C05_SOW_-_Water_Meter.pdf

PDF 183 KB Posted

Attached to
ECAO - WATER METER Federal contract opportunity
Solicitation number
140R6023Q0074
Issued by
Department of the Interior Bureau of Reclamation

About this file

This statement of work outlines requirements for a water meter installation project for the Bureau of Reclamation. The contractor will be required to install a new one-inch water meter and meter pit outside the ECAO yard access gate, pothole two existing water valves and the old water meter to inspect condition, replace valves if needed, and backfill locations after work is complete. Work hours are restricted to 8am to 5pm Monday through Friday, and no work is allowed on weekends. The related federal contract opportunity is solicitation number 140R6023Q0074 from the Department of Interior Bureau of Reclamation for the ECAO water meter project.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Solicitation No. _____________

ECAO Water Meter Installation of Water Meter and Meter Pit and Potholing Existing Valves

Loveland, Colorado Background:

The Bureau of Reclamation (Reclamation) will contract out the project to install a new water meter and meter pit at the ECAO Main Office. Three water valves will be potholed to inspect their condition as well. ECAO needs a larger water meter with the installation of new buildings within the ECAO yard.

This Statement of Work will provide a plan to complete this single-year project.

WORK REQUIREMENTS:

1) Water Meter Installation and Potholing:

The work under this requirement will include providing all items, materials, equipment, power, and labor to furnish, deliver, and fulfill all necessities for the water meter and meter pit installation.

Contracted employees are not allowed to work before 8am or after 5pm Monday through Friday. Work is not allowed on Saturday or Sundays.

The following criteria must be followed for the water meter installation:

• Install a water meter pit outside (North) of the ECAO yard access gate on the east side of the road.

• Install a new 1” water meter in the meter pit.

• Pothole at two water valves and pothole at the old water meter to inspect he condition. Replace the valves if needed.

• Backfill water meter pit and potholed locations after installation and investigations.