C04_Statement of Work.pdf
PDF 1 MB Posted
- Attached to
- La Grande Forestry Sciences Lab Security Fencing
- Solicitation number
- 1240BJ26Q0053
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the installation of security fencing at the La Grande Forestry Sciences Laboratory (LFSL), a USDA Forest Service facility located in La Grande, Oregon.
The primary requirement is to install approximately 404 linear feet of six-foot-tall galvanized steel chain-link security fencing with one non-motorized 10-foot-wide man gate to enclose the remaining unfenced areas of the 13,693 square-foot facility on 5.5 acres. The project addresses security concerns including vehicle break-ins, theft of agency items, and unauthorized personnel access. The work comprises two Contract Line Items: 121 feet on the west side and 278 feet on the south side, with the gate located on the south side. The estimated work period is October 1, 2026 through December 1, 2026, with a maximum of 60 calendar days for completion. Work hours are 8:00 a.m. to 4:30 p.m. Monday through Friday, excluding holidays, and must be coordinated with the Contracting Officer's Representative (COR).
Technical specifications require 36-inch-deep concrete footings with 8 inches of drain rock at the bottom, 4000 psi concrete, terminal posts at 2 7/8 inches diameter, line posts at 2 3/8 inches diameter spaced 8 feet on center, galvanized steel chain-link fabric with 1 3/4-inch mesh and 0.148-inch diameter wire (Class 2 coating per ASTM A 392), and compliance with ASTM F 567 and CLFMI standards. Payment is lump sum and includes all excavation, backfill, concrete supports, posts, fencing, equipment, materials, and work within 5 feet of the fence. The contractor must be state/county registered and licensed, with an on-site supervisor possessing minimum five years' chain-link fence installation experience. Compliance inspection requirements include verification of wire gauge, mesh size, wire coating, post spacing and sizes, footing specifications, and proper placement of drain rock.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Project Title La Grande Forestry Sciences Lab Security Fencing
General Information
1.0 Background and Purpose
The USDA Forest Service, Pacific Northwest Research Station has the need for Security Fencing at the La Grande Forestry Sciences Laboratory (LFSL) site. The LFSL is located at 1401 Gekeler Lane in La Grande, Oregon 97850. The LFSL facility is approximately 13,693 square feet and located on 5.5 acres of land.
The construction of the fence is paramount in keeping employees, property, and research safe.
The facility has had multiple vehicle break-ins and several agency items stolen over the past few years. Also had an individual living on grounds for several days. There has been evidence of people walking through compound at all hours. The resulting contract will improve the site security and will protect the property and research.
2.0 Definitions
Contracting Officer (CO) means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings within the limits of their warrant.
Contracting Officer’s Representative (COR) means an individual, designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.
Contractor Requirements
3.0 Technical Requirements / Tasks
Tasks:
Provide and install a six-foot-tall chain link security fence around to enclose the remaining unfenced areas of the LFSL facility. The footings should be a minimum of 36 inches deep due to the 24-inch frost line in La Grande. Install eight inches of drain rock at the bottom of each pole footing. One gate will be installed that will consist of one 6 foot high and 10-foot-wide man gate (non-motorized).
The work will be performed outside, the immediate area (grounds) parking lots are fairly level. There are exterior water bibs and power outlets on site. Bathroom facilities are available within close proximity of the administrative lobby.
The concrete mix will be 4000 psi. Keep the air temperature surrounding the fresh concrete above 40 degrees F for a period of five days after the concrete is placed. Mix dry concrete and water thoroughly according to the manufacturer. Concrete footings will be two inches above the finished ground with a slight sloping away from the posts.
Technical Requirements:
SECTION 033000 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section specifies cast-in place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.
1.2 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements.
1.3 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Design Mixtures: For each concrete mixture. Indicate amounts of mixing water to be withheld for later addition at Project site.
C. Steel Reinforcement Shop Drawings when project design requires special consideration.
D. Field quality-control test reports.
1.4 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.
PART 2 - PRODUCTS
2.1 STEEL REINFORCEMENT
A. Plain-Steel Wire: ASTM A 82, as drawn.
B. Deformed-Steel Wire: ASTM A 496.
2.2 CONCRETE MATERIALS
A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project:
1. Portland Cement: ASTM C 150, Type II.
B. Normal-Weight Aggregates: ASTM C 33, graded, from a single source.
1. Maximum Coarse-Aggregate Size: 1 inch (25 mm) nominal.
2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.
C. Water: ASTM C 94/C 94M and potable.
2.3 VAPOR RETARDERS
A. Penetrating Liquid Floor Treatment: Clear, chemically reactive, waterborne solution of inorganic silicate or siliconate materials and proprietary components; odorless; colorless;
that penetrates, hardens, and densifies concrete surfaces.
2.4 CURING MATERIALS
A. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry.
B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.
C. Water: Potable.
D. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating or non-dissipating. Liquid Membrane-Forming Compounds. Material shall be certified by curing compound manufacturer to not interfere with bonding of floor covering.
2.5 RELATED MATERIALS
A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber or ASTM D 1752, cork or self-expanding cork.
B. Semirigid Joint Filler: Two-component, semirigid, 100 percent solids, epoxy resin with a Type A shore durometer hardness of 80 per ASTM D 2240.
C. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301.
1. Use a qualified independent testing agency for preparing and reporting proposed mixture designs based on laboratory trial mixtures.
D. Limit water-soluble, chloride-ion content in hardened concrete to 0.06 percent by weight of cement.
E. Admixtures: Use admixtures according to manufacturer's written instructions.
F. Color Pigment: Add color pigment to concrete mixture according to manufacturer's written instructions and to result in hardened concrete color consistent with approved mockup.
2.6 CONCRETE MIXTURES FOR BUILDING ELEMENTS
A. Footings: Proportion normal-weight concrete mixture as follows:
1. Minimum Compressive Strength: 4000 psi (24.1 MPa) at 28 days.
2. Maximum Water-Cementitious Materials Ratio: 0.50.
3. Slump Limit: 3-5 inch (75-125 mm), plus or minus 1 inch (25 mm).
4. Air Content: 4 percent, plus or minus 1 percent at point of delivery for [1-inch (25-mm)] nominal maximum aggregate size.
B. Foundation Walls: Proportion normal-weight concrete mixture as follows:
1. Minimum Compressive Strength: 4000 psi (24.1 MPa) at 28 days.
2. Maximum Water-Cementitious Materials Ratio: 0.50.
3. Slump Limit: 4 inches, plus or minus 1 inch (25 mm).
4. Air Content: 5 percent, plus or minus 1 percent at point of delivery for 1-inch (25-
mm) nominal maximum aggregate size.
C. Slabs-on-Grade: Proportion normal-weight concrete mixture as follows:
1. Minimum Compressive Strength: 4000 psi (24.1 MPa) at 28 days.
2. Minimum Cementitious Materials Content: 540 lb/cu. yd. (320 kg/cu. m).
3. Slump Limit: 4 inches (100 mm), plus or minus 1 inch (25 mm).
4. Air Content: 5 percent, plus or minus 1 percent at point of delivery for 1-inch (25-
mm) nominal maximum aggregate size.
5. Air Content: Do not allow air content of troweled finished floors to exceed 3 percent.
6. Synthetic Fiber: Uniformly disperse in concrete mixture at manufacturer's recommended rate, but not less than [1.0 lb/cu. yd. (0.60 kg/cu. m)] [1.5 lb/cu. yd.
(0.90 kg/cu. m)].
2.7 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M and ASTM C 1116 and furnish batch ticket information.
1. When air temperature is between 85 and 90 deg F (30 and 32 deg C), reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F (32 deg C), reduce mixing and delivery time to 60 minutes.
B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-type batch machine mixer.
1. For mixer capacity of 1 cu. yd. (0.76 cu. m) or smaller, continue mixing at least 1- 1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released.
2. For mixer capacity larger than 1 cu. yd. (0.76 cu. m), increase mixing time by 15 seconds for each additional 1 cu. yd. (0.76 cu. m).
3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mixture type, mixture time, quantity, and amount of water added. Record approximate location of final deposit in structure.
PART 3 - EXECUTION
3.1 FORMWORK
A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.
B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.
C. Limit concrete surface irregularities, designated by ACI 347R as abrupt or gradual, as follows:
1. Class A, 1/8 inch (3.2 mm) for smooth-formed finished surfaces.
2. Class B, 1/4 inch (6 mm) for rough-formed finished surfaces.
D. Construct forms tight enough to prevent loss of concrete mortar.
E. Fabricate forms for easy removal without hammering or prying against concrete surfaces.
Provide crush or wrecking plates where stripping may damage cast concrete surfaces.
Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.
1. Do not use rust-stained steel form-facing material.
F. Chamfer or round exterior corners and edges of permanently exposed concrete.
G. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.
3.2 EMBEDDED ITEMS
A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.
1. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC's "Code of Standard Practice for Steel Buildings and Bridges."
3.3 VAPOR RETARDERS
A. Plastic Vapor Retarders: Place, protect, and repair vapor retarders according to ASTM E 1643 and manufacturer's written instructions.
1. Lap joints 6 inches (150 mm) and seal with manufacturer's recommended tape.
3.4 STEEL REINFORCEMENT
A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement.
1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.
B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that would reduce bond to concrete.
C. Accurate position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars.
D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
3.5 CONCRETE PLACEMENT
A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed.
B. Do not add water to concrete during delivery, at Project site, or during placement unless approved by the Contracting Officer.
C. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301.
D. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.
1. Deposit concrete in horizontal layers of depth to not exceed formwork design pressures and in a manner to avoid inclined construction joints.
2. Consolidate placed concrete with mechanical vibrating equipment according to
ACI 301.
3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches (150 mm) into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.
E. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.
1. When average high and low temperature is expected to fall below 40 deg F (4.4 deg C) for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301.
2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.
3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.
F. Hot-Weather Placement: Comply with ACI 301 and as follows:
1. Maintain concrete temperature below 90 deg F (32 deg C) at time of placement.
Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.
2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete.
Keep subgrade uniformly moist without standing water, soft spots, or dry areas.
3.6 FINISHING FLOORS AND SLABS
A. General: Comply with ACI 302.1R recommendations for screeding, restrengthening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.
B. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is small or inaccessible to power driven floats. Restraighten, cut down high spots, and fill low spots. Repeat float passes and restraighten Ing until surface is left with a uniform, smooth, granular texture.
1. Apply float finish to surfaces to receive trowel finish and to be covered with fluid-applied or sheet waterproofing.
C. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete by hand or power-driven trowel. Continue troweling passes and re-straighten until surface is free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.
D. Broom Finish: Apply a broom finish to exterior concrete platforms, steps, and ramps, and elsewhere as indicated.
1. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route. Coordinate required final finish with Contracting Officer before application.
3.7 MISCELLANEOUS CONCRETE ITEMS
A. Filling In: Fill in holes and openings left in concrete structures, unless otherwise indicated, after work of other trades is in place. Mix, place, and cure concrete, as specified, to blend with in-place construction. Provide other miscellaneous concrete filling indicated or required to complete the Work.
B. Curbs: Provide monolithic finish to interior curbs by stripping forms while concrete is still green and by steel-troweling surfaces to a hard, dense finish with corners, intersections, and terminations slightly rounded.
3.8 CONCRETE PROTECTING AND CURING
A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing.
B. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for the remainder of the curing period.
C. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including floors and slabs, concrete floor toppings, and other surfaces.
D. Cure concrete according to ACI 308.1, by one or a combination of the following methods:
1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials:
a. Water.
b. Continuous water-fog spray.
c. Absorptive cover, water saturated and kept continuously wet. Cover concrete surfaces and edges with 12-inch (300-mm) lap over adjacent absorptive covers.
2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches (300 mm), and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape.
a. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive floor coverings.
b. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive penetrating liquid floor treatments.
c. Cure concrete surfaces to receive floor coverings with either a moisture-retaining cover or a curing compound that the manufacturer certifies will not interfere with bonding of floor covering used on Project.
3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.
a. After curing period has elapsed, remove curing compound without damaging concrete surfaces by method recommended by curing compound manufacturer unless manufacturer certifies curing compound will not interfere with bonding of floor covering used on Project.
3.9 CONCRETE SURFACE REPAIRS
A. Defective Concrete: Repair and patch defective areas when approved by Contracting Officer. Remove and replace concrete that cannot be repaired and patched to Contracting Officer's approval.
B. Patching Mortar: Mix dry-pack patching mortar, consisting of one-part Portland cement to two and one-half parts fine aggregate passing a No. 16 (1.18-mm) sieve, using only enough water for handling and placing.
C. Perform structural repairs of concrete, subject to Contracting Officer's approval, using epoxy adhesive and patching mortar.
D. Repair materials and installation not specified above may be used, subject to Contracting Officer's approval.
END OF SECTION 033000
SECTION 323113
CHAIN-LINK FENCES AND GATES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Galvanized steel chain-link fabric.
2. Galvanized steel framework.
1.3 DEFINITIONS
A. CLFMI: Chain Link Fence Manufacturers Institute (https://chainlinkinfo.org/)
1.4 SUBMITTALS
A. Product Data: Material descriptions, construction details, dimensions of individual components and profiles, and finishes for the following:
1. Fence and posts, rails, and fittings.
2. Chain-link fabric, reinforcements, and attachments.
B. Shop Drawings: Show locations of fence, each gate, posts, rails, and tension wires and details of extended posts, extension arms, gate swing, or other operation, hardware, and accessories. Indicate materials, dimensions, sizes, weights, and finishes of components.
Include plans, elevations, sections, gate swing and other required installation and operational clearances, and details of post anchorage and attachment and bracing. Approval of the Contracting Officer’s Representative must be received before ordering products.
C. Product Certificates: Signed by manufacturers of chain-link fences and gates certifying that products furnished comply with requirements.
D. Qualification Data: For firms and persons specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other specified information.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: An experienced installer who has completed chain-link fences and gates similar in material, design, and extent to those indicated for this Project and whose work has resulted in construction with a record of successful in-service performance.
B. Source Limitations for Chain-Link Fences and Gates: Obtain each color, grade, finish, type, and variety of component for chain-link fences and gates from one source with resources to provide chain-link fences and gates of consistent quality in appearance and physical properties.
1.6 PROJECT CONDITIONS
A. Field Measurements: Verify layout information for chain-link fences and gates shown on Drawings in relation to property survey and existing structures. Verify dimensions by field measurements.
1.7 MEASUREMENT AND PAYMENT
A. Payment will be lump sum for the chain-link fence and will include the excavation and backfill, concrete supports, posts, fencing, and all equipment, material, work and incidentals within 5 feet of the fence required to complete the item.
PART 2 - PRODUCTS
2.1 CHAIN-LINK FENCE FABRIC
A. Steel Chain-Link Fence Fabric: Height indicated on Drawings. Provide fabric fabricated in one-piece widths for fencing in height of 6 feet. Comply with CLFMI's "Product Manual" and with requirements indicated below:
1. Mesh and Wire Size: 1 3/4-inch (44mm) mesh, 0.148-inch diameter Zinc-Coated Fabric: ASTM A 392, with zinc coating applied to steel wire, Type II, zinc coated (galvanized)] mesh fabric after weaving with the following minimum coating weight:
a. Class 2: Not less than 2 oz./sq. ft. of uncoated wire surface.
B. Selvage: Knuckled at both selvages.
2.2 INDUSTRIAL FENCE FRAMING
A. Round Steel Pipe: Standard weight, Schedule 40, galvanized steel pipe complying with ASTM F 1083. Comply with ASTM F 1043, Material Design Group IA, external and internal coating Type A, consisting of not less than 1.8-oz./sq. ft. (0.55-kg/sq. m) zinc; and the following strength and stiffness requirements:
1. Line, End, Corner, and Pull Posts and Top Rail: Per requirements for Light Industrial Fence.
B. Roll-Formed Steel Shapes: C-sections or other shape, produced from structural steel.
Comply with ASTM F 1043, Material Design Group II, with minimum yield strength of 45,000 psi (310 MPa); and the following coating and strength and stiffness requirements:
1. Coating: Type A, consisting of not less than minimum 2.0-oz./sq. ft. (0.61-kg/sq. m) average zinc coating per ASTM A 123/A 123M.
C. Post Brace Rails: Match top rail for coating and strength and stiffness requirements.
Provide brace rail with truss rod assembly for each gate, end, and pull post. Provide two brace rails extending in opposing directions, each with truss rod assembly, for each corner post and for pull posts. Provide rail ends and clamps for attaching rails to posts.
D. Top Rails: Fabricate top rail from lengths 21 feet (6.4 m) or longer, with wedged-end or fabricated for expansion-type coupling, forming a continuous rail along top of chain-link fabric.
2.3 GATES
A. Metal Pipe and Tubing: Galvanized steel. Comply with ASTM F 1083 and ASTM F 1043 for materials and protective coatings.
B. Frames and Bracing: Fabricate from round or square galvanized steel tubing with outside dimension and weight according to ASTM F 1184 for the following gate characteristics:
1. Gate Fabric Height: 6 feet (1.83 m) or less.
C. Gate Posts: Fabricate members from round galvanized steel pipe with outside dimension and minimum weight according to ASTM F 1184 for the following gate characteristics:
D. Hardware: Latches permitting operation from both sides of gate, locking devices roller assemblies and stops. Fabricated from galvanized steel. Fabricate latches with integral eye openings for padlocking; padlock accessible from both sides of gate.
2.4 FITTINGS
A. General: Provide fittings for a complete fence installation, including special fittings for corners. Comply with ASTM F 626.
B. Post and Line Caps: Hot-dip galvanized pressed steel or hot-dip galvanized cast iron.
Provide weathertight closure cap for each post.
C. Rail and Brace Ends: Hot-dip galvanized pressed steel or hot-dip galvanized cast iron.
Provide rail ends or other means for attaching rails securely to each gate, corner, pull, and end post.
D. Rail Fittings: Provide the following:
1. Top Rail Sleeves: Hot-dip galvanized pressed steel or round steel tubing. Not less than 6 inches (153 mm) long.
2. Rail Clamps: Hot-dip galvanized pressed
E. Tension and Brace Bands: Hot-dip galvanized pressed steel
F. Tension Bars: Hot-dip galvanized steel, length not less than 2 inches (50 mm) shorter than full height of chain-link fabric. Provide one bar for each gate and end post, and two for each corner and pull post, unless fabric is integrally woven into post.
G. Pipe Sleeves: For posts set into concrete, provide preset hot-dip galvanized steel pipe sleeves complying with ASTM A 53, not less than 6 inches (150 mm) long with inside dimensions not less than 1/2 inch (13 mm) more than outside dimension of post, and flat steel plate forming bottom closure.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for site clearing, earthwork, pavement work, and other conditions affecting performance.
1. Do not begin installation before final grading is completed, unless otherwise permitted by Contracting Officer’s Representative.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Stake locations of fence lines, gates, and terminal posts. Indicate locations of utilities, lawn sprinkler system, underground structures, benchmarks, and property monuments.
3.3 INSTALLATION, GENERAL
A. General: Install chain-link fencing to comply with ASTM F 567 and more stringent requirements specified.
1. Install fencing on established boundary lines inside property line.
B. Post Excavation: Drill or hand-excavate holes for posts to diameters and spacings indicated, in firm, undisturbed or compacted soil.
C. Post Setting: Hand-excavate holes for post foundations in firm, undisturbed or compacted soil. Place drain rock in the excavated hole 8 inches below the post. Set gate and gate operator-mounting posts in concrete footing. Protect portion of posts aboveground from concrete splatter. Place concrete around posts and vibrate or tamp for consolidation. Using mechanical devices to set line posts per ASTM F 567 is permitted. Verify that posts are set plumb, aligned, and at correct height and spacing, and hold in position during placement and finishing operations until concrete is sufficiently cured.
1. Dimensions and Profile: As indicated on Drawings.
2. Exposed Concrete Footings: Extend concrete 2 inches (50 mm) above grade, smooth, and shape to shed water.
3. Posts Set into Concrete in Sleeves: Use steel pipe sleeves preset and anchored into concrete for installing posts. After posts have been inserted into sleeves, fill annular space between post and sleeve with no shrink, nonmetallic grout, mixed and placed to comply with anchoring material manufacturer's written instructions, and finished sloped to drain water away from post.
4. Posts Set into Concrete in Voids: Form or core drill holes not less than 5 inches (125
mm) deep and 3/4 inch (20 mm) larger than OD of post. Clean holes of loose material, insert posts, and fill annular space between post and concrete with no shrink, nonmetallic grout, mixed and placed to comply with anchoring material manufacturer's written instructions, and finished sloped to drain water away from post.
3.4 CHAIN-LINK FENCE INSTALLATION
A. Terminal Posts: Locate terminal end, corner, and gate posts per ASTM F 567 and terminal pull posts at changes in horizontal or vertical alignment of 30 degrees or more. The terminal posts will be 2 7/8” diameter embedded within a 36-inch-deep footing 10-inches wide.
B. Line Posts: Space 2 3/8: diameter line posts uniformly at 8 feet on center, embedded within a 36-inch-deep footing 8-inches wide.
C. Post Bracing Assemblies: Install according to ASTM F 567, maintaining plumb position and alignment of fencing. Install braces at end and gate posts and at both sides of corner and pull posts. Locate horizontal braces at midheight of fabric on fences with top rail and at two-thirds fabric height on fences without top rail. Install so posts are plumb when diagonal rod is under proper tension.
D. Top Rail: Install according to ASTM F 567, maintaining plumb position and alignment of fencing. Run rail continuously through line post caps, bending to radius for curved runs and terminating into rail end attached to posts or post caps fabricated to receive rail at terminal posts. Provide expansion couplings as recommended by fencing manufacturer.
E. Chain-Link Fabric: Apply fabric to outside of enclosing framework. Leave 2 inches (50
mm) between finish grade or surface and bottom selvage, unless otherwise indicated. Pull fabric taut and tie to posts, rails, and tension wires. Anchor to framework so fabric remains under tension after pulling force is released.
F. Tension or Stretcher Bars: Thread through fabric and secure to end, corner, pull, and gate posts with tension bands spaced not more than 15 inches (380 mm) o.c.
G. Tie Wires: Use wire of proper length to firmly secure fabric to line posts and rails. Attach wire at one end to chain-link fabric, wrap wire around post a minimum of 180 degrees, and attach other end to chain-link fabric per ASTM F 626. Bend ends of wire to minimize hazard to individuals and clothing.
1. Maximum Spacing: Tie fabric to line posts 12 inches (304 mm) o.c. and to braces 24 inches (609 mm) o.c.
3.5 GATE INSTALLATION
A. General: Install gates according to manufacturer's written instructions, level, plumb, and secure for full opening without interference. Attach fabric as for fencing. Attach hardware using tamper-resistant or concealed means. Install ground-set items in concrete for anchorage. Adjust hardware for smooth operation and lubricate where necessary.
3.6 ADJUSTING
A. Gate: Adjust gate to operate smoothly, easily, and quietly, free from binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Confirm that latches and locks engage accurately and securely without forcing or binding. The gate will be a singular 10-feet wide gate located on the plans.
END OF SECTION
A. The Contractor must be registered/licensed with the State and or county and ensure that all personal are recognized professionals and/or supervised by recognized professional
B. The on-site supervisor shall have at least 5 years’ experience in installing chain link fences and demonstrate ability in both supervision and trades of work utilized to complete the contract.
4.0 Deliverable / Schedule
Deliverables:
Line Item
Description SCHEDULE
0001 Install approximately 404 feet of 6-foot-high chain link fence with a 10 wide man gate.
10/1/2026 to 12/1/2026
CLIN Description Estimated Quantity Pay Unit
Unit Cost Total
0001 West side 6' High Chain Link Fencing (121 ft.)
1 LS $ $
0002 South side 6' High Chain Link Fencing (278 ft.)
1 LS $ $
0003 South side 10' wide swing gate 1 LS $ $
TOTAL $
Work/Task Item Evaluation Notes Pass Fail
Design/layout of fencing system
Project schedule
Worksite safety plan
Site walk to note current conditions
Site cleanup, removal of all trash relating to fence installation activities
Fence product warranties
A. The estimated start work date is October 1, 2026, work shall be completed within 60 calendar days (on or before December 1, 2026. Contractor shall perform work so as not to interfere with Government operations. The Hours of operation shall be from 8:00 a.m. to 4:30 p.m. Monday through Friday (holidays excluded) all hours/schedules must be coordinated with the COR. Contractor should note that work may be performed with Forest Service personnel working in the general area.
B. Contractor must submit a work schedule for the installation of the fencing and the gate
C. Contractor shall Coordinate with the Contracting Officer Representative (COR) and/or
Administrative Officer any electrical power interruptions and work area closures. At least 48 hours’ notice shall be required.
G. Government Furnished Supplies
The Forest Service will deliver to the Contractor the following listed materials, supplies, property or services;
hereinafter referred to as Government-Furnished Items, at the pre-work conference or at a mutually agreeable time. The Contractor shall be liable for all loss, mishandled or the damage of Government-Furnished Items.
Government Furnished Items Quantity All items Located at LFSL
None
H. Contractor’s Key Personnel A. Contractor shall provide an onsite contractor’s representative who will oversee the performance of the work specified in this contract. Contractor shall designate in writing to the Contracting Officer (CO) and COR, the name of the contract representative and an alternate(s) who shall have the authority to act for the Contractor on all contract matters relating to daily operation of this contract.
B. The Contractor’s representative and alternate(s) must be a with a mid-level supervision and operational experience (minimum of 5 years’ experience) as well as be able to read, write, speak, and understand English. Contractor shall notify the CO/COR at least 10 workdays in advance of any subsequent change of personnel in this position. Replacement personnel shall have the same level or better experience as the person being replaced.
I. Security Requirements The Contractor’s personnel will sign in at the front desk daily and will be given temporary passes to access the building’s restrooms and/or parking areas.
J. Performance Requirement Measures
Compliance Inspection / Project Closeout:
1) Wire gauge and mesh size.
2) Wire coating as per specifications.
3) Line post spacing and sizes.
4) Framework strength by checking if post sizes are complying with the specifications.
5) Footing depth and psi concrete are with specifications.
6) Drain rock was used in the post holes at the correct depth.