CA NPS PP SEKI 2018(3) and CA NPS PP SEKI 2020(1),Pavement Preservation SEKI Phase I and Pavement Preservation SEKI Phase II

The work consists of Patching, crack sealing and resurfacing of asphalt surfaces throughout the National Parks and adjacent National Forest.

Project length: Base 70.99 Miles & Option X 7.94 Miles

Tentative Fixed Completion Date: Winter, 2021 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: $10 million to $15 million

Location: 60 Miles E of Clovis, California

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14

Sc h

Na m e Ba se

Na m e Op tio n

X

DIVISION 150 – Project Requirements 151 Mobilization (yes/no) Yes Yes 152 Construction Survey & Staking (yes/no) No No 153 Contractor Quality Control and Assurance (yes/no) Yes Yes 154 Contractor Sampling & Testing (yes/no) Yes Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes

DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Asphalt Concrete Pavement, Type 1 710 TON N/A 406 Fog Seal 718 TON N/A 407 Blotter 80 TON 40 TON 409 Micro Surfacing, Type 2 730,000 SQYD 90,000 SQYD 409 Micro Surfacing, Type 3 417,000 SQYD N/A 414 Asphalt Pavement Crack Cleaning & Filling 1,115 LNFT 52 414 Asphalt Pavement Crack Cleaning & Sealing 69 MILE 7.5 MILE 418 Asphalt Concrete Pavement Patching, Type 1 225 SQYD N/A 418 Asphalt Concrete Pavement Patching, Type 2 13,400 SQYD 2,000 SQYD DIVISION 600 – Incidental Construction 622 Rental Equipment (yes/no) Yes Yes 623 General Labor (yes/no) Yes Yes 633 Rumble Strips 22 SQYD N/A 634 Permanent Pavement Markings, (Type B) 2,500,000 LNFT 116,000 LNFT 634 Permanent Pavement Markings, Symbols (Type B) 350 EACH 85 EACH

Na m e Ba se

Na m e Op tio n

X

635 Temporary Traffic Control – Cone 220 EACH 220 635 Temporary Traffic Control – Portable Changeable Message Sign 6 EACH N/A 635 Temporary Traffic Control - Pavement Markings 250,000 LNFT 10,0000 635 Temporary Traffic Control – Construction Sign 250 SQFT 100 SQFT 635 Temporary Traffic Control – Flagger 14,000 HOUR 1,200 HOUR 635 Temporary Traffic Control – Pilot Car 330 HOUR N/A HOUR 635 Temporary Traffic Control – Traffic Control Supervisor 192 DAY 25 DAY

DIVISION 400 – Asphalt Pavements & Surface Treatments