C260531_Exhibit_A_SOW.pdf
PDF 185 KB Posted
- Solicitation number
- 260531
- Issued by
- Orange County, California
About this file
This is a Scope of Work document for construction management services related to a hydrogen fueling station and facility modifications project at the Garden Grove Bus Base in California. The project encompasses the design and construction of a new hydrogen fueling station, associated facility modifications, and related infrastructure improvements to support hydrogen fuel cell bus operations. The scope of work outlines the construction manager's responsibilities throughout the project lifecycle, including pre-construction planning, coordination with design professionals and contractors, quality assurance and control, schedule management, budget oversight, and administrative documentation. The construction manager must ensure compliance with all applicable codes, standards, and regulatory requirements while managing the construction process from initiation through substantial and final completion.
The construction manager will be responsible for coordinating between the owner, architect/engineer, general contractor, and all subcontractors to ensure seamless project execution. Key responsibilities include reviewing and approving construction documents, monitoring contractor performance, conducting site inspections, managing change orders and requests for information, maintaining project records, and facilitating communication among all project stakeholders. The construction manager must also ensure adherence to project budgets and schedules, verify contractor qualifications and insurance requirements, and document all aspects of construction progress and completion milestones.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 260531
EXHIBIT A
SCOPE OF WORK
CONSTRUCTION MANAGEMENT SERVICES
FOR HYDROGEN FUELING STATION AND FACILITY MODIFICATIONS
AT GARDEN GROVE BUS BASE
SECTION 1 – GENERAL
The Orange County Transportation Authority (OCTA or AUTHORITY) has procured the construction of a new hydrogen fueling station and facility modifications at Garden Grove Bus Base, hereinafter referred as the PROJECT. The new hydrogen fueling station will be constructed to provide hydrogen fueling for up to 100 fuel cell electric buses (FCEBs), with total daily fuel consumption of up to 3,000 kilograms. Facility modifications related work will be conducted at existing maintenance facilities that are affected by the introduction of hydrogen system to the property.
OCTA is seeking proposals from construction management consulting firms to provide construction management services related to the PROJECT on a Time and Expense basis. The selected firm (CM CONSULTANT) shall have expertise and experience in construction management of all aspects of similar hydrogen fueling station and facility modifications projects.
LIMITATION ON GOVERNMENTAL DECISIONS
Nothing contained in this scope of work permits CONSULTANT’S personnel to authorize or direct any actions, votes, appoint any person, obligate, or commit AUTHORITY to any course of action or enter into any contractual agreement on behalf of AUTHORITY. In addition, CONSULTANT’s personnel shall not provide information, an opinion, or a recommendation for the purpose of affecting a decision without significant intervening substantive review by AUTHORITY personnel, counsel, and management.
1.1. Project Overview
The PROJECT will be delivered as a design-build project to address the needs and requirements of OCTA bus operations. Installation of new 25,000-gallon tank, two (2) hydrogen fuel dispensers, and all other hydrogen equipment and components required for a turnkey code-compliant hydrogen fueling station are included as part of the PROJECT. Installation of new dedicated electrical service power feed and electrical service equipment to support the hydrogen fueling station are also included as part of the PROJECT. Facility modifications will include installation and integration of hydrogen detection systems, and all other work that is required due to the introduction of hydrogen system to the property.
The PROJECT includes, but is not limited to, the following work:
• Demolition, Soil Compaction Grouting, Earthwork, Concrete,
• Masonry Walls, Fencing, Safety Bollards,
• Electrical Service Equipment, Hydrogen Storage and Fueling Equipment,
• Area Lighting, Video Surveillance System Cameras, Signage,
• Hydrogen Detection Systems, Emergency Shutdown Systems,
• Battery Backup Systems,
• Maintenance Platform (for OCTA Bus Fleet),
• And All Other Related Work required.
1.2. Project Construction Schedule
Anticipated PROJECT construction related dates are as follows:
• Construction Start: November 1, 2027
• Construction Completion: June 1, 2028
• Commissioning and Construction Closeout Finish: August 1, 2028
1.3. Definitions
As used throughout this scope of work document, the following terms shall have the meanings set forth below:
• ‘OCTA’ or ‘AUTHORITY’ shall be the Orange County Transportation Authority.
• ‘PROJECT’ shall mean new hydrogen fueling station and facility modification at Garden Grove Bus Base, including all the components in the project plans/drawings, specifications, and other construction contract documents.
• ‘OCTA PROJECT MANAGER’ shall mean the Chief Executive Officer of OCTA acting either directly or through properly authorized agents or representatives acting within the scope of particular duties entrusted to them.
• ‘DESIGN-BUILDER’ shall mean the person or persons, firm, partnership, corporation, or combination thereof, who have entered into an agreement contract with OCTA, to design and construct the hydrogen fueling station and facility modification at Garden Grove Bus Base.
• ‘AUTHORITIES HAVING JURISDICTION’ or ‘AHJ’ shall mean the local City and agencies/authorities having jurisdiction over the PROJECT.
• ‘CITY’ shall mean the City of Garden Grove.
• ‘CM CONSULTANT’ shall mean the firm responsible for the scope of work related to construction management services, as required in this scope of work document.
• ‘CONSTRUCTION MANAGER’ shall mean the PROJECT’s direct responsible charge of construction management services.
• ‘Construction Contract Documents’ shall mean all project plans/drawings, specifications, and all other construction documents related to the Design- Build Contract.
• ‘Design-Build Contract’ shall mean the agreement between OCTA and DESIGN-BUILDER to design and construct the hydrogen fueling station and facility modification at Garden Grove Bus Base.
SECTION 2 – GENERAL CONDITIONS AND REQUIREMENTS
Under general direction of OCTA PROJECT MANAGER, CM CONSULTANT shall provide personnel for construction management services related to the construction and delivery of hydrogen fueling station and facility modifications, as required in this scope of work document.
Anticipated PROJECT construction management services related dates are as follows:
PROJECT Construction Management Services Construction Management Services Start: September 1, 2027 Construction Management Services Finish: August 1, 2028 PROJECT Construction Construction Start: November 1, 2027 Construction Completion: June 1, 2028 Commissioning and Construction Closeout Finish: August 1, 2028
2.1. Work Performance
CM CONSULTANT shall commence work immediately upon receiving the distributed agreement between OCTA and CM CONSULTANT.
2.2. Communication
CM CONSULTANT shall include OCTA PROJECT MANAGER and designated OCTA personnel, if any, in all PROJECT related communications. Unless otherwise directed by OCTA, all PROJECT related communications shall be through platforms listed below:
• Microsoft Outlook emails
• Microsoft Teams
• Other SharePoint (e.g., Microsoft OneDrive, etc.), at OCTA’s discretion
2.3. Project Management Plan
CM CONSULTANT shall prepare a Project Management Plan (PMP), which shall demonstrate CM CONSULTANT’s understanding of the scope of work, constraints, and requirements of the agreement between OCTA and CM CONSULTANT. PMP shall show the roadmap for successful delivery of services to be provided by CM CONSULTANT.
• PMP shall include template of Risk Register document that will be utilized and furnished by CM CONSULTANT throughout the duration of the agreement between OCTA and CM CONSULTANT. Risk Registers shall be updated regularly to record findings of the project risk assessment and to track management of identified risks. Risk Registers should identify each risk factor, individual or entity that is responsible for managing a risk factor, and a list of actions that shall be taken to monitor or mitigate risk factor.
CM CONSULTANT shall submit PMP to OCTA, for review and comments, within one (1) week of receiving the distributed agreement between OCTA and CM CONSULTANT; CM CONSULTANT shall address all OCTA’s comments, if any, then submit the final PMP for acceptance within one (1) week of receiving OCTA’s comments. CM CONSULTANT shall implement the accepted PMP throughout the duration of the agreement between OCTA and CM CONSULTANT.
2.4. Quality Management Plan
CM CONSULTANT shall prepare a Quality Management Plan (QMP), which shall provide comprehensive quality control (QC) processes and procedures that outline checking/reviewing procedures to be performed on preparation of reports, construction documents, cost estimates, management systems, and quality assurance (QA) for internal (including any subconsultants) surveillances and audits, to maintain product quality, schedule, and budget adherence.
• QMP shall include an organizational chart (o-chart) to clearly identify personnel working on PROJECT. O-chart shall include name, title, company, and role of each person on PROJECT.
CM CONSULTANT shall submit QMP to OCTA, for review and comments, within one (1) week of receiving the distributed agreement between OCTA and CM CONSULTANT; CM CONSULTANT shall address all OCTA’s comments, if any, then submit the final QMP for acceptance within one (1) week of receiving OCTA’s comments. CM CONSULTANT shall implement the accepted QMP throughout the duration of the agreement between OCTA and CM CONSULTANT.
2.5. Health, Safety and Environmental Requirements
CM CONSULTANT shall comply with all OCTA Health, Safety and Environmental (HSE) requirements.
SECTION 3 – CM CONSULTANT RESPONSIBILITIES
CM CONSULTANT shall provide professional services including, but not limited to, project coordination, construction oversight and documentation, construction quality assurance, project document control, project administration, and all other construction management related services. CM CONSULTANT shall take responsibility for the quality, efficient and timely completion of all PROJECT construction related work. CM CONSULTANT will be subject to periodic quality audits as determined by OCTA.
CM CONSULTANT shall provide qualified personnel consisting of Construction Manager, Assistant Construction Manager, and Administrative Staff. The level of support anticipated from CM CONSULTANT, as required in this scope of work document, are as follows:
• One (1) full-time Construction Manager: CM CONSULTANT shall assign personnel as CONSTRUCTION MANAGER to manage, oversee, and delegate all authorized work. CONSTRUCTION MANAGER shall be the PROJECT’s direct responsible charge of construction management services.
• One (1) part-time Assistant Construction Manager: CM CONSULTANT shall assign personnel as ASSISTANT CONSTRUCTION MANAGER to support construction management services provided by CONSTRUCTION MANAGER.
• One (1) part-time Administrative Staff: CM CONSULTANT shall assign personnel as ADMIN STAFF to manage daily clerical and organizational related work.
CONSTRUCTION MANAGER and ASSISTANT CONSTRUCTION MANAGER shall be knowledgeable of, and comply with, all local, state, and/or federal regulations applicable to the PROJECT. CONSTRUCTION MANAGER and ASSISTANT CONSTRUCTION MANAGER shall be thoroughly familiar with CITY and other AHJ requirements for the PROJECT. CONSTRUCTION MANAGER and ASSISTANT CONSTRUCTION MANAGER shall be thoroughly familiar with project drawings, specifications, and all other construction documents.
CONSTRUCTION MANAGER shall visit the PROJECT site on a daily basis during PROJECT construction. CONSTRUCTION MANAGER shall communicate, coordinate, and cooperate with OCTA personnel throughout the duration of the agreement between OCTA and CM CONSULTANT, and perform services to ensure that PROJECT is constructed in general accordance with project drawings, specifications, and all other construction documents.
3.1. Task 1: Construction Management Plan
CM CONSULTANT shall prepare a Construction Management Plan (CMP), which shall demonstrate CM CONSULTANT’s understanding of the PROJECT and all its construction management related requirements. CMP shall outline CM CONSULTANT’s procedures and strategies to manage PROJECT construction and related work, within budget and schedule, in compliance with Construction Contract Documents and all AHJ requirements.
Prior to preparation of the CMP, CM CONSULTANT shall conduct a constructability review of project drawings, specifications, and all other construction documents; CM CONSULTANT shall discuss their review findings with OCTA, including any constructability related issues/concerns and any necessary design clarifications.
At a minimum, CMP shall demonstrate CM CONSULTANT’s understanding of the following matters and their potential issues and concerns, if any:
• Public and site safety and security
• Coordination timeline with all AHJ and adjacent property owners
• Coordination timeline with typical bus operations and other stakeholders
• Site operating hours
• Project constructability
• General construction methodology and programs
• Site waste management
• Air, dust, stormwater, drainage/sediment controls
• Noise and vibration controls
• Traffic management including access routes to and from the site
• Site specific details which require detailed assessments
• Project document control CM CONSULTANT shall submit CMP to OCTA, for review and comments, within two (2) weeks of receiving the distributed agreement between OCTA and CM CONSULTANT; CM CONSULTANT shall address all OCTA’s comments, if any, then submit final CMP for acceptance within one (1) week of receiving OCTA’s comments. CM CONSULTANT shall implement the accepted CMP during PROJECT construction and related work.
3.2. Task 2: Construction Management Services
All construction management related services shall be provided by qualified full-time CONSTRUCTION MANAGER with support from qualified part-time ASSISTANT CONSTRUCTION MANAGER, per Section 4 of this scope of work document.
3.2.1. Project Controls and Meetings
CONSTRUCTION MANAGER shall attend PROJECT pre-construction meeting and weekly construction meetings, which will be coordinated and conducted by DESIGN-BUILDER throughout the duration of PROJECT construction.
CONSTRUCTION MANAGER shall participate/engage in construction meetings, with the intent to discuss/review matters that affect construction related work and timely delivery of the PROJECT.
CONSTRUCTION MANAGER shall regularly review construction schedules and related projected construction activities, then discuss with OCTA any review comments and recommendations, to ensure completion of PROJECT construction is within the scheduled timeframe; CONSTRUCTION MANAGER’s review approach shall include intent to improve construction performance and to limit any potential construction impacts.
3.2.2. Coordination with AHJ and all other PROJECT stakeholders DESIGN-BUILDER shall be responsible for PROJECT coordination with appropriate AHJ and PROJECT stakeholders, to ensure timely delivery of the PROJECT. AHJ related to the PROJECT includes, but are not limited to, City of Garden Grove, Orange County Fire Authority (OCFA), Orange County Healthcare Agency (OCHA), South Coast Air Quality Control Management District (AQMD), Southern California Edison (SCE), Federal Transit Administration (FTA).
CONSTRUCTION MANAGER shall assist on all required PROJECT coordination to ensure any issues and concerns are properly addressed in a timely manner, which may include coordination with OCTA PROJECT MANAGER, DESIGN- BUILDER, AHJ, adjacent property owners, and other PROJECT stakeholders.
CONSTRUCTION MANAGER shall keep records of all communications related to PROJECT coordination.
3.2.3. Construction Field Observations and Inspections
CONSTRUCTION MANAGER shall ensure that PROJECT construction meets all requirements under the terms of the Design-Build Contract. CONSTRUCTION MANAGER shall ensure DESIGN-BUILDER obtains all required permits and that PROJECT construction is performed in compliance with CITY and other AHJ requirements, as well as all required inspections and approvals.
CONSTRUCTION MANAGER shall monitor and inspect PROJECT construction for defects, deficiencies, and deviations from Construction Contract Documents.
CONSTRUCTION MANAGER shall notify OCTA promptly of any construction defect, deficiencies, and deviations; along with appropriate recommendations to OCTA. Subject to review and approval by OCTA, CONSTRUCTION MANAGER shall reject construction work that does not conform with Construction Contract Documents. CONSTRUCTION MANAGER shall monitor and inspect required corrections related to defects, deficiencies, and deviations until corrected and accepted by OCTA.
CONSTRUCTION MANAGER shall schedule and administer appropriate quality assurance material testing and inspections during PROJECT construction, which shall be coordinated with OCTA and DESIGN-BUILDER in a timely manner.
Material testing and inspection services, for quality assurance purposes, will be made available through OCTA’s on-call material testing and inspection consultant.
CONSTRUCTION MANAGER shall prepare reports on a daily basis (daily reports) to document the progress of PROJECT construction, which shall include daily-specific PROJECT information related to site weather condition, construction work performed by DESIGN-BUILDER and/or their subcontractors, number of construction workers, status of construction work at the end of the workday, construction related inspections and tests conducted, construction related issues/ concerns encountered, construction related delays, and other relevant information/ data related to construction activities. Daily reports shall also include photographs to capture the progress of construction activities and other relevant PROJECT matters.
CONSTRUCTION MANAGER shall furnish a log for daily reports, which shall be maintained by CONSTRUCTION MANAGER throughout the duration of PROJECT construction. Daily reports, as well as log of daily reports, shall be made available to OCTA upon request.
CONSTRUCTION MANAGER shall provide daily construction photos, and maintain records of all photos taken on OCTA SharePoint (Microsoft OneDrive) for the entire duration of PROJECT construction.
3.2.4. Construction Safety and Labor Compliance
CONSTRUCTION MANAGER shall ensure DESIGN-BUILDER complies with all safety provisions of the Construction Contract Documents, including all OCTA Health, Safety and Environmental (HSE) requirements.
CONSTRUCTION MANAGER shall verify that DESIGN-BUILDER complies with appropriate construction labor provisions.
• CONSTRUCTION MANAGER shall conduct field interviews with DESIGN- BUILDER’s onsite personnel and prepare field interview reports, at least once a month.
• CONSTRUCTION MANAGER shall obtain weekly certified payrolls (CPRs) from DESIGN-BUILDER; CONSTRUCTION MANAGER shall review CPRs for compliance with appropriate labor wage rates. CONSTRUCTION MANAGER shall compare labor and hours worked as indicated on the CPRs with construction labor records prepared and maintained by CONSTRUCTION MANAGER. DESIGN-BUILDER shall be notified by CONSTRUCTION MANAGER, in a timely manner, of any discrepancies between wages paid and appropriate labor wages.
3.2.5. Project Document Control
CONSTRUCTION MANAGER shall regularly review DESIGN-BUILDER's redlined as-built drawings onsite, to ensure changes and field conditions encountered are recorded. CONSTRUCTION MANAGER shall verify that DESIGN-BUILDER is accurately locating all underground utilities on their as-built drawings.
• CONSTRUCTION MANAGER shall keep and maintain their own redlined as-built drawings and specifications, to document all changes during construction. At PROJECT closeout phase, CONSTRUCTION MANAGER shall review DESIGN-BUILDER's redlined as-built drawings and specifications submittal with CONSTRUCTION MANAGER’s as-built plans and specifications prior to forwarding DESIGN-BUILDER's submittals to
OCTA.
CONSTRUCTION MANAGER shall be knowledgeable of all submittals required by Construction Contract Documents; CM CONSULTANT shall keep track of all submittals throughout the duration of PROJECT construction. CONSTRUCTION MANAGER shall provide general review of all submittals received from DESIGN- BUILDER, prior to forwarding any submittal to OCTA for review and acceptance;
CONSTRUCTION MANAGER shall be able to review and accept submittals that do not require technical assistance from OCTA (and their technical support).
CONSTRUCTION MANAGER shall ensure that all submittals are processed in a timely manner, as specified in the Construction Contract Documents.
CONSTRUCTION MANAGER shall maintain a log of all submittals received.
CONSTRUCTION MANAGER shall provide general review of all request for information (RFI) from DESIGN-BUILDER, and thoroughly understand all RFI prior to obtaining and preparing response to any RFI. CONSTRUCTION MANAGER shall identify any frivolous RFI and return it back to DESIGN-BUILDER.
CONSTRUCTION MANAGER shall work closely with OCTA to properly respond to RFI(s) in a timely manner. CONSTRUCTION MANAGER shall maintain a log of all RFIs received.
CONSTRUCTION MANAGER shall monitor and manage the initiation, preparation, justification of all contract change order (CCO). CONSTRUCTION MANAGER shall review and evaluate all change order request (COR) or similar request from DESIGN-BUILDER, then inform OCTA of all COR or similar request related impacts; CONSTRUCTION MANAGER shall advise OCTA of the acceptability of DESIGN-BUILDER’s COR(s) or similar request(s), including proposed adjustment(s) to the Contract Time and/or Contract Amount.
CONSTRUCTION MANAGER shall coordinate and negotiate all COR or similar request with DESIGN-BUILDER. CONSTRUCTION MANAGER shall coordinate with OCTA and obtain/prepare appropriate CCO documents which includes COR(s) or similar request, independent cost estimates (ICE), memoranda, and any other applicable documents. When necessary, for Force Account CCOs, CONSTRUCTION MANAGER shall keep track of costs related to labor, equipment, and materials; CONSTRUCTION MANAGER shall review DESIGN- BUILDER’s Force Account CCO related invoices for adequacy. CONSTRUCTION MANAGER shall process CCO packages in compliance with OCTA contract change order procedures.
CONSTRUCTION MANAGER shall keep accurate records of correspondence, reports, and other PROJECT documents. CONSTRUCTION MANAGER shall maintain files of all PROJECT documents; CONSTRUCTION MANAGER shall maintain a list of project drawings, specifications, and all other construction documents. CONSTRUCTION MANAGER shall administer the flow of documents and communications between OCTA, DESIGN-BUILDER, and AHJ.
3.2.6. Special Inspection
CONSTRUCTION MANAGER or ASSISTANT CONSTRUCTION MANAGER shall provide as needed special inspection services related to offsite visit(s) to inspect and document manufacturing of PROJECT related equipment/component, when deemed necessary by OCTA. A total of five (5) separate offsite visits are expected during PROJECT construction.
3.2.7. Project Commissioning and Performance Testing
CONSTRUCTION MANAGER shall review and thoroughly understand DESIGN- BUILDER’s commissioning plan and PROJECT’s performance testing requirements.
CONSTRUCTION MANAGER shall oversee and manage PROJECT commissioning process and performance testing, which shall be completed in a manner ensuring a fully operational station that meets all performance requirements based on commissioning plan, standard practices, and demonstrated performance testing. CONSTRUCTION MANAGER shall ensure appropriate participation by OCTA, AHJ, and/or other PROJECT stakeholders during commissioning process and performance testing are coordinated in a timely manner.
3.2.8. Project Closeout
CONSTRUCTION MANAGER shall perform PROJECT closeout in compliance with the Construction Contract Documents.
CONSTRUCTION MANAGER shall conduct inspections to determine PROJECT substantial completion date. CONSTRUCTION MANAGER shall coordinate with OCTA and all other PROJECT stakeholders to conduct preliminary and final punch list walks in compliance with Construction Contract Documents.
• CONSTRUCTION MANAGER shall coordinate with OCTA to prepare preliminary and final punch lists for DESIGN-BUILDER to address.
CONSTRUCTION MANAGER shall monitor and ensure that DESIGN- BUILDER addresses all punch list items in compliance with Construction Contract Documents and OCTA’s comments.
CONSTRUCTION MANAGER shall obtain all required closeout documents specified in the Construction Contract Documents including, but not limited to, the following:
• DESIGN-BUILDER's As-Built Drawings and Specifications
• Operating and Maintenance Manuals
• Emergency Response Plan (ERP)
• Process Safety Management (PSM) Requirements Documentation
• Warranty Certificates/Documentation
• Copy of Final Inspection (permit sign-off cards) from CITY
• Completed/signed-off Punch List
CONSTRUCTION MANAGER shall review written guarantees and related documents assembled by DESIGN-BUILDER for adequacy.
CONSTRUCTION MANAGER shall recommend OCTA on Notice of Completion (NOC) date, prepare NOC document, and record NOC with the County of Orange at the end of the PROJECT.
CONSTRUCTION MANAGER shall coordinate with OCTA to review and accept project closeout documents, to turn-over the PROJECT to OCTA.
3.2.9. All Other Construction Management Services
CM CONSULTANT shall review all services required within Task 2: Construction Management Services, per Section 3.2 of this scope of work document, and determine additional services that will be offered by CM CONSULTANT, if any, to enhance PROJECT’s construction management; the extent of additional services that CM CONSULTANT is offering shall be defined within their proposal.
3.3. Task 3: Administrative Support on Construction Management Services All administrative support on construction management related services shall be provided by qualified personnel, per Section 4 of this scope of work document.
3.3.1. Construction Progress Payments and Invoices
ADMIN STAFF shall obtain DESIGN-BUILDER’s monthly invoices during PROJECT construction for review and processing. CONSTRUCTION MANAGER shall review DESIGN-BUILDER’s monthly progress payment request and invoice for accuracy; CONSTRUCTION MANAGER shall recommend to OCTA PROJECT MANAGER any necessary revisions on progress payment request and invoice.
CONSTRUCTION MANAGER shall assist OCTA with processing DESIGN- BUILDER’s monthly progress payments in accordance with OCTA payment procedures.
CONSTRUCTION MANAGER shall review PROJECT construction related invoices from AHJ and/or other vendors, if any, for accuracy and compliance with appropriate documents; CONSTRUCTION MANAGER shall recommend to OCTA PROJECT MANAGER any necessary revisions on invoices.
For each DESIGN-BUILDER progress payment request and invoice, as well as other PROJECT construction related invoice, CONSTRUCTION MANAGER shall certify in writing that progress payment request and invoice are acceptable based on completion status and quality of work observed by CONSTRUCTION MANAGER, and in accordance with Construction Contract Documents.
3.3.2. Construction Management Invoicing
CM CONSULTANT shall be paid monthly on a Time and Expense basis.
3.3.3. All Other Administrative Support on Construction Management Services CM CONSULTANT shall review all services required within Task 3: Administrative Support on Construction Management Services, per Section 3.3 of this scope of work document, and determine additional services that will be offered by CM CONSULTANT, if any, to enhance PROJECT’s administrative support on construction management; the extent of additional services that CM CONSULTANT is offering shall be defined within their proposal.
SECTION 4 – CM CONSULTANT’S PERSONNEL QUALIFICATIONS
CM CONSULTANT shall provide personnel for construction management services related to the construction of the PROJECT. The typical workday includes all hours worked by DESIGN-BUILDER at the PROJECT site, which is anticipated to be in the order of 40 hours per week. If directed by OCTA, overtime and night work may be required. For days when work is not performed by the DESIGN-BUILDER (such as suspension of work, holidays, weather days, etc.), CM CONSULTANT services shall not be provided unless authorized in writing by OCTA.
CM CONSULTANT’s personnel qualifications/requirements shall be as below, per Sections 4.1 and 4.2 of this scope of work document.
4.1. Construction Manager and Assistant Construction Manager
CM CONSULTANT shall provide a full-time CONSTRUCTION MANAGER and part-time ASSISTANT CONSTRUCTION MANAGER who shall, on behalf of the OCTA within the limits authorized in writing by the OCTA, manage and perform construction management services required in this scope of work document.
CONSTRUCTION MANAGER and ASSISTANT CONSTRUCTION MANAGER shall:
• Have experience as a construction manager on a minimum of two (2) similar hydrogen fueling station projects and/or other relevant projects, as determined by OCTA.
• Have thorough knowledge of construction practices, and the ability to read and interpret plans and specifications, construction schedules, and all other construction related documents.
• Be able to work independently and to make effective decisions concerning field problems and work in progress.
• Be experienced in managing and processing submittals, request for information, change order request, change directives, contract change orders, payment applications, deficiency notices, and other similar construction documents.
• Be proficient in the use of computer application programs including, but not limited to Microsoft Word, Microsoft Excel, and Microsoft Teams.
• Possession of a current OSHA 10 Hour Certification.
4.2. Administrative Staff
CM CONSULTANT shall provide a part-time ADMIN STAFF who shall perform administrator services, to support construction management services, required in this scope of work document. ADMIN STAFF shall:
• Have experience as a project administrator on a minimum of two (2) similar construction projects or other equivalent experience, as determined by
OCTA.
• Be able to assist construction manager with facilitating construction progress payment applications and invoices for monthly processing.
• Be able to assist construction manager with facilitating construction documents for processing, which includes submittals, request for information, change order request, change directives, contract change orders, payment applications, deficiency notices, and other similar construction documents.
• Be able to assist construction manager with obtaining weekly certified payrolls from DESIGN-BUILDER for labor compliance review.
• Be able to perform typical duties of an office administrative staff-document controller, which includes storing and retrieving appropriate construction documents.
• Be able to prepare and submit construction management services related invoices with supporting information in a monthly basis.
• Be experienced in the use of computer application programs including, but not limited to Microsoft Word, Microsoft Excel, and Microsoft Teams.
• Be able to work independently and meet deadlines.
END OF SCOPE OF WORK