California Boulevard _ Taft Street Roundabout.pdf
PDF 12 MB Posted
- Attached to
- California Boulevard & Taft Street Roundabout
- Solicitation number
- 2091503
- Issued by
- San Luis Obispo County, San Francisco City, California
About this file
Summary
This is a project description document for the California Boulevard & Taft Street Roundabout project in California. The project consists of roadway reconstruction, drainage improvements, utilities work, sidewalk construction, landscaping, traffic control measures, and related improvements. The scope encompasses comprehensive infrastructure development at the intersection of California Boulevard and Taft Street to implement a roundabout configuration that will improve traffic flow and safety at this location.
The document provides the foundational project overview for the construction contract opportunity. Specific details regarding pricing terms, contract duration, bid submission deadlines, site visit requirements, pre-bid meetings, award timelines, and funding sources are not included in this project description file and would be found in accompanying solicitation documents or bid specifications.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
FOR
CITY OF SAN LUIS OBISPO
California Boulevard & Taft Street Roundabout
Specification No. 2091503
November 2026
PUBLIC WORKS DEPARTMENT
ENGINEERING DIVISION
919 Palm Street San Luis Obispo, CA 93401
(805) 781-7200
California Boulevard & Taft Street Roundabout
Specification No. 2091503
Approval Date: November 9th, 2026
Hai Nguyen
November 9th, 2026
Brian Nelson
November 9th, 2026
TABLE OF CONTENTS
NOTICE TO BIDDERS ..................................................................................................... I
BID SUBMISSION ...................................................................................................................................... I
BID DOCUMENTS .................................................................................................................................... II
PROJECT INFORMATION........................................................................................................................ II
QUALIFICATIONS .................................................................................................................................... III
AWARD ..................................................................................................................................................... V
ACCOMMODATION .................................................................................................................................. V
BID FORMS .................................................................................................................... A
BID ITEM LIST FOR CALIFORNIA BOULEVARD & TAFT STREET ROUNDABOUT, SPECIFICATION
NO. 2091503 ............................................................................................................................................. A
LIST OF SUBCONTRACTORS ................................................................................................................. F
LABOR CODE SECTION 1725.5 STATEMENTS ................................................................................... G
NONCOLLUSION DECLARATION .......................................................................................................... H
BIDDER ACKNOWLEDGEMENTS ............................................................................................................ I
QUALIFICATIONS ..................................................................................................................................... J
ATTACH BIDDER'S BOND TO ACCOMPANY BID .................................................................................. K
SPECIAL PROVISIONS
DIVISION I GENERAL PROVISIONS
1 GENERAL
3 CONTRACT AWARD AND EXECUTION
4 SCOPE OF WORK
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
8 PROSECUTION AND PROGRESS
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
13 WATER POLLUTION CONTROL
15 EXISTING FACILITIES
DIVISION III EARTHWORK AND LANDSCAPE
17 GENERAL
19 EARTHWORK
20 LANDSCAPE
26 AGGREGATE BASES
DIVISION V SURFACINGS AND PAVEMENTS
37 BITUMINOUS SEALS
39 ASPHALT CONCRETE
DIVISION VI STRUCTURES
47 EARTH RETAINING SYSTEMS
DIVISION VIII MISCELLANEOUS CONSTRUCTION
73 CONCRETE CURBS AND SIDEWALKS
DIVISION VIII MISCELLANEOUS CONSTRUCTION
77 LOCAL INFRASTRUCTURE
DIVISION IX TRAFFIC CONTROL DEVICES
82 SIGNS AND MARKERS
84 MARKINGS
DIVISION X ELECTRICAL WORK
86 GENERAL
87 ELECTRICAL SYSTEMS
DIVISION XIII APPENDICES
ADD SECTION 100 APPENDICES
APPENDIX A - FORM OF AGREEMENT
APPENDIX B – SEALMASTER SAFE RIDE DATA SHEET
APPENDIX C – CALTRANS ENCROACHMENT PERMIT REQUIREMENTS
APPENDIX D – GEOTECHNICAL REPORT
APPENDIX E – TEMPORARY TRAFFIC CALMING AND PEDESTRIAN CROSSING
PLANS
APPENDIX F – PG&E CONSTRUCTION SKETCH
APPENDIX G – EASEMENT DOCUMENTS
NOTICE TO BIDDERS
i
BID SUBMISSION
Sealed bids will be received by the City of San Luis Obispo at the Public Works Administration Office located at 919 Palm Street, San Luis Obispo, California 93401, until
11:00 a.m. on December 10th, 2026 at which time they will be publicly opened and read aloud. Public bid opening may also be viewed via Microsoft Teams video conference and conference call. Use the following link:
https://teams.microsoft.com/meet/2904485856218074?p=N757mEEpf4vpu1T2yJ or join by phone with this number: 1 (209) 645-4165 with Conference ID: 179 106 217#
Submit bid in a sealed envelope plainly marked:
California Boulevard & Taft Street Roundabout, Specification No. 2091503
Any bid received after the time and date specified will not be considered and will be returned to the bidder unopened. Bids received by Fax or Email will not be considered.
By submission of bid you agree to comply with all instruction and requirements in this notice and the contract documents.
All bids must be submitted on the Bid Item List form(s) provided and submitted with all other Bid Forms included in these Special Provisions.
Each bid must be accompanied by either a:
1. certified check
2. cashier's check
3. bidder's bond made payable to the City of San Luis Obispo for an amount equal to ten percent of the bid amount as a guaranty. Guaranty will be forfeited to the City San Luis Obispo if the bidder, to whom the contract is awarded, fails to enter into the contract.
The City of San Luis Obispo reserves the right to accept or reject any or all bids or waive any immaterial irregularities in a bid.
All bids are to be compared based on the City Engineer's estimate of the quantities of work to be done, as shown on the Bid Item List.
Bids will only be accepted from bidders that are licensed in compliance with the provisions of Chapter 9, Division III of Business and Professions Code.
ii
The award of the contract, if awarded, will be to the lowest responsive bid submitted by a responsible contractor whose bid complies with the requirements prescribed. If the contract is awarded, the contract will be awarded within 60 calendar days after the opening of the bids.
Failure to raise defects in the notice to bidders or bid forms prior to bid opening constitute a waiver of those defects.
BID DOCUMENTS
A copy of the plans and special provisions may be downloaded, free of charge, from the City’s website at:
www.slocity.org/government/department-directory/public-works/public-works-bids-proposals
No printed copies are available for purchase at the City office.
Request must include Specification Number. The office of the City Engineer is located at:
San Luis Obispo, CA 93401
Standard Specifications and Engineering Standards referenced in the Special Provisions may be downloaded, free of charge, from the City’s website at:
www.slocity.org/government/department-directory/public-works/documents-online/construction-documents
You are responsible to obtain all issued addenda prior to bid opening. Addenda will be available to download at the City’s website listed above or at the office of the City Engineer.
All questions must be submitted through BidNet and if the City determines that a response is required, the City will post an addendum on BidNet. Contact the project manager, Hai Nguyen at 805-781-7108 / hnguyen@slocity.org or the Public Works Department at (805) 781-7200 prior to bid opening to verify the number of addenda issued.
You are responsible to verify your contact information is correct on the plan holders list located on the City’s website at:
www.slocity.org/government/department-directory/public-works/public-works-bids-proposals.
PROJECT INFORMATION
In general, the project consists of roadway reconstruction, drainage, utilities, sidewalks, landscaping, traffic control, and related improvements.
iii
The project estimated construction cost is $5,000,000.
Contract time is established as 180 working days.
The fixed liquidated damages amount is established at $2,000 per day for failure to complete the work within the contract time.
Pursuant to Labor Code section 1720 et seq., the project is subject to the prevailing wage requirements applicable to the locality in which the work is to be performed for each craft, classification or type of worker needed to perform the work, including employer payments for health and welfare, pension, vacation, apprenticeship and similar purposes. In compliance with section 1773 of the Labor Code, the State of California Department of Industrial Relations (“DIR”) has established prevailing hourly wage rates for each type of workman. Current wage rates are on file with the City and may also be obtained from the DIR’s website at:
https://www.dir.ca.gov/oprl/DPreWageDetermination.htm
Each contractor and subcontractor must pay no less than the specified rates to all workers employed to work on the project. The schedule of per diem wages is based upon a working day of eight hours. The rate for holiday and overtime work must be at least time and one-half.
This project is subject to compliance monitoring and enforcement by the DIR.
QUALIFICATIONS
You must possess a valid Class A or C12 Contractor's License at the time of the bid opening.
You and any subcontractors must be registered with the DIR pursuant to section
1725.5 of the Labor Code. Subject to limited legal exceptions for joint venture bids and federally-funded projects, City may not accept a bid from a bidder without proof that the bidder is registered with the DIR to perform public work under Labor Code section 1725.5.
You must have experience constructing projects similar to the work specified for this project. Provide three similar reference projects completed as either the prime or subcontractor. All referenced projects must have been completed within the last five years from this project’s bid opening date.
One of the three reference projects must have been completed as prime contractor under contract with a city, county, state or federal government agency.
All referenced projects must include roadway excavation and paving, ADA curb ramp construction, and drainage facility improvements within the public right-of-way.
iv
Failure to provide reference projects as specified in this section and as required on the qualification form may be cause to reject a bid.
The City reserves the right to reject any bid based on non-responsiveness if a bidder fails to provide a bid that complies with all bidding instructions.
The City reserves the right to reject a responsive bid based on the non-responsibility of the bidder if the Director of Public Works and Utilities or Designee finds, after providing notice and a hearing to the bidder, that the bidder lacks the
1. knowledge
2. experience,
3. or is otherwise not responsible as defined in Section 3.24 of the San Luis Obispo Municipal Code to complete the project in the best interest of the City.
Rejected bidders may appeal this determination. Appeal must comply with the requirements in this Notice to Bidders.
It is the City of San Luis Obispo’s intent to award the contract to the lowest responsive bid submitted by a responsible bidder. If in the bidder’s opinion the contract may be improperly awarded, the bidder may protest the contract award.
Only a bidder who has actually submitted a bid is eligible to submit a bid protest against another bidder. Subcontractors are not eligible to submit bid protests. A bidder may not rely on the bid protest submitted by another bidder, but must timely pursue its own protest.
Protests must be filed no later than five working days after the bid opening date.
Protest must be in writing and received by the project manager located at:
San Luis Obispo, CA 93401.
Valid protests must contain the following information:
1. basis for the protest. The protest must refer to the specific portion or portions of the Contract Documents upon which the protest is based
2. all supporting documentation
3. the ruling expected by the City to remedy the protest.
Any protest not containing all required information will be deemed invalid and rejected.
The City will consider additional documentation or other supporting information regarding the protest if submitted in compliance with the specified time limits. Anything submitted after the specified time limit may not be considered.
v
The Director of Public Works and Utilities or Designee may request additional information to be submitted, unless otherwise specified, and will notify the protester of ruling.
If the protester is not satisfied with ruling, the protester may appeal the ruling to the City Council in compliance with Chapter 1.20 of the City of San Luis Obispo Municipal Code.
The procedure and time limits set forth in this Section are mandatory and are the bidder’s sole and exclusive remedy in the event of a bid protest. A bidder’s failure to comply with these procedures will constitute a waiver of any right to further pursue a bid protest, including appeal of the ruling to the City Council, filing a Government Code Claim, or initiation of legal proceedings.
City reserves the right, acting in its sole discretion, to reject any bid protest that it determines lacks merit, to award the Contract to the bidder it has determined to be the responsible bidder submitting the lowest responsive bid, and to issue a Notice to Proceed with the Work notwithstanding any pending or continuing challenge to its determination.
Pursuant to the Public Records Act (Government Code § 7920.000 et seq.), the City will make public records available upon request.
AWARD
The lowest bidder will be determined using the BID TOTAL
As a condition to executing a contract with the City, a payment bond and performance bond each equal to one hundred percent of the total contract price are required in compliance with Section 3-1.05 of the Standard Specifications. Each bond must be issued and executed by a surety admitted in California.
You may substitute securities in lieu of retention under the contract in compliance with the provisions of the Public Contract Code § 22300.
ACCOMMODATION
If any accommodations are needed to participate in the bid process, please contact Kelly Mokbel at (805) 781-7274 or by Telecommunications Device for the Deaf at (805) 781- 7107. Requests should be made as early as possible in the bidding process to allow time for accommodation.
BID FORMS
A
BID FORMS
All bid forms must be completed and submitted with your bid. Failure to submit these forms and required bid guaranty (bid bond, cashier’s check, or certified check) may be cause to reject the bid as nonresponsive. Staple all bid forms together.
THE UNDERSIGNED, agrees that they have carefully examined:
1. the location of the proposed work
2. the plans and specifications
3. read the accompanying instructions to bidders and propose to furnish all:
1. materials
2. labor to complete all the required work satisfactorily in compliance with
3. plans
4. specifications
5. special provisions for the prices set forth in the bid item list:
BID ITEM LIST FOR CALIFORNIA BOULEVARD & TAFT STREET ROUNDABOUT,
SPECIFICATION NO. 2091503
Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures)
1 7,12 Temporary Traffic Control Plan and Implementation
LS 1 --------------
2 12 Temporary Striping and Pavement Markings
LS 1 --------------
3 12 Portable Changeable Message Sign
EA 2
4 13 Storm Water Pollution and Prevention Plan and Implementation
LS 1 --------------
5 84 Remove Striping and Markings LS 1 --------------
6 15, 19 Demolition - Removal and Disposal of Existing Improvements
LS 1 --------------
7 5 Construction Surveying LS 1 --------------
8 7 Comply with Night Work Permit LS 1 --------------
9 3, 7 Comply with Caltrans Permit LS 1 --------------
10 7 Construction Phasing Plan LS 1 --------------
11 7 Temporary Construction Fencing LS 1 --------------
12 77 Utility Potholing and Verification LS 1 --------------
13 82 Relocate Roadside Sign-One Post
EA 4
B
Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures)
14 15 Adjust Manhole to Grade EA 3
15 15 Adjust Valve to Grade EA 2
16 15 Adjust Utility Vault to Grade EA 2
17 17 Clearing and Grubbing, Including Tree and Vegetation Removal
LS 1 --------------
18(F) 19 Roadway Excavation (Final Pay) CY 2,660
19(F) 19 24" Overexcavation within Planter Area (Final Pay)
CY 909
20 77 Relocate Water Meter EA 3
21 77 Relocate Backflow Preventer Assembly
EA 1
22 20 Modify Existing and Install New Irrigation System
LS 1 --------------
23 5, 15 Adjust Monument Cover to Grade
EA 3
24 5, 15 Remove and Replace Monument EA 2
25 20 Caltrans Class 2 Permeable Material
CY 97
26 20 Imported Biofiltration Soil CY 159
27 20 Imported Topsoil CY 587
28 20 Rock (Cobble) Mulch SQFT 484
29 20 Packet Fertilizer EA 2,038
30 20 Tree (36" box) EA 11
31 20 Shrub (1-gal) EA 1,446
32 20 Shrub (5-gal) EA 274
33 20 Plant Establishment Work - 1 year
LS 1 --------------
34 20 Wood Mulch CY 100
35 20 Root Barrier LF 48
36 20 Edging LF 640
37 20 Gravel Mulch SQFT 1,070
38 20 Cultivation SQYD 1,000
39(F) 26 Class 2 Aggregate Base (Final Pay)
CY 1,160
40 73 Concrete Pad per Detail AK, Sheet 24
SQFT 51
41 37 Slurry Seal (Type II) SQFT 22,340
42 15, 39 Cold Plane (2 Inches) SQFT 2,400
43 39 3/4" Hot Mix Asphalt (Type A) TON 1,380
44 39 1/2" Hot Mix Asphalt (Type A) TON 439
C
Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures)
45 47 City Std 5030 Retaining Wall LF 29
46 82 Sign Panels EA 71
47 82 Roadside Sign - One Post EA 40
48 82 Roadside Sign - Two Post EA 5
49 82 Install Sign (Strap and Saddle Bracket Method)
EA 3
50 77 4" PVC Pipe LF 55
51 77 8" PVC Pipe LF 23
52 77 18" HDPE LF 505
53 77 18" RCP LF 137
54 77 Sidewalk Underdrain With Pipes LF 178
55 77 18" Concrete Flared End Section EA 2
56 77 Cleanout EA 1
57 77 City Std 3510 SDMH EA 2
58 77 City Std 3350 SDCB EA 1
59 77 City Std 3360 SDCB EA 1
60 77 Type G6 DI EA 1
61 70 Overflow Structure incl SS trash capture insert & grate
EA 2
62 70 Tree box filter EA 1
63 70 Modular Wetland EA 1
64 20, 70 Cobble Rock CY 8
65 70 HDPE or PVC 30 mil liner SQYD 110
66 47, 72 Rock Slope Protection (No. 1, Method B)
CY 4
67 47, 72 Rock Slope Protection Fabric (Class 8)
SQYD 12
68 73 Minor Concrete (City Std 4020 Curb)
LF 634
69 73 Minor Concrete (Caltrans Type D4 Curb)
LF 250
70 73 Detectable Warning Surface SQFT 572
71 73 Curb Opening per Detail K, Sheet 14
EA 3
72 73 Minor Concrete (City Std 4030 Curb & Gutter)
LF 950
73 73 Minor Concrete (Modified City Std 4030 Curb & Gutter)
LF 53
74 73 Minor Concrete (Driveway) SQFT 1,931
75 73 Minor Concrete (Stamped Concrete)
SQFT 5,239
D
Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures)
76 73 Minor Concrete (Sidewalk, Pedestrian Walkway, Ramps)
SQFT 5,915
77 82 Type 8 Object Marker EA 6
78 84 6" Thermoplastic Traffic Stripe LF 4,340
79 84 8" Thermoplastic Traffic Stripe LF 158
80 84 Thermoplastic Pavement Marking
SQFT 2,037
81 84 6" Thermoplastic Traffic Stripe (Detail 39A)
LF 1,702
82 84 6" Thermoplastic Traffic Stripe (Detail 40)
LF 215
83 84 6" Thermoplastic Traffic Stripe (Detail SP2)
LF 698
84 84 Green Bike Lane SQFT 991
85 77 Remove Existing and Install New Fire Hydrant
EA 1
86 87 New Street Light Pole EA 8
87 87 Relocate Existing Parking Light EA 2
88 8, 86 Install RRFB System - California and Taft
LS 1 --------------
89 86 Relocate Existing California & Taft Monument Sign
LS 1 --------------
90 8, 86 Install RRFB System ‐ California & Hathway
LS 1 --------------
91 6, 87 Install City‐Furnished Streetlight W/ Solar Kit ‐ California & Hathway
LS 1 --------------
92 81 Install Rubber Speed Cushion EA 3
93 77 Install Rubber Median Refuge EA 3
94 77 Install Type 3 Object Marker EA 3
95 84 12" White Thermoplastic Traffic Stripe
LF 126
96 84 Install Detail 22 Traffic Stripe LF 213
97 15 Bike Lane Edge Grinding LS 1 --------------
98 37 Street Sweeping in Slurry Areas (1 Day and 30 Days)
LS 1 --------------
99* 19 Allowance Bid Item ‐ Rock Excavation
CY 100
100* 39 Allowance Bid Item ‐ Removal and Disposal of Unidentified Buried Concrete within Roadway
CY 100
101* 39 Allowance Bid Item ‐ Roadway Excavation
CY 100
E
Item Item Unit of Estimated Item Price Total No. SS(1) Description Measure Quantity (in figures) (in figures)
102* 39 Allowance Bid Item ‐ Class 2 Aggregate Base
CY 100
103* 39
Allowance Bid Item ‐ Subgrade Stabilization Geogrid (Tensar InterAx NX850 or Approved Equal)
SQFT 3,000
Bid Total $
Company Name:
(1) refers to section in the Standard Specifications, with modifications in the Special Provisions, that describe required work.
* Bid item exempt from Section 9-1.06B and 9-1.06C of the Standard Specifications. The unit price will not be adjusted regardless of the final bid item quantity.
(F) – Designates a final pay bid item in accordance with Section 9-1.02A of the City’s Standard Specifications.
F
LIST OF SUBCONTRACTORS
Pursuant to Section 4100 of the Public Contract Code and section 2-1.33C of the standard specifications, the Bidder is required to furnish the following information for each Subcontractor performing more than 1/2 percent (0.5%) of the total base bid. Do not list alternative subcontractors for the same work. Subcontracting must not total more than fifty percent (50%) of the submitted bid except as allowed in section 5-1.13 of the standard specifications.
For Streets & Highways projects, subcontractors performing less than ten thousand dollars ($10,000) worth of work need not be mentioned. Subcontractors must be registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 to be listed.
NOTE: If there are no subcontractors, write “NONE” and submit with bid.
Name Under Which Subcontractor is Licensed License Number
DIR Public Works Registration Number
Address and Phone Number of Office, Mill or Shop
Specific Description of Subcontract
% of Total Base Bid
Attach additional sheets as needed.
G
LABOR CODE SECTION 1725.5 STATEMENTS
The bidder has delinquent liability to an employee or the state for any assessment of back wages or related damages, interest, fines, or penalties pursuant to any final judgment, order, or determination by a court or any federal, state, or local administrative agency, including a confirmed arbitration award. Any judgment, order, or determination that is under appeal is excluded, provided that the contractor has secured the payment of any amount eventually found due through a bond or other appropriate means.
Yes No
The bidder is currently debarred under Section 1777.1 or under any other federal or state law providing for the debarment of contractors from public works.
Yes No
NOTE: The above Statements are part of the Bid. Signing this Bid on the signature portion constitute signature of this Statement. Bidders are cautioned that making a false certification may subject the certifier to criminal prosecution.
H
NONCOLLUSION DECLARATION
TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID
The undersigned declares:
I am the ____________________ [title] of _____________________________________ [business name], the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, `organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on _______________ [date], at __________________________________ [city], _______ [state].
s/________________________________________
Name [print]
I
BIDDER ACKNOWLEDGEMENTS
By signing below, the bidder acknowledges and confirms that this bid is based on the information contained in all contract documents, including the notice to bidders, plans, specifications, special provisions, and addendum number(s) . (Note: You are responsible to verify the number of addenda prior to the bid opening.)
The undersigned further agrees that in case of default in executing the required contract, with necessary bonds, within ten days, (not including Saturdays, Sundays, and legal holidays), after having received a mailed notice that the contract is ready for signature, the proceeds of the check or bond accompanying his bid will become the property of the City of San Luis Obispo.
Licensed in accordance with an act providing for the registration of contractors, License No. , Expiration Date .
The above statement is made under penalty of perjury, and any bid not containing this information may be considered non-responsive and may be rejected by the City.
Signature of Bidder
(Print Name and Title of Bidder) DIR– Public Works
Registration No:
Business Name (DBA):
Owner/Legal Name:
Indicate One: Sole-proprietor Partnership Corporation
List Partners/Corporate Officers:
Name Title
Business Address
Street Address
Mailing Address
City, State, Zip Code
Phone Number
Fax Number
Email Address
Date
J
QUALIFICATIONS
Failure to furnish complete reference information ON THIS FORM, as specified in this project’s Notice to Bidders and indicated below, may be cause to reject the bid. Additional information may be attached but is not a substitute for this form.
Reference Number 1 Customer Name & Contact Individual
Telephone & Email
Project Name (Site Address):
Did this project include roadway excavation and paving, ADA curb ramp construction, and drainage facility improvements within the R/W.
Yes □ No □
Describe the services provided and how this project is similar to that which is being bid:
Date project completed: Was this contract for a public agency?
Yes □ No □
Reference Number 2 Customer Name & Contact Individual
Telephone & Email
Project Name (Site Address):
Did this project include roadway excavation and paving, ADA curb ramp construction, and drainage facility improvements within the R/W.
Yes □ No □
Date project completed: Was this contract for a public agency?
Reference Number 3 Customer Name & Contact Individual
Telephone & Email
Project Name (Site Address):
Did this project include roadway excavation and paving, ADA curb ramp construction, and drainage facility improvements within the R/W.
Yes □ No □
Date project completed:
Was this contract for a public agency?
K
ATTACH BIDDER'S BOND TO ACCOMPANY BID
Know all men by these presents:
That we ____________________________________________, AS PRINCIPAL, and
_______________________________________________________, AS SURETY, are held and firmly bound unto the City of San Luis Obispo in the sum of:
____________________________________________________ Dollars (_____________) to be paid to said City or its certain attorney, its successors and assigns; for which payment, well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors or assigns, jointly and severally, firmly by these presents:
THE CONDITION OF THIS OBLIGATION IS SUCH, that if the certain bid of the above bounden ______________________________________________________________________ to construct ___________________________________________________________________ (insert name of street and limits to be improved or project) dated _____________________ is accepted by the City of San Luis Obispo, and if the above bounden _______________________________________________________, his heirs, executors, administrators, successors, and assigns shall duly enter into and execute a contract for such construction and shall execute and deliver the two bonds described within ten (10) days (not including Saturdays, Sundays, or legal holidays) after the above bounden, ______________________________________________________, has received notice by and from the said City of San Luis Obispo that said contract is ready for execution, then this obligation shall become null and void; otherwise, it shall be and remain in full force and virtue.
IN WITNESS WHEREOF, we hereunto set our hands and seals this ___ day of ______, 20____.
Bidder Principal:
Signature Date Title:
Surety:
Bidder's signature is not required to be notarized. Surety's signature must be notarized.
Equivalent form may be substituted (Rev. 6-30-14)
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main section heading of the Standard Specifications. Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications. Any paragraph added or deleted by a revision clause does not change the paragraph number of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
1 GENERAL
Add to Section 1-1.01 GENERAL:
The work must be done in compliance with the City of San Luis Obispo, Department of Public Works and Utilities:
1. California Boulevard & Taft Street Roundabout Special Provisions
2. City of San Luis Obispo Standard Specifications and Engineering Standards –
2025 edition
3. State of California, Department of Transportation Standard Specifications and
Standard Plans – 2024 edition
In case of conflict between documents, governing ranking must comply with section 5-
1.02 of the City of San Luis Obispo’s Standard Specifications.
Failure to comply with any obligation under the contract documents constitutes a breach of contract.
Add to Section 1-1.07 DEFINITIONS, Glossary:
Contract Documents: The executed Contract, including the component parts listed in Article III of the Agreement.
3 CONTRACT AWARD AND EXECUTION
Add Section 3-1.18B CONTRACT EXECUTION, Caltrans Encroachment Permit:
The City has applied for a Caltrans encroachment permit, which is anticipated to be approved prior to construction. The Contractor shall obtain a rider permit, comply with all permit conditions, and pay all associated fees. Refer to Appendix C for anticipated permit requirements. All associated costs shall be included in the contract lump sum price for "Comply with Caltrans Permit."
Measurement and Payment The lump sum contract price paid to comply with Caltrans Encroachment Permit shall include full compensation for furnishing all labor, materials, tools, equipment, personnel, and for doing all the work involved to comply with all Caltrans encroachment permit requirements.
4 SCOPE OF WORK
Add to Section 4-1.03 WORK DESCRIPTION:
Comply with the provisions of Sections 3, 5, 7, 8, 12, 13, 15, 17, 19, 20, 26, 37, 39, 47, 70, 72, 73, 77, 81, 82, 84, 86 and 87 for general, material, construction, and payment specifics.
Add Section 4-1.03A WORK DESCRIPTION, Project Specific Signage:
The Engineer will furnish Sales Tax signs mounted to moveable Barricades. Maintain Sales Tax signage in work area.
Sales Tax signs are stored at the City’s corporation Yard at Prado Road. The Contractor is responsible to load and transport from City Corporation Yard to job site and return them when the project is completed under direction of project inspector.
5 CONTROL OF WORK
Add to Section 5-1.24A CONSTRUCTION SURVEYS, General:
The Contractor shall retain a licensed land surveyor to research record maps and locate all existing survey monuments within the limits of work and all areas to be disturbed. Work shall include identification and verification of property corners, right-of-way monuments, control monuments, and benchmarks.
Special attention shall be given to existing benchmarks and property corners. All located monuments shall be documented, referenced, and protected from disturbance during construction. Payment for this work is included in the lump sum item for “Construction Surveying”. No separate or additional compensation will be allowed.
Any monument or benchmark disturbed or removed shall be reset by a licensed land surveyor in accordance with applicable regulations and with prior approval of the Engineer. Each monument or benchmark reset will be measured and paid on an each basis under the applicable bid item listed in the Bid Item List.
6 CONTROL OF MATERIALS
Add to Section 6-2.03A DEPARTMENT ACCEPTANCE, General:
For the purposes of avoiding potential delays to the first phases of work due to lengthy electrical equipment lead times, the City will furnish one streetlight pole (with mast arm) per City Standard 7910, and one solar lighting kit for the new solar streetlight at the California Boulevard & Hathway intersection shown in the Temporary Traffic Calming and Pedestrian Crossing Plans (Appendix E). Contractor is responsible for furnishing the streetlight pull box and all other materials.
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Add to Section 7-1.03B PUBLIC CONVENIENCE, Traffic Control Plan
WORK HOUR RESTRICTIONS
Unless stated otherwise below or approved by the Engineer, work hours are 7:00 a.m. to 4:00 p.m. (Monday through Friday) at all the affected streets. Liquidated damages will be assessed in the amount of $500 per hour, or any portion thereof, for work performed beyond the approved work hours.
WORK IN CALTRANS RIGHT-OF-WAY
See Caltrans encroachment permit requirements (Appendix C) for additional requirements within the State Right of Way.
WORK DURING CAL POLY SPECIAL EVENTS
The Contractor must meet with City representatives no less than two (2) weeks prior to the following planned Cal Poly special events to confirm any required work hour restrictions, adjustments to temporary traffic control plans or construction activities as needed to minimize impacts to access and circulation to California Boulevard during these dates. Unless otherwise approved by the Engineer, the Contractor shall assume that active road work may be prohibited, and additional temporary traffic control devices and guide signage may be required during these dates:
Open House – April 8-10, 2027 Commencement – May 21-23, 2027 Fall Student Move-In –August 17-23, 2027
NIGHT WORK
Unless otherwise approved by the Engineer, the Contractor shall assume that the following work must be performed during nighttime work hours:
Work that requires full lane closures and/or flagging two-way traffic through a single lane of traffic on California or Taft Street.
Work that requires closure of 101 On- or Off-Ramps.
Work that requires full closure of the pedestrian/bicycle shared-use path on the west side of California Boulevard.
Work that requires closure of the private parking lots and/or driveways at 552 or
578 California Boulevard (see further details below regarding work in temporary easement areas)
Night work is permitted separately. Night work shall comply with the restrictions set forth in the permit by the City of San Luis Obispo Community Development. It is the Contractor’s responsibility to monitor the Night Work Permit expiration date. Requests to extend the Night Work Permit must be submitted to the Engineer at least 5 weeks before the permit expires. Failure by the contractor to request an extension in time, resulting in delays, will be the contractor’s responsibility, and no additional compensation or extra working days will be granted.
Night work is limited to Sunday through Thursday between the hours of 7:00 p.m. to 7:00 a.m.
The Contractor must not work two consecutive shifts, day and night, unless approved by the Engineer.
Prior to commencing the project, the Contractor must notify businesses and residences within 300 feet of the worksite about proposed night work.
Any portable or fixed equipment that produces noise (such as generators, concrete saws, jack hammers, etc.) must be equipped with sound blankets, temporary sound barriers, or other attenuating devices so as to limit impacts to adjoining properties.
When not in use, equipment must be kept in its lowest (quietest) idling state or switched off to limit noise impacts.
Any portable lighting must be shielded and/or directed away from adjacent properties.
Loudspeakers or other similar forms of communication are prohibited.
Contractor will provide lighting for all operations, no exceptions are to be made. Any contractor personnel working outside the lights will be directed to return to a lighted area or the operation must be stopped.
All contractor work vehicles, including heavy equipment, backhoes, trenching machines must have two working headlights and taillights. Vehicles without appropriate lighting will be kept from working until they are brought to compliance.
Illumination level of 10-foot candles is required for all nighttime operations, which will normally be achieved with light plants or balloon lights. All lighting fixtures must be mounted and directed in manner precluding glare to approaching traffic.
CONSTRUCTION PHASING PLAN
The Contractor must provide a detailed Construction Phasing Plan for City approval, using the general phase construction plans provided in the project plans as a guiding reference. The plan must describe each construction phase, including sequencing, limits of work, and duration, phases including deployment of a temporary traffic signal, and must explain how access to adjacent businesses will be retained and how vehicle traffic, pedestrians, and bicycles will be safely maintained through the work zone. The plan must show any lane closures, detours, temporary striping, temporary traffic signal systems needed, modifications to signal operations (flashing operation, revised phasing, etc.), access provisions, ADA-compliant pedestrian routing, and coordination needs with businesses, transit, utilities, and emergency services. It must be consistent with the
Contractor’s Traffic Control Plans and the California Manual on Uniform Traffic Control Devices (CA MUTCD). The Contractor must update the plan when conditions change, obtain approval before implementing revisions, and adhere to the approved phasing throughout construction.
Unless otherwise approved, the Contractor must submit the Construction Phasing Plans to the Engineer at the preconstruction meeting.
PEDESTRIAN ACCESS
Unless otherwise approved by the Engineer, the Contractor must retain a temporary pedestrian access route along the east side of California Boulevard, including access to adjacent businesses on Taft Street and crossing Taft Street. Temporary pedestrian access plans may require use of Sidewalk Diversions with barricades and temporary ramps (per CA MUTCD Figure TA-28), temporary crosswalk markings, and/or flagging of pedestrian traffic around the work zone.
CHANGEABLE MESSAGE SIGNS
Two (2) changeable message signs (CMS) must be installed and operational 1 week prior to the start of construction and be maintained throughout the duration of the project at locations approved by the Engineer upon review of the submitted Traffic Control Plan.
Changeable message sign shall be programmed for two flashes with the messages to be approved by the Engineer.
TEMPORARY TRAFFIC SIGNAL SYSTEM
As detailed in the phase construction plans provided within the project plans, certain phases of construction are anticipated to require use of a temporary traffic signal to manage traffic operations at the California & Taft intersection and minimize potential for traffic queues to spillback on Taft Street to the nearby US 101 SB Off-Ramp. The Contractor shall provide, install, operate, and maintain a temporary traffic signal system to control traffic at the California & Taft intersection during certain phases of construction as identified in the project plans, or where otherwise directed by the Engineer. The system shall comply with applicable provisions of the CA MUTCD.
The temporary signal system should be capable of semi-actuated operation, with vehicle detection provided on the minor-street approach (Taft Street). In the absence of a minor-street vehicle call, the system should maintain a green indication for major-street (California Boulevard) traffic and serve minor-street traffic upon detection.
As a minimum, the system shall be capable of fixed-time operation with multiple independently programmable time-of-day (TOD) timing plans and an automatic TOD schedule. Timing plans shall include programmable cycle lengths, phase splits, and other parameters necessary for the approved signal phasing.
The temporary signal system shall be self-powered and capable of continuous 24-hour, 7-day-per-week operation without connection to a hard-wired electrical power source. The system shall include adequate power generation and/or energy storage capacity to maintain uninterrupted operation under anticipated environmental and operating conditions.
Prior to procurement, the Contractor shall submit the proposed equipment, controller capabilities, signal phasing and timing plans, TOD schedule, power system specifications, and detection layout (if applicable) for approval by the Engineer. The Contractor shall provide all necessary setup, timing adjustments, maintenance, and troubleshooting throughout the duration of the work. The Contractor shall provide an approved contingency plan for signal failure, including alternate traffic control measures as directed by the Engineer.
During periods where the temporary traffic signal is in operation, the Contractor must cover/remove stop signs and “STOP” pavement markings on Taft Street and place “TRAFFIC SIGNAL AHEAD” (CA MUTCD Sign Code W3-3) signage at each upstream approach to the California & Taft intersection.
TRAFFIC CONTROL PLAN
Provide traffic control plan and traffic control application at or before the preconstruction meeting. Unless otherwise approved by the Engineer, temporary traffic control plans must be drawn to scale and be signed and stamped by a California licensed Transportation Engineer or Civil Engineer. Traffic control application may be obtained on the City’s website:
www.slocity.org/government/department-directory/public-works/documents-online/construction-documents
Upon approval of the traffic control plan, the City will issue a no-fee Encroachment Permit.
Permittee is responsible to comply with all conditions of the traffic control plan. Complete work using due diligence to restore free flowing of traffic.
Add to Section 7-1.04 PUBLIC SAFETY:
Contractor shall provide a rigid 6-ft high (minimum) chain link or other rigid work site fence surrounding the work site (including any staging and storage areas) and provide other such safeguards and facilities to keep the public and unauthorized persons from entering the construction area. Contractor may be required to remove opaque screening from portions of construction fencing as directed by the Engineer if this visibility obstruction creates traffic safety concerns.
Contractor shall leave work site clean and free from hazards at the end of each day and on weekends. Walkways must be swept daily. All tools, forms, stakes, hardware, paint cans, building materials and/or any other items that could be a potential hazard to children and park users must be removed from the work site at the end of each day.
Parking lots must be accessible at all times and no construction equipment will be allowed in the parking lot except for closures authorized under the approved construction phasing plan.
Construction equipment will be allowed to be kept on-site after hours and over weekends provided it is fully contained within the fenced and secured work site and is not accessible to the public.
8 PROSECUTION AND PROGRESS
Add Section 8-1.01A GENERAL, Order of Work:
TEMPORARY TRAFFIC CALMING AND PEDESTRIAN CROSSWALK
Unless otherwise approved by the Engineer, the first order of work shall include installation of the temporary traffic calming measures and pedestrian crosswalk as shown in Appendix E. The Contractor must provide equipment submittals for materials required for this work for City approval at the time of the preconstruction meeting and must procure materials within one (1) week following City approval of submittals.
Phasing of remaining work must generally follow the phase construction plans provided in the project plans, unless otherwise approved by the Engineer.
CONSTRUCTION IN TEMPORARY EASEMENT AREAS
In coordination with the Contractor, the City is responsible for providing a Notice of Commencement of Construction to the property owners and tenants at 552 California Boulevard and 578 California Boulevard at least 30 days prior to start of construction activities, per the Easement Deeds (Appendix G).
The Contractor, in coordination with the City, shall be available to attend up to two (2) informational meetings with owners and tenants of the 552 California Boulevard and 578 California Boulevard properties prior to start of construction.
Contractor must provide notice to respective property owners and tenants of the 552 California Boulevard and 578 California Boulevard properties at least two (2) weeks prior to any work that requires temporary closure of access driveways and/or work that occupies the private parking lots at these properties. Contractor must endeavor to accommodate reasonable requests to facilitate access to these properties and to accommodate parking lot function and commercial delivery operations.
Unless otherwise approved by the City, Contractor must reconstruct access driveways to these properties one at a time to ensure continuous access and must limit full closures of any driveway to outside of normal business hours, where feasible.
552 California Boulevard (Northeast of California & Taft Intersection)
Work within the area designated as “Temporary Construction Easement (Landscaped Area)” or “Temporary Construction Easement Area 1”, as shown in Appendix G, must be completed no later than six (6) months from the date of the Notice of Commencement of Construction, unless otherwise approved by the Engineer.
The area designated as “Temporary Construction Easement (Parking Lot and Driveway)” or “Temporary Construction Easement Area 2”, as shown in Appendix G, may be used intermittently for a period not to exceed two (2) months within the six (6) month period allowed for the Temporary Construction Easement (Landscaped Areas).
The area designated as “Temporary Non-Exclusive Access Easement”, as shown in Appendix G, is provided for non-exclusive ingress and egress and for completing driveway conforms, and may be used intermittently for a period not to exceed two (2) months within the six (6) month period allowed for the Temporary Construction Easement (Landscaped Areas).
578 California Boulevard (Southeast of California & Taft Intersection)
Work within the area designated as “Temporary Construction Easement”, as shown in Appendix G, must be completed no later than six (6) months from the date of the Notice of Commencement of Construction, unless otherwise approved by the Engineer.
The area designated as “Temporary Non-Exclusive Access Easement”, as shown in Appendix G, is provided for non-exclusive ingress and egress and for completing driveway conforms, and may be used intermittently for a period not to exceed two (2) months within the six (6) month period allowed for the Temporary Construction Easement (Landscaped Areas).
Contractor shall endeavor to retain access to on-street parking on Taft Street where practicable, unless otherwise approved by the Engineer.
RECTANGULAR RAPID FLASHING BEACON (RRFB) INSTALLATION
Below is the required sequence of work for installation of Rapid Rectangular Flashing Beacon systems, signs and striping, unless otherwise approved by the Engineer.
1. All new pedestrian/bicycle crossing signage installed with RRFB systems shall remain covered until beacon systems are installed and operational, and crosswalk markings have been installed.
2. Unless otherwise approved by the Engineer, crossing pavement markings, including crosswalks and advance yield markings, shall not be installed until beacon system(s) are installed and operational.
3. Contractor must furnish and install all equipment needed for intended operation of RRFB system. Contractor shall provide beacon system equipment submittals for City review and approval prior to procurement.
4. Contractor is responsible for coordination with beacon system manufacturer’s representative(s) as needed to provide intended operation of beacon systems.
Replace the 1st paragraph in Section 8-1.02A SCHEDULE, General with:
Provide a Level 2 schedule for this work. A three-week look ahead schedule shall be provided to the Engineer before commencing the following week’s work. This requirement shall be completed in order to continue construction work.
DIVISION II GENERAL CONSTRUCTION
12 TEMPORARY TRAFFIC CONTROL
Add to Section 12-3.01 TEMPORARY TRAFFIC CONTROL DEVICES, General:
The Contractor shall maintain all temporary traffic control devices in conformance with the approved Temporary Traffic Control Plan (TCP) and applicable requirements of the California MUTCD.
Upon written notice from the City identifying a noncompliant condition and establishing a reasonable correction deadline, the Contractor shall promptly correct the deficiency.
Failure to correct the deficiency by the specified deadline shall result in liquidated damages of $500 per calendar day, or portion thereof, for each uncorrected deficiency, commencing upon expiration of the correction deadline and continuing until corrected to the satisfaction of the Agency.
Conditions presenting an imminent hazard to public safety shall be corrected immediately upon direction of the Agency.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .