C12 - TEST PROCEDURE A-311 REV C.pdf

PDF 51 KB Posted

Attached to
Small Business Set-Aside for Fabrication of SDV Din Valves ( Qty 75)
Solicitation number
N61331-23-T-DJ01
Issued by

View the file

Other files

File Type Posted
C12 - 1301047500 SYNOPSIS COMPETE.docx DOCX document
C12 - Clauses - Valves.docx DOCX document
C12 - SOW Valves.pdf PDF
C12 - Valve CDRLs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NSWC PCD

SEAL DELIVERY VEHICLE

TEST PROCEDURE

TEST PROCEDURE NO.

A-311

REV.

C

TITLE: DIN Valve Hydrostatic/Leak, PIT

PREPARING ACTIVITY: NSWC PCD, Code E12 NAVSEA APPROVAL

PREPARED BY: DATE:

David M. Fonzi 22-Jan-01

APPROVED BY: DATE:

D. A. Whithaus 25-Oct-04

APPROVED BY: DATE:

E.C. Maulbeck 03-Feb-05

RECORD OF REVISIONS

LETTER DESCRIPTION DATE APPROVED

A Revised in accordance with NOR R-0424 dated 09-Aug-06 on ECP E-0348. 16-Mar-07 S. Smith

B Revised in accordance with NOR R-0474 dated 06-Nov-08 on ECP E-0382. 13-Nov-08 Shawn O. Smith

C Revised in accordance with NOR R-0817 dated 19-May-16 on ECP E-0641. 12-Sep-2016 D. Maglich

PART NAME AND PART NUMBER(S) WITH ASSOCIATED SERIAL NUMBER(S)

Part Name P/N S/N

DIN Valve 7110360-__

CERTIFICATION, REVIEW, AND APPROVAL OF TEST RESULTS

Test Certification Signature

TEST CERTIFIED COMPLETE AND ACCURATE

Testing Activity:

TEST CONDUCTOR: DATE:

QCI: DATE:

Not Required

TEST DIRECTOR: DATE:

Review & Acceptance Signatures

REVIEW AND ACCEPTANCE OF TEST RESULTS

Reviewing Activity: NSWC PCD, Code ________

REVIEWER: DATE:

BRANCH HEAD: DATE:

NAVSEA ACCEPT: DATE:

A-311-C

1.0 TEST DESCRIPTION

1.1 TITLE: DIN Valve Hydrostatic/Leak

1.2 AUTHORITY

1.2.1 This Test Procedure is generated per the requirements of the MK8 MOD1 SDV drawing package and in accordance with CSS-SDV-0019, Integrated Test Plan for MK8 MOD1 SEAL Delivery Vehicles.

1.3 OBJECTIVE

1.3.1 To verify the tightness a DIN Valve prior to installation in an SDV.

1.4 TYPE OF TESTING REQUIRED

1.4.1 The following testing is required for each DIN Valve tested.

a. Closed Valve Hydrostatic

b. Open Valve Tightness

2.0 REFERENCES

NOTE

Only current revisions of direct support and/or supplemental documents shall be used in the conducting of this test.

2.1 DIRECT SUPPORT DOCUMENTS

2.1.1 None

2.2 SUPPLEMENTAL DOCUMENTS

2.2.1 CSS-SDV-0019, Integrated Test Plan for MK8 MOD1 SEAL Delivery Vehicles

2.2.2 Drawing 7110360, DIN Valve

2.2.3 Title 29, Code of Federal Regulations, Part 1910 Subpart S of the Occupational Safety

Standards.

3.0 GENERAL NOTES

3.1 NOTIFICATION

3.1.1 This test requires only a Test Conductor and a Reviewer.

3.2 TEST DATA RECORDING

3.2.1 Remarks and general observations are particularly important in maintaining an accurate and meaningful record. Any unusual event occurring during the performance of the test shall be noted on the Data Sheet.

3.2.2 If space is not provided on the Data Sheet for recording certain data, it shall be recorded on

Supplemental Data Sheet, Section 7.0.

3.2.3 The Data Sheet(s) shall be completely filled in, dated, and signed. If certain data called for was not recorded, an entry should be made explaining the missing data.

3.2.4 Any substitution of components or equipment during the course of the test must carry complete documentation IAW Section 3.3.

3.2.5 All times shall be documented using 24-hour time convention notation using one of the following formats: ‘hh:mm’ or ‘hhmm’. (e.g. 09:23 or 0923)

3.3 DEPARTURES

3.3.1 No deviations from test methods specified, or changes in installation from approved plans shall be made without prior written approval from cognizant Lead Engineer, through the procuring Government agency as required.

3.3.2 Any changes to the specified tolerances will require NSWC PCD engineering concurrence.

Every effort shall be made to meet such tolerances. Where this is not possible, the NSWC PCD Cognizant Lead Engineer shall be consulted immediately, through the procuring Government agency, as required.

4.0 PREPARATION

4.1 PREREQUISITE AND CONCURRENT TESTS

4.1.1 There are no prerequisite tests.

4.1.2 There are no concurrent tests to be performed, however this test may be performed in conjunction with test procedure A-312, DIN Valve Adapter Hydrostatic, PIT.

4.2 TEST LOGISTICS

4.2.1 Applicable test equipment used in conducting this test shall be maintained to the same cleanliness level of the equipment being tested.

4.2.2 Calibrated Test Equipment

NOTE

Test equipment shall have been calibrated in accordance with ISO 10012-1, Calibration System Requirements. The Test Conductor shall be responsible for using only IN DATE calibrated instruments.

4.2.2.1 0-8,000 to 0-15,000 psig Pressure Gauge with an accuracy of +0.5% or better

4.2.2.2 0-5,000 to 0-10,000 psig Pressure Gauge with an accuracy of +0.5% or better

4.2.3 Special Test Equipment

4.2.3.1 First and second stage diving regulators with DIN connector.

4.2.3.2 DIN Valve Adapter P/N 7110359-1 or other suitable connector.

4.2.4 Standard Test Equipment

4.2.4.1 Clean Connecting hoses and fittings

4.2.4.2 Hydrostatic pump

4.2.5 Test Spares and Consumables

4.2.5.1 Clean regulated compressed air supply

4.2.5.2 Bucket of clean water

4.2.5.3 MIL-PRF-27617 Oxidizer Resistant Grease

4.3 SAFETY AND EMERGENCY CONSIDERATIONS

4.3.1 The Test Conductor shall be familiar with the Occupational Safety and Health Standard

29 CFR 1910. The Test Conductor shall also be aware of potential hazards, safety precautions and emergency procedures associated with this test.

4.3.2 The Test Conductor Shall:

• review this test procedure throughout to become familiar with specific tasks to be performed, as well as any warning or caution statements which may be contained herein;

• verify that the test and support equipment meet the requirements of this test procedure;

and

• inspect all test and support equipment for serviceability and repair or replace as required prior to commencement of this test.

If any condition develops which, in the judgment of the Test Conductor, constitutes a danger to personnel or equipment, the test shall be stopped until the condition is corrected.

4.3.3 Specific Safety Procedures

4.3.3.1 Do not tighten or loosen pressurized components.

4.3.4 Specific Emergency Procedures

4.3.4.1 None

4.3.5 Additional Required Personnel

4.3.5.1 None

5.0 PROCEDURE

5.1 TEST PREPARATION

5.1.1 Verify that the DIN Valve has been tagged QC acceptable and has been serialized IAW

Reference 2.2.2.

5.1.2 Operate the DIN Valve handle through its full range to verify that it is operating correctly.

5.1.3 If the DIN Valve is not operating correctly or is otherwise unacceptable, abort the test.

5.1.4 Lubricate DIN Valve O-Ring with MIL-PRF-27617 Oxidizer Resistant Grease.

5.1.5 Connect DIN Valve to DIN Valve Adapter or other suitable adapter.

5.2 CLOSED VALVE HYDROSTATIC TEST

5.2.1 Connect the DIN Valve/Adapter to the hydrostatic pump with the appropriate calibrated pressure gauge (Sec. 4.2.2.1) in line. Record DIN Valve serial number and the gauge calibration information on Data Sheet 1.

5.2.2 Close the DIN Valve and flood the system ensuring that all air is vented.

5.2.3 Pressurize the system to 6,000 +50/-0 psig. Record the test pressure on Data Sheet 1.

5.2.4 Hold the pressure for 5 +2/-0 minutes and observe the DIN Valve for leaks. Record the start time on Data Sheet 1.

5.2.5 No leaks are acceptable. If no leaks are present proceed to step 5.2.7. If leaks are detected, continue with step 5.2.6.

5.2.6 Release the pressure, check the system setup, and begin again with step 5.2.1 recording the results of the retest on a Supplemental Data Sheet (Section 7.0). If a leak is detected on the retest, record the results and abort the test.

5.2.7 Release the pressure and drain the water from the DIN Valve. Indicate the results, record the stop and duration times, and complete Data Sheet 1.

5.3 OPEN VALVE TIGHTNESS TEST

5.3.1 Connect the DIN Valve to the clean air supply with the appropriate calibrated pressure gauge (Sec. 4.2.2.2) in line. Record DIN Valve serial number and the gauge calibration information on Data Sheet 2.

5.3.2 Close the DIN Valve, pressurize the system to 4,000 +50/-0 psig, and secure the air supply.

Record the test pressure on Data Sheet 2.

5.3.3 Install a first and second stage diving regulator on the DIN Valve, fully open the DIN Valve and fully immerse the entire assembly in a container of clean water for 5 +1/-0 minuets.

Record the start time on Data Sheet 2.

5.3.4 Observe the water for escaping air. No leaks are acceptable. Record the results on Data

Sheet 2. If no leak is detected, indicate the results and record the stop and duration times on Data Sheet 2. If a leak is detected, record the results on Data Sheet 2and abort the test.

5.3.5 Remove the DIN Valve from the water, vent the air from the hoses, remove the DIN

Valve/Adapter from the test setup and complete the Data Sheet 2.

DATA SHEET 1

DIN VALVE

DIN Valve, P/N 7110360-__, S/N

Required Actual Serial Calibration Accuracy Accuracy Number Due Date

0- psig Pressure Gauge +/-0.5% (0-8,000 to 0-15,000 psig)

CLOSED VALVE HYDROSTATIC TEST (5.2)

Measurement Required Actual

Water Pressure 6,000 – 6,050 psig psig

Start Time As Observed

Stop Time As Observed

Elapsed Time 5 - 7 Min. min

TEST ACCEPTANCE CRITERIA:

No Leaks during 5 minute test duration.

THE CLOSED VALVE HYDROSTATIC TEST RESULTS ARE: ( ) SAT ( ) UNSAT

Sections 2.0 and 4.1 have been fully complied with, as required.

Supplemental Data Sheet(s) are used: ( ) No ( ) Yes ___ ea.

Test Conductor ORG Date Signature

QC Inspector Not Required ORG Date

DATA SHEET 2

DIN VALVE

DIN Valve, P/N 7110360-__, S/N

Required Actual Serial Calibration Accuracy Accuracy Number Due Date

0- psig Pressure Gauge +/-0.5% (0-5,000 to 0-10,000 psig)

OPEN VALVE TIGHTNESS TEST (5.3)

Measurement Required Actual

Air Pressure 4,000 – 4,050 psig psig

Start Time As Observed

Stop Time As Observed

Elapsed Time 5 - 6 Min. min

TEST ACCEPTANCE CRITERIA:

No Leaks during 5 minute test duration.

THE OPEN VALVE TIGHTNESS TEST RESULTS ARE: ( ) SAT ( ) UNSAT

THE OVERALL TEST RESULTS ARE: ( ) SAT ( ) UNSAT

Sections 2.0 and 4.1 have been fully complied with, as required.

Supplemental Data Sheet(s) are used: ( ) No ( ) Yes ___ ea.

6.0 CONCLUSION

6.1 DEFICIENCIES

6.2 EVALUATION OF TEST

6.2.1 Actual in-service conditions and environment have been encountered or simulated.

( ) Yes ( ) No

Comments:

6.2.2 The system has complied with test objectives. ( ) Yes ( ) No

Comments:

6.3 RESULTS ( ) Satisfactory ( ) Unsatisfactory

( ) Satisfactory with Conditions

6.4 COMMENTS

DIN Valve, P/N 7110360-__, S/N _______________

Reviewer: Date:

Title: Code:

7.0 SUPPLEMENTAL DATA SHEET

TEST NAME: TEST NO:

REASON FOR TEST:

COMMENTS:

RESULTS:

NOTE
NOTE
Signature
Signature