STATEMENT OF WORK
1. General:
1.1 Project: Shiawassee NWR, 6975 Mower Road, Saginaw Michigan, 48601/ 237110 Water and Sewer Line and Related Structures Construction/Shiawassee NWR HQ.
1.2 On or about Febuary 2022 the refuge staff was notified by the township water department of exsesive water usage which indicated a system leak. The staff took measures to isolate and attempt to located the issue, it apprears the leak is somewhere between the HQ building and the check station. As a temporary fix the water leading to the check station has been shut off. Due to COVID restrictions the building is being used as a temporary office and will be used to facilitate other activities this fall. The restoration of water to this building is a critical compont for the success of these activities.
2. Place of Performance and Period of Performance
2.1 6975 Mower Road, Saginaw Michigan 48601
2.2 PoP - 15 September 2022 – 14 November 2020, earlier completion is authorized.
2.3 Normal duty hours Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.
2.4 Nonduty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin Luther King JR.s’s Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day) need to be approved by the CO.
3. Scope
· 3.1 EXCAVATE AND CONNECT 1.25" WATER LINE FROM EXISTING WATER SERVICE TO HEADQUARTERS BUILDING AND
· INST ALL CURB STOP AND BOX.
· DIRECTIONAL DRILL APPROXIMATELY 300' OF 1.25" HDPE WATER SERVICE LINE INTO SERVICE BUILDING AND
· ENDING IN STORAGE ROOM.
· DIRECTIONAL DRILL 1" HDPE CONDUIT FROM EAST SIDE OF HEADQUARTERS BUILDING TO SERVICE BUILDING FOR FUTURE INTERNET CABLE. (THIS IS A COST SAVING MESSURE FOR A FUTURE PROJECT UNRELATED TO THE WATERLINE)
· REMOVE CONCRETE SLAB IN STORAGE ROOM (APPROXIMATELY 6' X 4') TO RECEIVE WATER LINE AND CONDUIT -
· RESTORE FLOOR.
· INST ALL ¾" WATER METER (SUPPLIED BY TOWNSHIP) AND NECESSARY PIPING TO CONNECT TO EXISTING WATER
· PIPING IN SERVICE BUILDING.
· ALL DISTURBED LAWN AREAS TO BE BACKFILLED AND LEFT AS ROUGH GRADED LAWN SURFACE.
· ALL PERMITS MUST BE OBTAINED.