CDPG Greenhouse Final Drawings - Parlier.pdf
PDF 18 MB Posted
- Attached to
- Sources Sought/Synopsis Notice for New Greenhouse Construction for USDA ARS in Parlier, CA.
- Solicitation number
- 12905B24SS0022
About this file
This document is a Sources Sought/Synopsis Notice for a new greenhouse construction project for the USDA Agricultural Research Service (ARS) in Parlier, California. The notice is issued for market research and information gathering purposes only and does not constitute a solicitation for proposals or quotes.
The project requires the construction of a new approximately 1,800 square foot greenhouse facility. The government is seeking information from qualified sources, including small businesses, HUBZone small businesses, service-disabled veteran-owned small businesses, 8(a) small businesses, veteran-owned small businesses, women-owned small businesses, and small disadvantaged businesses, to assist in determining the appropriate acquisition method and potential set-aside options. Respondents should provide capability statements that include their ability to perform the work, their size standards, past similar requirements, and any other relevant information. The government is not obligated to provide feedback or acknowledgment of the responses received. A solicitation may be published on SAM.gov depending on the responses received. Responses are due to the identified point of contact by the specified deadline, and no pricing information should be submitted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CDPG Greenhouse Final Specification - Parlier.pdf | ||
| Sources Sought Notice New Greenhouse Parlier CA.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NO SCALELOCATION MAP
N
SAN JOAQUIN VALLEY
PACIFIC WEST AREA
USDA / AGRICULTURAL RESEARCH SERVICE
DWG. NO.
INDEX OF DRAWINGS
SHEET NO. TITLE
T-101 B-101 C-100 C-101 C-102 C-501 S-001 S-101 A-101 A-201 A-301 M-001 M-101 P-001 P-101 E-001 E-601
EL-101
EL-102
EP-101
ES-101
TITLE SHEET
BORING LOGS
GENERAL NOTES
SITE SURVEY & DEMOLITION
SITE PLAN
CIVIL DETAILS
GREENHOUSE STRUCTURAL NOTES
GREENHOUSE FOUNDATION PLAN
FLOOR PLAN
EXTERIOR ELEVATIONS
CROSS SECTION & SCHEDULES
MECHANICAL NOTES, ABBREVIATIONS, & LEGEND
MECHANICAL FLOOR PLAN
PLUMBING ABBREVIATIONS, NOTES, & LEGEND
PLUMBING FLOOR PLAN
ELECTRICAL LEGEND
PROPOSED SINGLE LINE DIAGRAM
LIGHTING FIXTURE SCHEDULE
LIGHTING PLAN
POWER PLAN
ELECTRICAL SITE PLAN
CDPG GREENHOUSE
USDA
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
PARLIER, CALIFORNIA
CALIFORNIA, USA NO SCALE
LOCATION
PROJECT
LOCATION
PROJECT
N
A/E DESIGN CONTRACT #12639521D0053
A/E DESIGN TASK ORDER #12905B23F0116
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
9611 S. RIVERBEND AVE.
PARLIER, CA 93648
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
TITLE SHEET
T-101 1 214/3/2024
RPP
RPP
FEJ
XXX
6323-A
T. GOEBEL
P. SMITH
Boring Log No. B1 Location:
Latitude: 36.5953° Longitude: -119.5147°
See Exploration Plan
Depth (Ft.) Elevation: 338 (Ft.) +/-
10-11-11
8-8-6 5.0 121
4.8 120 31
4-5-5
6.3 118
3-4-6 5.9 108
5-7-7 6.2 104 18
13.0 325
5-8-8
3.6 95
6-8-8
21.5 316.5
1.6 90
Gr ap hic Lo g
Mo de l L ay er
De pth
(F t.)
W ate r L ev el Ob se rva tio ns
Sa mp le Ty pe
Fie ld
Te st
Re su lts
W ate r Co nte nt
Dr y U nit W eig ht
(p cf)
Pe rce nt Fin es
Location:
Latitude: 36.5952° Longitude: -119.5146°
See Exploration Plan
Depth (Ft.) Elevation: 338 (Ft.) +/-
9-12-15
7-9-8
7.0
6.3
112 36
4-5-7
27-50/4" 6.7 89
7.4 116
13-14-19 4.4 120
13.0 325
7-9-10
1.5 88
9-8-10
21.5 Boring Terminated at 21.5 Feet
316.5
3.0 97
Water Level Observations Groundwater not encountered
Drill Rig D90 Truck Hammer Type Automatic
Notes Elevation Reference: Elevations Estimated Using Google Earth
Driller E. Santellan Logged by E. McArthur Boring Started 11-20-2023 Boring Completed 11-20-2023
Gr ap hic Lo g
Mo de l L ay er
De pth
(F t.)
W ate r L ev el Ob se rva tio ns
Sa mp le Ty pe
Fie ld
Te st
Re su lts
W ate r Co nte nt
Dr y U nit W eig ht
(p cf)
Pe rce nt Fin es
BORING LOCATIONS
FOR GREENHOUSE
BORING LOCATIONS
LABORATORY (FUTURE PHASE-NOT IN SCOPE)
SILTY SAND (SM), fine to medium grained, brown, medium dense loose reddish brown, very dense, weak cementation medium dense
POORLY GRADED SAND (SP), fine to coarse grained, tan, medium dense fine to medium grained
See Exploration and Testing Procedures for a description of field and laboratory procedures used and additional data (If any). See Supporting Information for explanation of symbols and abbreviations.
Advancement Method 4" Solid Stem Auger Abandonment Method Boring backfilled with cement grout upon completion.
POORLY GRADED SAND (SP), fine to medium grained, tan, medium dense fine to coarse grained
SILTY SAND (SM), fine to medium grained, brown, medium dense loose
SCALE:
BORING LOGS
NONE
B-101
SCALE:
EXPLORATION PLAN
NONE
B-101
Geotechnical Engineering Report Additional Greenhouses and Laboratory Buildings | Parlier, California December 22, 2023 | Terracon Project No. NA235092
Boring Terminated at 21.5 Feet
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
BORING LOGS
B-101 2 214/3/2024
RPP
T. GOEBEL
P. SMITH
ALL WORK THIS SHEET IS TO BE INCLUDED AS PART OF THE BASE BID
Boring Log No. B2 holivi Approved holivi Date 04/02/2024 holivi 04/02/2024 holivi
DEMOLITION NOTES
D-1 PROTECT ASSETS AND FINISHES NOT SHOWN TO BE REMOVED. ANY DAMAGE
CAUSED BY CONSTRUCTION OPERATIONS SHALL BE REPAIRED TO MATCH THE
EXISTING CONDITIONS AT NO COST TO THE GOVERNMENT.
D-2 AT A MINIMUM, PROVIDE 4' TALL TEMPORARY ORANGE HIGH DENSITY
POLYETHYLENE SAFETY FENCE TO ISOLATE HAZARD AND CONSTRUCTION
FROM UNAUTHORIZED ACCESS.
D-3 CARE SHALL BE TAKEN IN ALL OPEN SUBGRADES TO PREVENT DETERIORATION
CAUSED BY WEATHER. DEWATER ALL OPEN SUBGRADES AS REQUIRED TO
MAINTAIN STABILITY..
D-4 THE CONTRACTOR SHALL CONTROL THE SPREAD OF DUST AND IRRITANTS TO
OTHER SPACES, ADJACENT BUILDINGS AND OUTSIDE OF DESIGNATED WORK
AREAS.
D-5 THE CONTRACTOR SHALL PROVIDE CLEAN, STRAIGHT, NEAT CUTS FOR
DEMOLITION THAT MINIMIZE IMPACTS AND ADVERSE EFFECTS ON EXISTING
FINISHES. COORDINATE THE LOCATION OF THE CUTS TO ACCOMMODATE FINAL
FINISHES. ANY DAMAGED ASSET OR FINISH, NOT SHOWN TO BE REMOVED,
SHALL BE REPLACED AT THE CONTRACTOR'S EXPENSE TO MATCH IN A
"LIKE-IN-KIND" CONDITION.
D-6 THE REPAIR IS DESIGNED TO BE VIABLE IN ITS FULLY CONSTRUCTED, FINAL
CONFIGURATION. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE THE
SAFETY AND STABILITY OF ALL COMPONENTS DURING CONSTRUCTION.
GENERAL NOTES
GN-1 THESE GENERAL NOTES ARE NOT INTENDED TO REPLACE THE PROJECT
SPECIFICATIONS. REVIEW ALL PROJECT DOCUMENTS PRIOR TO START OF
CONSTRUCTION. REPORT ANY DISCREPANCIES TO CONTRACTING OFFICER
PRIOR TO PROCEEDING WITH WORK. DIMENSIONS RELATING TO EXISTING
CONSTRUCTION ARE TO BE FIELD VERIFIED. THE CONTRACTOR SHALL
IMMEDIATELY COMMUNICATE, IN WRITING TO THE CONTRACTING OFFICER,
CONCERNS WHERE THEY BELIEVE DESIGN DOCUMENTS ARE INSUFFICIENT,
INADEQUATE OR INCORRECT FOR PERFORMING THE CONSTRUCTION WORK.
GN-2 EXISTING UTILITIES ARE SHOWN IN THEIR APPROXIMATE LOCATIONS AS
LOCATED AT THE TIME OF THE DESIGN SITE VISIT.
AT THE BEGINNING OF THE PROJECT AND PRIOR TO ORDERING
MATERIALS:
· THE CONTRACTOR SHALL BE RESPONSIBLE FOR DETERMINING THE
EXACT LOCATION OF EXISTING UTILITIES ON SITE.
· WHERE NEW WORK IS INDICATED TO CROSS EXISTING UTILITIES,
THE CONTRACTOR SHALL ANTICIPATE RELOCATING THE EXISTING
SERVICE TO ACCOMMODATE THE NEW INSTALLATION.
· THE CONTRACTOR SHALL VERIFY THE LOCATION OF ALL UTILITIES,
DETERMINE THE POINTS OF CONNECTIONS (SUCH AS WATER,
SEWER, ELECTRIC, GAS, COMMUNICATION AND STORM DRAINAGE).
DOCUMENT ALL FINDINGS AND PROVIDE TO THE CONTRACTING OFFICER
PRIOR TO BEGINNING CONSTRUCTION. UNDERGROUND UTILITIES AND
OBSTRUCTIONS WERE NOT IDENTIFIED DURING THE DESIGN OF THIS
PROJECT. THE EXTENT OF UNDERGROUND UTILITIES IS UNKNOWN. IT IS THE
CONTRACTOR'S RESPONSIBILITY TO PROTECT ALL EXISTING
CONSTRUCTION DURING EXCAVATION.
GN-3 COORDINATE CIVIL WORKS AND OTHER TRADES.
GN-4 ALL DETAILS AND SECTIONS ON THE DRAWINGS ARE INTENDED TO BE
TYPICAL AND SHALL BE CONSTRUED TO APPLY TO ANY SIMILAR SITUATION
ELSEWHERE ON THE PROJECT EXCEPT WHERE A SEPARATE DETAIL IS
SHOWN.
GN-5 THE CONTRACTOR SHALL TAKE CARE, BY THE USE OF GRADING, DIVERSION
AND DEWATERING, TO PREVENT PONDING OF WATER ON SITE IN AREAS OF
STRUCTURAL AND PAVEMENT SUBGRADES.
GN-6 THE CONTRACTOR SHALL PROVIDE AS-BUILT DRAWINGS OF ALL OF THE NEW
UTILITIES AND SERVICE.
GN-7 PRODUCTS SHALL BE INSTALLED PER MORE STRINGENT REQUIREMENTS OF
THE DESIGN DOCUMENTS OR THE MANUFACTURER'S PRINTED INSTRUCTIONS
FOR THE INDICATED APPLICATION. THESE INSTRUCTIONS SHALL BE
MAINTAINED ON SITE FOR THE DURATION OF THE CONTRACT AT A MINIMUM.
GN-8 AT THE COMPLETION OF GRADING, THE CONTRACTOR SHALL RESPREAD 4"
ON ALL DISTURBED UNIMPROVED AREAS, AS REQUIRED TO ESTABLISH
VEGETATIVE COVER. AT THE COMPLETION OF THE PROJECT, HAUL EXCESS
OFF SITE.
GN-9 ALL STORM WATER, DE-WATERING, AND WASH-WATER SHALL BE
PRE-TREATED WITH AN ACCEPTED MANAGEMENT PRACTICE PRIOR TO BEING
DISCHARGED INTO A STORM WATER CONVEYANCE.
PERMIT NOTES
P-1 THE CONTRACTOR SHALL APPLY FOR, OBTAIN AND COMPLY WITH ALL NECESSARY
PERMITS.
P-2 COPIES OF ALL PERMITS SHALL BE MAINTAINED ON SITE. HARD COPIES OF ALL
PERMITS SHALL BE PROVIDED TO THE CONTRACTING OFFICER OR DESIGNATED
REPRESENTATIVE.
RECORD DRAWING NOTES:
RD-1 CONTRACTOR SHALL MAINTAIN UPDATED RECORD DRAWINGS AT ALL TIMES
THROUGH THE DURATION OF THE PROJECT. CONSTRUCTION RECORD DRAWINGS IN
CADD FORMAT, SHALL BE SUBMITTED TO THE CONTRACTING OFFICER.
RD-2 DURING CONSTRUCTION OF THE PROJECT, CONTRACTOR SHALL BE RESPONSIBLE
FOR KEEPING TRACK OF ANY CONTRACTING OFFICER APPROVED FIELD
CONSTRUCTION REVISIONS TO THE DESIGN DEPICTED ON APPROVED
CONSTRUCTION DRAWINGS. THESE REVISIONS SHALL BE USED TO PREPARE
RECORD DRAWINGS OF COMPLETED CONSTRUCTION.
RD-3 ALL VARIATIONS IN PROJECT CONDITIONS, LOCATIONS, AND CONFIGURATIONS, AND
ANY OTHER CHANGES OR DEVIATIONS FROM THE INFORMATION PRESENTED ON THE
ORIGINAL, APPROVED CONSTRUCTION DRAWINGS SHALL BE NOTED. THIS INCLUDES
BURIED OR CONCEALED CONSTRUCTION AND UTILITY FEATURES THAT WERE
REVEALED DURING CONSTRUCTION.
COORDINATION AND COMMUNICATION
CC-1 CONTRACTOR SHALL APPOINT A CONSTRUCTION SUPERINTENDENT, SUBJECT TO THE
APPROVAL OF THE CONTRACTING OFFICER, WHO SHALL BE PRESENT ON THE
CONSTRUCTION SITE AT ALL TIMES WHILE WORK IS IN PROGRESS. THE
SUPERINTENDENT SHALL BE DESIGNATED THE RESPONSIBLE CONTRACTOR'S
REPRESENTATIVE WHO SHALL BE AVAILABLE ON A 24-HOUR BASIS. WHEN THE
CONTRACTOR'S REPRESENTATIVE IS NOT AVAILABLE ON THE CONSTRUCTION SITE,
AN ALTERNATE REPRESENTATIVE SHALL BE PROVIDED.
CC-2 CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING CONSTANT COORDINATION
BETWEEN ALL SUBCONTRACTORS AND THE CONTRACTING OFFICER. ALL
CONSTRUCTION ACTIVITIES PLANNED BY THE CONTRACTOR SHALL BE
COORDINATED WITH THE CONTRACTING OFFICER.
OTHER SAFETY REQUIREMENTS
SR-1 CONTRACTOR SHALL MAINTAIN SAFETY PRACTICES THAT CONFORM TO
OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) REGULATIONS AND
THE USCAE EM 385-1-1 SAFETY AND HEALTH REQUIREMENT MANUAL".
SR-2 THE CONTRACTOR SHALL PERFORM ON-SITE INSPECTIONS DAILY AND PRIOR TO
LEAVING THE SITE EACH DAY TO REMEDY ANY SAFETY CONCERNS IMMEDIATELY.
SR-3 THERE SHALL BE NO PERMANENT WASTE SITES ON GOVERNMENT PROPERTY. ANY
TEMPORARY WASTE AREA SHALL BE APPROVED BY THE CONTRACTING OFFICER
AND SHALL BE KEPT IN AN ORDERLY CONDITION. ALL WASTE IS SUBJECT TO THE
REMOVAL AT DIRECTION OF THE CONTRACTING OFFICER.
SR-4 LOCATE ALL UTILITIES IN ACCORDANCE WITH STATE & LOCAL REQUIREMENTS.
CONTACT 811 BEFORE YOU DIG.
GT-2 GROUNDWATER:GROUNDWATER WAS NOT ENCOUNTERED IN OUR TEST BORINGS WHILE DRILLING.
GROUNDWATER LEVEL FLUCTUATIONS OCCUR DUE TO SEASONAL VARIATIONS IN THE AMOUNT OF
RAINFALL, RUNOFF, AND OTHER FACTORS NOT EVIDENT AT THE TIME THE BORINGS WERE
PERFORMED. THEREFORE, GROUNDWATER LEVELS DURING CONSTRUCTION OR AT OTHER TIMES IN
THE LIFE OF THE STRUCTURES MAY BE HIGHER OR LOWER THAN ANTICIPATED.
GT-3 FOUNDATIONS:
ALLOWABLE BEARING PRESSURE = 2,500 PSF.
GT-4 SITE PREPARATION:
PRIOR TO PLACING FILL, EXISTING VEGETATION, TOPSOIL, AND ROOT MATS SHOULD BE
REMOVED.REMEDIAL GRADING MUST INCLUDE OVER-EXCAVATION, REPLACEMENT, AND
COMPACTION OF SOILS BENEATH THE NEW CONSTRUCTION. THE SUBGRADE SOILS IN THE
FOOTPRINT AND AT LEAST 10 FEET BEYOND THE FOOTPRINT OF THE PROPOSED GREENHOUSE BE OVER-EXCAVATED TO 5 FEET. THE EXCAVATED SOILS MAY THEN BE REPLACED AND COMPACTED AS STRUCTURAL FILL. IN-SITU SOIL MATERIALS WHICH CONTAIN LESS THAN 3 PERCENT ORGANICS CAN
BE REUSED AS ENGINEERED FILL PROVIDED THE MATERIAL MEETS THE SPECIFICATIONS FOR
GENERAL OR STRUCTURAL FILL. IF EXISTING SOILS ARE USED, THEY SHOULD BE SUBMITTED AND
DOCUMENTED BY THE CONTRACTOR.
GT-5 EARTHWORK:
AS A MINIMUM, EXCAVATIONS SHOULD BE PERFORMED IN ACCORDANCE WITH OSHA 29 CFR, PART
1926, SUBPART P, “EXCAVATIONS” AND ITS APPENDICES, AND IN ACCORDANCE WITH ANY
APPLICABLE LOCAL AND/OR STATE REGULATIONS. STOCKPILES OF SOIL, CONSTRUCTION
MATERIALS, AND CONSTRUCTION EQUIPMENT SHOULD NOT BE PLACED NEAR TRENCHES OR
EXCAVATIONS. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING THE STABILITY OF ADJACENT
STRUCTURES DURING CONSTRUCTION.
PRIOR TO STRUCTURAL FILL PLACEMENT, THE UPPER 18 INCHES OF THE RESULTING SUBGRADE
SHOULD BE MOISTURE CONDITIONED AND RECOMPACTED TO MINIMIZE THE EFFECTS OF
COLLAPSIBLE SOILS. TESTED FOR COMPACTION TO VERIFY THE SOILS HAVE ACHIEVED THE
REQUIRED COMPACTION.
ONCE CUTS AND OVER-EXCAVATION OPERATIONS ARE COMPLETE, SUBGRADE THAT WILL RECEIVE
FILL OUTSIDE THE GREENHOUSE FOOTPRINT SHOULD BE PROOFROLLED WITH AN ADEQUATELY
LOADED VEHICLE . THE PROOFROLLING SHOULD BE PERFORMED UNDER THE OBSERVATION OF THE GEOTECHNICAL ENGINEER OR THEIR REPRESENTATIVE. AREAS EXCESSIVELY DEFLECTING UNDER THE PROOFROLL SHOULD BE DELINEATED AND SUBSEQUENTLY ADDRESSED. EXCESSIVELY WET OR
DRY MATERIAL SHOULD EITHER BE REMOVED, OR MOISTURE CONDITIONED AND RECOMPACTED.
ALL EXPOSED AREAS OUTSIDE THE GREENHOUSE FOOTPRINT WHICH WILL RECEIVE FILL,, SHOULD BE SCARIFIED, MOISTURE CONDITIONED AS NECESSARY, AND COMPACTED PER THE COMPACTION
REQUIREMENTS. THE SCARIFICATION SHOULD BE A MINIMUM OF 18 INCHES.
FOLLOWING SCARIFICATION, MOISTURE CONDITIONING, AND COMPACTION OF THE SUBGRADE
SOILS, COMPACTED STRUCTURAL FILL SOIL SHOULD THEN BE PLACED TO THE PROPOSED DESIGN
GRADE AND THE MOISTURE CONTENT AND COMPACTION OF SUBGRADE SOILS SHOULD BE
MAINTAINED UNTIL FOUNDATION CONSTRUCTION.
ANY IMPORTED FILL MATERIALS (STRUCTURAL ENGINEERED FILL) MUST MEET THE FOLLOWING
MATERIAL PROPERTY REQUIREMENTS:
SOIL TYPE USCS CLASSIFICATIONACCEPTABLE PARAMETERS (FOR STRUCTURAL FILL)
LOW PLASTICITY
GRANULAR
ML (SANDY SILT)
GW, GM, SW, SM
COHESIVE
LIQUID LIMIT LESS THAN 30
LESS THAN 50% PASSING NO. 200 SIEVE
PLASTICITY INDEX LESS THAN 10
LESS THAN 60% PASSING NO. 200 SIEVE
PLACE FILLS IN ACCORDANCE WITH THE FOLLOWING:
- 8 INCHES OR LESS IN LOOSE THICKNESS WHEN HEAVY, SELF-PROPELLED COMPACTION
EQUIPMENT IS USED.
- 4 TO 6 INCHES IN LOOSE THICKNESS WHEN HAND-GUIDED EQUIPMENT (I.E., JUMPING JACK
OR PLATE COMPACTOR) IS USED.
COMPACT FILLS TO A MINIMUM OF 95% OF MAXIMUM DENSITY AND OPTIMUM WATER
CONTENT AS DETERMINED BY THE MODIFIED PROCTOR TEST (ASTM D 1557).
GT-6 GRADING:
ALL GRADES MUST PROVIDE EFFECTIVE DRAINAGE AWAY FROM THE BUILDING DURING AND
AFTER CONSTRUCTION AND MUST BE ESTABLISHED AND MAINTAINED.
FINDINGS AND RECOMMENDATIONS FOR THIS WORK ARE BASED ON THE
“ADDITIONAL GREENHOUSES AND LABORATORY BUILDINGS GEOTECHNICAL
ENGINEERING REPORT”(DATED JANUARY 10, 2023 - TERRACON PROJECT NO.
NA235092). THESE ARE INCLUDED IN THE APPENDICES OF THE PROJECT
SPECIFICATION. ALL EARTHWORK FOR THIS PROJECT SHALL CONFORM TO THE
MORE STRINGENT REQUIREMENTS OF THE GEOTECHNICAL REPORT OR THE
PROJECT SPECIFICATIONS.
REUSE OF ON-SITE SOIL: EXCAVATED ON-SITE SOIL MAY BE SELECTIVELY REUSED
AS FILL. MATERIAL PROPERTY REQUIREMENTS FOR ON-SITE SOIL FOR USE AS
GENERAL FILL AND STRUCTURAL FILL ARE NOTED IN THE FOLLOWING TABLE:
GT-8 OBSERVATION AND TESTING:
THE EARTHWORK EFFORTS SHOULD BE OBSERVED BY THE THIRD PARTY TESTING
AGENCY. OBSERVATION SHOULD INCLUDE DOCUMENTATION OF ADEQUATE REMOVAL
OF SURFICIAL MATERIALS (VEGETATION, TOPSOIL, DEBRIS) AS WELL AS
PROOFROLLING AND MITIGATION OF UNSUITABLE AREAS DELINEATED BY THE
PROOFROLL.
EACH LIFT OF COMPACTED FILL SHOULD BE TESTED, EVALUATED, AND REWORKED,
AS NECESSARY, AS RECOMMENDED BY THE ENGINEER PRIOR TO PLACEMENT OF
ADDITIONAL LIFTS. EACH LIFT OF FILL SHOULD BE TESTED FOR DENSITY AND WATER
CONTENT AT A FREQUENCY OF AT LEAST ONE TEST FOR EVERY 1,000 SQUARE FEET
OF COMPACTED FILL IN THE BUILDING AREA. WHERE NOT SPECIFIED BY LOCAL
ORDINANCE, ONE DENSITY AND WATER CONTENT TEST SHOULD BE PERFORMED FOR
EVERY 30 LINEAR FEET OF COMPACTED UTILITY TRENCH BACKFILL A MINIMUM OF
ONE TEST PERFORMED FOR EVERY 12 VERTICAL INCHES OF COMPACTED BACKFILL.
IN AREAS OF FOUNDATION EXCAVATIONS, THE BEARING SUBGRADE SHOULD BE
EVALUATED BY THE CONTRACTOR. IF UNANTICIPATED CONDITIONS ARE OBSERVED,
THE ENGINEER SHOULD PRESCRIBE MITIGATION OPTIONS.
GEOTECHNICAL NOTES
THE RECOMMENDATIONS BELOW ARE BASED ON GEOTECHNICAL REPORT
TITLED "ADDITIONAL GREENHOUSES AND LABORATORY BUILDINGS"
(TERRACON PROJECT NO. NA235092) IS TO BE INCLUDED WITH
SPECIFICATIONS AND SHALL BE ADHERED TO BY CONTRACTOR.
GT- 1 CHARACTERIZATION IS GENERALLY DESCRIBED AS:
· LOOSE TO VERY DENSE, POORLY GRADED SAND WITH VARIOUS AMOUNTS OF SILT AND
MEDIUM STIFF TO STIFF, SILT WITH VARIOUS AMOUNTS OF FINE-GRAINED SAND TO THE
MAXIMUM DEPTH EXPLORED OF 21½ FEET.
· BASED ON THIS SOURCE, THE NEAR-SURFACE MATERIALS ARE RATED “LOW” FOR
CORROSION TO CONCRETE AND “LOW” FOR CORROSION OF STEEL.
TRENCH BACKFILLS SHOULD BE MECHANICALLY PLACED AND COMPACTED AS
MENTIONED ABOVE. COMPACTION OF INITIAL LIFTS SHOULD BE ACCOMPLISHED WITH
HAND -OPERATED TAMPERS OR OTHER LIGHTWEIGHT COMPACTORS. FLOODING OR
JETTING FOR PLACEMENT AND COMPACTION OF BACKFILL IS NOT RECOMMENDED.
ALL TRENCH EXCAVATIONS SHOULD BE MADE WITH SUFFICIENT WORKING SPACE TO
PERMIT CONSTRUCTION INCLUDING BACKFILL PLACEMENT AND COMPACTION. CLEAN
GRANULAR FILL SHOULD BE TRACKED OR TAMPED IN PLACE WHERE POSSIBLE IN
ORDER TO LIMIT THE AMOUNT OF FUTURE DENSIFICATION WHICH MAY CAUSE
LOCALIZED SETTLEMENTS OVER TIME.
MATERIAL SUITABILITY MUST BE DETERMINED IN THE FIELD AT TIME OF
CONSTRUCTION.
EXPOSED GROUND SHOULD BE SLOPED AND MAINTAINED AT A MINIMUM 5 PERCENT
AWAY FROM THE BUILDING FOR AT LEAST 10 FEET BEYOND THE PERIMETER OF THE
BUILDING.
STRUCTURAL FILL -
LIFTS 8 INCHES OR LESS IN LOOSE THICKNESS WHEN HEAVY, SELF-PROPELLED
COMPACTION EQUIPMENT IS USED. 4 TO 6 INCHES IN LOOSE THICKNESS WHEN HAND-
GUIDED EQUIPMENT (I.E., JUMPING JACK OR PLATE COMPACTOR) IS USED.
COMPACTION: 95% OF MAX. FOR STRUCTURAL FILL BELOW FOUNDATIONS AND
SLABS, FOR AGGREGATE BASE, AND FOR FILLS THICKER THAN 5 FEET. 90% OF MAX.
FOR ALL OTHER LOCATIONS
WATER CONTENT (MOISTURE CONDITIONING): LOW PLASTICITY COHESIVE: +1% TO
+3% ABOVE OPTIMUM. GRANULAR: -2% TO +2% OF OPTIMUM. MOISTURE CONTENT
AND COMPACTION OF SUBGRADE SOILS SHOULD BE MAINTAINED UNTIL FOUNDATION
AND SLAB CONSTRUCTION.
COMPACT FILLS TO A MINIMUM OF 95% OF MAXIMUM DENSITY AND OPTIMUM WATER
CONTENT AS DETERMINED BY THE MODIFIED PROCTOR TEST (ASTM D 1557).
GT-6 GRADING:
ALL GRADES MUST PROVIDE EFFECTIVE DRAINAGE AWAY FROM THE BUILDING DURING AND
AFTER CONSTRUCTION AND MUST BE ESTABLISHED AND MAINTAINED.
GT-7 UTILITY TRENCH BACKFILL:
ANY SOFT OR UNSUITABLE MATERIALS ENCOUNTERED AT THE BOTTOM OF UTILITY
TRENCH EXCAVATIONS SHOULD BE REMOVED AND REPLACED WITH STRUCTURAL
FILL OR BEDDING MATERIAL IN ACCORDANCE WITH PUBLIC WORKS SPECIFICATIONS.
THIS RECOMMENDATION IS PARTICULARLY APPLICABLE TO UTILITY WORK REQUIRING
GRADE CONTROL AND/OR IN AREAS WHERE SUBSEQUENT GRADE RAISING COULD
CAUSE SETTLEMENT IN THE SUBGRADE SUPPORTING THE UTILITY. TRENCH
EXCAVATION SHOULD NOT BE CONDUCTED BELOW A DOWNWARD 1:1 PROJECTION
FROM EXISTING FOUNDATIONS WITHOUT ENGINEERING REVIEW OF SHORING
REQUIREMENTS AND GEOTECHNICAL OBSERVATION DURING CONSTRUCTION.
ON-SITE MATERIALS ARE CONSIDERED SUITABLE FOR BACKFILL OF UTILITY AND PIPE
TRENCHES FROM 1 FOOT ABOVE THE TOP OF THE PIPE TO THE FINAL GROUND
SURFACE, PROVIDED THE MATERIAL IS FREE OF ORGANIC MATTER AND
DELETERIOUS SUBSTANCES. WHERE TRENCHES ARE PLACED BENEATH SLABS OR
FOOTINGS, THE BACKFILL SHOULD SATISFY THE GRADATION AND ATTERBERG LIMIT
REQUIREMENTS OF STRUCTURAL ENGINEERED FILL.
PROPERTY STRUCTURAL FILL GENERAL FILL
COMPOSITION FREE OF DELETERIOUS MATERIAL FREE OF DELETERIOUS MATERIAL
MAXIMUM PARTICLE SIZE
FINES CONTENT
PLASTICITY
3 INCHES
LESS THAN 60% PASSING NO. 200
MAXIMUM LIQUID LIMIT OF 30
6 INCHES (OR 2
3 OF THE LIFT THICKNESS)
SIEVE NOT LIMITED
MAXIMUM PLASTICITY INDEX OF 10 NOT LIMITED
EXPANSION INDEX LESS THAN 20
GEOMODEL LAYER
EXPECTED TO BE
SUITABLE
1,2 1,2,3
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
GENERAL NOTES
C-100 3 214/3/2024
RPP
T. GOEBEL
P. SMITH
ALL WORK THIS SHEET IS TO BE INCLUDED AS PART OF THE BASE BID
holivi Approved holivi Date 04/02/2024 holivi
SS SS
335.00
340.00
0.0
331.00
337.00
337.00
337.00
337.00
8.0
8.0
338.00
338.00
339.00
4.0
4.0
338.00
339.00
SS SS
SET MAG NAIL337.38
SET 60D 337.45
SS
FL
SSCO
EP/EC
BUILDING
BUILDING
BUILDING
CONCRETE PATIO COVER
EDGE TREE LINE
SCALE:
SITE SURVEY & DEMOLITION
1' = 15'-0"
C-101
BOTTOM OF POND 330.65
6" INLET PIPE INV 334.12
TOP OF DIRT MOUND 345.17
PLAN
NORTH
SCALE:
LEGEND (EXISTING FEATURES):
EXISTING SHADE OVERHANG
EXISTING BUILDING
PILE OF DEBRIS OUTLINE TO BE REMOVED
SURVEY CONTROL POINT
WATER VALVE
SANITARY SEWER MANHOLE
GUY POLE
SPOT ELEVATION & DESCRIPTION
WATER STRUCTURES
CONTOUR
SANITARY SEWER CLEAN OUT
FLOW LINE
EDGE OF PAVEMENT / EDGE OF CONCRETE
APRON
WATER VALVE
EP 337.29
EP 337.41
EP 337.43
EP/EC AP 337.58
SET N/T 337.47
SET N/T 337.46
CONC. PAD
SHED
GENERATOR PAD (E)
SSCO 338.61 SSCO 338.72
AIR SYSTEM
EDGE ORCH/PP E/W336.45
EP 336.18
EP 336.20
EP 336.19
EP 336.17
EDGE ORCHARD 336.12
EP 336.27
EP 336.31
EDGE ORCHARD 336.21PP GUYWIRE 336.16
ELEC. PANEL
EP AP 337.56 EP 337.85
TMP 342.37
EP 337.39
RIM 337.83
EP/EC AP 337.72
EP/EC AP 337.74
EP/EC AP 337.75
TP GUY WIRE 337.76
RIM 337.75
EP 337.84
RIM 337.70
DI GRT 336.91
DI GRT 337.07
ELEC PANELS
PIPE RISER
GAS PIPE
RISER
SSCO
SSCO
EM BOX
EV
WV
SSCO SSCO
THE PLANS ARE BASED ON A SURVEY PERFORMED BY CENTRAL VALLEY ENGINEERING AND SURVEYING, INC. ON 11/2/2023.
HORIZONTAL (BASIS OF BEARINGS):
STATE PLAN COORDINATES CCS 1983 ZONE IV
VERTICAL (BENCH MARK):
NAVD 1988 DATIM (DERIVED FROM GPS METHOD)
THIS SURVEY DOES NOT ADDRESS THE EXISTENCE OR NONEXISTENCE OF WETLANDS, ENVIRONMENTAL HAZARDS, CEMETERIES OR ANY UNDERGROUND STRUCTURE NOT OBSERVED DURING THE COURSE OF THE SURVEY.
GENERAL NOTES:
337.00
SET 60D 337.63
INVERTER PAD
REMOVE AND DISPOSE OF PILE CONSISTING OF CONCRETE, DEBRIS, SOILS, ETC. REFERENCE NEW GRADING PLAN. REMOVE TO THE APPROXIMATE ELEVATION OF 337.50 AND GRADE UNIFORMLY TO DRAIN TO THE SOUTH.
REFERENCE PHOTO ON DETAIL 2/C-101. THE CONTRACTOR WILL BE RESPONSIBLE FOR REMOVING ALL THE SPOIL PILE FROM THE SITE AND DISPOSING PROPERLY OF ALL MATERIAL "OFF OF PROPERTY". GRADE TO
FACILITATE NEW CONSTRUCTION AND ESTABLISH POSITIVE DRAINAGE.
KEYED NOTES:
WV
WATER LINE INTO BUILDING
PYLONPYLON
EP AP 337.51
PVMT 337.57
CONCRETE LINED DITCH
AP
GENERATOR ON
CONCRETE PAD
PYLONS
ELEC. SWITCHGEAR
AIR SYSTEM
SCALE: 1" =
015 15
15'
SCALE:
PILE OF DEBRIS
NONE
C-101
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
SITE SURVEY AND DEMOLITION
C-101 4 214/3/2024
RPP
T. GOEBEL
P. SMITH
ALL WORK THIS SHEET IS TO BE INCLUDED AS PART OF THE BASE BID
holivi Approved holivi Date 04/02/2024 holivi
SS SS SS SS
GASGASGAS
G
AS
G
AS
G
AS
GVW
V
N: 2,100,231.51 E: 6,410,602.05
N: 2,100,171.51 E: 6,410,602.05N: 2,100,171.51
E: 6,410,556.05
N: 2,100,231.51 E: 6,410,556.05
EP
BUILDING (E)
CONCRETE PATIO COVER
EDGE TREE LINE
SCALE:
SITE PLAN
1' = 15'-0"
C-102
BOTTOM OF POND 330.65
6" INLET PIPE INV 334.12
PLAN
NORTH
SCALE:
335.00
331.00
337.00
337.00
LEGEND:
EXISTING SHADE OVERHANG
EXISTING BUILDING
NEW BUILDING
EXISTING CONTOUR
NEW CONTOUR
SANITARY SEWER CLEAN OUT
EDGE OF PAVEMENT
EDGE OF CONCRETE
SANITARY SEWER LINE
WATER LINE
GAS OR WATER VALVE
EP 337.29
EP 337.41
337.00
EP 337.43
337.00
EP/EC AP 337.58
CONC. PAD
SHED (E)
GENERATOR PAD (E)
AIR SYSTEM
EDGE ORCH/PP E/W336.45
EP 336.18
EP 336.20
EP 336.19
EP 336.17
EDGE ORCHARD 336.12
EP 336.27
EP 336.31
EDGE ORCHARD 336.21PP GUYWIRE 336.16
ELEC PANEL
EP AP 337.56 EP 337.85
8.0
EP 337.39
RIM 337.83
EP/EC AP 337.72
EP/EC AP 337.74
EP/EC AP 337.75
TP GUY WIRE 337.76
RIM 337.75
EP 337.84
RIM 337.70
DI GRT 336.91
DI GRT 337.07
ELEC PANELS
PIPE RISER
GAS PIPE
RISER
SSCO SSCO
EM BOX
EV
WV
SSCO SSCO
GENERAL NOTES:
339.00
338.00
338.00
339.00
INVERTER PAD
NEW GREENHOUSE. REFERENCE DETAIL 4/C-501 FOR SUBGRADE
AND BACKFILL REQUIREMENTS. LIMITS OF UNDERCUT/BACKFILL
SHALL BE 10' BEYOND FOOTPRINT OF BUILDING AS SHOWN.
POINT OF CONNECTION FOR NEW 2" GAS LINE IS LOCATED ABOVE
GROUND. ROUTE LINE DOWN FACE OF EXISTING BUILDING
UNDERGROUND TO NEW GREENHOUSES. PROVIDE NEW VALVE
AS INDICATED. SEE 1/C-501 & 3/C-501.
POINT OF CONNECTION FOR WATER IS LOCATED ABOVE GROUND.
ROUTE LINE DOWN FACE OF EXISTING BUILDING UNDERGROUND
TO NEW GREENHOUSES. PROVIDE NEW VALVE AS INDICATED.
SEE 1/C-501 & 3/C-501.
POINT OF CONNECTION FOR SANITARY SEWER. 4" SANITARY LINE
BELOW GRADE @ -2.042' IE. GRADE NEW 4" SANITARY SEWER TO
DRAIN. PROVIDE CLEANOUTS AT EACH POINT OF CONNECTION.
REFERENCE DETAIL 1/C-501 & 2/C-501.
REFERENCE ELECTRICAL DRAWINGS FOR POWER AND
COMMUNICATIONS ROUTING AND REQUIREMENTS.
KEYED NOTES:
F.F.E. = 339.00
BUILDING (E)
BUILDING (E)
1. ANTICIPATED UTILITY POINTS OF CONNECTION ARE INDICATED ON THE PLANS. THESE INCLUDE.
A. SANITARY SEWER
B. WATER
C. NATURAL GAS
D. ELECTRIC
2. THE CONTRACTOR SHALL FIELD VERIFY SIZES, DEPTHS AND LOCATION OF ALL POINTS OF CONNECTION DURING THE INITIAL STAGES OF PROJECT MOBILIZATION AND IMMEDIATELY PROVIDE ANY DISCREPANCIES TO THE PRIME
CONTRACTOR IN WRITING.
3. ALL UTILITIES/PIPING SHOWN SHALL HAVE FLEXIBLE CONNECTIONS TO ACCOUNT FOR MOVEMENT OF NEW BUILDING.
PROVIDE MASON TYPE FFL FLEX CONNECTORS RATED FOR 3" OF MOVEMENT. SUBMIT PRODUCT DATA FOR APPROVAL.
4. REFERENCE ELECTRICAL DRAWINGS FOR POWER INFORMATION.
5. REFERENCE ARCHITECTURAL DRAWINGS FOR LOCATIONS AND DETAILS OF BOLLARDS AT CORNERS OF BUILDING.
338.00
338.00
EC
338.00
ROAD CENTERLINE
AIR SYSTEM
SCALE: 1" =
015 15
15'
CO
1-1/2" W
GAS
SS
SS
1 - 1/2" W
338.00
337.00
GV/WV
COORDINATES ARE PROVIDED TO ESTABLISH THE APPROXIMATE BUILDING LOCATION. COORDINATE THE FINAL DIMENSIONS
WITH ARCHITECTURAL DRAWINGS.
F.E.E. NOTE:
CIVIL 339.00 (NAVD 88) = ARCHITECTURAL 0' 0" F.F.E.
LIMITS OF UNDERCUT AND BACKFILL
LIMITS OF UNDERCUT AND BACKFILL
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
SITE PLAN
C-102 5 214/3/2024
RPP
T. GOEBEL
P. SMITH
ALL WORK THIS SHEET IS TO BE INCLUDED AS PART OF THE BASE BID
holivi Approved holivi Date 04/02/2024 holivi
MIN
SCALE:
TYPICAL UTILITY TRENCH DETAIL
NONE
C-501
20 0 2010
20 'SCALE: 1" =
BRASS PLUG
C.I. BOX W/
COVER
FINISHED GRADE
1" MIN. CLEARANCE BETWEEN PLUG & COVER
6" (MIN.)
4" 45 DEGREE C.I. BEND
1" MIN. CLEAR
5 - 1 / 2"
1 / 2"
C.I. WYE BRANCH
TIE NEW PIPING AS
REQUIRED
CONCRETE 6" THICK X 1'-0" WIDE
VERIFY ELEVATION AND CONNECT
TO EXISTING PIPING.
4" CAST IRON PIPE
SQUARE CONCRETE PAD
SCALE:
SANITARY CLEANOUT DETAIL
NONE
C-501
WARNING TAPE (ALL PIPE) TRACER WIRE
(NONMETALLIC PIPE)
PLACE 4" OF TOPSOIL,
FERTILIZE AND SEED (OVER 6"
CLAY TOP LAYER)
TURFED AREA
WARNING MINIMUM COVER FOR ALL UTILITIES SHALL
BE 30 INCHES OR AS SPECIFIED.
PLACE BACKFILL IN 4" LIFTS AND COMPACT TO A
MIIMUM 95% ASTM D 1557 DENSITY.
HAUNCHING
INITIAL
BACKFILL
FINAL
BACKFILL30" TYP.
(FOR NATURAL GAS &
DOMESTIC WATER)
PIPE
ZONE
SPRINGLINE
18"
OD 8"8"
D
NOTE: BUILDING FOOTPRINT AND 10' BEYOND THE GREENHOUSE SHOULD RECEIVE OVER-EXCAVATION AND 6'-6", SUBGRADE STABILIZATION, AND RECOMPACTED IN SITU SOIL OR ENGINEERED FILL. SLOPE SOILS IN ACCORDANCE WITH OSHA 29 CFR DURING CONSTRUCTION. LIFTS SHOULD BE COMPACTED IN NO LARGER THAN 8" IN LOOSE THICKNESS WHEN HEAVY EQUIPMENT IS USED. IN SITU SOIL MAY BE USED PENDING IT MEETS THE REQUIREMENTS OF THE GEOTECHNICAL REPORT, IS TESTED AND IS SUBMITTED FOR APPROVAL.
STRUCTURAL FILL :
LIFTS: 8 INCHES R LESS IN LOOSE THICKNESS WHEN HEAVY, SELF-PROPELLED COMPACTION EQUIPMENT IS USED. 4 TO 6 INCHES
IN LOOSE THICKNESS WHEN HAND- GUIDED EQUIPMENT (I.E., JUMPING JACK OR PLATE COMPACTOR) IS USED.
COMPACTION: 95% OF MAX. FOR STRUCTURAL FILL.
WATER CONTENT (MOISTURE CONDITIONING): LOW PLASTICITY COHESIVE: +1% TO +3% ABOVE OPTIMUM. GRANULAR: -2% TO +2%
OF OPTIMUM. MOISTURE CONTENT AND COMPACTION OF SUBGRADE SOILS SHOULD BE MAINTAINED UNTIL FOUNDATION
AND SLAB CONSTRUCTION.
SCALE:
TYPICAL UNDERCUT & BACKFILL DETAIL
BELOW NEW BUILDING FOOTPRINT
NONE
C-501
SCALE:
TYPICAL WATER/GAS VALVE DETAIL
NONE
C-501
VALVE
VALVE BOX
CONCRETE SLAB
FINISHED GRADE
LETTERS "WATER"/"GAS" CAST IN
METAL COVER
6" 6"
MIN
S 1/2" S 1/2"
6"
" M
IN
(T
YP
PIPING SIZE / VALVE TYPES:
2" OR LESS = GLOBE VALVE
GREATER THAN 2" = OS&Y GATE
VALVES SHALL BE CERTIFIED PER AMERICAN WATER WORKS ASSOCIATION C509.
WATER PIPING INSTALLATION PARALLEL WITH SEWER PIPING
(1) NORMAL CONDITIONS: LAY WATER PIPING AT LEAST 10 FEET HORIZONTALLY FROM A SEWER OR SEWER MANHOLE
WHENEVER POSSIBLE. MEASURE THE DISTANCE EDGE-TO-EDGE.
(2) THE BOTTOM (INVERT) OF THE WATER PIPING SHALL BE AT LEAST 18 INCHES ABOVE THE TOP (CROWN) OF THE SEWER
PIPING.
(3) WHERE THIS VERTICAL SEPARATION CANNOT BE OBTAINED, THE SEWER PIPING SHALL BE CONSTRUCTED OF
AWWA-APPROVED WATER PIPE AND PRESSURE TESTED IN PLACE WITHOUT LEAKAGE PRIOR TO BACKFILLING.
APPROVED WASTE WATER DISPOSAL METHOD SHALL BE UTILIZED.
INSTALLATION OF WATER PIPING CROSSING SEWER PIPING
(1) NORMAL CONDITIONS: WATER PIPING CROSSING ABOVE SEWER PIPING SHALL BE LAID TO PROVIDE A SEPARATION OF
AT LEAST 18 INCHES BETWEEN THE BOTTOM OF THE WATER PIPING AND THE TOP OF THE SEWER PIPING.
(2) UNUSUAL CONDITIONS: WHEN LOCAL CONDITIONS PREVENT A VERTICAL SEPARATION DESCRIBED ABOVE, USE THE
FOLLOWING CONSTRUCTION:
(A) SEWER PIPING PASSING OVER OR UNDER WATER PIPING SHALL BE CONSTRUCTED OF AWWA-APPROVED DUCTILE IRON WATER PIPING, PRESSURE TESTED IN PLACE WITHOUT LEAKAGE PRIOR TO BACKFILLING.
(B) WATER PIPING PASSING UNDER SEWER PIPING SHALL, IN ADDITION BE PROTECTED BY PROVIDING A VERTICAL SEPARATION OF AT LEAST 18 INCHES BETWEEN THE BOTTOM OF THE SEWER PIPING AND THE TOP OF THE WATER PIPING; ADEQUATE STRUCTURAL SUPPORT FOR THE SEWER PIPING TO PREVENT EXCESSIVE DEFLECTION OF THE JOINTS AND THE SETTLING ON AND BREAKING OF THE WATER PIPING; AND THAT THE LENGTH, MINIMUM 20 FEET, OF THE WATER PIPING BE CENTERED AT THE POINT OF THE CROSSING SO THAT JOINTS SHALL BE EQUIDISTANT AND AS
FAR AS POSSIBLE FROM THE SEWER PIPING.
3000 PSI CONCRETE ENCASEMENT W/ 4-#4
BARS LONGITUDINAL 10' EITHER SIDE
CROSSING WHEN <18" VERTICAL
SEPARATION
WHERE WATER AND SEWER LINES
18" MIN. VERTICAL SEPARATION
LINE
SEWER
6" TYP.
AROUND PIPE
INTERSECT
LINE
WATER
SCALE:
WATER & SEWER LOCATION DETAIL
NONE
C-501
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
CIVIL DETAILS
C-501 6 214/3/2024
RPP
T. GOEBEL
P. SMITH
ALL WORK THIS SHEET IS TO BE INCLUDED AS PART OF THE BASE BID
1 MIN.
16'- 6"
REFERENCE STRUCTURAL
DRAWINGS FOR SLAB ON GRADE
5% MIN. (10' MIN.)
18" OF MOISTURE CONDITIONED
COMPACTED SUB-GRADE
IN SITU SOIL OR IMPORTED
MATERIAL MEETING THE
SPCIFICED CRITERIA PLACED
AS STRUCTURAL FILL
10'-0"
DRILLED PIER
SEE STRUCTURAL
holivi Approved holivi Date 04/02/2024 holivi
MINIMUM STRUCTURAL LOADING REQUIREMENTS
GENERAL INFORMATION
ELEVATION: 337 FT (NAVD 88)
LAT 36.595318
LONG -119.514641
STANDARD: ASCE/SEI 7-22RISK
CATEGORY: II
USE / OCCUPANCY GREENHOUSE / GROUP 'U'
SOILS
SOIL CLASS: D
ALLOWABLE PRESSURE 2500 PSF
LATERAL BEARING 150 PSF
ROOF LOADS
DEAD PER VENDOR REQUIREMENTS
LIVE 20 PSF
COLLATERAL 5 PSF
WIND
WIND SPEED (BASIC) 94 MPH
SEISMIC DATA
SS 0.65
S1 0.22
SMS 0.93
SM1 0.59
SDS 0.62
SD1 0.4
TL 12
R 1.25
PGAM 0.34
VS30 260
SEISMIC DESIGN CATEGORY D
SNOW
GROUND SNOW LOAD, PG 5 LB/FT2
20-YEAR MRI VALUE, PG 1.08 LB/FT2
WINTER WIND PARAMETER, W20.25
SNOW IMPORTANCE 0.8
THERMAL FACTOR 0.85
RAIN
15-MINUTE RAINFALL INTENSITY2.1 IN./HR
GENERAL NOTES
G-1 THESE GENERAL NOTES ARE NOT INTENDED TO REPLACE THE PROJECT
SPECIFICATIONS. SEE PROJECT SPECIFICATIONS FOR REQUIREMENTS IN ADDITION
TO GENERAL NOTES. REVIEW ALL PROJECT DOCUMENTS PRIOR TO FABRICATION AND
START OF CONSTRUCTION. REPORT ANY DISCREPANCIES TO ARCHITECT PRIOR TO
PROCEEDING WITH WORK. DIMENSIONS RELATING TO EXISTING CONSTRUCTION ARE
TO BE FIELD VERIFIED. THE CONTRACTOR SHALL IMMEDIATELY COMMUNICATE, IN
WRITING TO THE CONTRACTING OFFICER, CONCERNS WHERE THEY BELIEVE DESIGN
DOCUMENTS ARE INSUFFICIENT, INADEQUATE OR INCORRECT FOR PERFORMING THE
CONSTRUCTION WORK.
G-2 THE STRUCTURE IS DESIGNED TO BE VIABLE IN ITS FINAL, FULLY ERECTED
CONFIGURATION. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE THE SAFETY
AND STABILITY OF THE BUILDING AND ITS COMPONENT PARTS DURING THE
CONSTRUCTION PHASE OF THE PROJECT.
G-3 THE EXTENT OF UNDERGROUND UTILITIES IS UNKNOWN. IT IS THE CONTRACTOR'S
RESPONSIBILITY TO PROTECT ALL EXISTING CONSTRUCTION DURING EXCAVATION.
G-4 NO STRUCTURAL MEMBER SHALL BE CUT, NOTCHED OR OTHERWISE REDUCED IN
SIZE OR STRENGTH WITHOUT PRIOR APPROVAL IN WRITING FROM THE CONTRACTING
OFFICER.
G-5 COORDINATE STRUCTURAL AND OTHER DRAWINGS THAT ARE PART OF THE
CONTRACT DOCUMENTS FOR ANCHORED, EMBEDDED OR SUPPORTED ITEMS WHICH
MAY AFFECT THE STRUCTURAL DRAWINGS.
G-6 ALL DETAILS AND SECTIONS ON THE DRAWINGS ARE INTENDED TO BE TYPICAL AND
SHALL BE CONSTRUED TO APPLY TO ANY SIMILAR SITUATION ELSEWHERE ON THE
PROJECT EXCEPT WHERE A SEPARATE DETAIL IS SHOWN.
G-7 THE INTENTION OF THE PLANS AND SPECIFICATIONS IS TO PROVIDE ALL NECESSARY
DETAILS TO CONSTRUCT A COMPLETE STRUCTURE. WHEN SPECIFIC INFORMATION IS
MISSING OR IS IN CONFLICT, BRING THE CONFLICT TO THE ATTENTION OF THE
CONTRACTING OFFICER.
G-8 USE OF CONTRACT DRAWINGS REPRODUCED IN WHOLE OR IN PART IN SHOP
DRAWINGS SHALL NOT RELIEVE THE CONTRACTOR NOR SUBCONTRACTORS FROM
THEIR RESPONSIBILITY TO ACCURATELY LAYOUT, COORDINATE, DETAIL, FABRICATE
AND INSTALL A COMPLETE STRUCTURE.
G-9 REVIEW ALL SHOP DRAWINGS FOR CONFORMANCE WITH THE CONTRACT
DOCUMENTS AND FOR COMPLETENESS AND ANSWER ALL CONTRACTOR RELATED
QUESTIONS. STAMP AND INITIAL ALL SHEETS PRIOR TO SUBMITTING SHOP DRAWINGS
TO ARCHITECT FOR REVIEW.
G-10 PRODUCTS SHALL BE INSTALLED PER MORE STRINGENT REQUIREMENTS OF THE
DESIGN DOCUMENTS OR THE MANUFACTURER'S PRINTED INSTRUCTIONS FOR THE
INDICATED APPLICATION. THESE INSTRUCTIONS SHALL BE MAINTAINED ON SITE FOR
THE DURATION OF THE INSTALLATION AT A MINIMUM.
REINFORCED CONCRETE
RC-1 ALL CONCRETE DESIGN AND PLACEMENT SHALL BE IN STRICT ACCORDANCE WITH
THE ACI "BUILDING CODE REQUIREMENTS FOR STRUCTUAL CONCRETE," ACI 318.
RC-2 STRUCTURAL CONCRETE SHALL CONFORM TO ACI 301 SPECIFICATIONS AND SHALL
DEVELOP A MINIMUM COMPRESSIVE STRENGTH OF 3,600 PSI AT 28 DAYS.
RC-3 USE REGULAR WEIGHT CONCRETE.
RC-4 SUBMIT DESIGN MIX FOR REVIEW PRIOR TO PLACEMENT OF CONCRETE. ALL MIX
DESIGNS MUST CLEARLY INDICATE INTENDED USE AND LOCATION.
RC-5 CHAMFER ALL EDGES OF EXPOSED CONCRETE 3/4" UNLESS NOTED OTHERWISE.
RC-6 ALL REINFORCING STEEL SHALL BE DETAILED, FABRICATED AND INSTALLED IN
ACCORDANCE WITH ACI 318 AND ACI DETAILING MANUAL, ACI-315 MOST CURRENT
EDITIONS.
RC-6 SHOP DRAWINGS FOR PLACEMENT SHALL BE SUBMITTED FOR REVIEW PRIOR TO
REBAR FABRICATION.
RC-8 WELDED WIRE FABRIC SHALL CONFORM TO ASTM-A185.
RC-8 PROVIDE THE FOLLOWING CONCRETE COVERAGES OVER REINFORCING:
FOOTINGS: BOTTOM AND UNFORMED EDGES3" CLR.
TOP AND FORMED EDGES 2" CLR.
RC-10 PLACE CONCRETE PER ACI 304. USE INTERNAL MECHANICAL VIBRATION FOR ALL
CONCRETE. LIMIT MAXIMUM FREE FALL DROP TO 3'-0". ALL PRECAUTIONS SHOULD
BE TAKEN TO AVOID SEGREGATION OF CONCRETE DURING PLACEMENT.
RC-11 MINIMUM REQUIRED REBAR DEVELOPMENT
FY = 60 KSI AND F'C = 3600 PSI
BAR DL (INCHES)
#3 16 #4 22 #5 32 #6 43 #7 69 #8 86
DELEGATED DESIGN NOTE:
GREENHOUSES AND RELATED PRE-FABRICATED COMPONENTS ARE DELEGATED DESIGN
ENGINEERED SYSTEMS. THE MANUFACTURER SHALL SUBMIT SHOP DRAWINGS THAT ARE
SEALED BY A LICENSED ENGINEER, EMPLOYED BY THE CONTRACTOR/MANUFACTURER,
INDICATING THAT THE SUPPLIED COMPONENTS ARE IN COMPLIANCE WITH THE CONTRACT
DOCUMENTS AND THE SPECIFIED CRITERIA. PROVIDE A COMPLETE DESIGN ANALYSIS
SHOWING ALL CALCULATIONS FOR ALL STRUCTURAL COMPONENTS AND ANY MODIFIED
FOUNDATION REQUIREMENTS. FULLY COORDINATE THE LAYOUT OF THE FOUNDATION AND
EMBEDDED ITEMS. DELEGATED DESIGNS MUST COMPLY WITH THE REQUIREMENTS OF THE
AIA A201-2017 SECTION 3.12.10, AND THE INTERNATIONAL BUILDING CODE. ALL SUBMITTALS
MUST BE APPROVED BY THE CONTRACTING OFFICER PRIOR TO ANY FABRICATION OR
RELATED FIELD CONSTRUCTION.
DETAILS SHOWN ON THESE CONSTRUCTION DRAWINGS ARE THE DESIGNER OF RECORD'S
ESTIMATE OF REQUIREMENTS BASED ON ANTICIPATED SYSTEMS AND CONFIGURATION.
ITEMS SPECIFIED IN THESE CONTRACT DOCUMENTS, SUCH AS THICKNESS AND GAUGES,
SHALL BE INCORPORATED AS THE MINIMUM ALLOWED.
COMMON STRUCTURAL ABBREVIATIONS :
@ - AT
AFF - ABOVE FINISHED FLOOR
BFF - BELOW FINISHED FLOOR
CJ - CONTROL JOINT
Ø - DIAMETER
EW - EACH WAY
FF - FINISHED FLOOR (SEE CIVIL/ARCHITECTURAL FOR ELEVATIONS)
FT - FEET OR FOOT
FT2 - SQUARE FEET
HR - HOUR
IN - INCH
K - KIP
KSI - KIPS PER SQUARE INCH
LB - POUND FORCE
MIN - MINIMUM
MPH - MILES PER HOUR
OC - ON CENTER
PSF - POUNDS PER SQUARE FOOT
PSI - POUNDS PER SQUARE INCH
TYP - TYPICAL
UNO - UNLESS NOTED OTHERWISE
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
GREENHOUSE STRUCTURAL NOTES
S-001 7 214/3/2024
RPP
T. GOEBEL
P. SMITH
ALL WORK THIS SHEET IS TO BE INCLUDED AS PART OF THE BASE BID
lhenderson Parlier lhenderson
6"
6"
'-0
6'-
0" 8'-
0" 4'-
0"
'-0
5'-
10'-0"
10'-0"
10'-0"10'-0"
6'- 2"
6'- 0"
S-101
2 FOUNDATION SECTION
SCALE: 1/2"= 1'-0"
VARIES
#4 AT 16" OC,EW
2" TOP COVER
+0'-0" (FF)
T.O. SLAB
S-101
3 DRILLED PIER DETAIL
SCALE: 1/2"= 1'-0"
4'
SCALE: 1/2"=1'-0"
0 1' 2' 6'
4'
SCALE: 1/2"=1'-0"
0 1' 2' 6'
1'-4"1'-10"
(2) #4 TOP, MID,
BOTTOM. #3
TIES AT 12" O.C.
6"
SLAB
SLOPE WITH 1" FALL
TO FLOOR DRAIN
1" SAND
10 MIL VAPOR
BARRIER
3" CAPILLARY
BARRIER
GREENHOUSE STRUCTURE
AND FOUNDATION PLACEMENT
MUST BE COORDINATED TO
MEET THE GREENHOUSE
MANUFACTURER'S
REQUIREMENTS FOR MODULAR
CONSTRUCTION AND
OPTIMIZED TO ALLOW FOR
FUTURE EXPANSION
REMOVE AND RE-COMPACT
TO A STABLE SUBGRADE
-REFERENCE CIVIL
DRAIWNGS FOR
REQUIREMENTS
ENGINEERED
SUBGRADE
(SEE CIVIL
DRAWINGS)
2'- 0"
2' Ø TYPE A, TYP (UNO)
1'-6" TYPE B
(6) #5 VERT.
W/ #4 TIES
DRILLED
PIER
(4 ) A
T 3"
(4 ) A
T 101 2"
TYPICAL AT ALL UPRIGHT
LOCATIONS. COORDINATE WITH
MANUFACTURER
-0'-1" BFF
T.O. SLAB
0'-0"" (FF)
1'-4"
SLOPE WITH 1" FALL
S-101
1 GREENHOUSE (GH2) FOUNDATION PLAN
SCALE: 1/4"= 1'-0"
NORTH
8'0 2' 4' 12'
SCALE: 1/4"= 1'-0"
TYP. AT
LEAN-TO
#3 TIES AT 12"
O.C.
4'- 9"
M
IN
2"
#5 AT 16" OC
2" COVER
1" BFF
6"
S-101
5 TRENCH DRAIN DETAIL
SCALE: 1"= 1'-0"
COMPACTED AND
STABLE SUBGRADE
- REFERENCE CIVIL
DRAWINGS.
(2) #5
(3) #5
HEAVY -DUTY TYPE "P" ABA CAST
IRON TRENCH GRATE (NON-BOLTED)
CAST IRON SEAT ANCHOR ACCORDING
TO THE MANUFACTURER'S WRITTEN
INSTRUCTIONS FOR THIS APPLICATION
SLAB
REINFORCING
(TYPICAL)
8"
1'- 0"
SLAB CONTROL JOINT
(TYP)
SLOPE WITH 1" FALL
6'-10 1/2"
S-101
S-101
S-101
TYP
S-101
#3 TIE
(OR SIMILAR)
CONTINUE THE
TURNDOWNS (6) #4
CONTINUOUS THROUGH
THE PIER (ADJUST TO
AVOID GREENHOUSE
UPRIGHT/SUPPORT)
CONCRETE SLAB ON GRADE
REINFORCING NOT SHOWN
6" GRAVEL PAD
6" GRAVEL PAD
TYPE B
TYPE B
TYPE B
TYPE B
TYPE B
TYPE B TYPE B
TYPE B
TYPE B
TYPE B
TYPE B
TYPE B
TYPE B
2'
SCALE: 1"=1'-0"
0 6" 1' 3'
TYPE A TYP, UNLESS
NOTED OTHERWISE
** FIRST SAWCUT-SHALL BE MADE AS SOON AS
CONCRETE HAS HARDENED SUFFICIENTLY TO
PREVENT RAVELING OR SPAWLING AND PRIOR TO
THE FORMATION OF ANY RANDOM CRACKING IN
THE CONCRETE.
STRUCTURAL SLAB ON GRADE NOTES
1. CAPILLARY BARRIER SHALL BE A COMPACTED DURABLE COARSE AGGREGATE WITH #57 GRADATION OR APPROVED EQUAL.
2. VAPOR RETARDERS SHALL MEET THE REQUIREMENTS OF ASTM E1745. ALL LAPS SHALL BE FULLY SEALED IN ACCORDANCE WITH THE
MANUFACTURERS WRITTEN INSTRUCTIONS.
3. CONCRETE SHALL OBTAIN A MINIMUM 4000 PSI STRENGTH AT 28 DAYS. CONCRETE SLUMP SHALL NOT EXCEED 5" WITHOUT THE WRITTEN
APPROVAL OF THE CONTRACTING OFFICER.
4. THE MINIMUM DENSITY OF SUBGRADE SHALL BE 95% MODIFIED PROCTOR (ASTM D698).
5. IMPORTED SOIL (REFER TO CIVIL DRAWINGS)
6. CONCRETE AGGREGATES SHALL BE SELECTED TO MINIMIZE SHRINKAGE, FACILITATE CONSTRUCTION AND CONFORM TO ASTM C33/C33M, UNIFORMLY GRADED AND AS FOLLOWS: NOMINAL MAXIMUM AGGREGATE SIZE OF 1 INCH. A COMBINED SIEVE ANALYSIS MUST INDICATE A WELL GRADED AGGREGATE FROM COARSEST TO FINEST WITH NOT MORE THAN 18 PERCENT AND NOT LESS THAN 8 PERCENT RETAINED ON AN INDIVIDUAL SIEVE, EXCEPT THAT LESS THAN8 PERCENT MAY BE RETAINED ON COARSEST SIEVE AND ON NO. 50 SIEVE,AND LESS THAN 8
PERCENT MAY BE RETAINED ON SIEVES FINER THAN NO. 50.
8. REINFORCING SHALL BE CONTINUOUS, UNLESS NOTED OTHERWISE (U.N.O.)
9. SECURE REINFORCEMENT WITH HIGHCHAIRS, TIES AND ANCHORAGE AS REQUIRED TO PREVENT MOVEMENT OR DISPLACEMENT DURING
CONSTRUCTION.
2" CL
R.
6"
SEE 'STRUCTURAL SLAB
ON GRADE' NOTES
4000 PSI
CONCRETE
#4 @ 16" OC (EACH WAY,
TOP AND BOTTOM)
1" SAND,
VAPOR RETARDER,
3" CAPILLARY BARRIER
REFERENCE CIVIL
DRAWINGS
* SECOND SAWCUT
1/8" 1 1 /2"
**5/8
TY
PI
CA
L
3/1 6"
1/1 6"
LIQUID JOINT
SEALANT
SEPARATING TAPE
3/8"
S-101
4 SLAB ON GRADE DETAIL
SCALE:NONE
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
GREENHOUSE FOUNDATION PLAN
S-101 8 214/3/2024
RPP
T. GOEBEL
P. SMITH
ALL WORK THIS SHEET IS TO BE INCLUDED AS PART OF THE BASE BID
S-101 SIMILAR
1'-
SEE 'SLAB
ON GRADE'
DETAIL
1'-8"
6" TY
P
A-A
SECTION A-A
CONTROL JOINT
lhenderson Parlier lhenderson
3'- 4"
22"
2"
4'- 0"
2"
6" SCH. 40 STEEL BOLLARD
CONCRETE FILLED. PAINT AN
APPROVED YELLOW
CONCRETE
MOUND 1" AROUND BASE
(2) 12" #4 BARS THREADED
THROUGH AN APPROX. 3/4"
HOLE AND TACK WELDED
FINISHED GRADE
A-101
1 GREENHOUSE FLOOR PLAN
SCALE: 1/4"= 1'-0"
NORTH
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
FLOOR PLAN
A-101 9 214/3/2024
RPP
T. GOEBEL
P. SMITH
8'0 2' 4' 12'
SCALE: 1/4"= 1'-0"
1 2 3
A
B
C
D
E
F
4 5 6
5'-8" 4" 10'-0" 10'-0" 10'-0" 4" 9'-8" 4" 6'-0" 30'-8" 10'-0"
'-0
'-0
'-0
'-0
'-0
4"
'-8
VESTIBULE
GH-A EXHAUST
CORRIDOR
GH-B EXHAUST
CORRIDOR
8 MM DIFFUSED POLY-
CARBONATE ENDWALL
SKIN ON 18 GA WALL GIRTS
STAINLESS
STEEL SERVICE
SINK
STAINLESS
STEEL SERVICE
SINK
36" HIGH
COOLING
PADS W/
CONT. PAD
VENT
INSECT CLOTH
ENCLOSURE
(CLIN 3)
INSECT CLOTH
ENCLOSURE
(CLIN 3)
8 MM DIFFUSED
POLYCARBONATE
ENDWALL SKIN ON 18 GA
WALL GIRTS
8 MM DIFFUSED POLY-
CARBONATE ENDWALL
SKIN ON 18 GA WALL GIRTS
A-301 1A-301
A-201
A-201
A-201
A-201
GREENHOUSE A
8 MM WHITE OPAL POLY-
CARBONATE SKIN ON
18 GA WALL GIRTS
TRENCH DRAIN
TRENCH DRAIN
GREENHOUSE B
CONCRETE FILLED
STEEL PIPE BOLLARDS--
THREE PER CORNER.
SEE 2/A-101
CONCRETE FILLED
STEEL PIPE BOLLARDS--
THREE PER CORNER.
SEE 2/A-101.
CONCRETE FILLED
STEEL PIPE BOLLARDS--
THREE PER CORNER.
SEE 2/A-101
CONCRETE FILLED
STEEL PIPE BOLLARDS--
THREE PER CORNER.
SEE 2/A-101
INSECT CLOTH
ENCLOSURE
(CLIN 3)
INSECT CLOTH
ENCLOSURE
(CLIN 3)
INSECT CLOTH
ENCLOSURE
(CLIN 3)
INSECT CLOTH
ENCLOSURE
(CLIN 3)
8 MM WHITE OPAL POLY-
CARBONATE SKIN ON
18 GA WALL GIRTS
UNISTRUT FRAME
FOR MOUNTING
ELEC. PANELS &
ENVIRONMENTAL
CONTROL SYSTEM
E.F.
E.F.
E.F.
E.F.
E.F.
C.F.
C.F. C.F.
C.F.
C.F. C.F.
U.H.
U.H.
LEGEND
E.F.
C.F.
U.H.
GREENHOUSE TABLES
(CLIN 2)
WALL MOUNTED
EXHAUST FAN
SUSPENDED CIRCULATING
FAN
SUSPENDED UNIT HEATER
CONCRETE FILLED
STEEL PIPE
BOLLARDS. SEE
2/A-101
CONDENSING UNIT ON
CONCRETE PAD--SEE
MECHANICAL DWGS.
A.1
INSECT CLOTH
ENCLOSURE
(CLIN 3)
INSECT CLOTH
ENCLOSURE
(CLIN 3)
A
B
C
C.1
D
E.1
E
D.1
F
4" 6'-
2" 5'-
'-0
4'-
0" 8'-
0" 6'-
0" 6'-
0" 6'-
0" 6'-
0" 4"
TRENCH DRAIN
COOLING PADS
W/ CONTINUOUS
TOP HINGED
PAD VENT
36" HIGH
COOLING
PADS W/
CONT. PAD
VENT
36" HIGH
COOLING
PADS W/
CONT. PAD
VENT
36" HIGH
COOLING
PADS W/
CONT. PAD
VENT
COOLING PAD
CORRIDOR
4"
" T
YP
28" TYP.
A-101
2 BOLLARD DETAIL
SCALE: 3/4"= 1'-0"
8 MM DIFFUSED
POLYCARBONATE
SIDEWALL SKIN ON 18 GA
WALL GIRTS
8 MM DIFFUSED
POLYCARBONATE
SIDEWALL SKIN ON 18 GA
WALL GIRTS
8 MM DIFFUSED
POLYCARBONATE
SIDEWALL SKIN ON 18 GA
WALL GIRTS
8 MM DIFFUSED
POLYCARBONATE
SIDEWALL SKIN ON 18 GA
WALL GIRTS
6" SCH. 40 STEEL BOLLARD
CONCRETE FILLED. PAINT AN
APPROVED YELLOW
CONCRETE
MOUND 1" AROUND BASE
(2) 12" #4 BARS THREADED
THROUGH AN APPROX. 3/4"
HOLE AND TACK W
ELDED
FINISHED GRADE
A-201
2 GREENHOUSE SOUTH ELEVATION
SCALE: 3/8"= 1'-0"
SCALE: 3/8"=1'-0"
0 1' 2' 4' 8'
8 MM DIFFUSED POLY-
CARBONATE
GLAZING AT ROOF
INSECT CLOTH
INSECT CLOTH
CONTINUOUS STEEL
BASE STRINGER
BURIED INTO GRADE
INSECT CLOTH
INSECT CLOTH
3 4
5 6
8 MM DIFFUSED POLYCARBONATE
ENDWALL GLAZING
METAL DOWNSPOUTMETAL DOWNSPOUT
'-0
" G
RE
EN
HO
US
E
EA
VE
LEAN-TO
FRAMING
LEAN-TO
FRAMING
A-201
1 GREENHOUSE EAST ELEVATION
SCALE: 3/8"= 1'-0"
F E D C1 B AC
'-0
" G
RE
EN
HO
US
E
EA
VE
8 MM DIFFUSED POLYCARBONATE
GLAZING AT ROOF
8 MM DIFFUSED POLY-
CARBONATE SIDEWALL
GLAZING
STAINLESS STEEL
SINK AND
DRAINBOARD
STAINLESS STEEL
SINK & DRAINBOARD
GREENHOUSE B GREENHOUSE A
METAL
DOWNSPOUT
TRANSITION BOX
AT GUTTER END
BOTTOM OF BOTTOM CHORD
OF TRUSS = EAVE HEIGHT
VESTIBULE
8 MM DIFFUSED POLYCARBONATE
SIDEWALL GLAZING
FEDCBA
A-201
4 GREENHOUSE WEST ELEVATION
SCALE: 3/8"= 1'-0"
GREENHOUSE A GREENHOUSE B
8 MM DIFFUSED POLYCARBONATE
GLAZING AT ROOF
8 MM DIFFUSED POLY-
CARBONATE
SIDEWALL GLAZING
METAL DOWNSPOUT
TRANSITION BOX
AT GUTTER END
COOLING PADS
WITH CONTINUOUS
TOP HINGED VENT
6 5
INSECT CLOTH
LEAN-TO
FRAMING
INSECT CLOTH
8 MM DIFFUSED POLY-
CARBONATE
ENDWALL GLAZING
INSECT CLOTH
CONTINUOUS STEEL
BASE STRINGER
BURIED INTO GRADE
A-201
3 GREENHOUSE NORTH ELEVATION
SCALE: 3/8"= 1'-0"
VESTIBULE DOOR
BEYOND
VESTIBULE DOOR
BEYOND
8 MM WHITE OPAL POLYCARBONATE
GLAZING AT VESTIBULE WALLS
INSECT CLOTH & FRAMING AT EXHAUST
CORRIDOR OMITTED FOR CLARITY
INSECT CLOTH & FRAMING AT EXHAUST
CORRIDOR OMITTED FOR CLARITY
INSECT CLOTH & FRAMING AT COOLING
PAD CORRIDOR OMITTED FOR CLARITY
A.1D.1E.1
TRANSITION BOX
AT GUTTER END
TRANSITION BOX
AT GUTTER END
'-0
" L
EA
N-
TO
E
AV
E
'-0
'-0
" L
EA
N-
TO
E
AV
E
'-0
'-0
" L
EA
N-
TO
V
ES
TI
BU
LE
E
AV
E
'-0
'-0
' L
EA
N-
TO
E
AV
E
'-0
EXHAUST FAN BY
GHSE MFR.--TYP.
5 1 4 6 7
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
EXTERIOR ELEVATIONS
A-201 10 214/3/2024
RPP
T. GOEBEL
P. SMITH
2.5
2.512
ROOM NO ROOM NAME FLOOR BASE
MAT'L FINISH
EAST WALL
MAT'L FINISH
WEST WALL
MAT'L FINISH
NORTH WALL
MAT'L FINISH
SOUTH WALL
WALLS
MAT'L HEIGHT
CEILING NOTES
101 SC WOPC
COOLING PAD CORRIDOR
SC
- DPC - IS - IS - IS -
IS IS
IS
- DPC - IS - DPC -102
VARIES
VARIES
VARIES
G
VESTIBULE
GH-A EXHAUST CORRIDOR
SC IS - DPC IS
SC DPC - DPC - DPCDPC -
VARIESGH-B EXHAUST CORRIDOR
GREENHOUSE B
- DPC - WOPC - WOPC -
DPC - IS
FINISH SCHEDULE
WOPC
DPC
- VARIES-
SC DPC DPC- DPC - DPC - DPC -103 VARIESGREENHOUSE A -
DPC DIFFUSED POLYCARBONATE PANEL
G WASHED GRAVEL
IS INSECT SCREEN
WOPC WHITE OPAL POLYCARBONATE PANEL
SC SEALED CONCRETE
ABBREVIATIONS
A-301
1 GREENHOUSE CROSS SECTION
SCALE: 3/8"= 1'-0"
1 2
3 4
5 6
GREENHOUSE A
COOLING PAD
CORRIDOR
GREENHOUSE A EXHAUST
CORRIDOR
SCALE: 3/8"=1'-0"
0 1' 2' 4' 8'
8 MM DIFFUSED POLY-
CARBONATE
GLAZING AT ROOF
GREENHOUSE ROOF
TRUSSES
SIDEWALL KNEE
BRACE
4" SQUARE SIDEWALL
COLUMNS 12' O.C. BEYOND
4" SQUARE ENDWALL
COLUMNS AT ENDWALL
BEYOND
' E
AV
E
HE
IG
HT
A
T
GH
SE
S
ID
EW
AL
LS
COOLING PADS
LEAN-TO COLUMN
MATCH GREENHOUSE
COLUMN SPACING
INSECT CLOTH
CONTINUOUS STEEL
BASE STRINGER BURIED
INTO GRADE
CONCRETE FLOOR SLAB
LEAN-TO COLUMN
MATCH GREENHOUSE
COLUMN SPACING
INSECT CLOTH
ALUMINUM RIDGE
FLASHING
TRENCH DRAIN
EXHAUST FAN
HOOD
EQUIPMENT BARS
48" O.C.
ENERGY CURTAIN
SYSTEM
SLOPE FLOOR SLAB 1"SLOPE FLOOR SLAB 1"
CONTINUOUS TOP
HINGED VENT
CONCRETE FLOOR
SLAB
'-0
"12 '-0
'-0
" 12 '-0
GUTTER
GUTTER
A-301
2 DOOR SCHEDULE
SCALE: 3/8"= 1'-0"
3'-0"
7'- 0"
3'-0"
7'- 0"
1-3/4" THICK FLUSH HOLLOW CORE
METAL DOOR AND FRAME
1-1/4" THICK STILE AND RAIL
SCREEN DOOR AND FRAME
61 THRU 7
PPM
REVISIONS
Agricultural
Service Research
DESCRIPTION
SHEET
DATE
c P.A.
FIRM
U
NO.
DEPM
SAFETY & HEALTH
REAL PROPERTY
A
DATE
PROJECT NO.
SUSDA
BY
OF
THE
DESIGNER
PROJECT MANAGER
JOB #
CHECKED BY
A-E FIRM
P.O. BOX 513, GREENWOOD, MISSISSIPPI - (662) 455-4943
Johnson M Adams
ARCHITECTS/ENGINEERS PLANNING SURVEYING MANAGEMENT
USDA - ARS - PWA
800 BUCHANAN STREET
ALBANY, CA 94710
SAN JOAQUIN VALLEY
AGRICULTURAL SCIENCES CENTER
PARLIER, CALIFORNIA
CDPG GREENHOUSE
CROSS SECTION & SCHEDULES
A-301 11 214/3/2024
RPP
T. GOEBEL
P. SMITH
2.512
4'- -V
ER
IF
Y 3'-
0"
6" DEEP GRAVEL
1. COORDINATE MECHANICAL AND ELECTRICAL SUCH THAT MECHANICAL PIPING, DUCTWORK AND EQUIPMENT IS NOT LOCATED OVER OR
ABOVE ANY ELECTRICAL, COMMUNICATIONS, OR DATA EQUIPMENT.
2. AT START OF CONSTRUCTION, PREPARE TYPED LISTS OF EQUIPMENT THAT IS BEING SUPPLIED REQUIRING ELECTRICAL WORK, AND
SEND LISTS TO THE ELECTRICAL CONTRACTOR FOR REVIEW AND COORDINATION.
3. EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S APPROVED CLEARANCE, UNIFIED FACILITIES CRITERIA, AND INTERNATIONAL BUILDING CODE / INTERNATIONAL MECHANICAL CODE.
4. INSTALLATION OF EQUIPMENT SHALL PERMIT ACCESSIBILITY FOR SERVICE AND/OR REPLACEMENT WITHOUT NECESSITATING
REMOVAL OR MODIFICATION TO OTHER PIPING, WIRING, OR EQUIPMENT.
5. CEILING-MOUNTED EQUIPMENT SHALL BE INSTALLED IN SUCH A MANNER THAT LIGHTS, PIPING, DUCTWORK, ETC., DO NOT BLOCK
ACCESS TO EQUIPMENT AND RELATED ACCESSORIES.
6. COORDINATE WALL, FLOOR, AND ROOF PENETRATIONS WITH APPLICABLE TRADES.
7. CAULK WITH SILICONE ALL GAPS BETWEEN WALL, CEILING, AND FLOOR OPENINGS AND HVAC EQUIPMENT PENETRATIONS. PATCH
LARGE GAPS BEFORE CAULKING IS APPLIED.
8. SUPPLEMENTAL STEEL MEMBERS REQUIRED TO SUPPORT HVAC EQUIPMENT FROM MAIN STRUCTURE SHALL BE PROVIDED BY THE
HVAC CONTRACTOR UNLESS SPECIFICALLY NOTED…