This is a Bid Quote Sheet for preventive maintenance services for boiler systems and ancillary equipment at New York City Children's Center, issued by the New York State Office of Mental Health (OMH) under contract number OMH01-C203223-3650771. The solicitation requests bidders to provide unit cost pricing for preventive maintenance tasks on dual-fuel condensing boilers (units 1A, 1B, 2A, 2B), fuel oil systems, filtration equipment, and hot water meters. Specific maintenance tasks include semi-annual and annual preventive maintenance, tune-up services, inspections, cleaning, and testing with varying service frequencies ranging from monthly to annually. The contract term is five years, with bidders required to submit signed original bid quote sheets with all unit costs completed or risk disqualification. No specific response dates, site visit requirements, or bidder conference information is provided in this document.
Pricing for preventive maintenance tasks must be submitted as unit costs per service occurrence across all five contract years, with annual and total costs calculated automatically based on service frequency. The Time and Material section establishes a fixed material allowance of $20,000 annually (totaling $100,000 over five years) with material markup fixed at 10%, requiring bidders to submit hourly labor rates for straight time, overtime, and training hours. No reimbursement is provided for travel time, mileage, or fuel costs, and emergency on-site service must be provided within two hours of facility request. The estimated total bid is $100,000, though actual payment is contingent only on services actually performed. Bidders must attest to prevailing wage rate compliance, receipt of questions and answers, New York State payroll restrictions, electronic payment capability, and applicable ethics requirements based on award type.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C203223 - NYCCC - Brooklyn - Boiler - BP.pdf | ||
| C203223 - NYCCC - Brooklyn - Boiler - IFB.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Boiler #C203XXX
| ATTACHMENT D - BID QUOTE SHEET: NEW YORK CITY CHILDREN'S CENTER #OMH01-C203223-3650771 |
| Provide Preventive Maintenance Service for the Boiler Systems and Ancillary Equipment per Appendix D of the Contract. The FACILITY reserves the right to alter the scheduling of the services as necessary. There is no reimbursement for travel time and/or travel expenses including mileage and fuel costs. |
Subcontractors Costing: The prices/rates quoted include all direct and indirect costs of any subcontractors, including those used to meet any stated M/WBE/SDVOB participation goals.
| Directions: 1) Insert the Unit Cost in the Unit Cost ($) column for each preventive maintenance service task listed (unless blocked); 2) The Annual Cost for each Contract Year, which is equal to the Bid Unit x Service Frequency per Year x Unit Cost will be calculated automatically; 3) The Total Amount (Years 1 – 5) for each preventive maintenance service task listed, which is equal to the total sum of the Annual Costs for each Contract Year (1 through 5) will be calculated automatically; 4) The Subtotal Bid for Preventive Maintenance Tasks, which is equal to the sum of the Total Amount (Years 1 – 5) column will be calculated automatically. | |||||
| Failure to follow these directions exactly may result in your bid being disqualified. Please be advised that only actual services performed may be invoiced at the Unit Costs quoted as per Appendix C of the contract. The Unit Cost for each item must be completed for each item listed (unless blocked). Do not leave any areas blank or the bid may be disqualified. Bidders are bound by the Unit Costs provided and cannot be changed after the Bid Opening. | |||||
| Page 1: Preventive Maintenance Services for the Boiler Systems and Ancillary Equipment | |||||
| Item / Bldg. | Maintenance Task | Bid Unit | Service Freq. per Year | Year 1 | |
| Unit Cost ($) | Year 1 | ||||
| Annual Cost ($) | Year 2 | ||||
| Unit Cost ($) | Year 2 | ||||
| Annual Cost ($) | Year 3 | ||||
| Unit Cost ($) | Year 3 | ||||
| Annual Cost ($) | Year 4 | ||||
| Unit Cost ($) | Year 4 | ||||
| Annual Cost ($) | Year 5 | ||||
| Unit Cost ($) | Year 5 | ||||
| Annual Cost ($) | Total Amount |
(Years 1-5)
| Boilers, Condensing – Dual Fuel (GASMASTER) / Boilers 1A, 1B, 2A, 2B | Semi-Annual PM | 4 | 2 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||
| Semi-Annual Tune-up Service | 4 | 2 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Boiler Annual Inspection & Cleaning Service | 4 | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Fuel Oil Set & Pumps | Semi-Annual PM | 2 | 2 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||
| Fuel Oil System / Main Fuel Storage Tanks | Monthly PM Service | ||||||||||||||
| (Test Kits & Analysis - As Requested) | 2 | 12 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Semi-Annual PM Service | |||||||||||||||
| (As Needed and Requested by Facility) | 2 | 2 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Fuel Oil System Filtration | Semi-Annual PM Service | ||||||||||||||
| (As Needed and Requested by Facility) | 1 | 2 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Meters (In-Line) - Hot Water | Annual PM | 2 | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||
| Page 1: Subtotal Bid for Preventive Maintenance Tasks ($) | $0.00 | ||||||||||||||
| Page 2: Time and Material Rates | |||||||||||||||
| With respect to labor and material for repairs not covered under the routine maintenance (including emergency service), provide labor rate quote. If on-site emergency service is requested by the FACILITY, a CONTRACTOR Service Technician shall arrive on-site within two (2) hours of the FACILITY's request for an on-site CONTRACTOR Technician. Prior FACILITY approval is required for all repairs. Material markup will be fixed at 10%. Shipping costs are not to be included in the material markup. There is no reimbursement for travel time and/or travel expenses including mileage and fuel costs. | |||||||||||||||
| Straight Time is defined as an eight (8) hour day Monday thru Friday. Overtime includes all other times except hours/days indicated as Straight Time, i.e.: NY State Holidays, weekends, etc. | |||||||||||||||
| Directions: 1) Insert the Hourly Labor Rate in the Unit Cost ($) column for Straight Time, Overtime, and Training. Do not enter any pricing for the Material Allowance; 2) The Annual Cost for the Contract Year, which is equal to the Estimated Service Frequency per Year x Unit Cost is calculated automatically; 3) The Total Amount (Years 1 – 5) for Straight Time, Overtime, and Training for each Contract Year (1 through 5) is calculated automatically; 4) The Time & Material Allowance Subtotal which is equal to the sum of the Total Amount (Years 1 – 5) column (Total Material Allowance + Total Straight Time + Total Overtime + Total Training) is calculated automatically. | |||||||||||||||
| The Unit Cost for each item must be completed for each item listed (unless blocked). Do not leave any areas blank or the bid may be disqualified. Please be advised that only actual services performed may be invoiced at the Unit Costs quoted as per Appendix C of the contract. Bidders are bound by the Unit Costs provided and cannot be changed after the Bid Opening. | |||||||||||||||
| Item | Bid Unit | Est. Service Freq. per Year | Year 1 | ||||||||||||
| Unit Cost ($) | Year 1 Annual Cost ($) | Year 2 | |||||||||||||
| Unit Cost ($) | Year 2 Annual Cost ($) | Year 3 | |||||||||||||
| Unit Cost ($) | Year 3 Annual Cost ($) | Year 4 Unit Cost ($) | Year 4 Annual Cost ($) | Year 5 | |||||||||||
| Unit Cost ($) | Year 5 Annual Cost ($) | Total Amount (Years 1-5) | |||||||||||||
| Material Allowance | LOT | 1 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $100,000.00 | ||
| Technician Straight Time | HRS | 72 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Technician Overtime | HRS | 24 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Training Rate | HRS | 8 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| Page 2: Time and Material Allowance Subtotal ($) | $100,000.00 | ||||||||||||||
| Note: The material allowance and the number of straight time, overtime and training hours are estimated and are only used for purposes of determining the lowest responsible bidder and an estimated contract total cost. Payment will only be made on the actual number of hours for repairs and the cost of materials used. | |||||||||||||||
| Page 3: Bid Totals | |||||||||||||||
| Directions: When finished, be sure to sign and date the bottom of the Bid Totals sheet. Only the signed original Bid Quote Sheet can be submitted with the proposal. | |||||||||||||||
| Preventive Maintenance Task Subtotal (Page 1) | $0.00 | ||||||||||||||
| Time and Material Allowance Subtotal (Page 2) | $100,000.00 | ||||||||||||||
| TOTAL BID | $100,000.00 |
| When applicable, | |
| -The bidder’s signature below attests that they have reviewed the prevailing wage rates that apply to this solicitation. | |
| -The bidder’s signature below attests to the receipt and understanding of the questions & answers associated with this solicitation. | |
| -The bidder’s signature below attests that they will inform the OMH in writing of the name(s) of any individual(s) who will provide any service under the resulting contract who has not been off the New York State payroll for at a minimum of two years from the start date of the resulting contract. The bidder must notify the OMH of such individual(s) prior to the start of the contract or prior to that individual(s) providing any service in accordance with resulting contract. | |
| -The bidder’s signature below attests they have reviewed and understand the requirements stated in the IFB (section 17) and the OMH contract boilerplate (Appendix C) regarding the necessity to accept Electronic Payments for all invoices if awarded this contract, and certifies that it has already applied to participate in the State Comptroller’s Electronic Payment system, or will do so within 10 days of receiving notification of contract selection. | |
| -If award is to an individual: | |
| □ | The signature below attests that I have not been on the New York State payroll during the last two years. |
| OR | |
| □ | The signature below attests that I have been on the New York State payroll during the last two years and the N.Y. State Ethics Commission Approval Letter is attached. |
Name of Firm_______________________________________________________ Date _________________________
Authorized Representative (Print):_____________________________________ Authorized Signature________________________________________
&"Arial,Regular"ATTACHMENT D - BID QUOTE SHEET
NEW YORK CITY CHILDREN'S CENTER #OMH01-C203XXX-3650771
File details come from the government source that posted it. Updated .