Camp Perry Helipad Concrete Request for Quotes 25JUN2024 1039.pdf

PDF 116 KB Posted

Attached to
Camp Perry Helipad Concrete Delivery and Pour
Solicitation number
SRC0000021496
Issued by
Putnam County, Ohio

About this file

This document is a Request for Quotes (RFQ) issued by the Adjutant General's Department of the State of Ohio for the delivery and pouring of concrete for a helipad at Camp Perry. The project requires 370 cubic yards of 5000 psi fiber reinforced, air entrained concrete with water reducer, retarder, and plastol to be delivered over 45 days in 5 separate pours. The contractor is not responsible for forming, placing, or finishing the concrete. Bids must be submitted online through OhioBuys by the due date of June 25, 2024 at 10:39 AM. The award will be made to the lowest responsive and responsible bidder.

Pricing for the concrete must remain fixed for 60 days from the bid due date, and the awarded contractor must hold the accepted prices for the initial term of the contract. No price changes are allowed without prior written consent from the Adjutant General's Department. There are several compliance verification documents that must be submitted with the bid, including insurance certificates, business registration, and affirmative action program verification. Funding for the project is dependent on appropriations by the Ohio General Assembly and the availability of cooperative agreements through the National Guard Bureau.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Adjutant General’s Department

STATE OF OHIO

Adjutant Generals Department

Installation Management and Resources State Contracting Section

Request for Quotes: Camp Perry Helipad Concrete Delivery and Pour

Commodity Code: 30111500 – Concrete and Mortars

BID NUMBER: SRC0000021496

BIDS CAN ONLY BE SUBMITTED ONLINE THROUGH OHIOBUYS, VISIT

https://ohiobuys.ohio.gov/page.aspx/en/rfp/request_browse_public

FOR INSTRUCTIONS:

OhioBuys provides the primary platform for Supplier partners to engage in procurement activities with the State of Ohio.

For additional information on submitting proposals see the “Viewing and Responding to Solicitations” Learner Guide or the “Viewing and Responding to Solicitations” Supplier Training Video linked below.

Learner Guide https://procure.ohio.gov/static/pdf/S- LG.2%20Ohio%20Buys%20Viewing%20and%20Responding%20to%20Solicitations%20LG%20v2.1.pdf

Viewing and Responding to Solicitations https://www.youtube.com/watch?v=K6iE32BUMJ0&feature=youtu.be

If you have any difficulties, please contact Ohio Shared Services at 1-877-644-6771.

INSTRUCTIONS, TERMS AND CONDITIONS FOR BIDDING, STANDARD CONTRACT TERMS AND CONDITIONS, SUPPLEMENTAL CONTRACT TERMS AND CONDITIONS AND ADDITIONAL SPECIFICATIONS Revised 4/10/2023, are a part of this Request for Quotes. All prior versions of Instructions to Bidders, Contract Terms and Conditions are null and void.

BIDS OR QUOTES CAN ONLY BE SUBMITTED ONLINE. Please download and review all documents. Attach an itemized quote on company letterhead or business form in the questionnaire section. Note: Any pre-printed terms and conditions on forms used by the supplier do not supplement or replace the Standard Terms and Conditions of the State of Ohio, or any Specific Terms and Conditions of the resulting contract of any solicitation. No quotes sent by email, or any other means will be accepted.

Bidders should be aware that they are entering a military installation. No bidder shall bring a weapon of any sort onto the property even if said bidder is in possession of a concealed carry permit. A definition of a weapon will include any item identified by Ohio law as a deadly weapon, such as handguns, rifles, shotguns, dangerous ordnance, etc. Bidders will not be permitted onto the property with any item deemed a weapon by security personnel. There will be no exceptions.

**All prices, costs, and conditions outlined in the submitted bid shall remain fixed and valid for acceptance for 60 days, starting on the due date for bids. The awarded contractor must hold the accepted prices and/or costs for the initial term of the contract. No price change shall be effective without prior written consent from ADJ. The State shall not be liable for any costs the Bidder does not identify in its bids. **

Post questions as an inquiry through OhioBuys only. To make an inquiry, Offerors must login to OhioBuys, navigate to the solicitation, open the Inquiry tab, and submit their inquiry. Offerors will not receive a personalized e-mail response to their question, nor will they receive notification when the question has been answered. Offerors may view inquiries and responses on the OhioBuys Public Solicitations page by opening the Solicitation Overview and navigating to the inquiries section of that page. ADJ will try to respond to all inquiries within 48 hours of receipt, excluding weekends and State holidays. ADJ will not respond to any inquiries received after 8:00am on the inquiry end date.

https://ohiobuys.ohio.gov/page.aspx/en/rfp/request_browse_public https://procure.ohio.gov/static/pdf/S-LG.2%20Ohio%20Buys%20Viewing%20and%20Responding%20to%20Solicitations%20LG%20v2.1.pdf https://procure.ohio.gov/static/pdf/S-LG.2%20Ohio%20Buys%20Viewing%20and%20Responding%20to%20Solicitations%20LG%20v2.1.pdf https://www.youtube.com/watch?v=K6iE32BUMJ0&feature=youtu.be

SPECIFICATIONS

DESCRIPTION: Please see the attached Scope of Work.

1. AWARD: Any award made pursuant to this Request for Quotes shall be placed with the lowest responsive and responsible bidder having proper facilities to insure prompt performance of the work. Bidder shall not insert a unit cost more than 3 digits after the decimal point. Digit(s) beyond 3, after the decimal point shall be dropped by ADJ and not used in evaluation and any subsequent award.

A completed copy of the Bidder Certification must accompany the submitted quote as a separate document.

BIDDER CERTIFICATION: A completed and signed copy of the Bidder Certification must accompany the submitted quote. This document becomes the contract after award to include the respective proposal, proposal submission instructions, Specific Terms and Conditions (if any), Standard Terms and Conditions (Attachment 2), addenda to the solicitation, specifications, pricing schedules, Scope of Work (Attachment 1), and any attachments incorporated by reference and accepted by ADJ become a part of this Contract and constitutes the entire agreement between the parties, and any changes or modifications to this Contract must be in writing by amendment.

2. SPECIFICATIONS: Scope of Work: See attachment 1

3. CONTRACT STANDARD TERMS AND CONDITIONS: See attachment 2

4. INSTRUCTIONS TO BIDDERS: See attachment 3

5. COMPLIANCE VERIFICATION DOCUMENTATION TO BE SUBMITTED WITH QUOTE (any quote submitted that does not include compliance verification documents will not be considered):

• Acord Certificate or Certificate of Liability Insurance with Endorsements and Stop Gap coverage

• Verify Current Address and Contact Information – Signed Bidder’s Certification Form (blank form provided)

• PROHIBITION OF THE EXPENDITURE OF PUBLIC FUND FOR OFFSHORE SERVICES

No State Cabinet Agency, Board or Commission will enter into any contract to purchase services provided outside of the United States or that allows State data to be sent, taken, accessed, tested, maintained, backed-up, stored, or made available remotely outside (located) of the United States, unless a duly signed waiver from the State has been attained. Notwithstanding any other terms of this Contract, the State reserves the right to recover any funds paid for services the Contractor performs outside of the United States for which it did not receive a waiver. The State does not waive any other rights and remedies provided to the State in the Contract.

Further, no State agency, board, commission, State educational institution, or pension fund will make any purchase from or investment in any Russian institution or company. Notwithstanding any other terms of this Contract, the State reserves the right to recover any funds paid to Contractor for purchases or investments in a Russian institution or company in violation of this paragraph. The provisions of this paragraph will expire when the applicable Executive Order is no longer effective.

The Contractor must complete the Contractor/Subcontractor Affirmation and Disclosure Form https://procure.ohio.gov/pdf/EO2022-02D/04-Affirmation%20and%20Disclosure%20Form_3-4-22.pdf affirming the Contractor understands and will meet the requirements of the above prohibition. During the performance of this Contract, if the Contractor changes the location(s) disclosed on the Affirmation and Disclosure Form, Contractor must complete and submit a revised Affirmation and Disclosure Form reflecting such changes.

• Affirmative Action Program Verification Form (AAPV)

• Secretary of State Charter/Registration Number (questions regarding registration should be directed to (614) 466-3910 or visit the web site at https://www.ohiosos.gov/

• Current BWC Certification

• MBE, VBE, EDGE, WBE business must provide a copy of their certification.

https://procure.ohio.gov/pdf/EO2022-02D/04-Affirmation%20and%20Disclosure%20Form_3-4-22.pdf https://development.ohio.gov/business/construction-compliance/affirmative-action-program https://www.ohiosos.gov/

6. APPROPRIATION OF FUNDS: This agreement, and the exercise by ADJ of any option to renew the Contract

Term, is subject to appropriation by the General Assembly, and certification by the Director of Budget and Management of available funds as required by Chapter 126 of the Ohio Revised Code and approval by the State Controlling Board, if required pursuant to Chapter 127 of the Ohio Revised Code. Furthermore, funding for this agreement is also dependent on the availability of cooperative agreements through the National Guard Bureau, Office of Grants and Cooperative Agreements utilizing NGR 5-1. If at any time these funds are no longer available, the ADJ will be released from its obligations on the date funding is set to cease.