C05_01__140R2024Q0071_Solicitation_NCAO_Fire_Alarm_Systems_Modification.pdf
PDF 2 MB Posted
- Attached to
- NCAO Fire Alarm Systems Modification Federal contract opportunity
- Solicitation number
- 140R2024Q0071
About this file
This document is a solicitation for the NCAO Fire Alarm Systems Modification project. The key objectives are to modify fire alarm systems at the Bureau of Reclamation's IT Building and Keswick Office Building Room 103 to accommodate a remodel and ensure the systems remain operational and code-compliant. The work includes installing new smoke detectors, horn/strobes, and extending existing devices.
The estimated price range for the fixed-price contract is $10,000 to $25,000. The procurement is set aside for small businesses under NAICS code 561621. Offers are due by June 12, 2024 at 5:00 pm local time. The period of performance is 5 days, including 1 day for mobilization and 1 day for demobilization. The contractor must have NICET Level III or higher certification in Fire Alarm Systems and must be factory-certified by Siemens (or the equipment manufacturer) to perform the required work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2024Q0071_Amd_0003.pdf | ||
| Amendment_3_to_Solicitation_140R2024Q0071_0003.pdf | ||
| Amendment_002_to_140R2024Q0071_0002.pdf | ||
| Sol_140R2024Q0071_Amd_0002.pdf | ||
| Sol_140R2024Q0071_Amd_0001.pdf | ||
| C05_04_140R2024Q0071_-_SECTION_L_0001.pdf | ||
| C05_02__Att_1_-_Wage_Rate_Determination_-_CA20240007.pdf | ||
| C05_02__Att_2_-_Release_of_Claims.pdf | ||
| Sol_140R2024Q0071.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No.140R2024Q0071
NCAO Fire Alarm Systems Modification
Northern California Area Office (NCAO)
This page intentionally left blank.
TABLE OF CONTENTS
SECTION A - Solicitation, Offer and Award Form (SF 1442)
SECTION B - Pricing Schedule
SECTION C - Statement of Work
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
SECTION F - Deliveries or Performance
SECTION G - Contract Administration Data
SECTION H - Special Contract Requirements
SECTION I - Contract Clauses
SECTION J - List of Documents, Exhibits, and Other Attachments
SECTION K - Representations, Certifications and Other Statements of Offerors
SECTION L - Instructions, Conditions and Notices to Offerors
SECTION M - Evaluation Factors for Award
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040657029
Bureau of Reclamation
Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
8. ADDRESS OFFER TO
Bureau of Reclamation - Interior Region 10 2800 Cottage Way, RM. E1815
Sacramento, CA 95825-1898 rgamo@usbr.gov
Ronald Gamo 916-978-4304
105/13/2024
140R2024Q0071
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
A. NCAO Fire Alarm Systems Modification
B. Work Site Location: Work is located at NCAO Area Office, Redding, CA.
C. Estimated Price Range: $10,000.00 to $25,000.00.
D. Set-aside Information: This requirement is being procured under the Simplified
Acquisition Procedures, Federal Acquisition Regulation (FAR) Part 13. NAICS Code:
561621 and applicable size standard $25 million.
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
7 10 calendar days and complete it within ________________ ________________ calendar days after receiving
Section F
06/12/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
X
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Abelardo Lopez
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140R2024Q0071
00010
Section B - Supplies and Services and Prices "AU" Activity Unit is solely for the purpose of allowing progress payments under the Department of Interior's Financial Business System (FBMS).
NCAO Fire Alarm Systems Modification
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
1 AU
Pricing Schedule: CLIN 1-2
NCAO Fire Alarm Systems Modification Solicitation No. 140R2024Q0071 Redding, California
Price Schedule
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
NCAO Fire Alarm Systems Modification
B.1 PRICE SCHEDULES
(a) Quotes will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Quotes are subject to the terms and conditions of this solicitation.
(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory
Work, for CLIN 0010.
B.2 DEFINITIONS
(a) CLIN – Contract Line Item Number.
CLIN Section Supplies or Services Quantity and Unit
Unit
Price
Amount
0010 WBR
1452.232-81
Mobilization
& Preparation
For the lump sum of $
0020 C - SOW Fire Alarm Systems
Modification For the lump sum of $
TOTAL FOR PRICE SCHEDULE $ ______________
NCAO Fire Alarm Systems Modification Solicitation No. 140R2024Q0071 Redding, California
Price Schedule
B - 2
B.2. Prevision:
WBR 1452.236-85 INSTRUCTION FOR MOBILIZATION AND MAR 2022
PREPARATORY WORK SCHEDULE LINE
ITEM – BUREAU OF RECLAMATION
The Contracting Officer estimates that the Section B Mobilization and Preparatory Work schedule line item should not exceed 10 percent of the total bid price. Your attention is directed to contract clause WBR 1452.232-81 Payment for Mobilization and Preparatory Work, which reflects how the Government will pay for this line item, including how payment will be made when the price bid for this schedule line item is higher than the percentage stated herein.
END OF SUPPLIES OR SERVICES AND PRICES
STATEMENT OF WORK
IT BUILDING AT SHASTA DAM,
KESWICK OFFICE BUILDNG ROOM 103
FIRE ALARM SYSTEM MODIFICATION
U.S. Bureau of Reclamation, Northern California Area Office
1.1. OBJECTIVES:
1.1.1. Objective. IT Building,16349 Shasta Dam Boulevard, Shasta Lake, CA 96019:
The objective is to run new conduit and wire for two (2) new smoke detectors, one
(1) in the secure IT room and one (1) in the waiting room. Run new conduit and wire for one (1) new horn/strobe in the waiting room. Two (2) devices need to be extended from wall, one (1) horn/strobe in the break room and one (1) horn/strobe in the office. Relocate and extend from wall two (2) pull stations one in the main office and one in the break room. The contractor shall inspect, test, and document modifications, in accordance with NFPA 72, fire alarm systems at the Bureau of Reclamation’s (BOR) Northern California Area Office (NCAO) IT Building (Reference attached diagram).
1.1.2. Objective. Keswick Office Building Room 103, 16515 Keswick Dam Road, Redding, CA 96003: The objective is to run new conduit and wire to one (1) new smoke detector.
1.2. Background: NCAO operates and maintains several dams and powerplants, a visitor center, an office building, and a maintenance center. New Siemens fire alarm systems were installed and commissioned at 10 of these facilities in 2020 and 2021. The fire alarm systems at these facilities are networked to provide system status and trouble information to a central monitoring station located at Shasta Powerplant. The general requirement is to modify the systems at the IT Building and Keswick Office Building Room 103 to accommodate a remodel and assure that modification maintains the system in an operational, code-compliant condition.
2. TASKS: Specifically, the contractor shall provide all materials and labor required to do the following tasks:
2.1.1. In the secure IT room (IT Building), install conduit, wire, and one (1) new smoke detector to a height of 109.75 inches at the back of the sensor.
2.1.2. In the waiting room (IT Building), install conduit, wire, and one (1) new smoke detector to a height of 96 inches at the back of the sensor. Install conduit, wire, and new horn/strobe to be four inches away from existing wall.
2.1.3. In the IT Building, extend the following three devices so that the back of device is four inches away from the existing wall: break room – one (1) pull station and one
(1) horn/strobe; main office – one (1) horn/strobe.
2.1.4. In the main office (IT Building), relocate one (1) smoke detector roughly four inches to the right of its existing location. Extend one (1) pull station to be four inches from the wall.
2.1.5. In the break room (IT Building), relocate one (1) smoke detector roughly four inches to the right of its existing location. Extend one (1) pull station to be four inches from the wall.
2.1.6. In Room 103 supervisor’s office (Keswick Office Building), install conduit, wire and one (1) new smoke detector.
2.1.7. All modifications are to be in accordance with the Fire Alarm Plan Drawings.
2.1.8. Re-program system appropriately to accommodate changes.
2.1.9. Test all sensors in affected system in accordance with NFPA 72.
2.1.10. Provide as-built drawings of changes.
2.1.11. Re-certify that system meets NFPA 72.
2.2. Fire Alarm System Description.
1.3.1. Fire Alarm Network. The fire alarm systems at the 10 facilities are connected by a copper line and fiber optic network to a Central Monitoring Station located in the Shasta Powerplant control room. This arrangement allows the NCAO senior operator to monitor fire alerts and system trouble conditions from one location.
The fire alarm network reporting diagram is shown in Appendix 1.
1.3.2. Facilities, Physical Addresses & General Fire Alarm System Components. The table below is representative of the magnitude and complexity of the fire alarms system at the Shasta Dam facilities. Not all alarm components are listed.
Facility Supervisory Control Equipment
FACU Remote Annunciator
Pull Stations
Heat/Smoke Detectors
Projected Beam Smoke Detectors
Horn/Strobe Notification Appliances
Shasta Dam Facilities 16349 Shasta Dam Blvd Shasta Lake, CA 96019
1 1 1 24 82 3 95
2. DEFINITIONS AND REFERENCES
2.3. Definitions.
2.3.1. Business day – Weekdays excluding federal holidays listed in paragraph 7.2.
2.3.2. COR – Contracting Officer’s Representative
2.3.3. Days – Calendar days
2.3.4. FACU – Fire Alarm Control Unit
2.3.5. NFPA – National Fire Protection Association
2.3.6. NFPA-72 – National Fire Alarm and Signaling Code
2.3.7. OGR – On-site Government Representative
2.3.8. PIV – Personal Identity Verification
2.4. References. Compliance with the applicable portions of the following documents is required in the performance of this contract:
2.4.1. National Fire Protection Association: National Fire Alarm and Signaling Code, NFPA 72, 2019
2.4.2. U.S. Bureau of Reclamation: Reclamation Safety and Health Manual, 2021
3. LICENSES, CERTIFICATIONS, PERSONNEL, CONDUCT OF WORK AND
SAFETY
3.1. Licenses.
3.1.1. The Contractor shall possess, in current status for the duration of this contract, a California Contractor Specialty License Classification, C-10 Electrical Contractor.
Provide the CA contractor license number with the proposal, prior to contract award.
3.2. Certifications.
3.2.1. Inspection and Testing. Contractor personnel who perform fire alarm system inspection and testing under this contract must have a current National Institute for Certification in Engineering Technologies (NICET) Level III or higher certification in either Fire Alarm Systems or Inspection and Testing of Fire Alarm Systems. NICET certified personnel below Level III may perform services under this contract but must be under the direct (on site) supervision of a NICET Level III or higher certification holder.
3.2.2. Contractor personnel who perform fire alarm system modifications must have current NICET Level III or higher certification in Fire Alarm Systems. NICET Fire Alarm Systems certified personnel below Level III may perform repair services under this contract but must be under the direct (on site) supervision of a NICET Level III or higher certification holder.
3.2.2.1. Factory Certification. In addition to NICET certification, contractor personnel who perform testing and modifications described in paragraphs 5.4 and 5.5 shall be factory-certified by Siemens (or the equipment manufacturer for non- Siemens equipment) to perform such work on equipment identified in paragraph 1.3.3.
3.2.3. The Contractor shall submit valid and current certification documents with their proposal. For any change or addition to personnel who are required to be certified after https://www.usbr.gov/safety/rshs/index.html the start of the contract, provide certification documents to the COR at least 5 business days prior to their arrival on site.
3.3. Personnel Management
3.3.1. The Contractor shall maintain sufficient credentialed personnel, certified as required in paragraph 3.2, to complete all of the scheduled and unscheduled work within the time and quality standards specified by the contract and the Contracting Officer. The Contractor’s organization shall include the necessary support and administrative personnel such as work reception, clerical support, buyers, file clerks, logistics specialists, etc. to ensure that the maintenance and repair activities are carried out in a timely and efficient manner.
3.3.1.1. All on-site contractor personnel shall be able to read, write, speak, and understand English.
3.3.2. The Contractor shall ensure satisfactory standards of employee conduct and shall promptly investigate complaints of poor performance, unsafe conduct, or inappropriate behavior.
3.3.3. The Contractor shall immediately remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of safety and security.
3.3.4. All on-site Contractor employees shall wear clothing appropriate for work in an industrial environment, including a sturdy work shirt, long pants and safety footwear.
For safety reasons, t-shirts, tank tops, shorts, dresses, and sandals or other open footwear are unacceptable attire. A distinctive nameplate, emblem, or patch with the contractor/subcontractor company name shall be attached to a prominent place on an outer garment so as to be readily visible to government employees.
3.4. Conduct of Work.
3.4.1. Scheduled and Unscheduled Work. The approved Baseline Schedule (paragraph 5.1.1) constitutes the scheduled work. Unscheduled work may be generated when malfunctioning equipment is discovered during scheduled activities. Additionally, the Government may notify the Contractor of system malfunctions between scheduled activities.
3.4.2. Work Planning. The contractor shall implement all necessary work and quality control procedures to ensure timely and acceptable accomplishment of all work requirements. The Contractor shall adequately plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified response time limits and in conformance with the quality standards established in this contract. Written or verbal scheduling and reports on the status of any work item shall be provided when requested by the COR or OGR.
3.4.3. Contractor’s Work Reception. The Contractor shall, at the post-award meeting with the Government, provide and thereafter maintain telephone number(s) and email address(es) to enable the COR or OGR to reach the Contractor between the hours of 0800 and 1700, Monday through Friday, excluding holidays, during the contract period. A contractor-maintained web-based online intake form may be used in lieu of an email address. The Contractor shall have a Responsible Managing Employee (RME) with authority to speak and act for the Contractor, available to respond at the contact method provided during the specified hours and be ready to provide the required services specified by the contract.
3.4.4. Least Interference with Government Business. The Contractor shall schedule and arrange work so as to cause the least interference with the normal Government business and mission. In cases where some interference may be unavoidable, the Contractor shall make every effort to minimize the impact of the interference. Because of the nature of power and water operations, sometimes there can be no interference with normal Government business.
Under these circumstances, work must be coordinated with the COR.
3.4.5. Parking. Contractor vehicles may be parked in government parking areas adjacent to a facility. Do not park in spaces marked for exclusive use by others.
3.5. Safety. The contractor shall comply with Reclamation Safety and Health Standards (RSHS) Section 3, Contractor Safety.
3.5.1. Contractor Safety Program. The contractor shall submit a comprehensive written safety program covering all aspects of onsite and applicable offsite operations and activities associated with the contract in accordance with RSHS Appendix B. The contractor’s safety program must be organized in the same fashion as the Program Outline shown in RSHS Appendix B. The safety program must be reviewed and approved by the COR before the contractor mobilizes to perform under this contract.
3.5.2. Hard hats and safety footwear must be worn while inside power plants. Hard hats must also be worn while in the vicinity of work or operations that could result in a head impact injury, such as near an operating forklift or crane. Safety footwear must also be worn while in the vicinity of work or operations that could result in a foot crushing injury.
3.5.3. High-visibility vests or similar outerwear shall be worn when in the presence of moving vehicles and industrial equipment such as cranes, manlifts and material handlers (forklifts, telehandlers).
https://www.usbr.gov/safety/rshs/index.html https://www.usbr.gov/safety/rshs/documents/appB.pdf https://www.usbr.gov/safety/rshs/documents/appB.pdf
3.5.4. Sound levels in some areas of power plants may reach levels hazardous to hearing. These areas are well-marked. Contractor personnel shall wear hearing protection before entering and while working in these areas.
3.5.5. Contractor personnel must be conscious of and work well back from open electrical cabinets and rotating machinery. Minimum safe distances are shown on the outer door of electrical cabinets. Dangerous locations are sometimes bounded by red plastic tape. Contractor personnel shall not cross into areas so bounded.
4. ACCESS TO FACILITIES
4.1. Access to Facilities. It is the Contractor’s responsibility to obtain the credentials and keys necessary to access the buildings to be serviced under this contract.
5. DELIVERABLES:
5.1. Record of Inspection and Testing. Document all inspection and testing in accordance with NFPA 72, section 7.6.6. Use the record of inspection and testing forms shown in NFPA 72, Figure 7.8.2(g) through 7.8.2(l) as appropriate, or alternate forms with identical information.
5.1.1. Inspection and testing forms are to be signed by the technician who performed the work.
5.2. Provide As-Built Drawings. Provide as-built drawings and/or diagrams of changes.
6. PERIOD OF PERFORMANCE
6.1. The period of performance shall be for five (5) days. The Period of Performance reads as follows:
6.1.1. Day 1 Mobilization
6.1.2. Day2 Perform work
6.1.3. Day 3 Perform work
6.1.4. Day 4 Perform work
6.1.5. Day 5 Demobilization
7. HOURS OF OPERATION
7.1. Normal operations. The contractor will conduct on-site business for fire alarm system modifications between the hours of 7:00 am to 5:00pm Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
7.2. Federal Holidays.
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Juneteenth National Independence Day Christmas Day Independence Day
END OF SOW
SECURE lb
BREAK ROOM
0 = EXISTING SENSOR
0 = EXISTING HORN/STROBE
/j. = EXISTING PULL SWITCH
• ■ = EXTEND BOX TO BE 4" FROM WALL
= New 2x3 Walls
0 = NEW SENSOR
0 = NEW HORN/STROBE
6 = NEW PULL SWITCH
• ■ = EXTEND BOX TO BE 4" FROM WALL
HALL
RESTROOM
UNCHANGED
JANITOR
STORAGE
FIRE ALARM PLAN
Scale: 1/4" = 1'-0" 1,548.50 Sq. Ft. Ceiling Height= 10'-1"
---1,1
I :1 WAITING AREA
I :1 I :1 I :1
-----------�Ji 0
I I I I I I I I
MAIN
OFFICE
SUPERVISOR'S
OFFICE
12-18-2023 aholland Text Box
MOVE 4"
aholland Text Box
MOVE 4"
aholland Line aholland Line aholland Text Box 2-22-2024
Solicitation No. 140R2024Q0071 j
D-1
SECTION D - PACKAGING AND MARKING
There are no clauses in this section.
E-1
SECTION E - INSPECTION AND ACCEPTANCE
Clause
Title
Date
52.246-12
Inspection of Construction
AUG 1996
F-1
SECTION F - DELIVERIES OR PERFORMANCE
Clause Title Date
52.242-14 Suspension of Work APR 1984
FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND APR 1984
COMPLETION OF WORK
The Contractor shall be required to
(a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 10 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
FAR 52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION SEP 2000
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $200.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
G-1
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 This contract shall be administered by the California Great Basin Regional Office, 2800
Cottage Way, Sacramento, California 95825-1898.
G.2 DIAR 1452.201-70 AUTHORITIES AND DELEGATIONS SEP 2011
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
The COR will be named at time of award.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction
(written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the
Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the
COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting
Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G-2
G.3. WBR 1452.201-80 CONTRACTING OFFICER’S MAY 2018
REPRESENTATIVE’S AUTHORITIES
AND LIMITATIONS – BUREAU OF
RECLAMATION
(a) Performance of the work under this contract shall be subject to the technical direction of the
Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:
(1) Inspecting and accepting or rejecting work performed under the contract.
(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.
(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.
(b) The Contractor will receive a copy of the written COR designation from the Contracting
Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting
Officer.
(c) Technical direction must be within the scope of work stated in the contract. Only the
Contracting Officer is authorized to determine if a change is within the scope of the contract;
therefore, the COR does not have the authority to, and may not, issue any technical direction that
(1) Constitutes a direction of additional work outside the Contract requirements;
(2) Constitutes a change as defined in the contract clause entitled “Changes;”
(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;
(4) Changes any of the expressed terms, conditions or specifications of the contract; or
(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.
(d) All technical direction shall be issued in writing by the COR.
(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the
COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the
Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting
Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -
(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the
Changes clause of the contract; or
(2) Advise the Contractor that the Government will issue a written change order.
(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction
G-3 is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”
H-1
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1 - INTERMEDIATE MILESTONES AND LIMITATIONS
A) The information provided below refers to the time period specified in FAR Clause 52.211-10 located in Section F of this solicitation.
a) The contractor shall complete all work in accordance with Section F and in accordance with all sections in the SOW.
B) WBR 1452.242-80 POSTAWARD CONFERENCE—BUREAU MAR 2022
OF RECLAMATION
(a) Prior to the Contractor starting work, a post-award conference (as described in FAR
Subpart 42.5), will be convened by the contracting activity or contract administration office.
The Contractor's Project Manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.
(b) The conference will be held by conference call.
(c) The Contracting Officer and the Contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the Contracting
Officer shall establish the date for the conference.
(d) The Contractor shall include any associated costs for attendance at the conference, in its quote.
e) (End of clause)
I-1
SECTION I - CONTRACT CLAUSES
FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEB 1998
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far (FAR 52.XXX-XX formatted clauses)
FAR Clauses Title Date
52.203-15 Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009
JUN 2010
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-1 Approval of Contract DEC 1989
52.204-2 Security Requirements. MAR 2021
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
JAN 2020
52.204-12 Unique Entity Identifier Maintenance OCT 2016
52.204-13 System for Award Management Maintenance OCT 2018
52.204-18 Commercial and Government Entity Code
Maintenance
AUG 2020
52.204-19 Incorporation by Reference of Representations and Certifications
DEC 2014
http://www.acquisition.gov/browse/index/far(FAR
I-2
52.204-21 Basic Safeguarding of Covered Contractor Information
Systems
NOV 2021
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities
NOV2021
52.204-25 Prohibition on Contracting for Certain
Telecommunications and Video Surveillance Services or Equipment
NOV 2021
52.204-27 Prohibition on a ByteDance Covered Application JUN 2023
52.207-5 Option to Purchase Equipment FEB 1995
52.208-9 Contractor Use of Mandatory Sources of Supply or
Services
MAY 2014
52.209-9 Updates of Publicly Available Information Regarding
Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations
NOV 2015
52.209-14 Reserve Officer Training Corps and Military Recruiting on Campus
NOV 2021
52.211-15 Defense Priority and Allocation Requirements APR 2008
52.213-4 Terms and Conditions—Simplified Acquisitions (Other Than Commercial Products and Commercial Services)
SEPT 2023
52.215-21 Requirements for Certified Cost or Pricing Data and
Data Other Than Certified Cost or Pricing Data-
Modifications
NOV 2021
52.216-23 Execution and Commencement of Work APR 1984
52.216-24 Limitation of Government Liability APR 1984
52.219-1 Small Business Program Representations SEP 2023
52.219-6 Notice of Total Small Business Set-Aside NOV 2020
52.219-13 Notice of Set-Aside of Orders MAR 2020
52.219-28 Post-Award Small Business Program Representation SEP 2023
52.219-31 Notice of Small Business Reserve MAR 2020
52.219-32 Orders Issued Directly Under Small Business Reserves MAR 2020
52.219-33 Nonmanufacturer Rule SEP 2021
52.222-1 Notice to the Government of Labor Disputes FEB 1997
52.222-3 Convict Labor JUN 2003
52.222-6 Construction Wage Rate Requirements AUG 2018
52.222-7 Withholding of Funds MAY 2014
I-3
52.222-8 Payrolls and Basic Records JUL 2021
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) MAY 2014
52.222-12 Contract Termination – Debarment MAY 2014
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility MAY 2014
52.222-20 Contracts for Materials, Supplies, Articles, and Equipment
JUN 2020
52.222-21 Prohibition of Segregated Facilities APR 2015
52.222-22 Previous Contracts and Compliance Reports. FEB 1999
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction
FEB 1999
52.222-26 Equal Opportunity SEP 2016
52.222-27 Affirmative Action Compliance Requirements for Construction
APR 2015
52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020
52.222-50 Combating Trafficking in Persons NOV 2021
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026
JAN 2022
52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies to Ban Text
Messaging While Driving
JUN 2020
52.225-13 Restrictions on Certain Foreign Purchases FEB 2021
52.228-2 Additional Bond Security OCT 1997
52.228-11 Pledges of Assets FEB 2021
52.228-12 Prospective Subcontractor Requests for Bonds DEC 2022
52.228-14 Irrevocable Letter of Credit NOV 2014
52.228-15 Performance and Payment Bonds - Construction JUN 2020
I-4
52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014
52.232-17 Interest MAY 2014
52.232-18 Availability of Funds APR 1984
52.232-23 Assignment Of Claims MAY 2014
52.232-27 Prompt Payment for Construction Contracts JAN 2017
52.232-33 Payment by Electronic Funds Transfer – System for
Award Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013
52.232-40 Providing Accelerated Payments to Small Business
Subcontractors.
MAR 2023
52.233-1 Alt I Disputes - Alternate I MAY 2014
52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law For Breach Of Contract Claim OCT 2004
52.236-2 Differing Site Conditions APR 1984
52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
52.236-5 Material and Workmanship APR 1984
52.236-6 Superintendence by the Contractor APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-8 Other Contracts APR 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Accident Prevention NOV 1991
52.236-15 Construction Schedules for Construction Contracts APR 1984
52.243-5 Changes and Changed Conditions JUN 2007
52.244-6 Subcontracts for Commercial Products and Commercial Services
SEP 2023
52.246-21 Warranty of Construction MAR 1994
52.248-3 Value Engineering – Construction OCT 2020
52.249-2 Alt I Termination for Convenience of the Government (Fixed- Price) – Alternate I
APR 2012
52.249-10 Default (Fixed-Price Construction) APR 1984
I-5
FAR 52.225-9 BUY AMERICAN— CONSTRUCTION MATERIALS OCT 2022
(a) Definitions . As used in this clause—
Commercially available off-the-shelf (COTS) item —
(1) Means any item of supply (including construction material ) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product ” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Quoted to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products .
"Construction material " means an article, material , or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work . The term also includes an item brought to the site preassembled from articles, materials , or supplies .
However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies , not construction material .
Cost of components means —
(1) For components purchased by the Contractor , the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor , all costs associated with the manufacture of the component , including transportation costs as described in paragraph (1) of this definition , plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material .
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both -
(i) An unmanufactured construction material mined or produced in the United States ; or
(ii) A construction material manufactured in the United States , if–
(A) The cost of its components mined, produced, or manufactured in the United
States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.
Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both , a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material . The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron https://www.acquisition.gov/far/part-2#FAR_2_101
I-6 or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of
"cost of components ".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material .
Foreign iron and steel means iron or steel products not produced in the United States . Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States , from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States " means the 50 States, the District of Columbia, and outlying areas .
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material . In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both , the domestic content test is applied only to the iron and steel content of the construction materials , excluding COTS fasteners. (See FAR 12.505(a)(2)).
The Contractor shall use only domestic construction material in performing this contract , except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
none___________________________________________
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United
States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1) http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505
I-7
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials ;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material .
However, when the basis for the exception is the unreasonable price of a domestic construction material , adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data . To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars) *
Item 1
Foreign construction material
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response;
I-8 if oral, attach summary.]
[Include other applicable supporting information .]
FAR 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSE NOV 2020
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR
Chapter 1) clause with an authorized deviation is indicated by the addition
"(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Department of the Interior or Bureau of
Reclamation (48 CFR Chapter 5) clause with an authorized deviation is indicated by the addition of
"(DEVIATION)" after the name of the regulation.
(End of clause)
WBR 1452.237-80 SECURITY REQUIREMENTS -- MAR 2022
BUREAU OF RECLAMATION
(a) General Security Requirements:
(1) This clause addresses security requirements, including general procedural requirements, information security requirements, contractor employee suitability requirements, identification card requirements, site security requirements, vessel exclusion barriers, and information technology security requirements. Within this clause, COR means Contracting Officer's Representative. If there is no COR appointed and identified to the Contractor, the term instead will mean the Program
Manager or any other authorized individual responsible for technical oversight under the contract.
“Work site” means the Government facility, office, construction site, and any other area within the
Government office or facility that the Contractor must access to accomplish work under this contract.
(2) The work performed under this contract shall only be accomplished by individuals (in the employment of the Contractor or any subcontractors) whose conduct and behavior…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .