calcasieu parish pj sewer pumps and replacement parts SB-2026-PW-177 (S).pdf
PDF 2 MB Posted
- Attached to
- Sewer Pumps and Replacement Parts
- Solicitation number
- 2026-PW-177
- Issued by
- Calcasieu Parish, Louisiana
About this file
Summary
This is a sealed bid solicitation issued by the Calcasieu Parish Police Jury in Louisiana for the procurement of sewer pumps and replacement parts, identified as bid number SB-2026-PW-177. The solicitation requests factory-built and tested grinder pump units with simplex and duplex tank configurations in fiberglass, high-density polyethylene (HDPE), and polyethylene materials, along with comprehensive replacement parts for E-One grinder pumps. Specific pump configurations include simplex fiberglass tanks (24" x 60"), simplex HDPE tanks (24" x 60"), duplex polyethylene tanks (48" x 75"), and duplex fiberglass tanks (48" x 75"). The bid includes pricing for pumps only and pumps with integrated tanks in quantity ranges of 1-25 units and 26-50 units, with an extensive parts list of 329 line items. The sealed bid opening is scheduled for Thursday, November 19, 2026, at 2:00 P.M. Central Time at the Parish Government Building in Lake Charles, Louisiana. Contract unit prices are effective from January 1, 2027, through December 31, 2027, for sewer pumps and replacement parts, with a potential extension of up to 60 months total upon written agreement between parties.
Bid prices must be firm, include all delivery costs on an F.O.B. destination, freight prepaid basis, and exclude sales tax. All bids require a five percent (5%) bid guarantee in the form of a certified check, cashier's check, or surety bond. The Parish reserves the right to award items separately, grouped, or on an all-or-none basis and to reject any or all bids. A Louisiana preference of ten percent (10%) is available for Louisiana products meeting specified criteria. The successful bidder must provide warranty services, in-house training at no cost to the Parish, and visit the Parish every six months to address equipment concerns. No minimum order quantities are established, and purchases will be made only as needed during the contract period. The Parish emphasizes compliance with detailed technical specifications including UL listing requirements, NSF certification, OSHA confined space compliance, and comprehensive preventative maintenance protocols as defined in the bid documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid for Sewer Pumps and Replacement Parts
Calcasieu Parish Police Jury
Bid Number: SB-2026-PW-177
Sealed bids will be received by:
THE PURCHASING AGENT
1015 PITHON, PARISH GOVERNMENT BUILDING, 1ST FLOOR
LAKE CHARLES, LOUISIANA 70601
Until
2:00 P.M., Central Time Zone
Thursday, November 19, 2026 Advertisement in the Official Journal
LAKE CHARLES AMERICAN PRESS
Please read the updated bidding instructions on the following pages carefully.
The Calcasieu Parish Police Jury reserves the right to award items separately, grouped or on an all-or-none basis and to reject any or all bids.
SEWER PUMP & TANK SPECIFICATIONS
Where name brands, models, make or definite specifications are used within these specifications, it is in order only to denote the quality and standard required. Equivalent and compatible products may be acceptable.
The Bidder is to check each specification item “yes” or “no” to indicate compliance with the specifications herein. If “no” is checked, please list the deviation. You may include deviations on an additional sheet of paper if necessary.
Sewer Pumps with Simplex Tanks Technical Specifications
1.0 GENERAL YES NO DEVIATION
1.01 GENERAL DESCRIPTION: The MANAFACTURER
shall furnish complete factory-built and tested Grinder Pump Unit(s), each consisting of a grinder pump core suitably mounted on an integral stand of stainless steel, electrical quick disconnect (NEMA 6P), pump removal harness, discharge hose and shut-off valve, anti-siphon valve and check valve assembly, electrical alarm assembly, and all necessary internal wiring and controls.
For ease of serviceability, all pump motor/grinder units shall be of like type and horsepower throughout the system. The awarded vendor must provide a usage for the time period of the bid.
1.02 SHOP DRAWINGS: Upon request, after receipt of notice
to proceed, the MANUFACTURER shall furnish a minimum of three (3) sets of shop drawings detailing the equipment to be furnished including dimensional data and materials of construction. The ENGINEER, or Parish Representative, shall promptly review this data, and return one (1) copy as accepted, or with requested modifications. Upon receipt of accepted shop drawings, the MANUFACTURER shall proceed immediately with fabrication of the equipment.
1.03 The Successful bidder should visit the Parish at least once every six (6) months in order to address issues, concerns, and/or provide updates on equipment and technology, at no cost to the Parish.
1.04 Upon request, the successful bidder must provide in-house training at the Calcasieu Parish Police Jury’s request, at no cost to the Parish.
SB-2026-PW-177
YES NO DEVIATION
1.05 MANUFACTURER: The equipment specified shall be a
product of a company with experience in the design and manufacture of grinder pumps for specific use in low pressure sewage systems. Upon request, the company shall submit detailed installation and user instructions for its product; submit evidence of an established service program including complete parts and service manuals and be responsible for maintaining a continuing inventory of grinder pump replacement parts.
As part of the equipment evaluation, the Engineer, or Parish Representative, should consider the cost of manufacturer required preventative maintenance. The manufacturer shall indicate required preventative maintenance and periods as part of the bid package. Preventative maintenance not so listed shall be considered as inclusive of the manufacturer’s warranty and shall not be considered as justification of refusal of warranty claims.
Required Preventative Maintenance Required Frequency (Months) Clean sensing balls of floats _______________ Clean solids from basin _______________ Replace cutter assembly _______________ Replace shredder ring _______________ Reverse shredder ring _______________ Replace motor dielectric oil _______________ Un-jam grinder mechanism or pump
Upon request, the manufacturer shall provide a reference and contact list from three (3) of its largest contiguous grinder pump replacement installations for the exact type of pump proposed with an operational history of at least (3) years relative to a pressure sewer system. An installation is defined as (50) or more pumps discharging into a common force main.
1.06 OPERATING CONDITIONS: The pumps shall be capable
of delivering 14 GPM against a total dynamic head of 0 feet (0 PSIG) and 9 GPM against a total dynamic head of 138 feet (60 PSIG) at a maximum of 8.0 amps. The pump(s) must also be capable of operating at negative total dynamic head without overloading the motor(s). Under no conditions shall in-line piping or valving be allowed to create a false apparent head.
1.07 WARRANTY: The grinder pump MANUFACTURER shall
provide a part(s) and labor warranty on the complete station and accessories, including, but not limited to, panel and redundant check valve, for a period of sixty (60) months after notice of OWNER’S acceptance, but no greater than sixty (60) months after receipt of shipment. Any defects found during the warranty period will be reported to the MANUFACTURER by the OWNER.
1.08 While the unit is under warranty, the Manufacturer will be responsible for reimbursement to the Calcasieu Parish Police Jury, a stipend for warranty repair work completed in the field by Parish staff. Reimbursement rates will be determined by the manufacturer’s estimated time required to make the repair and issue reimbursement accordingly. Hourly rate $_____________
1.09 Warranty replacement parts are to be shipped to the customer at no cost to the Parish.
2.0 PRODUCT
2.01 PUMP: The pump shall be a custom designed, integral, vertical rotor, motor driven, solids handling pump of the progressing cavity type with mechanical seal. Centrifugal type pumps will not be acceptable. Double radial O-ring seals are required at all casting joints to minimize corrosion and create a protective barrier. All pump castings shall be cast iron, fully epoxy coated to 8-10 mil Nominal dry thickness, wet applied. The rotor shall be through-hardened, highly polished, precipitation hardened stainless steel. The stator shall be of a specifically compounded ethylene propylene synthetic elastomer. Buna N is not acceptable as a stator material. The material shall be suited for domestic wastewater service. Its physical properties shall include high tear and abrasion resistance, grease resistance, water and detergent resistance, temperature stability, good aging properties, and outstanding wear resistance
2.02 GRINDER: The grinder shall be placed immediately below
the pumping elements and shall be direct driven by a single, one-piece stainless steel motor shaft. The grinder impeller assembly shall be securely fastened to the pump motor shaft by means of a threaded connection attaching the grinder impeller to the motor shaft. Attachment by means of pins or keys will not be acceptable.
The grinder impeller shall be a one-piece, 4140 cutter wheel of the rotating type with inductively hardened cutter teeth. The cutter teeth shall be inductively hardened to Rockwell 50 – 60c for abrasion resistance. The shredder ring shall be of the stationary type and the material shall be white cast iron. The teeth shall be ground into the material to achieve effective grinding.
(cont. next page)
2.02 GRINDER: (continued)
The shredder ring shall have a staggered tooth pattern with only one edge engaged at a time, maximizing the cutting torque. These materials have been chosen for their capacity to perform in the intended environment as they are materials with wear and corrosive resistant properties.
This assembly shall be dynamically balanced and operate without objectionable noise or vibration over the entire range of recommended operating pressures. The grinder shall be constructed so as to eliminate clogging and jamming under all normal operating conditions including starting. Sufficient vortex action shall be created to scour tank free of deposits or sludge banks which would impair the operation of the pump. These requirements shall be accomplished by the following, in conjunction with the pump:
1. The grinder shall be positioned in such a way that solids are fed in an upward flow direction.
2. The maximum flow rate through the cutting mechanism must not exceed 4 feet per second. This is a critical design element to minimize jamming and as such must be adhered to.
3. The inlet shroud shall have a diameter of no less than 5 inches. Inlet shrouds that are less than 5 inches in diameter will not be accepted due to their inability to maintain the specified 4 feet per second maximum inlet velocity which by design prevents unnecessary jamming of the cutter mechanism and minimizes blinding of the pump by large objects that block the inlet shroud.
4. The impeller mechanism must rotate at a nominal speed of no greater than 1800 rpm.
The grinder shall be capable of reducing all components in normal domestic sewage, including a reasonable amount of “foreign objects” such as paper, wood, plastic, glass, rubber and the like, to finely divided particles which will pass freely through the passages of the pump and the 1-1/4” diameter s/s discharge piping.
2.03 ELECTRIC MOTOR: As a maximum, the motor shall be
a 1 HP, 1725 RPM, 240 Volt 60 Hertz, 1 Phase, capacitor start, ball bearing, air-cooled induction type with Class F installation with a low starting current not to exceed 30 amperes and high starting torque of 8.4-foot pounds. The motor shall be press-fit into the casting for better heat transfer and longer winding life.
Inherent protection against running overloads or locked rotor conditions for the pump motor shall be provided by the use of an automatic-reset, integral thermal overload protector incorporated into the motor. This motor protector combination shall have been specifically investigated and listed by Underwriters Laboratories, Inc. for the application.
Non-capacitor start motors or permanent split capacitor motors will not be acceptable because of their reduced torque and consequent diminished grinding capacity. The wet portion of the motor armature must be 300 Series stainless.
Motors in general require periodic maintenance. To reduce the potential environmental problems and the expense of handling and disposing of oil, oil filled motors will not be acceptable.
2.04 MECHANICAL SEAL: The core shall be provided with a
mechanical shaft seal to prevent leakage between the motor and pump. The seal shall have a stationary ceramic seat and carbon rotating surface with faces precision lapped and held in position by a stainless-steel spring.
2.05 DISCHARGE HOSE AND DISCONNECT/VALVE: All
discharge fittings and piping shall be constructed polypropylene, EPDM or PVC. The discharge hose assembly shall include a shut-off valve rated for 200 psi WOG and a quick disconnect feature to simplify installation and removal. The bulkhead penetration shall be factory installed and warranted by the manufacturer to be watertight.
2.06 ELECTRICAL QUICK DISCONNECT: The grinder
pump unit shall include a single NEMA 6P electrical quick disconnect for all power and control functions. The EQD will be supplied with 32’, 25’ of useable, electrical supply cable (ESC) to connect to the alarm panel. The EQD shall require no tools for assembly, seal against water before the electrical connection is made, and include radial seals to assure a watertight seal regardless of tightening torque. Plug-type connections of the power cable onto the pump housing will not be acceptable due to the potential for leaks and electrical shorts. Junction boxes are not acceptable due to the large number of potential leak points. The EQD shall be so designed to be conducive to field wiring as required.
2.07 CHECK VALVE: The pump discharge shall be equipped
with a factory installed, gravity operated, flapper-type integral check valve built into the stainless-steel discharge pipe. The check valve will provide a full-ported passageway when open and shall introduce a friction loss of less than 6 inches of water at maximum rated flow. Working parts will be made of a 300 series stainless steel and fabric reinforced synthetic elastomer to ensure corrosion resistance, dimensional stability, and fatigue strength.
A non-metallic hinge shall be an integral part of the flapper assembly providing a maximum degree of freedom to assure sealing even at a very low back pressure. The valve body shall be an injection molded part made of an engineered thermoplastic resin. The valve shall be rated for continuous operating pressure of 235 psi. Ball-type check valves are unacceptable due to their limited sealing capacity in slurry applications.
2.08 ANTI-SIPHON VALVE: The pump discharge shall be
equipped with a factory-installed, gravity-operated, flapper-type integral anti-siphon valve built into the discharge piping. Moving parts will be made of 300 Series stainless steel and fabric-reinforced synthetic elastomer to ensure corrosion resistance, dimensional stability, and fatigue strength. A nonmetallic hinge shall be an integral part of the flapper assembly, providing a maximum degree of freedom to ensure proper operation even at a very low pressure. The valve body shall be injection-molded from an engineered thermoplastic resin. Holes or ports in the discharge piping are not acceptable anti-siphon devices due to their tendency to clog from the solids in the slurry being pumped. The anti-siphon port diameter shall be no less than 60% of the inside diameter of the pump discharge piping.
2.09 CORE UNIT: The Grinder Pump Station shall have an
easily removable core assembly containing pump, motor, grinder, all motor controls, check valve, anti-siphon valve, electrical quick disconnect and wiring. The watertight integrity of the core unit shall be established by 100% factory test at a minimum of 5 PSIG. Core assemblies that do not contain all motor controls will not be accepted.
2.10 CONTROLS: All necessary motor starting controls shall be located in the cast iron enclosure of the core unit secured by stainless steel fasteners. Locating motor starting controls in a plastic enclosure is not acceptable. Wastewater level sensing controls shall be housed in a separate enclosure from motor starting controls. Level sensor housing must be sealed via a radial type seal;
solvents or glues are not acceptable. (cont. next page)
2.10 CONTROLS: (continued)
Level sensing control housing must be integrally attached to pump assembly so that it may be removed from the station with the pump and in such a way as to minimize the potential for the accumulation of grease and debris accumulation, etc. Level sensing housing must be a high-impact thermoplastic copolymer over-molded with a thermo plastic elastomer. The use of PVC for the level sensing housing is not acceptable.
Non-fouling wastewater level controls for controlling pump operation shall be accomplished by monitoring the pressure changes in an integral air column connected to a pressure switch.
The air column shall be integrally molded from a thermoplastic elastomer suitable for use in wastewater and with excellent impact resistance. The air column shall have only a single connection between the water level being monitored and the pressure switch.
Any connections are to be radial sealed with redundant O-rings.
The level detection device shall have moving floatation parts in direct contact with the wastewater and shall be integral to the pump core assembly in a single, readily exchanged unit. Depressing the push to run button must operate the pump even with the level sensor housing removed from the pump.
All fasteners throughout the assembly shall be 300 Series stainless steel. High-level sensing will be accomplished in the manner detailed above by a separate air column sensor and pressure switch of the same type. Closure of the high-level sensing device will energize an alarm circuit as well as a redundant pump-on circuit.
For increased reliability, pump ON/OFF and high-level alarm functions shall not be controlled by the same switch. To assure reliable operation of the pressure switches, each core shall be equipped with a factory installed equalizer diaphragm that compensates for any atmospheric pressure or temperature changes.
Tube or piping runs outside of the station tank or into tank-mounted junction boxes providing pressure switch equalization will not be permitted due to their susceptibility to condensation, kinking, pinching, and insect infestation. The grinder pump will be furnished with a 6 conductor 14-gauge, type SJOW cable, pre-wired and watertight to meet UL requirements with a FACTORY INSTALLED NEMA 6P EQD half attached to it.
2.11 ALARM PANEL: Each grinder pump station shall include
a NEMA 4X, UL listed alarm panel suitable for wall or pole mounting. The NEMA 4X enclosure shall be manufactured of thermoplastic polyester to ensure corrosion resistance. The enclosure shall include a hinged, lockable cover with padlock, preventing access to electrical components, and creating a secured safety front to allow access only to authorized personnel. The enclosure shall not exceed 10.5" W x 14" H x 7" D, or 12.5" W x 16" H x 7.5" D if certain options are included.
For each core, the panel shall contain one (1) – 15-amp double pole circuit breaker for the power circuit and one (1) 15-amp single pole circuit breaker for the alarm circuit. The panel shall contain a push-to-run feature, an internal run indicator, and a complete alarm circuit. All circuit boards in the alarm panel are to be protected with a conformal coating on both sides and the AC power circuit shall include an auto resetting fuse.
The alarm panel shall include the following features: external audible and visual alarm; push-to-run switch; push-to-silence switch; redundant pump start; and high-level alarm capability. The alarm sequence is to be as follows when the pump and alarm breakers are on:
1. When liquid level in the sewage wet-well rises above the alarm level, the contacts on the alarm pressure switch activate, audible and visual alarms are activated, and redundant pump starting system is energized.
2. The audio alarm may be silenced by means of the externally mounted, push-to-silence button.
3. Visual alarm remains illuminated until the sewage level in the wet-well drops below the “off” setting of the alarm pressure switch.
The visual alarm lamp shall be inside a red, oblong lens at least 3.75" L x 2.38" W x 1.5" H. Visual alarm shall be mounted to the top of the enclosure in such a manner as to maintain NEMA 4X rating. For duplex units, in addition to the requirements above, two high level indicator lights shall be mounted behind the access cover. During a high-level alarm condition, the appropriate light will illuminate to indicate which pump core requires servicing.
The audible alarm shall be externally mounted on the bottom of the enclosure, capable of 93 dB @ 2 feet. The audio alarm shall be capable of being deactivated by depressing a push-type switch which is encapsulated in a weatherproof silicone boot and mounted on the bottom of the enclosure (push-to-silence button).
2.12 SERVICEABAILITY: The grinder pump core, including
level sensor assembly, shall have two lifting hooks complete with lift-out harness connected to its top housing to facilitate easy core removal when necessary. The level sensor assembly must be easily removed from the pump assembly for service or replacement. All mechanical and electrical connections must provide easy disconnect capability for core unit removal and installation. Each EQD half must include a water-tight cover to protect the internal electrical pins while the EQD is unplugged. A pump push-to-run feature will be provided for field trouble shooting. The push-to-run feature must operate the pump even if the level sensor assembly has been removed from the pump assembly. All motor control components shall be mounted on a readily replaceable bracket for ease of field service. Due to the inherent problems associated with guide rails over time, guide rails will not be acceptable.
2.13 OSHA CONFINED SPACE: All maintenance tasks for
the grinder pump station must be possible without entry into the grinder pump station (as per OSHA 1910.146 Permit-required confined spaces). “Entry means the action by which a person passes through an opening into a permit-required confined space.
Entry includes ensuing work activities in that space and is considered to have occurred as soon as any part of the entrant’s body breaks the plane of an opening into the space.”
2.14 CORROSION PROTECTION: All materials exposed to
wastewater shall have inherent corrosion protection. Acceptable corrosion protection includes epoxy power coat, cast iron, fiberglass, stainless steel, PVC.
2.15 SAFETY: The Grinder Pump shall be free from electrical
and fire hazards as required in a residential environment. As evidence of compliance with this requirement, the completely assembled and wired Grinder Pump Station in its tank shall be listed by Underwriters Laboratories, Inc. to be safe and appropriate for the intended use. UL listing of components of the station, or third-party testing to UL standard are not acceptable.
The grinder pump shall meet accepted standards for plumbing equipment for use in or near residences, shall be free from objectionable noise, odor, or health hazards, and shall have been tested by an independent laboratory to certify its capability to perform as specified in either individual or low-pressure sewer system applications. As evidence of compliance with this requirement, the grinder pump shall bear the National Sanitation Foundation seal. Third-party testing to NSF standard is not acceptable.
3.0 EXECUTION
3.01 FACTORY TEST: Each grinder pump shall be submerged
and operated for 1.5 minutes (minimum). Included in this procedure will be the testing of all ancillary components such as, the anti-siphon valve, check valve, discharge assembly and each unit’s dedicated level controls and motor controls. All factory tests shall incorporate each of the above listed items. Actual appurtenances and controls which will be installed in the field shall be particular to the tested pump only. A common set of appurtenances and controls for all pumps is not acceptable.
Certified test results shall be available upon request showing the operation of each grinder pump at two different points on its curve. Additional validation tests include integral level control performance, continuity to ground and acoustic tests of the rotating components.
The ENGINEER or PARISH REPRESENTATIVE reserves the right to inspect such testing procedures with representatives of the OWNER, at the GRINDER PUMP MANUFACTURER’S facility.
All HDPE basins shall be factory leak tested to assure the integrity of all joints, seams and penetrations. All necessary penetrations such as inlets, discharge fittings and cable connectors shall be included in this test along with their respective sealing means (grommets, gaskets etc.). Fiberglass basins with stainless steel discharge bulkhead shall be factory tested to be watertight.
3.02 DELIVERY: All Grinder Pump units will be delivered to
the job site, 100% completely assembled, including testing, ready for installation.
3.03 MANUALS: As stated on the Bid Form, the successful
bidder will supply at least two copies of the complete Operation and Maintenance manual covering the equipment as delivered.
This requirement should be satisfied at the beginning of the bid period. Cost of the manuals is to be included in the bid price.
Simplex Sewer Pump Fiberglass Tank Technical Specifications for 24” x 60” Tank
Tank should be a wet-well design consisting of a single wall, laminated fiberglass construction. The resin used should be of a commercial grade suitable for the environment. The reinforcing material should be a commercial grade of glass fiber capable of bonding with the selected resin. The inner surface shall have a smooth finish and be free of cracks and crazing. The exterior tank surface shall be relatively smooth with no exposed fiber or sharp projections present.
The tank wall and bottom should be of sufficient thickness and construction to withstand the imposed loading due to saturated soil at the specified burial depth for each available tank height. All station components should function normally when exposed to the external soil and hydrostatic pressures developed at the specified burial depth. The tank bottom shall be reinforced with a fiberglass plate extending beyond the tank walls to support concrete anchoring, as required, to prevent flotation.
The tank shall have a stainless-steel discharge bulkhead which terminates outside the tank wall with a 1-1/4” female pipe thread. The discharge bulkhead shall be factory installed and warranted by the manufacturer to be watertight. The tank shall be furnished with a field installed EPDM grommet to accept a 4.50” O.D. (4” DWV or SCH 40) inlet pipe. The power and control cable shall connect to the pump body by means of the provided NEMA 6P electrical quick disconnect (EQD) and shall enter the tank through a field installed watertight strain relief connector (or equal) supplied by the manufacturer. An electrical junction box shall not be permitted in the tank. Installation of the inlet grommet and cable strain relief should require field penetration of the tank wall by the installing party. The tank shall also be vented to prevent sewage gases from accumulating inside the tank by means of a factory-provided, field installed mushroom vent (or equal). The station cover shall be factory drilled to accept the mushroom vent (or equal). The tank and stainless-steel discharge bulkhead shall be factory-tested to be watertight.
Simplex Sewer Pump High Density Polyethylene Construction (HDPE) Tank Technical Specifications for 24” x 60” Tank
The tank should be a wet-well design made of high-density polyethylene of a grade selected for environmental stress cracking resistance. Corrugated sections are to be made of a double wall construction with the internal wall being generally smooth to promote scouring. Corrugations of the outside wall are to be of a minimum amplitude of 1-1/2" to provide necessary transverse stiffness. Any incidental sections of a single wall construction are to be a minimum .250 inch thick. All seams created during tank construction are to be thermally welded and factory tested for leak tightness. Tank wall and bottom must withstand the pressure exerted by saturated soil loading at maximum burial depth. All station components must function normally when exposed to maximum external soil and hydrostatic pressure.
The tank should be furnished with a factory installed PVC inlet flange to accept a 4.50" OD (4" DWV or SCH 40) inlet pipe.
The tank should include a lockable cover assembly providing low profile mounting and watertight capability.
The cover shall be high density polyethylene, green in color, with a load rating of 150 lbs per square foot. The cover assembly shall also include an integral 2-inch vent to prevent sewage gases from accumulating in the tank.
The accessway design and construction shall facilitate field adjustment of station height in increments of 3" or less without the use of any adhesives or sealants requiring cure time before installation can be completed.
The power and control cable should connect to the pump by means of the provided NEMA 6P Electrical Quick Disconnect (EQD) and should enter the tank through a factory installed watertight strain relief connector. An electrical junction box shall not be permitted in the tank.
The station shall have all necessary penetrations factory sealed and tested. No field penetrations shall be acceptable.
Sewer Pumps With Duplex Tanks Technical Specifications
YES NO DEVIATION
1.0 GENERAL
Will meet all the same General Specifications of the Sewer Pumps with Simplex Tanks in Section 1.0 to Section 1.9.
2.0 PRODUCT
Will meet all the same Product Specifications of the Sewer Pumps with Simplex Tanks in Section 2.1 to Section 2.15 with the exception of Section 2.11 Alarm Panel.
2.1 ALARM PANELS: MOD T260 DUPLEX
Each grinder pump station shall include a NEMA 4X, UL-listed alarm panel suitable for wall or pole mounting. The NEMA 4X enclosure shall be manufactured of thermoplastic to ensure corrosion resistance. The enclosure shall include a hinged, lockable cover with padlock, preventing access to electrical components, and creating a secured safety front to allow access only to authorized personnel. The standard enclosure shall not exceed 12.5" W x 16" H x 7.5" D. The panel shall contain one 15-amp single pole circuit breaker for the alarm circuit and one 15-amp double pole circuit breaker per core for the power circuit. The panel shall contain a push-to-run feature, an internal run indicator, and a complete alarm circuit. All circuit boards in the alarm panel are to be protected with a conformal coating on both sides and the AC power circuit shall include an auto resetting fuse.
The visual alarm lamp shall be inside a red, oblong lens at least 3.75" L x 2.38" W x 1.5" H. Visual alarm shall be mounted to the top of the enclosure in such a manner as to maintain NEMA 4X rating. The audible alarm shall be externally mounted on the bottom of the enclosure, capable of 93 dB @ 2 feet.
The audible alarm shall be capable of being deactivated by depressing a push-type switch that is encapsulated in a weatherproof silicone boot and mounted on the bottom of the enclosure (push-to-silence button).
(Cont. on next page)
2.1 ALARM PANELS: MOD T260 DUPLEX (Continued)
The high-level alarm system shall operate as follows:
1. The panel will go into alarm mode if either pump’s alarm switch closes. During the initial alarm mode both pumps will run, and the alarm light and buzzer will be delayed for a period of time based on user settings (default is 3-1/2 minutes). If the station is still in high-level alarm after the delay, the light and buzzer will be activated.
2. The audible alarm may be silenced by means of the externally mounted push-to-silence button.
3. The visual alarm remains illuminated until the sewage level in the wet well drops below the “off” setting of the alarm switch for both pumps.
The entire alarm panel, as manufactured and including any of the following options shall be listed by Underwriters Laboratories, Inc.
3.0 EXECUTION
Will meet all the same Execution Specifications of the Sewer Pumps with Simplex Tanks in Section 3.1 to Section 3.3.
Duplex Sewer Pump Polyethylene Tank Technical Specifications for 48" x 75" Tank
YES NO DEVIATION
The tank shall be made of rotational molded polyethylene with high environmental stress cracking resistance. All seams created during tank construction are to be factory tested for leak tightness.
The tank wall and bottom must withstand the pressure exerted by saturated soil loading at maximum burial depth. All station components must function normally when exposed to 150 percent of the maximum external soil and hydrostatic pressure.
The overall basin capacity shall be 486 gallons. The basin shall incorporate a tapered bottom with an inside diameter of no greater than 46 inches, reducing to a diameter of no greater than 42 inches to minimize the retained volume. The largest diameter must be no less than 50 inches and no greater than 52 inches.
A station that is 75 inches tall shall have no greater than a 50 inch outside diameter hinged aluminum cover. The 75-inch-tall station can be extended in 6-inch increments with normal cylindrical fiberglass extensions.
Taller stations shall have a fiberglass accessway with a hinged, aluminum cover. The accessway shall be an extension of the wetwell assembly and shall include a lockable cover assembly, with vent, providing low profile mounting. The cover shall be aluminum, with a load rating of 300 pounds per square foot. The cover shall have an outside diameter of no greater than 50 inches.
Accessway design and construction shall enable field extension of station height in 6-inch increments without the use of any adhesives or sealants requiring cure time before installation can be completed. The accessway wall must withstand the pressure exerted by saturated soil loading at maximum burial depth and must function normally when exposed to 150 percent of the maximum external soil and hydrostatic pressure.
The tank and factory penetrations shall be factory tested and guaranteed to be watertight.
The tank shall be furnished with one EPDM grommet fitting to accept a 4.50" OD DWV or Schedule 40 pipe. Tank dimensions shall be as shown on the contract drawings.
The discharge bulkheads (manifolds) shall be factory installed and warranted by the manufacturer to be watertight. The following provides a description and orientation of the discharge bulkhead(s) for each station type: The tank shall have one stainless steel duplex discharge manifold terminating outside the tank wall with a 1-1/4” female NPT pipe thread. 48" x 75"
Duplex Sewer Pump Fiberglass Tank Technical Specifications for 48" x 75" Tank
Tank should be a wet-well design consisting of a single wall, laminated fiberglass construction. The resin used should be of a commercial grade suitable for the environment. The reinforcing material should be a commercial grade of glass fiber capable of bonding with the selected resin. The inner surface shall have a smooth finish and be free of cracks and crazing. The exterior tank surface shall be relatively smooth with no exposed fiber or sharp projections present.
The tank wall and bottom should be of sufficient thickness and construction to withstand the imposed loading due to saturated soil at the specified burial depth for each available tank height. All station components should function normally when exposed to the external soil and hydrostatic pressures developed at the specified burial depth. The tank bottom shall be reinforced with a fiberglass plate extending beyond the tank walls to support concrete anchoring, as required, to prevent flotation.
The tank shall have a stainless-steel discharge bulkhead which terminates outside the tank wall with a 1-1/4” female pipe thread. The discharge bulkhead shall be factory installed and warranted by the manufacturer to be watertight. The tank shall be furnished with a field installed EPDM grommet to accept a 4.50” O.D. (4” DWV or SCH 40) inlet pipe. The power and control cable shall connect to the pump body by means of the provided NEMA 6P electrical quick disconnect (EQD) and shall enter the tank through a field installed watertight strain relief connector (or equal) supplied by the manufacturer. An electrical junction box shall not be permitted in the tank. Installation of the inlet grommet and cable strain relief should require field penetration of the tank wall by the installing party. The tank shall also be vented to prevent sewage gases from accumulating inside the tank by means of a factory-provided, field installed mushroom vent (or equal). The station cover shall be factory drilled to accept the mushroom vent (or equal). The tank and stainless-steel discharge bulkhead shall be factory-tested to be watertight.
The station shall have a fiberglass accessway with a hinged, aluminum cover. The accessway shall be an extension of the wet well assembly and shall include a lockable cover assembly, with vent, providing low profile mounting. The cover shall be aluminum, with a load rating of 300 pounds per square foot. The cover shall have an outside diameter of no greater than 50 inches. Accessway design and construction shall enable field extension of station height in 6-inch increments.
BID FORM
SEWER PUMPS ONLY AND/OR SEWER PUMPS COMPLETE WITH SEWER TANKS
Please complete the spaces below with your company’s bid prices, sewer pumps only and/or sewer pumps complete with sewer tanks, complete as per bid specifications:
WARRANTY:
The bidder’s Factory authorized dealer to perform warranty work is:
Name:
Location: Phone:
Expected delivery date: ______________________
SEWER PUMPS ONLY
Item Quantity Ordered Price per Each
1 1 - 25 $ /Each 2 26 - 50 $ /Each
List Year, Make and Model of Equipment being bid:
E/ONE METERING PUMP
Item Quantity Ordered Price per Each
3 1 - 25 $ /Each 4 26 - 50 $ /Each
List Year, Make and Model of Equipment being bid:
SEWER PUMPS WITH SIMPLEX FIBERGLASS SEWER TANKS 24”X60”
Item Quantity Ordered Price per Each
5 1 - 25 $ /Each 6 26 - 50 $ /Each
List Year, Make and Model of Equipment being bid:
SEWER PUMPS WITH SIMPLEX HDPE SEWER TANKS 24”X60”
Item Quantity Ordered Price per Each
7 1 - 25 $ /Each 8 26 - 50 $ /Each
List Year, Make and Model of Equipment being bid:
SEWER PUMPS WITH DUPLEX SEWER TANKS
9 1 - 25 $ /Each 10 26 - 50 $ /Each
SEWER PUMPS WITH DUPLEX POLYETHYLENE SEWER TANKS 48”X75”
11 1 - 25 $ /Each 12 26 - 50 $ /Each
SEWER PUMPS WITH DUPLEX FIBERGLASS SEWER TANKS 48”x75”
13 1 - 25 $ /Each 14 26 - 50 $ /Each
Repair/Replacement Parts for E-One Grinder Pumps
Parts offered on bid must be designed to work in E-One Grinder Pumps. Part numbers are provided for reference. Bidders must include their company part numbers in addition to the unit prices on this form.
Item # Part Number Description Unit of
Measure
Vendor Part
Number Unit Price
1 0202-308S SCREW, SELF-TAP, BT, SS, #6X 500 Each
2 0714-056S Spring Pin, .125 Dia x .750 Lg, SS (Slider) Each
3 1001 Sensing RFI Each
4 1008 Seal Assembly Each
5 1043 CORE BOLT ASM, w/ WASHER Each
6 1046 CORE BOLT ASM, w/o WASHER Each
7 1061 BREATHER VENT, FIELD ASM
Each
8 1070 HOOD, EQD, w/o hole & insr Each
9 1090 Equalizer - includes tubing, hose barb, clamps and hanging bracket
Each
10 1094 HOSE FLEX DISCHARGE KIT, 60”
Each
11 1095 HOSE FLEX DISCHARGE KIT, 72”
Each
12 1096 HOSE FLEX DISCHARGE KIT, 84”
Each
13 1098 SLIDE FACE RECEIVER ASSMEBLY
Each
14 1103 Replacement Duplex Circuit Board Each
15 1201 TOP HOUSING ASSEMBLY, I - SERIES
Each
16 1203 Cutter Wheel, Forged, Mach/Hardened Each
17 1207 CHECK VLV ASM W/ RCV, 1-1/2NPT, DW
Each
18 1208 Mechanical Seal Kit Extreme - includes seal, lubricant, (2) o-ring sets and 6 nuts
Each
19 1209
PUMP POWER CABLE 7’, STRT CABLE
ASM, SVC, CORE SIDE
Each
20 1210
ND0128G03-CORE CABLE ASSY, SERVICE,
12’ WIRELESS
Each
Item # Part Number Description
Unit of Measure
Vendor Part Number
Unit Price
21 1213
EQUALIZER TUBE ASSEMBLY, 9', FOR 7'
CABLE
Each
22 1214 Equalizer Tube ASM, 14’ for 12’ Cable
23 1221
LEVEL SENSOR ASM, HARDWIRED, 12FT
CABLE
24 1231
REPLACEMENT LEVEL SENSOR
ASSEMBLY
25 1241
COMPLETE KIT, CONVERSION
ASSEMBLY, WETWELL
26 1250 LSH PLUG
27 1251 CONTROL COVER RECEPTACLE
28 1262 EQD ASM Supply Cable Side
29 1263 EQD ASM, Core Side
30 1265 Control Brkt Assy, 240V/60HZ, Extreme
31 1276 Check Valve, ASM, Upgrade, Wetwell
32 1288 Extreme Motor Housing
33 1290 Equalizer ASM
34 2051 NIPPLE, 1–1/4 NPT x 2 BRASS
35 2054 VALVE WYE (SS DISCHARGE)
36 2055 VALVE HOUSING (SS DISCHARGE)
37 2056 Slip Joint Nut 1.5 PVC PA0986P01
38 2057 SPLIT RING, SS DISCHARGE Each
39 2059 Hood, EQD
40 2067
AMGP/1000 SERIES 1 1/4” NPT ANTI-
SIPHON ADAPTER
41 2068
AMGP COVER ASM, SERVICE - INCLUDES
O-RING FOR AMGP
42 2069 PUMP STAND, WIRE FORM (2000)
Measure
Vendor Part Number
Unit Price
43 2079 SPLIT RING, SS, SWAGED DISCHARGE
44 2080 BRACKET, DISCHARGE SUPPORT, AMGP
45 2081 HOOD, EQD, NO. 10-32 INSERT
46 2083 HOSE CLAMP, 7/16 IN NYLON (used on equalizer tubing)
47 2201
NUT, EQD TIGHTENING, BLACK, SUPPLY
CABLE SIDE Each
48 2202 Nut, Split, Cable Compression
49 2203 EQUALIZER TUBING, BLACK, PER FOOT
50 2204 GROMMET, MOTOR HOUSING, INTERNAL
51 2205
CLIP, RETAINING, LEVEL SENSING
HOUSING BOTTOM
52 2208 RETAINER, PRESSURE SWITCH
53 2222 COMPRESSION NUT
54 2224
ND0148P01-CTRL CVR, 2-PORT, MACH,
EXTREME
55 2225 LEVEL SENSOR HOUSING
56 2227 LSA CONNECTOR LOCK
57 2230 LSH CAP, WETWELL
58 2235 LEVEL SENSOR HOUSING STRAP
59 2241
CONTROL COVER SERVICE ASSEMBLY,
WETWELL, HW
60 2259
EQD SOCKET HOUSING, SUPPLY CABLE
SIDE
61 2260 EQD PIN HOUSING, CORE CABLE SIDE
62 2263
STAINLESS STEEL DISCHARGE CANDY
CANE, SWAGED, EXTREME
63 2264 SS STRAIGHT DISCHARGE - EXTREME
64 2269 Stand, Core, 3/8 rod, SS (1 side)
Measure
Vendor Part Number
Unit Price
65 2270
FTG, COUPLING, 1 1/4 PVC SCH80
THREAD BOTH ENDS
Each
66 24-Lid 24” Diameter Solid Fiberglass Lid Each
67 2412 Extension 24” x 12” Fiberglass Flanged Extension w/ SS Bolts
Each
68 2424 Extension 24” x 24” Fiberglass Flanged Extension w SS Bolts
Each
69 2460 Basin 24” x 60” Fiberglass Pre-Plumbed Basin, Slide face valve, SS Bulkhead
Each
70 3005 WASHER, SPRING LOCK, SS #10 (SHROUD)
Each
71 3006
WASHER, PLAIN, SS, 1/4 (TIE ROD
BOTTOM)
Each
72 3009 SCREW, SELF–TAP, #6 x .37 (PRESSURE
SWITCH)
Each
73 3014 SCREW, TAMPER PROOF, 8–32
Each
74 3015 WASHER, PLAIN, SS, #8 (TAMPER PROOF)
Each
75 3022
WASHER, SPRING LOCK, SS 1/4 (SUCTION
HOUSING)
Each
76 3023 SCREW, HEX HD, 1/4–20 x .75 (SUCTION
HOUSING)
Each
77 3024 SCREW, SL HX HD, 10–24 x 1.50 (CAST
IRON ONLY)
Each
78 3040 CONNECTOR, 3/4 IN NPT (12-2, 14-2)
Each
79 3049 SCREW, DRIVE, SS, #4 x .188 (NAME
PLATE)
Each
80 3050 NUT, STOP (ELASTIC), 1/4–24 (TIE ROD)
Each
81 3051 SCREW, PHILLIPS PN HD, 8–32 x .44
(CONTROLS)
Each
82 3058 SCREW, SLOTTED FL HD, 10–32 x .38
(CAPACITOR)
Each
83 3091 CONNECTOR, (12–3) CABLE
Each
84 3095 WASHER, FLAT, SS, 1/4
Each
85 3096
SCREW, O–RING (CORE BOLT)
Each
Measure
Vendor Part Number
Unit Price
86 3097 WASHER, PLAIN, SS, 3/8 (O-RING SCREW)
87 3104 SCREW, HEX HD, 1/4–20 x 1.6 2
88 3105 SCREW, HEX HD, 1/4–20 x 1.50
89 3111 VALVE STEM, BREATHER
90 3114 O–RING, 1.287 x 1.707 (COPPER
DISCHARGE)
91 3119 BOLT, 5/16–18 x 1.75 (2000 MOTOR)
92 3121 WASHER, SPRING LOCK, 5/16
93 3122 Screw, Captive .75
94 3123 Connector, 3/4 NPT, .35-.63 Cable
95 3125 Nut, Stop (elastic) 5/16-18
96 3126 Washer, Plain, SS, 5/16
97 3128 Washer, Plain, SS #10
98 3129
SCREW, 10-24 HXHD PRCOAT W/
LOCKTITE (inlet shroud, motor, ground screw), Each
99 3130 EYE BOLT (AMGP)
100 3131 Screw, Hex, SS, 5/16-18 x 2”
101 3132
RETAINING RING, STAND, SS, 4PK (AMGP,
1000)
102 3133 CHECK VALVE SCREW
103 3134 CHECK VALVE WASHER
104 3137 Expansion Plug, 2-1/16” concave
105 3138
SCREW, HXHD 1/4-20x1 PRCOAT W/
LOCKTITE (SUCTION HOUSING) NOT
USED IN PLACE OF .75 1/4-20 BOLT
Each
106 3139
SCREW, 10-32 (HOLD DOWN SCREWS FOR
IDU COVER)
Measure
Vendor Part Number
Unit Price
107 3143 5/16-18, SS, NUT (FOR EYEBOLT)
Each
108 3146 GROUNDING STRIP, AL, 2000 IDU
Each
109 3147 SCREW, CAPTIVE, 10-32x1.25 Each
110 3149 AMGP BREATHER CLAMP, SS, SPRING
Each
111 3150
SCREW, ALARM BOARD, SENTRY
(PLASTITE 45, #10X 1/2)
Each
112 3155 EYE BOLT, GAPPED, 3”L,5/16-18,SS
Each
113 3201 Spring Pin .187 Dia x .75 LG, Ss for check valve Each
114 3202 Spring Pin .250 Dia x 1.50 LG, Ss for control cover
Each
115 3203 WASHER, .19 X .63 X .04 SS
Each
116 3204 Screw, Phillip, RD Head, SS 6-32 x 2.5 Each
117 3205 SCREW, PLASTITE 45, #4 X 1/2, SS
Each
118 3206 Plug 1/8 NPT SS Each
119 3207 Screw SKT Head 10-24 x .5 Pre-Coat, Control Bracket
Each
120 3208
SCREW, PLASTITE, SH, SS, 48-2 #10 - 14 X
1.25 (EXTREME TOP HSG)
Each
121 3209 Screw, Phillips, RD Head SS 6-32 x 3.00 Each
122 3210
SCREW, HUB BASE RETAINING, 1/4-20 X
.38 LG
Each
123 3211
WASHER, 1/4, SS, FOR HUB BASE RET.
SCREW
Each
124 3212 Cord Grip, 1/2 NTP (for hardwired level sensor housing
Each
125 3215 SCREW, #8-16X3/4” PHILLIPS
Each
126 3217 Screw, Oring Seal, ¼-20 x .5L, SS Each
127 3222 CABLE CONNECTOR
Each
128 3224 Screw, Lock, Hex Mach, 10-24 x .75 Each
Measure
Vendor Part Number
Unit Price
129 3230 D-Hook, Lifting
130 4001 SOCKET, TAMPER PROOF, #6
131 4017 Grease Silicone, 5.3 oz.
132 4018 Pipe Sealer, TFE, 8 oz.
133 4021 Press-On Tool Pump Bearing
134 4028 Seal ASM Tool, Ceramic/Carbon
135 4033 METER, VOLT/AMP/OHM
136 4034 Bearing Puller
137 4035 Bearing Puller, Pump
138 4038 TEST FIXTURE, SENSING BELL
139 4041 Testing Fitting Motor Cavity
140 4042 TAMPER PROOF SOCKET, #20
141 4043 METER, VOLT/OHM
142 4045 PRESS-ON TOOL UPPER BEARING
143 4201 SILICONE, MOLYCOTE 55, 5.3OZ.
144 4202 LEVEL SENSING SIMULATOR (WIRELESS)
145 4203
SCREWDRIVER 5/32” HEX DRIVE
HOLDING
146 4204 SERVICE TAGS, BOX OF 100 TAGS
147 4205 LOCTITE 598, 0.5 OZ. CABLE ENTRY
148 4206
MANOMETER FIELD TEST KIT (PRICE IS
NET)
149 4207
MANOMETER SHOP TEST KIT (PRICE IS
150 4208 HAND TOOL, CRIMPER (PRICE IS NET)
Measure
Vendor Part Number
Unit Price
151 4209 BOTTOMING TAP, M32 x 1.5 (PRICE IS
152 4210 LOCTITE 641, 10ML BEARING
153 4219 NA0237P03-BOTTOM TAP, M24XI.5
154 5015 Bearing, Pump end
155 5033 MOTOR ASSEMBLY
156 5034 WASHER, WAVE SPRING, STL
157 5035 BEARING, MOTOR END
158 5201 Motor Rotor w/ Bearings
159 5202 THERMAL PROTECTOR, 240V 60Hz
(EXTREME)
160 5203 THERMAL PROTECTOR, 120V 60Hz
(EXTREME)
161 5237
MOTOR HEAD, STANDARD (INCLUDES
1208 SEAL KIT)
162 6025 O-Ring, 7.725 x 8.145, GE Motor Head
163 6029
TOP HOUSING GASKET, FLAT (AMGP,
1000)
164 6035
GROMMET, BUNA-N, TOP
HSG/DISCHARGE, BLK
165 6036 O–RING, .145 x .285, CAPTIVE SCREW EQD
166 6038 O–RING, SLIDE FACE (1.57 x .197) (AMGP, 1000, 300)
167 6039 O-Ring Motor (2000)
168 6041 O-ring, .984 x 1.262, Buna, Cable, Conn
169 6047 O–RING, 1.266 ID, BACK-UP
170 6049 O–RING, 30 mm x 5 mm, AMGP DISCHARGE
171 6050 FLOOD PLAIN GASKET KIT
172 6051 O-Ring Cast AMGP Cover
Measure
Vendor Part Number
Unit Price
173 6130 O-Ring for M24 Plug, .862 x .070, Buna N
174 6201
GROMMET, 6 HOLE OVERMOLD, EQD,
SUPPLY CABLE SIDE
175 6202 O-ring Casting 4.975 x 5.525, Buna N EXT
176 6203 Seal, Level Sensing Housing, Extreme
177 6204 GROMMET, PUMP CABLE, BLACK
178 6205 GROMMET, EQUALIZER TUBE, BLUE
179 6206 O-Ring, 18mm x 2mm Buna N (Level Sensor Cord Grip)
180 6208
NC0521P01-LSH SEAL COUPLING (2-0-
RING GLAND)
181 6209 O-RINGS-LSH SEAL COUPLING
182 6223 O-RINGS-LEVEL SENSOR ASM
183 6230 EQD O-Ring 2.489 x 2.629 Buna N
184 6231 GASKET, TOP HOUSING
185 6232 CV/AS O-ring, 1.609 x 1.887, Buna-N
186 7067
TRANSFORMER, BUCK BOOST, AUTO
(SIMPLEX 1.9KVA)
187 7068
TRANSFORMER, BUCK BOOST, AUTO
(DUPLEX 5.7KVA)
188 7071 TERMINAL, STA-KON, 16–14GA (T260)
189 7092 RELAY, SOLID STATE, 25A (possible replacement for 7070)
190 7094 EQD Insert, Female, 6 Pos
191 7095 EQD Insert, Male 6 Pos
192 7102 SPLICE KIT FOR TRAY CABLE (approved for underground use)
193 7104 CONTACTOR, MOTOR 220V/240V (Alarms panels and 2000 Series flat control bracket)
194 7114 TERMINAL 250F, 22-18 AWG
Measure
Vendor Part Number
Unit Price
195 7115 TERMINAL, FLG, FLG, 22-18GA, RED
196 7116 SPLICE, 18-16 AWG, BLUE
197 7201 CAP, EQD SOCKET SUPPLY CABLE SIDE
198 7202 CAP, EQD, PIN CORE CABLE SIDE
199 7205
PRESSURE SWITCH, ON/OFF, IDU
HARDWIRED W/ O-RINGS
200 7207 WIRE CRIMP, 3-WIRE
201 7290 On/Off Switch
202 7291 Alarm Switch
203 8003 Pump Stator
204 8004 PUMP LINER
205 8005 STATOR, OIL RESISTANT
206 8006 Stationary Shredder Each 207 8007 PLASTIC INLET SHROUD Each 208 8008 PUMP ROTOR Each 209 8009 GROOVE PIN, 5/32 x 1 Each 210 8203 STATOR/LINER ASSEMBLY EXTREME Each 211 8206 SHREDDER RING, EXTREME Each 212 8207 INLET SHROUD, EXTREME Each
213 8210
SUCTION HOUSING, EXTREME, STD
(REPLACES ALL, P04 & P05) Each
214 8220 Bolt, ¼-20, 1.25” serrated flange, ss, 1.25” Each
215 8222 Screw, 48-s#10-14 Heck, .51 in flange dia, 18-8 SS 1” Each
216 9002 TUBE CONNECTOR, 1/8 NPT Each 217 9009 LABEL, CAUTION Each
218 9026 LABEL, “NEVER THROTTLE”
219 9054 FLAPPER
220 9075 LABEL, FOR SIGNAL LEADS Each
Measure
Vendor Part Number
Unit Price
221 9076 LABEL, FOR POWER LEADS
222 9077 LABEL, FOR OUTDOOR USE
223 9094 SEALANT, SIKAFLEX
224 9095 CORE LIFTING ROPE, 10'
225 9201 FITTING, STRGHT CONN, 1/8 NPT x 3/16 HOSE Each
226 9202 CASTING PLUG, WIRELESS Each
227 9203 NAMEPLATE, SS
228 9205
NB0357G01-FITTING, M20 W/O-RING
(ADAPTER FITTING, BARB, W/O-RING Each
229 9206 SEAL PLUG, M24X1.5,SS (9206) Each 230 9503 BREAKER, 2 POLE, 15A Each
231 9504 BREAKER, 1 POLE, 15A
232 9505 BREAKER, 1 POLE, 20A Each 233 9506 PUSH BUTTON SWITCH, SPST, N.O. Each 234 9507 REPLACEMENT BULB, 130V Each 235 9509 AC CURRENT RELAY, SPST 20A Each
236 9512
REPLACEMENT BD, MOD250 PANEL, 120V
& 240V (3R & 4X WITH DINRAIL)
237 9514
CIRCUIT BREAKER, 1 POLE, 15A, DIN RAIL
MT Each
238 9515
CIRCUIT BREAKER, 2 POLE, 15A, DIN RAIL
MT Each
239 9516
CIRCUIT BREAKER, 1 POLE, 20A, DIN RAIL
MT, 120V PUMPS
240 9517 FUSE, TIME-LAG, 5x20 MM, 1A, IDU
241 9522
ALARM REPLACEMENT PC BOARD,
SIMPLEX SENTRY, 240/120 Each
242 9527
BREAKER, SERVICE DISCONNECT, 2
POLE, 30A, SENTRY
243 9528 BUZZER, ALARM, SENTRY Each
244 9529 GASKET, BUZZER, ALARM, SENTRY
Measure
Vendor Part Number
Unit Price
245 9530 BULB, ALARM, 130V, 15W, SENTRY
Each
246 9531
LAMP SOCKET, SPRING TABS, SCREW
BASE Each
247 9534 LENS AND GASKET ASSEMBLY, SENTRY Each
248 9540
ADAPTER ASM, T260, FOR 240V WIRELESS
CORES
Each
249 9541
ADAPTER ASM, T260 W/ PHLA, FOR 240V
WIRELESS CORES Each
250 9542
REPLACEMENT LATCH KIT, SENTRY (1
LATCH) Each
251 9543
ALARM REPLACEMENT PC BOARD,
SENTRY PROTECT, 240V
Each
252 9547 LAMP, 130V, 15W, BAYONET BASE
Each
253 9552 Protect Plus NB0072G25-EONE DUPLEX
BOARD
Each
254 9602 GROMMET, 2 PVC. 1/4 WALL
Each
255 9603
GROMMET 4 IN. (INLET SDR 35 - 1/4 IN
WALL)
Each
256 9604
GROMMET 4 IN. (INLET SCH 40 - 1/4 IN
WALL) Each
257 9605
GROMMET 6 IN. (INLET SCH40 - 3/8 IN
WALL)
Each
258 9606
GROMMET 6 IN. (INLET SDR35 - 3/8 IN
WALL)
Each
259 9610
VENT NIPPLE (THREADED BY GLUE, 2 IN
PVC X 2.5 IN LG - MUSH VENT KIT)
Each
260 9611 SLIP JOINT NUT, 2 PVC Each
261 9618 HINGE RING FOR TANK LID
Each
262 9619 1/4-20x1” BOLTS FOR TANK LID Each
263 9620 WASHER, PLAIN, SS 1/4 (2000 lid bolts and IDU core bolts) Each
264 C125FG
1 ¼” NPT BOLT – ON COMPOSITE FG
COUPLING
Each
265 C24WFNST LID 24”-FG COVER FOR 24” BASIN Each
FS-BC-
C48WFNST 48” Fiberglass Lid Each
Measure
Vendor Part Number
Unit Price
FS-BF-
FB48X072
48”X72” DUPLEX FIBERGLASS BASIN
WITH 48” ALUMINUM COVER WITH DOOR
268 FPPF400 GUIDE CLAW
269 FPFG400 GASKET
270 NA0219P06
FTG, ADAPTER, ¼ In NPT x 3/16 In Barb (4240) Each
NA0775
NA0775P01
Spacer for Eye-Bolts on Extreme Metering Pump
272 NB0035G04 EXP TRANSCEIVER ASSEMBLY, 240V
273 NB0070G03
Panel Boards Assembly, Extreme, Standard with Contact Group (DIN Rail Mount Panel Guts For Upgrades)
274 NB0098G05
WW PUMP KIT, EQD HANGER Each
275 NB0101G02
MEMBRANE/DF ASM,120
SD/240,PPSENTRY PROTECT PLUS,
REPLACEMENT
276 NB0101G04
MEMBRANE/DF ASM,240V, SD, 2P, 99
SENTRY PROTECT PLUS REPL (DUP PP)
277 NB0184P01
CURB STOP WITH CHECK VALVE Each
278 NB0296G10
SPA-Sentry Advisor Assembly, Stand Alone, DUPLEX, For Existing Panel that does not have Dry Contacts, Standard Cell Carrier (US &
CANADA)
279 NB0290G013
The Sentry Advisor Retrofit Kit for most Sentry Simplex & Protect, Standard
NB040G01
CUTTER WHEEL REMOVAL TOOL Each
NC0304G01
Panel, Manual Float, 3 Pole, 240V, 1PH Each
NC0305G01
T206 Duplex…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .