CAFB_Bird Detection Radar System_SOW.docx
DOCX document 81 KB Posted
- Attached to
- Bird Radar 24
- Solicitation number
- FA485524BirdRadar
About this file
This document is a Statement of Work (SOW) for a bird detection radar system to be provided to Cannon Air Force Base (CAFB). The key requirements include:
The contractor shall provide a fully self-contained, trailered or fixed radar system capable of detecting birds from raptor-sized to flocks, tracking aircraft, and assessing aircraft-bird strike risk. The system must include radar sensors, aircraft tracking via ADS-B, real-time display and alerting, data archiving, and comprehensive maintenance/support for 5 years. The system shall be installed, commissioned, and training provided at CAFB within 90 days of contract award. The contractor will also provide permitting support, on-site installation oversight, and post-deployment site visits and maintenance. The government will provide the necessary infrastructure, with the contractor responsible for the complete radar system.
The related federal contract opportunity is a Sources Sought announcement, not a formal solicitation. Cannon AFB is gathering information from interested vendors registered in SAM.gov to determine if there are enough qualified contractors capable of meeting the requirements outlined in the attached SOW. There is currently no funding or obligation to award a contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bird Detection Radar (BDR Specifications Sheet - 27 SOW SEF.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Vision Statement | 4 |
| 1 Introduction | 4 |
| 1.1 Mission | 4 |
| 1.2 Background | 4 |
| 1.3 Scope | 4 |
| 2 General Requirements | 4 |
| 2.1 Business Relations | 4 |
| 2.2 Contract Administration and Management | 4 |
| 2.2.1 Contract Management | 5 |
| 2.2.2 Contract Administration | 5 |
| 2.3 Location and Hours of Work | 5 |
| 2.4 Range Safety Training | 5 |
| 2.5 General System Requirements | 5 |
| 3 Performance Requirements | 6 |
| 3.1 Provide a fully self-contained, trailered or custom fixed skid mounted Bird Detection Radar system, functional at delivery for MAFR | 6 |
| 3.2 Radar Capability and Design | 8 |
| 3.3 Operating software | 8 |
| 3.4 Provide SQL Datasystem for Bird Detection Radar System at Melrose Air Force Range. | 9 |
| 3.5 Provide remote user displays | 9 |
| 3.6 Delivery | 9 |
| 3.7 Site Visit | 9 |
| 3.8 Permitting and Approval Support | 9 |
| 3.9 Drawings | 10 |
| 3.10 Installation | 10 |
| 3.11 System Start-up and Commissioning | 10 |
| 3.12 User Concept of Operations (CONOPS) | 10 |
| 3.13 Training | 10 |
| 3.14 Reproducible Digital Copies of User Operations & Maintenance (O&M) Manuals | 10 |
| 3.15 Follow-on Support | 10 |
| 3.16 Archiving and Analysis | 11 |
| 3.17 Technical Support | 11 |
| 3.18 Upgrades | 11 |
| 3.19 Warranty | 11 |
| 3.20 Emergency Power System | 11 |
Statement of Work (SOW) Bird Detection Radar System Vision Statement Provide vertical and horizontal aircraft bird strike avoidance radar system for Cannon Air Force Base (CAFB) 1 Introduction
1.1 Mission
Provide an accessible, realistic, comprehensive military training facility that is dynamic and responsive to SOCOM, AFSOC, and USAF training needs.
1.2 Background
Cannon Air Force Base is home to the 27 Special Operations Wing accommodating Air Force Special Operations’ largest flight mission with multiple types air and ground missions. Located 5 miles from the city of Clovis, this base executes specialized and contingency operations including support missions for all Special Operations activities. Cannon Air Force Base consists of 5.3 square miles and operates the AC-130J Ghostriders, MC-130J Commando II, MQ-9 Reaper, CV-22 Osprey and U-28 Draco. The installations hosts all support required for this mission set and its 12,049 personnel assigned and their families. The 27 SOW at Cannon Air Force Base supports all DoD and non-interfering civilian agency training requirements.
1.3 Scope
In accordance with this Statement of Work (SOW) the contractor will supply and support a bird strike detection radar system to provide a cost-effective, comprehensive solution for advance detection, alerting and management of aircraft-bird strike risk at Cannon Air Force Base (CAFB), New Mexico. The contractor will supply the system, installation, and maintenance necessary to provide a complete and functional system.
2 General Requirements
2.1 Business Relations
The contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The contractor shall manage the timeliness, completeness, and quality of problem identification. The contractor shall seek to ensure customer satisfaction and professional and ethical behavior of all contractor personnel.
2.2 Contract Administration and Management
The following subsections specify requirements for contract, management, and personnel administration.
2.2.1 Contract Management
The contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of the resources assigned to the requirement. The contractor must maintain continuity between the support operations at CAFB and the contractor's corporate offices.
2.2.2 Contract Administration
The contractor shall establish processes and assign appropriate resources to effectively administer the requirement. The contractor shall respond to Government requests for contractual actions in a timely fashion. The contractor shall have a single point of contact between the Government and Contractor personnel assigned to support contracts or task orders. The point of contact shall have full authority to act for the Contractor on all matters relating to the daily operation of the contract. The contractor shall designate this individual, in writing, to the Contracting Officer (CO) before the contract start date.
2.3 Location and Hours of Work
Accomplishment of the results contained in this SOW requires work at Cannon Air Force Base, NM 88101. Normal workdays at CAFB are Monday through Friday except US Federal Holidays. The airfield is generally open from 0400-0200 (following day). The contractor will determine the hours necessary for workers to be present during normal operations hours. It is not a requirement for the contractor to be present during all of the operations hours. In the event of severe/adverse weather, the contractor will be notified to take the appropriate action. That action may include not reporting (base closure), evacuation, or to seek shelter. Initial safety training will include locations of shelter and evacuation rendezvous points.
2.4 Flightline and Safety Training
All workers will attend Flightline and Safety training in order to operate within the restricted areas of the airfield. The contractor is required to maintain radio contact with the Tower atl all times when moving within the Controlled Movement Area. Radios will be monitored at all times. Failure to monitor or answer radio calls may result in worker removal from the installation until Flightline and Safety retraining can take place. Flightline and Safety Officer training is provided by 27 SOSS/OSA. This training can be scheduled by calling (575)784-2148. Training must be scheduled and received prior to contract start.
2.5 General System Requirements
The system will be designed and constructed utilizing highly reliable and field proven components and provide a reliable, easily maintained and supported solution for bird detection and avoidance on CAFB. The technology supplied, including the system hardware and software, must be proven technology in use throughout the U.S. within the DoD and civilian applications. The system shall be developed for bird-aircraft strike risk assessment and avoidance for DoD, U.S. Government agencies, and commercial airports worldwide for aviation safety, environmental management and research. The system will provide real-time display of bird activity, real-time aircraft-bird strike risk alerting and deconfliction at CAFB with risk information and strike alerts in the Control tower. This system should also be available to aircrews via commercially accessible web base service(s).
The system will provide precise, tactical, automated bird-aircraft strike risk alerts to controllers at CAFB. The contractor shall provide the complete radar system, all the tools and supplies necessary for installation, installation, functional check/system validation to present a fully operational system at commissioning. The Bird Detection Radar will use a system comprised of solid-state doppler radars with open array, appropriate beam antennas to provide continuous bird detection of the operating airspace 360 degrees around CAFB from ground level to aircraft operational altitudes (>10,000 ft AGL). All maintenance of the system and included components, including initial validation, shall be included in the contract and performed by the contractor. The number and placement of the radar sensors is determined by the Contractor in consultation with the customer based on coverage modeling and site survey of CAFB. The government will provide electrical and communications infrastructure where required and will coordinate with the contractor and make final connections.
3 Performance Requirements
3.1 Provide a fully self-contained, trailered or custom fixed skid mounted Bird Detection Radar system, functional at delivery for CAFB.
Performance Standards
a) Standard: Provide design, equipment, installation, successful functional checks, and commissioning at locations determined during the site survey in coordination with 27 SOW/SE and 27 SOSS/OSA on CAFB.
AQL: Fully operational system upon completion of installation, checks, and commissioning on Cannon Air Force Base.
Deliverables A001 Functional Testing Documentation
3.1.1 Base equipment platform, radar towers and key structural components of marine grade corrosion resistant materials
3.1.2 Power system components consisting of switches, controllers, applicable code compliant wiring and commercial power connection with 25 ft power cable (110/220 VAC, 60/30 amp service required).
3.1.3 Bird detection radar sensors shall consist of the following:
· Solid State Pulsed Doppler
· ASTERIX (All-purpose Structured Eurocontrol Surveillance Information Exchange) Format-Compliant
· Integrated ADS-B (Automatic Dependent Surveillance-Broadcast) receiver
· High-rate signal processing (16 bit or better)
· J/F-12 Certification to radiate Note: The number and location of the radar sensors is determined by the Contractor in consultation with the customer based on coverage modeling and site survey of the airfield/airport and based on availability of infrastructure.
Performance Standards
a) Standard: System has greater than 45,000 operating hours of Mean Time Between Failures (MTBF) AQL: Contractor met requirement 95% of the time with no more than two customer complaints per year
b) Standard: System complies with most current edition of EUROCONTROL Specification for Surveillance Data Exchange AQL: Contractor met requirement 95% of the time with no more than two customer complaints per year
c) Standard: ADS-B receiver fully functions during operation AQL: Contractor met requirement 95% of the time with no more than two customer complaints per year
3.1.4 The contractor shall provide secondary surveillance ADS-B (Automatic Dependent Surveillance-Broadcast) receiver for secondary aircraft tracking and display of aircraft overlay on bird target display with different symbols
3.1.5 The contractor shall provide a display and remote software for real-time display of bird activity and current risk; includes advisory bird strike risk analysis and alerting software
3.1.6 Remote monitoring of the system, providing fully automated altering of the system 24-7 Performance Standards
a) Standard: Remote monitoring and automated alerting fully function during system operation AQL: System performed 99% of the time with one deficiency per year
3.1.7 Cellular WWAN uplink system for remote administration if required.
3.1.8 Ancillary support equipment including as applicable for mobile systems, spare tire, wheel chocks, tie-downs and ground anchors, and for all systems, lightning protection, tools, safety equipment (first aid and fire extinguishers), and safety signage.
3.1.9 System must be capable of transmitting radar data to central internet collection node via point-to-point microwave as required (fiber/copper may not be available).
3.2 Radar Capability and Design
Radar scanning design capable of characterizing the volume of airspace encompassing Cannon Air Force Base Class D Airspace and the common approach paths to all runways from surface to 10,000 AGL feet for bird detection (from Raptor-sized birds to flocks of small and large birds), avian and aircraft tracking, automatic BASH level determination and risk assessment.
Performance Standards
a) Standard: System provides real-time BASH level determination and risk assessment.
AQL: System performed 99% of the time with one deficiency per year.
b) Standard: System reliably detects varying sizes of birds, from Raptor-sized to flocks of small to large birds from surface to 10,000 feet Above Ground Level (AGL).
AQL: System performed 99% of the time with one deficiency per year.
c) Standard: System reliably detects aircraft from surface to 10,000 feet Above Ground Level (AGL).
AQL: System performed 99% of the time with one deficiency per year.
3.3 Operating software
System software shall be designed and engineered for bird detection (from Raptor-sized birds to flocks of small and large birds), avian and aircraft tracking, automatic BASH level determination and risk assessment. Modular operating system capable of upgrade to drone detection/tracking and target classification including target verification camera system.
Performance Standards
a) Standard: System software functions properly during hours of operation.
AQL: System performed properly 99% of the time with two deficiencies per year.
3.4 Provide SQL Data system for Bird Detection Radar System at Cannon Air Force Base.
Performance Standards
a) Standard: SQL data system (MS SQL based) and webserver for real-time risk assessment, display, alerting, archiving, analysis and reporting of processed bird target and track data at the site; includes auto reporter and full set of standard BASH reports and queries.
Deliverables A001 Functional Testing Documentation.
3.5 Provide remote user displays.
Deliverables A001 Functional Testing Documentation.
3.5.1 Workstations
Two (2) remote display and control workstations with high resolution 27 inch display monitors.
3.5.2 Wireless Display
One (1) remote cellular wireless enabled mobile tablet/pad radar display.
3.5.3 Risk status and Alerting Displays
Web-based, customized, zoned risk status and alerting displays, including multiple user formats for ATC, airfield management and bird/wildlife control.
3.6 Delivery
Delivered to Cannon Air Force Base, NM 88108 no greater than 90 days from contract award.
3.7 Site Visit
Pre-delivery scoping site visit and meeting to occur within 30 days of receipt of order and supplemental detailed radar coverage modeling to validate preliminary design.
Deliverables A003 Site Survey Verification
3.8 Permitting and Approval Support
Permitting and approval support (e.g. frequency, Approval to Radiate, and ATO) to include document submittals, agency interface and meetings.
Deliverables A002 US DoD JF/12 Frequency Approval Certification and Number.
3.9 Drawings
The contractor shall provide engineering drawings for foundation, system and electrical.
Deliverables A007 Drawings
3.10 Installation
The contractor shall provide installation, oversight and support, 5 days on-site.
3.11 System Start-up and Commissioning
System start-up and commissioning to include 10 days on-site plus remote support.
3.12 User Concept of Operations (CONOPS)
Contractor will provide the user CONOPS procedures development and integration support.
3.13 Training
The contractor will provide the user any operations and maintenance on-site training, 2 days.
3.14 Reproducible Digital Copies of User Operations & Maintenance Manuals The contractor shall provide reproducible digital copies of User Operations & Maintenance Manuals (user and technical; one to be installed on main system) Fully integrated communications between base system, sensors, and stations. Integrated radar with base system and satellite sensors/stations.
3.15 Follow-on Support
Post start-up site visit and assessment for year 1 at 3 months after commissioning, 6 months and 12 months and one (1) trip per year for the following five (5) years. Site visit to be coordinated with 27 SOW/SE and 27 SOSS/OSA.
3.15.1 One on-site annual radar inspection and maintenance visit for five years.
3.15.2 On-site maintenance response within 48 hours of failure notification for five years.
Page
3.16 Archiving and Analysis
Five (5) years custom archive data processing and analysis to commence after commissioning. Non-volatile storage of all recorded data including all BASH information including daily, weekly, quarterly, and annual BSH/aircraft activity reports for five years.
3.17 Technical Support
24-hour technical support, Mon-Sun for five years (minimum).
3.18 Upgrades
All software upgrades released during system ownership of unit.
Performance Standards
a) Standard: Five (5) years of software upgrades.
3.19 Warranty
Five years (minimum) full on-site parts and labor warranty.
3.20 Emergency Power System
Diesel or propane 4 kilowatt (kW) emergency backup power generator system with extended run fuel tank (supports about 10 24-hour days of operation; oil and filter change required every 250 hours) and automatic commercial/generator power transfer switch that will start the generator should commercial power fail. Page