caddo parish mira myrtis road bridge 26-17.pdf
PDF 12 MB Posted
- Attached to
- Mira Myrtis Road Bridge Replacement
- Solicitation number
- 26-17
- Issued by
- Caddo Parish, Louisiana
About this file
This is a geotechnical exploration report prepared by Goldman Geotechnical Consulting, LLC for the proposed Mira Myrtis Road Bridge Replacement project in Caddo Parish, Louisiana, authorized by Land & Aquatic Resource Management, LLC. The project consists of replacing an existing bridge located approximately 1.31 miles west of Interstate 49 with precast concrete bridge span(s) supported on a deep foundation system. The geotechnical investigation included two soil borings completed on March 23-24, 2026—one through the eastern abutment and one through the western abutment—to evaluate subsurface conditions and develop recommendations for safe and economical foundation design. The report was prepared on April 8, 2026, and includes laboratory testing, Standard Penetration Tests, groundwater observations, and engineering analysis in accordance with ASTM Standards.
The geotechnical findings indicate subsurface conditions consisting of four generalized strata, including fill material, clayey sandy silt, and gray lean-to-fat clay, with groundwater encountered at approximately 15 feet depth. The report recommends a deep foundation system utilizing 14-, 16-, or 18-inch square precast concrete piles with embedment depths ranging from 35 to 60 feet, with allowable loads ranging from 23 to 105 tons depending on pile size and depth. Pre-drilling is anticipated to be required, and a minimum test pile program is recommended. For pavement sections, the report specifies 4 inches of Hot Mixed Asphaltic Concrete over either 8 inches of Density Controlled Aggregate Base or 8 inches of Cement Stabilized Soil Base, with select fill or in-situ subgrade preparation to achieve a CBR value of approximately 6. The report includes detailed site preparation requirements, including scarification, compaction standards, proof-rolling procedures, and specifications for select fill material. Grain size analysis for scour analysis yielded D90 and D50 values of 0.178 and 0.056, respectively.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
10/06/2026
(Owner to provide name and address of owner) (Owner to provide name of project and other identifying information)
(Owner to provide name of entity preparing bid documents)
(Owner to provide description of alternate and state whether add or deduct)
(Owner to provide description of alternate and state whether add or deduct)
(Owner to provide description of alternate and state whether add or deduct)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
(Quantity X Unit Price)
MIRAMYRTIS ROAD BRIDGE REPLACMENT
CADDO PARISH PROJECT NO. 26 17
MIRAMYRTIS ROAD BRIDGE REPLACEMENT
http://www.revenue.louisiana.gov/forms/taxforms/1020(11_04)F.
Louisiana Department of Revenue or oc nolo contendere permanent disbarment period of five (5) years nolo contendere
GEOTECHNICAL EXPLORATION
PROPOSED MIRA MYRTIS ROAD BRIDGE REPLACEMENT
CADDO PARISH, LOUISIANA
FILE NO. G26-03-036
Prepared for
MR. JACOB RUMBAUGH, PE
LAND & AQUATIC RESOURCE MANAGEMENT, LLC
132 LONE OAK STREET
BENTON, LOUISIANA 71006
GOLDMAN GEOTECHNICAL CONSULTING, LLC
April 8, 2026
Mr. Jacob Rumbaugh, PE Land & Aquatic Resource Management, LLC 132 Lone Oak Street Benton, Louisiana 71006
RE: Geotechnical Exploration
Proposed Mira Myrtis Road Bridge Replacement Caddo Parish, Louisiana File No. G26-03-036
Dear Mr. Rumbaugh:
This office is pleased to transmit our geotechnical engineering services report for the above referenced project. The attached report presents the results of site investigations, laboratory testing, and engineering analysis and recommendations.
We appreciate the opportunity to provide our services to you and look forward to serving as your geotechnical consultant throughout this project. Please do not hesitate to contact this office if you have any questions regarding the information presented or if we may be of further service.
Sincerely, Goldman Geotechnical Consulting, LLC
Taylor M. Goldman, PE Member/Manager
GEOTECHNICAL EXPLORATION
PROPOSED MIRA MYRTIS ROAD BRIDGE REPLACEMENT
PROJECT DESCRIPTION
This report presents the results of the geotechnical exploration performed for the proposed replacement of an existing bridge on Mira Myrtis Road in Caddo Parish, Louisiana. The bridge to be replaced is located approximately 1.31 miles west of
Interstate 49. Two (2) soil borings were completed, one (1) through the eastern abutment on the north half of the roadway and one (1) through the western abutment on the south half of the roadway. The general locations of the investigation are indicated on the attached Boring Location Diagram. Preliminary design information indicates the rehabilitation project will likely consist of replacing the existing bridge with precast concrete bridge span(s) supported on a deep foundation system. Pavement structure is anticipated to consist of hot mix asphaltic concrete (HMAC) surface. It is anticipated that the top of the pavement elevation following the construction will be at or near that of the existing grade at the time of the field operations.
GENERAL
The study was authorized by Mr. Jacob R. Rumbaugh, PE, of Land & Aquatic
Resource Management, LLC on March 11, 2026, via email. The purpose of the investigation was to evaluate the general subsurface conditions and develop recommendations for the safe and economical design of the foundation system for the bridge replacement, pavement sections, and subgrade preparation. The study included drilling sample borings, performing laboratory testing, and engineering analysis of the subsurface conditions. The field and laboratory investigations included in this report have been conducted in accordance with applicable standards and procedures set forth in ASTM Standards.
FIELD OPERATIONS
The subsurface conditions were evaluated by two (2) sample borings drilled between March 23 and 24, 2026. One (1) boring was completed on each end of the bridge for the approaches. The number and depth of the borings performed were specified through consultation with the design professional. The boring locations were selected and staked by representatives of Goldman Geotechnical Consulting, LLC. The approximate locations of the borings are indicated on the attached Boring
Location Diagram. Descriptive terms and symbols used on the logs are in accordance with the Unified Soil Classification System. Surface elevation at the borehole location was not supplied prior to field operations.
A truck mounted auger drill rig was used to advance the test borings. Intermittent undisturbed samples were obtained in the following manner. Standard penetration tests were performed in accordance with ASTM procedures. This test is conducted by recording the number of blows required for a one hundred forty (140) pound hammer falling thirty (30) inches to drive a split spoon sampler eighteen (18) inches into the substrata. Depths at which split spoon samples were taken are indicated by two (2) crossed lines in the “Samples” column on the Log of Boring. The number of blows required to drive the sampler for each 6-inch increment were recorded. The penetration resistance is the number of blows required to drive the split spoon sampler the final twelve (12) inches of penetration. Information related to the penetration resistance is presented under the “Field Data” head of the Log of
Boring. All samples were extruded in the field, sealed to maintain in-situ conditions, and packaged for transport to the laboratory for additional testing.
Water observations were recorded during the drilling operations and again in the open boreholes upon completion of the field services to evaluate groundwater conditions. All borings were backfilled at completion of the field operations.
LABORATORY TESTING
Upon return to the laboratory all samples were visually logged in accordance with the Unified Soils Classification System. Selected samples were subjected to standard laboratory tests under the supervision of a geotechnical engineer to verify classification and to determine pertinent engineering properties of the substrata.
The results of laboratory testing and soil classifications are tabulated on the attached Logs of Boring. Samples obtained during our field studies and not consumed by laboratory testing procedures will be retained for a period of thirty (30) days. Arrangements for storage beyond that period must be made in writing to this office.
SUBSURFACE CONDITIONS
The existing pavement section developed by this investigation consists of approximately six (6) inches asphaltic concrete. The soils encountered directly beneath the asphaltic concrete in this investigation are comprised of four (4) generalized strata. The initial stratum is comprised of apparent fill material consisting of medium dense to loose reddish brown and gray clayey sand and slightly clayey sandy silt to approximately three and a half (3.5) to five (5) feet depth. The clayey sand exhibits low plasticity, moderate to low shear strength, low to moderate compressibility. The sandy silt portion of this stratum exhibits no plasticity and is considered to be moisture sensitive. These soils generally lose significant strength and begin to “pump” and yield upon saturation and disturbance.
The surficial stratum in each boring is comprised of loose to medium dense yellowish brown and gray slightly clayey sandy silt to approximately eight (8) to sixteen (16) feet depth. The silt exhibits low plasticity, low to moderate shear strength, and is considered to be moisture sensitive. The clayey, sandy silt in B-1 is underlain by loose yellowish brown and gray silty sand to approximately seventeen
(17) feet. The silty sand exhibits no plasticity. The lower stratum encountered to the eighty (80) feet termination depth is comprised of stiff to very hard gray lean-to-fat and lean clay with silty sand seams. The clay stratum exhibits moderate to low plasticity, moderate to high shear strength, and low compressibility.
The subsurface descriptions provided in this section are of a generalized nature to highlight the major stratification features and material characteristics. For a detailed description of the subsoils refer to the soil profiles located on the attached Logs of
Boring.
Groundwater was encountered in both borings at approximately fifteen (15) feet depth during drilling operations. Upon completion of field operations, the water level in B-1 was recorded at ten (10) feet depth. No measurable groundwater was detected in B-2 upon completion. The borehole walls of each boring collapsed between ten (10) and thirteen (13) feet. Based on site topography, subsurface stratigraphy, and anticipated construction techniques required for this project, groundwater is not anticipated to present any significant problems out of typical for projects of this type during the construction phase of the project. However, the depth of perched water and shallow groundwater is influenced by seasonal moisture variations. Consequently, the depth to shallow subsurface water should be verified prior to the start of construction of the project.
ANALYSIS AND RECOMMENDATIONS
It is the understanding of this office that the proposed bridge will likely be supported by a deep foundation system consisting of precast concrete driven piles. Based on experience with similar bridge replacement projects, it is anticipated that the foundation system will likely consist of either fourteen (14) inch, sixteen (16) inch, or possibly eighteen (18) inch square concrete piles. Provided in the following table are allowable loads for the anticipated pile sizes at various depths. The embedment lengths provided are depths below the roadway elevation at the time of the geotechnical investigation.
PILE TYPE EMBEDMENT
LENGTH (feet)
ALLOWABLE LOAD (tons)
COMPRESSION
14” Square Concrete 35 23 40 29 45 43 50 55 55 66 60 78
16” Square Concrete 35 27 40 34 45 51 50 64 55 78 60 91
18” Square Concrete 35 32 40 39 45 59 50 75 55 90 60 105
The bearing values contain a factor of safety on the order of two (2). Due to the results of the Standard Penetration Tests, as represented by the N-values on the
Logs of Boring, pre-drilling of the piles will likely be required to install the piles to the required depth. Pre-drilling shall be terminated a minimum of five (5) feet above the final tip elevation. The diameter of the augers utilized in pre-drilling operations should be no larger than the nominal width of the pre-cast concrete piles.
It is recommended a minimum of one (1) test pile of the type and length selected for the design be installed. Allow a minimum of five (5) days after driving for set to occur prior to testing the pile. The test pile program should be utilized to determine an installation procedure and the single pile load capacity. Pile group capacity may be assumed to be the sum of the properly installed piles, provided a minimum pile to pile spacing is maintained. For this site, the minimum recommended pile spacing is three (3) diameters.
An accurate driving record should be maintained by experienced personnel for all foundation pile installations. All piles should be driven to the same approximate tip elevation. Total settlement potential of properly prepared installed piles is estimated to be less than one (1) inch, and differential settlement is estimated to be less than half (0.5) of an inch.
Additionally, grain size analysis of the soils that line the stream bed were collected and tested for particle size distribution for later scour analysis. The values collected for the scour analysis are D90 and D50. The values calculated for these two (2) parameters are 0.178 and 0.056, respectively.
PAVEMENT SECTIONS
The design of pavement sections for this site is based upon subsurface conditions inferred by the test borings and the anticipation of the subgrade materials consisting of select fill material or in-situ soils prepared as per the Site Preparation section of this report. Select fill of the type specified in this report and in-situ soils will have
Unified Soil Classifications of CL, CL-ML, SC, SC-SM, or ML and should yield a
CBR value on the order of six (6) and a corresponding modulus of subgrade reaction (k) of 115 pci if prepared as described in the Site Preparation section of this report. It is the anticipation of this office that the pavement section will consist of Hot
Mixed Asphaltic Concrete surface.
The following flexible pavement section is recommended for this project:
Mira Myrtis Road Bridge Approaches
4.0 inches Hot Mixed Asphaltic Concrete over
8 inches Density Controlled Aggregate Base over
12 inches Density Controlled Select Fill or In-Situ Subgrade
Alternatively, in lieu of crushed stone base, the in-situ clayey sand to sandy silt soils or select fill material may be treated with cement to create a cement stabilized base course for the new HMAC surfaced pavement.
The following semi-flexible pavement sections are provided for this project:
Mira Myrtis Road Bridge Approaches
4.0 inches Hot Mixed Asphaltic Concrete over
8 inches Cement Stabilized Soil Base
The quantity of cement required for stabilization should be determined after initial pulverization of the proposed base. However, for bid purposes, it is anticipated that six (6) to seven (7) percent by volume will be acceptable to achieve a base course compressive strength minimum of 300 psi. Hot Mixed Asphaltic Concrete shall consist of Asphaltic concrete as defined by section 502 of The Louisiana Standard of Specifications for Roads and Bridges issued by the Louisiana Department of
Transportation and Development.
SITE PREPARATION
Site preparation will likely begin with removing the existing bridge structure and stripping of the existing pavement structure and any organic laden soil along the shoulders. A stripping depth on the order of six (6) inches is expected to remove the existing pavement. Additional excavation and backfill may be required in isolated areas of the site due to any undiscovered soft strata. It should be noted that the in-situ sandy silt soils encountered in B-2 may exhibit moisture sensitive characteristics due to saturation and disturbance through construction activities and may require additional undercutting and replacing with select fill. Once all deleterious matter has been removed, provide drainage of the exposed subgrade by sloping grades and ditching.
Following stripping and cutting and prior to any fill placement, the exposed surface of areas to receive select fill or base course should be scarified to a minimum depth of twelve (12) inches, the moisture content adjusted to within two (2) percent below to two (2) percent above optimum and compacted to a minimum of ninety-five (95) percent of the maximum dry density determined by ASTM D-698. Subsequently, the subgrade should be proof-rolled with a loaded tandem-wheel dump truck or equivalent equipment. Proof-rolling should be observed by a representative of the qualified construction materials testing laboratory to verify stable subgrade conditions. All soft or loose soils encountered within the construction areas should be undercut, stabilized, processed, and recompacted or excavated and replaced with select fill, whichever is appropriate.
Place select fill in thin, essentially horizontal layers not exceeding eight (8) inches in loose thickness and compact to a minimum of ninety-five (95) percent of the maximum density established by ASTM D-698 with the moisture content adjusted and maintained to within two (2) percent below to three (3) percent above optimum moisture content. All select fill should be sandy clay or clayey sand possessing a liquid limit no greater than thirty-five (35), a plasticity index ranging between five (5) and eighteen (18), and not greater than sixty-five (65) percent passing the No. 200 mesh sieve. Soils possessing a plasticity index less than five (5) or a percent passing the No. 200 sieve greater than sixty-five (65) shall NOT be utilized as structural fill at this site without prior approval by the design professional.
LIMITATIONS
The analysis and recommendations presented in this report are based upon the data obtained from the borings performed at the indicated locations and from any other information discussed in the report. This report does not reflect any variations which may occur between the borings or across the site. The nature and extent of such variations may not become evident until construction. If variations appear evident it will be necessary to reevaluate the recommendations of this report.
It is recommended the geotechnical engineer be given the opportunity to review the plans and specifications so comments can be made regarding the interpretation and implementation of our geotechnical recommendations in the design and specifications. Sound engineering judgement must be followed when applying the recommendations to designs, plans, and during the construction monitoring.
This report has been prepared for the exclusive use of our client for specific applications to the project discussed and has been prepared in accordance with generally accepted geotechnical engineering practices. No warranties, either expressed or implied, are intended or made. In the event any changes in the nature, design, or location of the project as outlined in this report are planned, the conclusions and recommendations contained in this report shall not be considered valid unless the changes are reviewed and the conclusions of this report or verified in writing by the Geotechnical Engineer.
BORING LOCATION DIAGRAM
MIRA MYRTIS ROAD BRIDGE REPLACEMENT
April 7, 2026 Project: G26-03-036
B-1
Note: Boring location is approximate and is just intended to represent the general area involved in the subsurface investigation.
B-2