casework addendum, due date change
Solicitation number
RFP-OWOS-190000002446-1
Issued by
Shiawassee County, Michigan

About this file

This document is an Addendum No. 3 for the Owosso Public Schools 6-12 Campus project, prepared by Clark Construction Company for Bid Release No. 4 Casework. The addendum, dated 6/03/19, extends the bid proposal due date to Wednesday, June 12, 2019, at 11:00am, with the bid proposal to be submitted for Project No. 2770. The document provides key modifications to the original contract documents, specifically addressing bidding and contract requirements.

The primary modification outlined in the addendum is an expansion of manufacturer options, allowing bidders to propose alternate suppliers beyond the initially listed manufacturers, provided they meet the quality and performance specifications detailed in the Project Manual. The addendum emphasizes that all bidders are responsible for reviewing the document and including in their bid proposal all work reasonably inferred to be part of the project's scope, even if not explicitly specified. The document maintains the overall character and requirements of the original contract documents while providing flexibility in manufacturer selections.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 3 Project No. 2770

Owosso – 6-12 Campus

Bid Release No. 4 Casework

6/03/19

ADDENDUM NO. 3

PROJECT: Owosso Public Schools

DESCRIPTION: 6-12 Campus

BID PACKAGE RELEASE NUMBER: 3

CLARK PROJECT NO: 2770

BID PROPOSAL DUE DATE/TIME: 11:00am Wednesday June 12, 2019

The following clarifications and/or Changes made to the Contract Documents are hereby made part of the

Contract Documents.

The general character of the Work clarified or revised by this Addendum shall be the same as required by the complete set of Contract Documents. All incidentals required in connection with the Work of this

Addendum shall be included in the Scope of Work even though not specifically specified.

All bidders shall be held responsible to review the Addendum and to include in its Bid Proposal all Work reasonably inferred to be included in its Scope of Work.

Acknowledge receipt of this Addendum in the space provided on the Bid Proposal Form.

A. Bidding and Contract Requirement Modifications:

1. Bid Due date extended to Wednesday June 12, 2019 at 11:00am.

B. Scope Changes / Clarifications:

General

1. Manufacture options are open beyond the listed manufacturers as long as alternate suppliers meet the quality and performance specifications of the

Project Manual.