CAT initial engine start and break-in (1).doc

DOC document 55 KB Posted

Attached to
OEM (CATERPILLAR) SSDG LONG BLOCK OVERHAUL SERVICES
Solicitation number
5200025RFQ0001742
Issued by

About this file

This is a technical document outlining the initial start and break-in procedures for Caterpillar D-398, D-348, or 3406 series engines, which relates to a Coast Guard solicitation for OEM Caterpillar SSDG long block engine overhaul services. The document provides a detailed 15-step process for engine initialization, including fluid filling, system priming, pre-lubrication, manual engine turning, startup monitoring, load testing, and maintenance requirements.

The associated solicitation (5200025RFQ0001742) is a small business set-aside from the US Coast Guard Surface Force Logistics Center for Caterpillar SSDG long block engine overhaul services to be performed at USCGC EAGLE in Baltimore, MD. The period of performance is October 15 - December 9, 2025. Quotes are due by January 17, 2025, at 10:00 AM EST and must include cost breakdown, unit cost, extended price, total price, payment terms, and company information. Award will be made on a firm-fixed-price basis to the responsible contractor offering the best value, considering specification, price, past performance, and quality.

View the file

Other files

File Type Posted
15-4265.txt TXT text file
EAGLE SOW of NO. 2 SSDG OVHL (1).doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SSDG/EDG INITIAL START AND BREAK-IN PROCESS

The subject of initial startup and break-in procedures for D-398, D-348, or 3406 series engines isn’t provided in the CATERPILLAR Service Manuals.

Please utilize the following guidelines to complete this process.

1. Fill all fluids to normal operating levels.

2. Energize all heaters and allow sufficient time (24 hrs) for them to bring temps to within their designed range.

3. Prime the fuel system. Check for any fuel leaks.

4. Pre-lube engine and pour a quart of oil into the turbocharger housing (s) via the oil inlet/supply line to provide lubrication prior to initial start.

5. Bar the engine over by hand (DO NOT USE STARTER) at least two full revolutions or more in the same direction as normal engine rotation (do not rotate backwards) to ensure it doesn't bind up at any point. IF the engine feels abnormally tight or reaches a point you can’t turn it over by hand STOP and investigate possible causes. DO NOT ATTEMPT TO START until the issue is identified and corrected.

6. Start the engine locally and observe the gauge panel for oil pressure (Note: oil pressure is the most critical concern at this point). Once oil pressure has been confirmed check all other parameters for normal operation.

7. Listen for any unusual noise and check over the engine multiple times for leaks while continuing to monitor the gauge panel.

8. If the engine is free of leaks, has no abnormal noise, and all parameters (oil, fuel, jacket water, raw water) are within the normal range continue to operate for 30 minutes to allow temperatures to stabilize. Continue to check for any signs of leakage, abnormal sounds, or vibration.

9. After 30 mins of no load operation and the engine is operating properly (temps & pressures are within the normal operating ranges) place the engine under load and continue to look & listen for anything abnormal.

10. Recommend a minimum of 24.0 engine hours (under load) before getting underway. Remember to pull and test oil samples for fuel dilution. This will give you the ability to monitor engine performance over an extended period to identify and correct any potential issues before getting underway

11. Test all safety devices for proper operation.

12. Remember to “zero” out your engine hours following overhaul and note the date in your machinery history.

13. Remember to record this MPC as complete.

14. Once the engine has approximately 100 hrs. you will need to complete a base line set of DEMPS.

15. Complete your first oil and filter change IAW the MPC and send off oil samples for testing.