C04a Attachment 1 Mesa Falls Boardwalk Specifications 1240LT26Q0049.pdf
PDF 383 KB Posted
- Attached to
- GAOA Const Mesa Falls Boardwalk CTNF
- Solicitation number
- 1240LT26Q0049
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a federal contract specification document for the Mesa Falls Boardwalk Replacement project issued by the USDA Forest Service, Region 4, located in the Ashton/Island Park Ranger District of the Caribou-Targhee National Forest in Fremont County, Idaho.
The project scope includes removal and replacement of boardwalk lumber, stringers, deck boards, and connecting hardware for the Mesa Falls boardwalk, plus replacement of lumber and hardware for ten benches along the boardwalk and asphalt pathways. Existing metal railings, posts, anchors, and supports will remain in place for reuse. Work must occur between September 8, 2026, and November 12, 2026, with no extensions permitted due to weather constraints. The contract duration is 301 calendar days, with an estimated start date of January 15, 2026. The contractor must submit a stream protection plan, traffic control plan, and construction schedule for approval prior to work commencement. Equipment must be pressure-washed before entering National Forest lands to prevent noxious weed transportation. Water and utilities are unavailable at the site; the contractor is responsible for coordinating temporary power installation and costs. Toilet facilities are available. The project requires compliance with multiple specifications including Rough Carpentry (Section 061000), Heavy Timber Construction (Section 061323), Wood Patio Decking (Section 061533), Structural Glued-Laminated Timber (Section 061850), and Staining and Transparent Finishing (Section 099300). All lumber must comply with AWPA U1 preservative treatment standards, with UC4A treatment required for members in contact with ground and UC3B for above-grade lumber. Materials include pressure-treated dimension lumber, timber, fasteners, metal framing anchors, and exterior wood stains using Sherwin Williams or approved MPI-listed products. The contractor must maintain quality control systems, submit test and inspection reports, provide as-built drawings, and implement a waste management plan with documentation of salvage, recycling, and disposal activities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
MESA FALLS BOARDWALK REPLACEMENT
09/08/2025
1.1 SCOPE OF CONTRACT
A. This project includes the removal and replacement of boardwalk lumber as well as connecting hardware for the Mesa Falls boardwalk.
B. The work includes removing and disposing of old pressure-treated lumber. Replacing all lumber with comparable stringers, deck boards, and other lumber as well as connecting hardware. Existing metal railings, posts, anchors, and other supports will remain in-place to be re-used. Redwood Bench lumber and connecting hardware will also be replaced for the 10 benches along the boardwalk and asphalt pathways.
C. Quantities associated with these options are identified in the Schedule of Items.
1.2 PROJECT LOCATION
A. The project is located in the Ashton/Island Park Ranger District of the Caribou-Targhee National Forest, Fremont County, Idaho, in Section 13 Township 10 North, Range 43 East. It is located approximately 16 miles Northeast of Ashton, Idaho. The project may be accessed from State Highway ID-47 (Mesa Falls Scenic Byway/Old Highway 47 Scenic) and Forest Road 20295/Upper Mesa Falls Road.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.
2. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.
3. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
4. Water is not available at the site for construction purposes. Utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
5. Toilet facilities are available at the site.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage on site.
B. No overnight camping will be allowed on site. Camping may be arranged near the work site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 ESTIMATED START DATE
A. 01/15/2026
NOTE: ON-SITE WORK MAY NOT BEGIN UNTIL SEPTEMBER 8, 2026 AND
MUST BE COMPLETED PRIOR TO NOVEMBER 12, 2026. WEATHER WILL NOT
ALLOW EXTENSIONS OF THIS TIMEFRAME!
1.8 CONTRACT TIME
A. 301 Calendar Days
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
NOTE: ON-SITE WORK MAY NOT BEGIN UNTIL SEPTEMBER 8, 2026 AND
MUST BE COMPLETED PRIOR TO NOVEMBER 12, 2026. WEATHER WILL NOT
ALLOW EXTENSIONS OF THIS TIMEFRAME!
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
SECTION 011250 - MEASUREMENT AND PAYMENT
SECTION 011900 - MOBILIZATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 017320 - SELECTIVE DEMOLITION
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
SECTION 061000 - ROUGH CARPENTRY
SECTION 061323 - HEAVY TIMBER CONSTRUCTION
SECTION 061533 - WOOD PATIO DECKING
SECTION 061850 - STRUCTURAL GLUED-LAMINATED TIMBER
SECTION 099300 - STAINING AND TRANSPARENT FINISHING
END OF SECTION C
September 2025
MEASUREMENT AND PAYMENT 011250-1
USDA FOREST SERVICE, R4
MESA FALLS BOARDWALK REPLACEMENT
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
MEASUREMENT AND PAYMENT 011250-2
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
MEASUREMENT AND PAYMENT 011250-3
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
MOBILIZATION 011900-1
MESA FALLS BOARDWALK REPLACEMENT
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
SUBMITTAL PROCEDURES 013300-1
MESA FALLS BOARDWALK REPLACEMENT
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Sectio n Section Title
Subse ction
Required Submittal
C General Specifications 1.3A Stream Protection Plan
C General Specifications 1.4A Traffic Control Plan
01330
Submittal Procedures 2.1D Construction Schedule
01410
Quality Control
1.3 A Contractor quality control plan
01410
Quality Control
1.3 B Permits, Licenses, and
Certificates
01410
Quality Control
1.3 C Test and inspection reports
01410
Quality Control
1.3 D As-Built drawings
06100
Rough Carpentry 1.3.A Product Data
06100
Rough Carpentry 1.3A Product Data
09911
Exterior Paints and Coatings 1.3A-
B Product Data, Samples
09930
Staining and Transparent Finishing 1.2A-
B Product Data, Samples
END OF SECTION 013300
QUALITY CONTROL 014100-1
MESA FALLS BOARDWALK REPLACEMENT
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
QUALITY CONTROL 014100-2
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
QUALITY CONTROL 014100-3
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
END OF SECTION 014100
SELECTIVE DEMOLITION 017320-1
MESA FALLS BOARDWALK REPLACEMENT
SECTION 017320 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes demolition and removal of the following:
1. Selected portions of a boardwalk.
2. Repair procedures for selective demolition operations.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
C. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.
1.4 SUBMITTALS
A. Schedule of Selective Demolition Activities: Indicate detailed sequence of selective demolition and removal work, with starting and ending dates.
B. Waste Manifests for materials deemed hazardous by the State of Idaho.
1.5 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI A10.6 and NFPA 241.
C. Pre-demolition Conference: Conduct conference at Project site with contractor, subcontractors and Contracting Officer’s Representative.
SELECTIVE DEMOLITION 017320-2
1.6 PROJECT CONDITIONS
A. Conduct selective demolition so Government operations will not be disrupted. Provide not less than 72 hours' notice to CO of activities that will affect Government operations.
B. Maintain access to existing building amenities, pathways, and other adjacent occupied or used facilities.
1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the COR.
C. Government assumes no responsibility for condition of areas to be selectively demolished.
1. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.
D. Storage or sale of removed items or materials on-site will not be permitted.
1.7 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.
PART 2 - PRODUCTS
2.1 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.
2. Use materials whose installed performance equal or surpasses that of existing materials.
3. Salvage benches and all railings and supports as noted in the plans and store for reinstallation.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
B. When unanticipated structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.
3.2 PREPARATION
SELECTIVE DEMOLITION 017320-3
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct roads, without permission from CO. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.
2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.
3. Protect existing site improvements, appurtenances, and landscaping to remain.
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
3.3 POLLUTION CONTROLS
A. Dust Control: Use temporary enclosures, and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.
B. Disposal: Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas..
C. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
3.4 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.
1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
3. Do not use cutting torches until work area is cleared of flammable materials.
Maintain portable fire-suppression devices during flame-cutting operations.
4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supports.
5. Dispose of universal hazardous waste as required by EPA and State laws.
B. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.
2. Protect items from damage during transport and storage.
SELECTIVE DEMOLITION 017320-4
3. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.5 REPAIRS
A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.
B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Dispose of universal hazardous waste as required above.
C. Burning: Do not burn demolished materials.
D. Disposal: Transport demolished materials off Government property and legally dispose of them.
END OF SECTION 017320
JANUARY 2025
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419-1
MESA FALLS BOARDWALK REPLACEMENT
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous demolition and construction waste.
3. Disposing of nonhazardous demolition and construction waste.
B. Related Requirements:
1. Section 024116 "Structure Demolition" for disposition of waste resulting from demolition of buildings, structures, and site improvements, and for disposition of hazardous waste.
2. Section 311000 "Site Clearing" for disposition of waste resulting from site clearing and removal of above- and below-grade improvements.
1.2 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
1.3 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan within 30 days of date established for the Notice of Award.
1.4 INFORMATIONAL SUBMITTALS
A. Waste Reduction Progress Reports: Concurrent with each Application for Payment, submit report. Include the following information:
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419-2
1. Material category.
2. Generation point of waste.
3. Total quantity of waste in tons.
4. Quantity of waste salvaged, both estimated and actual in tons.
5. Quantity of waste recycled, both estimated and actual in tons.
6. Total quantity of waste recovered (salvaged plus recycled) in tons.
7. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste.
B. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work.
C. Records of Donations: Indicate receipt and acceptance of salvageable waste donated to individuals and organizations. Indicate whether organization is tax exempt.
D. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to individuals and organizations. Indicate whether organization is tax exempt.
E. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
F. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
G. A spreadsheet that may be used for documenting waste is attached to this specification.
The contractor may also submit a form they have used in the past for approval. Guidance on the Teton County Integrated Waste and Recycling program is attached at the end of this specification.
1.5 QUALITY ASSURANCE
A. Waste Management Coordinator Qualifications: Experienced person, with a record of successful waste management coordination of projects with similar requirements.
B. Waste Management Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination."
1.6 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to ASTM E 1609 and requirements in this Section. Plan shall consist of waste identification, waste reduction work plan, and cost/revenue analysis. Distinguish between demolition and construction waste. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419-3
B. Waste Identification: Indicate anticipated types and quantities of demolition site-clearing and construction waste generated by the Work. Include estimated quantities and assumptions for estimates.
C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures.
1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project, describe methods for preparing salvaged materials before incorporation into the Work.
2. Salvaged Materials for Sale: For materials that will be sold to individuals and organizations, include list of their names, addresses, and telephone numbers.
3. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses, and telephone numbers.
4. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.
5. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
6. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
B. Waste Management Coordinator: Engage a waste management coordinator to be responsible for implementing, monitoring, and reporting status of waste management work plan.
C. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at Project site. Conduct a Waste Management meeting including the Government COR and Inspectors to ensure the entire team understands the importance of the recycling goals.
1. Distribute waste management plan to everyone concerned within three days of submittal return.
2. Distribute waste management plan to entities when they first begin work on-site.
Review plan procedures and locations established for salvage, recycling, and disposal.
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419-4
D. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, reused, donated, and sold.
2. Comply with Section 015000 "Temporary Facilities and Controls" for controlling dust and dirt, environmental protection, and noise control.
3.2 SALVAGING DEMOLITION WASTE
A. Salvaged Items for Reuse in the Work:
1. Clean salvaged items.
2. Store items in a secure area until installation.
3. Protect items from damage during transport and storage.
4. Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated.
3.3 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Contractor.
C. Procedures: Separate recyclable waste from other waste materials, trash, and debris.
Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until they are removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.
a. Inspect containers and bins for contamination and remove contaminated materials if found.
2. Stockpile processed materials on-site without intermixing with other materials.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
3. Stockpile materials away from construction area. Do not store within drip line of remaining trees.
4. Store components off the ground and protect from the weather.
5. Remove recyclable waste from Government’s property and transport to recycling receiver or processor.
3.4 RECYCLING DEMOLITION WASTE
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419-5
A. Concrete: Remove reinforcement and other metals from concrete and sort with other metals.
1. Pulverize concrete to maximum 1-1/2-inch size.
B. Wood Materials: Sort and stack members according to size, type, and length. Separate lumber, engineered wood products, panel products, and treated wood materials. Remove large pieces of metal as directed by the Solid Waste & Recycling Center.
C. Metals: Separate metals by type.
1. Structural Steel: Stack members according to size, type of member, and length.
2. Remove and dispose of bolts, nuts, washers, and other rough hardware.
D. Conduit: Reduce conduit to straight lengths and store by type and size.
3.5 RECYCLING CONSTRUCTION WASTE
A. Packaging:
1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.
2. Polystyrene Packaging: Separate and bag materials.
3. Pallets: As much as possible, require deliveries using pallets to remove pallets from
Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood.
4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.
B. Wood Materials:
1. Clean Cut-Offs of Lumber: Grind or chip into small pieces.
2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood.
C. Gypsum Board: Stack large clean pieces on wood pallets or in container and store in a dry location.
1. Clean Gypsum Board: Grind scraps of clean gypsum board using small mobile chipper or hammer mill. Screen out paper after grinding.
3.6 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419-6
C. Disposal: Remove waste materials from Government's property and legally dispose of them.
3.7 SAMPLE FORMS
A. Forms provided by Contracting Officer at award.
END OF SECTION 017419
JANUARY 2019
ROUGH CARPENTRY 061000-1
MESA FALLS BOARDWALK REPLACEMENT
SECTION 061000 - ROUGH CARPENTRY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Framing with dimension lumber.
2. Framing with engineered wood products.
3. Wood blocking and nailers.
4. Wood furring.
1.2 ACTION SUBMITTALS
A. Product Data: For each type of process and factory-fabricated product.
1.3 INFORMATIONAL SUBMITTALS
A. Material Certificates: For dimension lumber specified to comply with minimum allowable unit stresses. Indicate species and grade selected for each use and design values approved by the ALSC Board of Review.
B. Evaluation Reports: For the following, from ICC-ES:
1. Wood-preservative-treated wood.
2. Engineered wood products.
3. Power-driven fasteners.
4. Post-installed anchors.
5. Metal framing anchors.
1.4 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.
ROUGH CARPENTRY 061000-2
PART 2 - PRODUCTS
2.1 WOOD PRODUCTS, GENERAL
A. Lumber: DOC PS 20 and applicable rules of grading agencies indicated. If no grading agency is indicated, comply with the applicable rules of any rules-writing agency certified by the ALSC Board of Review. Grade lumber by an agency certified by the ALSC Board of Review to inspect and grade lumber under the rules indicated.
1. Factory mark each piece of lumber with grade stamp of grading agency.
2. Rough sawn lumber, unless otherwise indicated.
B. Maximum Moisture Content of Lumber: 15 percent unless otherwise indicated.
1. If contractor is unable to meet 15 percent moisture content, provide 19 percent moisture content and delay finishing wood until 15 percent moisture content can be obtained.
C. Engineered Wood Products: Acceptable to authorities having jurisdiction and for which current model code research or evaluation reports exist that show compliance with building code in effect for Project.
1. Allowable design stresses, as published by manufacturer, shall meet or exceed those indicated. Manufacturer's published values shall be determined from empirical data or by rational engineering analysis and demonstrated by comprehensive testing performed by a qualified independent testing agency.
2.2 WOOD-PRESERVATIVE-TREATED LUMBER
A. Preservative Treatment by Pressure Process: AWPA U1; Use Category UC4A for any member in contact with the ground. If lumber is above grade, UC3B treatment may be used.
1. Preservative Chemicals: Acceptable to authorities having jurisdiction.
B. Kiln-dry lumber after treatment to a maximum moisture content of 19 percent. Do not use material that is warped or that does not comply with requirements for untreated material.
C. Mark lumber with treatment quality mark of an inspection agency approved by the ALSC Board of Review.
D. Application: Treat all rough carpentry unless otherwise indicated.
2.3 DIMENSION LUMBER FRAMING
A. Framing: Per the structural drawings.
ROUGH CARPENTRY 061000-3
1. Application: Framing for boardwalk.
2. Species:
a. Hem-fir (north); NLGA.
b. Douglas fir-larch; WCLIB or WWPA.
c. Spruce-pine-fir; NLGA.
d. Douglas fir-south; WWPA.
e. Hem-fir; WCLIB or WWPA.
f. Douglas fir-larch (north); NLGA.
g.…