This is a Statement of Work (SOW) for storm debris removal at the Carl Sandburg National Historic Site in Flat Rock, North Carolina, resulting from damage caused by Hurricane Helene. The project scope involves removing approximately 400 cubic yards of downed trees and debris from various locations within the 264-acre site, including the hikers' lot parking lot, Carl Sandburg Lane, Buck House, Orchard Trail, Boneyard, Visitor Contact Station, Main Lot, Main House lawn, Tenant House restrooms, amphitheater, and front and side pastures.
The contractor will be responsible for completely removing all storm-related debris within 25 feet of specified locations, including bucking, limbing, and removing approximately 20 downed trees in the pastures. Work must be completed with a focus on ensuring public safety, preserving the site's historic and natural integrity, and adhering to National Park Service preservation standards. The project aims to create safer areas, reduce insect and fire hazards, and minimize impacts to natural resources. All chipped or ground debris must be removed from the site and disposed of offsite. Contract operations are limited to 7:00 am to 5:00 pm, and the contractor must provide all necessary personnel, equipment, and transportation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources_Sought_Worksheet_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
Carl Sandburg National Historic Site
81 Carl Sandburg Lane, Flat Rock, NC 28731
Primary Contact: Ryan Williams, Facility Manager
Project Title
Storm Debris Removal
Prepared by
Ryan Williams
PEPC Project ID: 109666
1.0 – BACKGROUND
Hurricane Helene caused extensive tree damage at Carl Sandburg. Immediate threats to life and property have been mitigated, however considerable debris continues to hamper visitor use and normal park operations.
This project entails the removal of heavy timber and debris from various locations within the Carl Sandburg Home National Historic Site. The objectives are to clear tree debris from the hikers' lot parking lot, Carl Sandburg Lane, Buck House, Orchard Trail, Boneyard, VC Contact Station, Main Lot, Main House lawn, Tenant House restrooms, amphitheater and the front & side pastures at Carl Sandburg Home National Historic site.
This will be accomplished with a focus on ensuring public safety and adhering to National Park Service preservation standards.
2.0 – SCOPE
Approximately 400 cubic yards of downed trees and debris have been cut, chipped into manageable sizes, and relocated to designated areas within the park. The debris is currently staged along Carl Sandburg Lane, the Hikers Lot Parking Lot, Boneyard, orchard trail, Buck House, Main House lawn, Tenant House Restrooms, Visitor Contact Station, Main Lot and the amphitheater area. Although the park encompasses 264 acres, only accessible areas near visitor facilities, trails, and operational zones managed by the National Park Service are included in the scope of this project. The prime contractor shall remove all the remaining storm debris staged in these identified areas and dispose of off-site from Carl Sandburg Home National Historic Site. In addition, there is storm debris in the front and side pastures that needs to be cleared while preserving the site's historic and natural integrity. Approximately 20 downed trees in these areas require removal. These trees have not yet been bucked, so they will need to undergo complete bucking, limbing, and removal from the pastures and off-site from CARL.
3.0 - OBJECTIVES - GENERAL REQUIREMENTS
The intent is that all-storm related tree debris in these designated areas shall be removed by the contractor:
• Within 25 feet of the specific locations identified (i.e. pathways, trails, roadways, historic interpretive areas or displays, pastures, facilities and parking lots).
• Front & Side Pastures.
• Carl Sandburg Lane
• Main Parking Lot & Visitor Center Contact Station.
• Hikers Lot Parking Lot.
• Boneyard
• Orchard Trail
• Buck House
• Amphitheater
• Main House Lawn
• Tenant House Restrooms
Work shall be completed to achieve the following outcomes:
• The final result of the work will reflect safer areas for people to navigate, reduce insect loading potential and reduce fire danger from the storm debris.
• Preservation of CSL and to ensure that the work maintains National Historic Landmark standards.
• Minimize impacts to natural resources by limiting scraping and compaction of soil and vegetation.
• Preserve and maintain roadside features, such as pullouts, culverts, and grassed areas.
• Photos at the end of this document identify all debris that needs to be removed in each location.
• All chipped or grinded storm debris shall be removed from Carl Sandburg Home NHS and disposed offsite.
4.0 - TASK AND DESIGN PERFORMANCE REQUIREMENTS:
-Contractor to provide all services required to achieve the general requirements.
-Contractor to provide all required equipment to including but not limited to: tandem dump, heavy equipment(excavators), woodchipper (can do up to 10 diameter trees), and saws.
-Contractor to provide all required personnel to include laborers, saw operator, equipment operators, and supervisor.
-Contractor to provide all transportation for equipment and personnel throughout project.
-Contractor will carry all debris from all work locations that cannot be chipped to a disposal facility.
-Contractor will pay all associated fees, pertaining to the refuse and debris.
5.0 Contractor Responsibility
• The contractor is responsible for compliance with all local, state, and federal laws regarding the removal and disposal of debris.
• Contractor personnel and equipment are subject to government inspection for safety compliance.
• The contractor must always provide administrative access for NPS and emergency services, including:
o Emergency response.
o Utilities servicing of water systems and restrooms.
o Utilities operations of wastewater systems.
o NPS concessionaire access.
6.0 Protection of Vegetation, Structures, and Utilities
• The contractor must protect all structures and vegetation not designated for removal. Any damage to limbs, branches, or infrastructure must be repaired or compensated.
7.0 Road and Facilities Protection
• Appropriate actions must be taken to ensure that road surfaces and edges are not damaged when, moving logs, or loading equipment on and off the road surface for travel to another site. Damage shall be considered any gouges, breaks, or any undesired modification which creates a potential hazard to traffic or hastens erosion. Logs may not be skidded on paved roads or in wooded areas.
• b) Cutting or processing equipment will not be permitted that will damage the paved road surface unless mitigation steps are taken to protect the road surface from damage. Steel-tracked equipment must be outfitted with rubber track pads.
• c) Protect existing rock walls, rock and ditches, culvert inlets, outlets, and headwalls from damage. Any roadside ditches or culverts which are altered from their original state must be restored immediately.
• d) Any damage to the road surface or appurtenances must be repaired to its original state as determined by the COR.
8.0 Natural Resource Protection
• Contractor shall instruct all workers and subcontractors to avoid conducting activities beyond the tree hazard mitigation limit.
• NPS will flag rare plant locations prior to contract operations. Avoid placement of piles and debris on rare plant locations. Avoid soil disturbance.
• Trucks and heavy equipment must remain on the road surface at all times.
• Maintain all equipment on the project in a clean, weed-free and well-functioning condition to avoid or minimize contamination from mechanical fluids.
• Contractor must submit a hazardous spill plan prior to the Notice to Proceed, detailing what actions would be taken in the case of a spill, notification measures, and preventive measures to be implemented, such as the placement of refueling facilities, storage, and handling of hazardous materials.
• Undesignated woody material removal: damage, cutting, or removal of undesignated material will be sufficient reason for termination of contract. For resource protection, if undesignated woody material is damaged or cut unnecessarily, the material shall be identified to the COR upon the next inspection and approval by the COR must be obtained in writing prior to removal of or further handling of material.
9.0 Cultural Resource Protection
• Logs shall not be dragged through sites which are flagged for avoidance.
• If any artifacts are exposed during contract operations, they shall be left in place and the Contractor must notify the COR or contact the Park Cultural Resources Specialist immediately.
10.0 DELIVERY:
-Contractor responsible for transport of all personnel, equipment, trucks, and debris.
-Contractor responsible for lodging and per diem of all personnel.
11.0 USE OF GOVERNMENT FURNISHED PROPERTY:
A. There is no use of any government furnished property. Contractor will provide all necessary personnel, tools, and equipment.
12.0 Temporary Facilities
STAGING AREA: The contractor shall arrange the location for exterior stockpiling of materials (i.e., storage) with the COR. The contractor must be present when any materials are delivered to ensure proper placement within the designated location.
1. The Government will provide an adequate staging area as close to the project site as practicable.
2. The Government will NOT provide any secured storage/staging areas for the contractor.
3. The contractor shall be responsible for protecting materials stockpiled against adverse weather, damage, theft, and other risks of loss. The Government assumes no responsibility for material or equipment left in the storage area. Neither barbed wire nor razor wire is permitted to be used for security purposes for this requirement.
13.0 Project Restrictions
• Damage Mitigation: Any damage caused by contractor equipment shall be rehabilitated to its original state. Heavy machinery will not be allowed on slopes or beyond mowed areas. Any further damage caused by contractor must be reported immediately.
• Equipment: The park will not be responsible for lost time due to contractors damaged or broken equipment.
• Access Restrictions: Hauling on park roads shall adhere to speed restrictions, with special care on saturated ground. Haul vehicles must turn only at intersections or parking areas.
• Designated Mulching Areas: Areas for placing and operating machinery for grinding and mulching debris will be designated by the park. These areas will be restricted to authorized personnel and operators only during operational periods.
14.0 SECURITY/ SAFETY:
NPS provides no site security. All accidents must be reported immediately to the Contracting Officer.
15.0 PLACE OF PERFORMANCE:
Carl Sandburg National Historic Site 81 Carl Sandburg Lane, Flat Rock, NC 28731
Contract operations shall not occur before sunrise or after sunset. Contract operations are limited to the hours of 7:00 am to 5:00 pm. In the event that the National Park Service determines that the safety of visitors is threatened by the Contractor’s operations, all or part of the Contractor’s operations may be suspended until agreement is reached on additional safety measures and precautions.
16.0 PERIOD OF PERFORMANCE:
TBD
17.0 Inspection and Times/Place of Work
• Work will be monitored by a representative of the Contracting Officer, Contracting Officer’s Representative or Project Inspector/Manager with regular meetings held to ensure compliance and safety.
END OF SECTION
Amphitheatre
Amphitheatre Cont’d
Bone Yard
Bone Yard Cont’d
Main House
Carl Sandburg Ln (Near historic entrance)
Orchard Trail
Buckhouse
Hikers Lot
Carl Sandburg Ln (Near FM yard)
Visitor Center Contact Station
Tenant House Restrooms
Main Lot
Front Pasture
Side Lake Pasture (Directly Near Side Lake) 1
Side Lake 2
Side Lake 3
Side Lake 4
Side Lake 5
Side Lake 6
Side Lake 7
Side Lake 8
Side Lake 9
Side Lake 10
Side Lake 11
Side Lake 12
Side Lake 13
Side Lake 14
Side Lake 15
Side Lake 16
Side Lake 17
Side Lake 18