Performance Work Statement (PWS) Geese Wildlife Management
11 June 2020
Program Executive Office Command, Control and Communications-Tactical (PEO C3T) Aberdeen Proving Ground, MD
1. Introduction:
The Army’s Program Executive Office for Command, Control and Communications-Tactical (PEO C3T) upholds its mission of developing, acquiring, fielding and supporting the Army’s tactical network through a dedicated workforce in order to provide soldiers the information they need to fight and win our nation’s wars. PEO C3T is located in Building 6010 on the Aberdeen Proving Ground (APG) campus in Maryland. The campus provides a central location utilized by leadership and staff personnel to support the PEO C3T mission.
1. General Specifications:
The purpose of this Performance Work Statement (PWS) is to provide the specifications for wildlife management as the Canadian geese population has migrated to Building 6010, the location of PEO C3T at APG, MD. The Canadian geese populations are excessive and are repopulating aggressively at the building location. The geese are fouling the ponds with excessive fecal waste. Additionally, they are leaving excessive amounts of droppings in the public areas of campus causing a bio-hazard situation where employees are tracking goose feces into the buildings.
1. Purpose:
The PEO C3T building (6010) is a large facility, housing many subordinate Program Management Offices (PMOs) and other supporting organizations. It is a highly active environment with high traffic throughout the day. Due to the critical nature of the operations at the facility, PEO C3T desires to engage the services of a contractor on a Firm-Fixed-Price (FFP) basis to remedy the excessive goose population in the area of Building 6010 on a recurring annual basis.
1. Objectives:
· The contractor shall be responsible for the cleaning of geese droppings on the sidewalks outside of Building 6010 once per week. The method of cleaning shall be determined by the contractor. Please note that a water source will not be made available for cleaning. It will be the responsibility of the contractor to provide the water source. This includes all three entrances to the building and the front sidewalk leading to the circle on the west side. Approximately 12,000 square feet of sidewalk.
· The contractor shall be responsible for keeping the geese away from Building 6010 and surrounding sidewalks as effectively as possible during normal business hours of operation (0800 – 1700).
· The contractor shall be responsible for controlling the geese population in the area year round, utilizing environmentally-safe techniques.
· The use of trained dogs (e.g. border collies) is required to encourage the geese to relocate from the area and migrate to another place.
· The trained dogs will be allowed to work off leash but must be in near contact and highly obedient to the handler.
· Mitigation shall be done without physically touching, injuring, or destroying the geese. Properly trained dogs shall not harm or touch the geese in anyway. The presence of the dogs will merely cause the geese to feel threatened, although they will be perfectly safe.
· Chemical repellants shall not be allowed regardless of environmental impact.
· The service hours must be scheduled in coordination with representatives of the PEO C3T facility. Staggered service hours are required to maximize performance.
· Weekend mitigation shall be required if necessary.
· The contractor shall be required to “addle” the goose eggs during nesting season using best practices/treatment of the eggs and immediately replacing them to the nests.
· The contractor shall be required to keep PEO C3T in compliance with any federal and state regulations that apply to geese mitigation.
· The contractor shall be licensed and must be in compliance with all federal and state environmental codes that apply to their business.
1. Deliverables and Schedule:
Monthly spot reports are required. Additionally, an annual goose mitigation report is required detailing the methods used, their outcomes, and proposed remedies and mitigation solutions for the next year. Monthly spot reports shall be sent to the technical point of contact electronically (e-mail). There is no specific format required. Contractor format is acceptable.
4. General Specifications
The vendor shall coordinate the schedule with the PEO C3T facilities manager/representative.
4. Deliverables
Deliverables
Due
| Spot Reports |
| Monthly |
| Goose Mitigation Reports |
| Annually |
| Invoicing |
| Monthly |
1. Place of Performance:
PEO C3T HQ, 6010 Frankford Street, Aberdeen Proving Ground, MD 21005
1. Period of Performance:
Total estimated performance will be five (5) years: One base year (12 months) with four (4) option years (12 months each). Performance shall commence upon receipt of the fully executed contract.
1. Time of Performance:
The contractor shall propose a time of performance not limited to the regular duty hours for the campus (0800 – 1700).
1. Special Provisions:
· Contractor personnel proposed to work under this contract must be United States citizens.
· Contractor is responsible for any special permits, certifications, and insurance required to complete all specified tasks.
· Contractor personnel must ensure that the PEO C3T facilities manager/representative or government personnel familiar with this requirement are informed of the contractor’s presence while performing at the APG campus under this contract.
1. Security:
Access and General Protection/Security Policy and Procedures:
Contractor and all associated subcontractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures. The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
11. Contractor Manpower Reporting Application (CMRA):
The Office of the Assistant Secretary of the Army Manpower & Reserve Affairs (ASAM&RA) operates and maintains a secure Army data collection site where the contractor will report ALL contractor manpower (including subcontractor manpower) required for performance of this contract. The contractor is required to completely fill in all the information in the format using the following web address: https://cmra.army.mil. The required information includes: (1) Contract Number; (2) Fiscal Year (FY that the work was performed); (3) Order Number (Delivery Order, Task Order, or Purchase Order Number); (4) Requiring Activity Unit Identification Code; (5) Command (Command of the Requiring Activity that would be performing the mission if not for the contractor); (6) Contractor Name; (7) Total Invoiced Amount (the total dollar amount invoiced during the fiscal year, at the Delivery Order and/or Task Order level. This is the responsibility of the contractor); (8) Questions about Contract Performance (Contractors: Indicate if the contract/order includes the above services); (9) Government Supervision (Are the contractor personnel subject to relatively continuous supervision and control by a Government employee or officer); (10) Government’s Tools and Equipment (Does the Government furnish the principal tools and equipment needed for contract performance); (11) Government Facility (Are some or all of the contractor employees provided with a workspace in a Government facility for use on a regular basis?); (12) Contracting Officer (First Name, Last Name, Phone Number, and Email); (13) COR/COTR (First Name, Last Name, Phone Number, and Email); (14) Contractor (First Name, Last Name, Phone Number, and Email); (15) Location Information (Federal Supply Code (FSC), City of Installation or Services, State, Zip, and Country); (16) Direct Labor Hours; (17) Direct Labor Dollars; (18) Fund Cite. As part of its submission, the contractor will also provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period will be the period of performance not to exceed 12 months ending 30 September of each Government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a contractor’s systems to the secure web site without the need for separate data entries for each required data element at the web site. The specific formats for the XML direct transfer may be downloaded from the web.