This is a Statement of Work (SOW) for a gravel supply contract at the Bloomington Lake Trailhead in Bear Lake County, Idaho, managed by the Montpelier Ranger District. The project involves hauling and supplying 850 cubic yards of gravel with gradation T (16402 1" Road Base-Early Pit) for trailhead improvement and temporary traffic control measures. Local traffic will be closed during construction with temporary traffic control in place. The project location is Bloomington Canyon access road #30409 off US Highway 89 in Bloomington, Idaho, at coordinates 42.1495° N, 111.5837° W.

The contract period of performance begins upon issuance of the Notice to Proceed (NTP) and runs for 15 calendar days, with an estimated start date of June 1, 2027. The SOW references an associated contract document for all other terms and conditions, including pricing, payment terms, and additional contractual obligations. Detailed driving directions are provided from the Montpelier Ranger District office (322 N 4th Street, Montpelier, ID 83254) to the project site, including a map showing the route via US Highway 89 south through Bloomington and continuing 7.5 miles on Bloomington Canyon Road (FS Road 30409), then turning left for 3.2 miles to reach the trailhead.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

0415 GAOA SUPP CONST CT TRAIL DEFR MAINT BLOOMINGTON LAKE

TRAILHEAD 3

Description:

Montpelier Ranger District Bloomington Lake Trailhead

Gravel Supply Contract

BRIEF DESCRIPTION OF PROJECT:

The project is located on the Bloomington Canyon access road #30409 off US Highway 89 in Bear Lake County, Idaho.

Project consists of hauling and supplying 850 CY of gravel, gradation T (16402 1” Road Base-Early Pit) for the trail head, as well as temporary traffic control. Local traffic shall be closed during construction with temporary traffic control measures in place.

Location: Bloomington Canyon Trailhead in Bloomington, Bear Lake County, Idaho (42.1495° N, 111.5837° W)

Period of Performance:

Contract time begins on the effective date of the Notice to Proceed (NTP) and runs for 15 calendar days. Estimated time to start work is June 01, 2027.

Reference contract for all other terms and conditions.

Driving Directions: From Montpelier Ranger District, 322 N 4th St, Montpelier, ID 83254 Take US 89 S 16 miles to W Canyon St., in Bloomington, Idaho.

Continue onto Bloomington Canyon Road (FS Road 30409) for approximately 7.5 mi, turn left to stay on Forest Road 30409, 3.2 miles to

Bloomington Lake Trailhead, Forest Rd 816, Preston, ID 83263 @ 42.1495° N, 111.5837° W

STATEMENT OF WORK (SOW)

File details come from the government source that posted it. Updated .