Steel Pipe.
HDPE: High Density Polyethylene plastic.
NPWL: Non-potable waterline (includes sewerline).
PVC: Polyvinyl chloride plastic.
SUBMITTALS
Product Data: For the following:
Packaged submersible pump system, including:
All structures, electrical components, disconnect panels, and pumps.
All design calculations, volumes, and pump curves.
Pipe and fittings.
Shop/Fabrication Drawings: Include all components associated with the packaged submersible pump system.
Wet well.
Pumps.
Pump Controls and Disconnect Panel.
Coordination Drawings: Show piping, underground structures, and other utilities. Indicate size and invert elevations of piping and structures.
Operation and Maintenance Data. Include operation, maintenance manuals for the following:
Wet Well.
Pumps, including emergency operation manuals.
Control and Disconnect Panel.
Sewer Lift System Transition and Operation Plan During Construction: include a detailed plan for operation of the Sewer Lift System during construction and transitioning the systems from the existing to the new, shutdown procedures, proposed temporary bypasses, etc.
QUALITY ASSURANCE
All work is to be completed according to applicable Federal, State and Local codes.
QUALITY CONTROL
The single source lift system supplier shall furnish an onsite representative that will provide quality control during lift system installation.
PERFORMANCE REQUIREMENTS
Force-Main, Pressure-Piping Pressure Rating: At least equal to system operating pressure, but not less than 125 psig.
MEASUREMENT AND PAYMENT
Payment will be as listed for the following items:
Packaged Sewer Pumps and Motors: Lump Sum for the complete packaged system and all work within 8 feet of the pump and motor, new piping from wet well to valve vault and connections to existing gravity lines. This work includes furnishing and installing pumps, wet well, piping, valves, fittings, pump controls, disconnect panel, float assemblies, pump rails, and any incidentals necessary to complete the system.
Incidentals include the following: Core drilling the new wet wall, piping, pipe cutting, excavation and embankment.
PRODUCTS
PACKAGED SEWER PUMPS AND MOTORS SYSTEMS
The packaged system shall consist of the following integrated components:
Pumps Motors Incidentals Electrical Controls, Panels, and Connections Plumbing Controls, and Connections Other items listed under products may be provided by the packaged sewer pumps and motors system manufacturer or provided/constructed separately.
PUMPS and MOTORS and VALVES Pumps & Motors Pumps and Motors shall be:
Pump and Motor shall meet the Dimensions, Specifications, and Pump Curve attached. Attachments are for the existing FlowWay Pumps and Motors that are to be removed and replaced (SEE ATTACHMENTS).
Description: Vertical Turbine style pump, suitable for pumping wastewater and sewage with the following (SEE ATTACHMENTS):
Hardened stainless steel cutters Autocoupling.
Explosion proof motor.
Body: Cast iron with epoxy coating, corrosion resistant.
Mechanical Seals: Silicon Carbide.
Service Factor: 1.15.
Shaft: AISI 430 F.
Fasteners: Stainless Steel.
Capacity and Characteristics (Each Pump): (SEE ATTACHMENTS) Valves A combination of both a 4-inch Swing Check Valve and a new 4-inch Gate Valve Wheel Operated, at both the Lower Lift Station and Upper Lift Station, at each of the Four(4) Pumps.
Wood & Metal Exterior Support Panels:
REPLACE ALL WOOD FROM THE EXTERIOR SUPPORTS for each of the two (2) Support Panels for each of the two (2) Control Panel Weather-proof Boxes.
REPLACE ALL EXTERIOR ANCHORING HARDWARE to secure each of the two (2) weather-proof panel boxes to the new wood.
The existing metal supports for the control panels do not need to be replaced; only the wood & anchoring hardware needs to be replaced. (See PHOTO LOG).
Controllers, Electrical Devices, and Wiring: Installation requirements and electrical devices and connections are specified in Section 260500 “Common Work Results for Electrical.”
Control Panel: NEMA 3R.
The electrical service is single phase, 240/120 VAC.
Provide properly sized single phase to three phase converting variable frequency drive (VFD) for each motor and adjusted by manufacturer for this installation as part of the control panel.
The pumps, controls and floats shall be installed to alternate as lead/lag pumps., with both pumps being able to run simultaneously during peak flows.
DISTRIBUTION PIPES AND FITTINGS
Sewer Pipe and Fittings: Pressurized: Per Section 221300 “Onsite Water Treatment System."
MAINTENANCE ITEMS
In addition to the operation and maintenance manuals required in Part 1, provide specific maintenance schedules for all new equipment installed, including all mechanical parts in the valve vault. The contractor shall furnish equipment specific tools (if any) and enough spare parts to do routine maintenance all newly installed equipment for 5 years.
EXECUTION
EARTHWORK
Refer to Section 312000 “Earthwork” for excavating, trenching, bedding, and backfilling.
Stockpile topsoil for reuse in finish grading without intermixing with other excavated material. Stockpile materials away from edge of excavation and do not store within drip line of remaining trees.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
Excavating and Backfilling for Wet Well:
Excavate sufficient width and length for well to depth determined by inlet elevations. Provide level bottom.
Backfill with excavated soil.
According to Section 312000 “Earthwork.”
PACKAGED SUBMERSIBLE PUMP SYSTEM
The packaged submersible pump system shall be installed according to the manufacturer’s directions. The onsite representative provided by the single source lift system supplier shall coordinate with the contractor to ensure proper installation of the pump system.
WET WELL (MANHOLE) INSTALLATION
Install complete with appurtenances and accessories indicated.
Install precast concrete manhole sections with joint sealant according to ASTM C891.
Core drill or use hole former for pipe openings in pre-cast base section of shallow manhole.
Connect pipe to structures with specified pipe gasket.
PIPING INSTALLATION
Piping: Per Section 221300 “Onsite Water Treatment System."
HYDROSTATIC TESTING FOR ALL SEWERLINE
Hydrostatic Testing: Per Section 221300 “Onsite Water Treatment System."
FIELD QUALITY CONTROL
Packaged Lift System: Demonstrate to the Contracting Officer that the entire system is working correctly.
Pumping system shall process at least 15,000 gallons of water within a 24 hour period. Contracting Officer or representative shall observe the test, including the following:
Proper operation of floats and controls.
Demonstrate duplexing of pumps, including the use of the standby pump.
Demonstrate correct method of pump removal and reinstallation, including pump lift chain operation.
Emergency Operations: Demonstrate to the Contracting Officer that the entire system is working correctly during a power outage.
Emergency auto-dialer shall activate and notify the appropriate authorities.
Pumping system shall properly process 5,000 gallons of water within 6 hours using power a portable generator. Contracting Officer or representative shall observe the test.
The contractor is responsible for transporting the water to each lift system for the test. Potable water, non-potable water or wastewater may be used. The existing potable water system may be used if the system is still operational (not winterized) at the time of the test.
The contractor is responsible for obtaining or renting a portable generator suitable to supply power to the lift system for the “Emergency Operations” test.
Leakage Tests: Fill underground structures with water and let stand overnight. If water level recedes, locate and repair leaks and retest. Repeat tests and repairs until no leaks exist.
Other System Test: Perform additional testing of completed onsite wastewater pumping system and structures according to authorities having jurisdiction.
TRAINING
Notify Contracting Officer if and when manufacturer’s representatives are scheduled to be at the project site. Provide at least 5 business days advance notice. Coordinate training of Forest Service personnel with manufacturer’s representatives, if training is available for any components or equipment included in this Section.
CLEANUP
Clean up the area by removing the unused and waste materials. Disposal of waste materials shall be in accordance with Section 024100 “Waste Material Disposal.”
END OF SECTION 221310
PACKAGED SEWER PUMPS & MOTORS SYSTEMS 221310-6
USDA FOREST SERVICE, R-4
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 260500 - COMMON WORK RESULTS FOR ELECTRICAL
1. GENERAL
SUMMARY
Section Includes:
Electrical equipment coordination and installation.
Grout.
Common electrical installation requirements.
SUBMITTALS
Product Data:
For any substitutions for equipment referred to by name in Division 26 specifications or the drawings.
QUALITY ASSURANCE
The installation shall conform to the 2014 Edition of the National Electrical Code (NFPA 70) and to the requirements specified herein.
The Contractor shall perform all work necessary and required to accomplish the task as detailed on the drawings and discussed in the installation notes. All work shall be done by a state licensed electrician.
MEASUREMENT AND PAYMENT
The work in this section, including all incidentals in other electrical sections, shall be measured and paid for by one or more of the following methods as shown in the Schedule of Items:
Electrical Distribution System - Lump Sum including full compensation for all labor, materials, and incidentals necessary to complete the work as shown on the drawings including all wiring, trenching, bedding, backfill, and all other incidentals necessary for a functional system.
Power company fees shall be paid for directly by the Government.
Electrical demolition shall be considered incidental to the lift system removal items.
PRODUCTS
PRODUCTS REFERRED TO BY NAME
The materials referred to by trade name, make, or catalog number on the drawings shall be regarded as establishing a minimum standard of quality; substitutions of equal or greater quality can be made by submitting a data sheet of the proposed substituted item to the Contracting Officer, for approval.
GROUT
Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive, nonstaining, mixed with water to consistency suitable for application and a 30-minute working time.
EXECUTION
COMMON REQUIREMENTS FOR ELECTRICAL INSTALLATION
Comply with NECA 1.
Equipment: Install to facilitate service, maintenance, and repair or replacement of components of both electrical equipment and other nearby installations. Connect in such a way as to facilitate future disconnecting with minimum interference with other items in the vicinity.
Right of Way: Give to piping systems installed at a required slope.
RACEWAY AND SIMILAR PENETRATIONS (NON-FIRE RATED, NOT SLEEVED)
Use pre-established penetrations when possible.
Concrete Slabs and Walls: Core-drilled holes.
Fill oversized holes with grout.
Seal exterior opening around the raceway or cable, using a flexible, waterproofing, joint sealant appropriate for size, depth, and color to closely match the surrounding surface.
END OF SECTION 260500
COMMON WORK RESULTS FOR ELECTRICAL 260500-2
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
1. GENERAL
SUMMARY
Section includes grounding and bonding systems and equipment.
QUALITY ASSURANCE
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
Comply with UL 467 for grounding and bonding materials and equipment.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PRODUCTS
CONDUCTORS
Insulated Conductors: Copper or tinned-copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.
Bare Copper Conductors:
Solid Conductors: ASTM B 3.
Stranded Conductors: ASTM B 8.
Tinned Conductors: ASTM B 33.
CONNECTORS
Listed and labeled by an NRTL acceptable to authorities having jurisdiction for applications in which used and for specific types, sizes, and combinations of conductors and other items connected.
Bolted Connectors for Conductors and Pipes: Copper or copper alloy.
Welded Connectors: Exothermic-welding kits of types recommended by kit manufacturer for materials being joined and installation conditions.
GROUNDING ELECTRODES
Ground Rods: Copper-clad steel; 3/4 inch by 10 feet (19 mm by 3 m).
EXECUTION
APPLICATIONS
Conductors: Install solid conductor for No. 8 AWG and smaller, and stranded conductors for No. 6 AWG and larger unless otherwise indicated.
GROUNDING AT THE SERVICE
Equipment grounding conductors and grounding electrode conductors shall be connected to the ground bus. Install a main bonding jumper between the neutral and ground buses.
Existing service drop poles have additional pole grounding installed which shall be bonded to the required grounding electrode system.
EQUIPMENT GROUNDING
Install insulated equipment grounding conductors with all feeders and branch circuits.
INSTALLATION
Grounding Conductors: Route along shortest and straightest paths possible unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.
Ground Rods: Drive rods until tops are 2 inches (50 mm) below finished floor or final grade unless otherwise indicated.
Interconnect ground rods with grounding electrode conductor below grade and as otherwise indicated. Make connections without exposing steel or damaging coating if any.
For grounding electrode system, install at least two rods spaced at least one-rod length from each other and located at least the same distance from other grounding electrodes, and connect to the service grounding electrode conductor.
Ground-Rod Connections: Install bolted connectors for underground connections and connections to rods.
END OF SECTION 260526
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526-2
SEWER PUMPS & MOTORS REPLACEMENT - CEDAR SPRINGS LIFT STATIONS
SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
1. GENERAL
SUMMARY
Section Includes:
Metal conduits, tubing, and fittings.
Nonmetal conduits and fittings.
Boxes, enclosures, and cabinets.
Handholes and boxes for exterior underground cabling.
DEFINITIONS
GRC: Galvanized rigid steel conduit.
IMC: Intermediate metal conduit.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PRODUCTS
METAL CONDUITS, TUBING, AND FITTINGS
Listing and Labeling: Metal conduits, tubing, and fittings shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
GRC: Comply with ANSI C80.1 and UL 6.
IMC: Comply with ANSI C80.6 and UL 1242.
PVC-Coated Steel Conduit: PVC-coated rigid steel conduit or IMC.
Comply with NEMA RN 1.
Coating Thickness: 0.040 inch (1 mm), minimum.
EMT: Comply with ANSI…
This is the start of the file's text. The full file is on GovTribe.