C04 1240LP26Q0199 1449 Revised 09-25-2026 with Clauses and Provisions.pdf

PDF 294 KB Posted

Attached to
GAOA Trujillo Meadows Old Toilet Building Replacement RGNF
Solicitation number
127EAY26Q0199
Issued by

About this file

This is a Request for Quote (RFQ) for the purchase of three commercial vaulted toilets for the Rio Grande National Forest, Conejos Peak Ranger District. The solicitation number is 127EAU26Q0199, issued by the USDA Forest Service, and quotes are due by September 25, 2026, at 5:00 PM Pacific Time. The solicitation is a small business set-aside (100% for small business), with NAICS code 327331 and a size standard of 500 employees. Delivery must occur within 180 days after receipt of order (ARO) to Trujillo Meadows Campground in Del Norte, Colorado, on an F.O.B. Destination basis.

The required toilets must be double vault, brown-colored units with shake shingle roofs, board and batten or barnwood construction, rock bottoms, ADA-compliant design, plastic toilet risers (no urinals), 6-roll toilet paper dispensers, solar vent fans, and chain door straps. All items must have clear traceability to original equipment manufacturers. Evaluation will be based on lowest price technically acceptable criteria, with technical acceptability determined by meeting all salient characteristics and providing adequate documentation. Past performance will be assessed as acceptable, neutral, or unacceptable. Offerors must provide pricing in the attached spreadsheet and submit all required certifications, including Buy American Certificate (Oct 2022) and Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025). A firm-fixed price contract will be awarded to a single offeror. Questions are due by September 30, 2026, at 12:00 PM Pacific Time and should be directed to Mary Bosch at 802-345-9284 or Mary.Bosch@usda.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

40LP

OGDEN UT 84401-2310

324 25TH ST

USDA-FS CSA INTERMOUNTAIN 4

1282AK CODE 16. ADMINISTERED BYCODE

X

X

X

327331

SIZE STANDARD:

100.00 % FOR:SET ASIDE:UNRESTRICTED OR40LP

REQUEST FOR

PROPOSAL

(RFP)

INVITATION

FOR BID (IFB)

10. THIS ACQUISITION ISCODE

REQUEST FOR

QUOTE (RFQ)

14. METHOD OF SOLICITATION

13b. RATING

NORTH AMERICAN INDUSTRY

CLASSIFICATION STANDARD

(NAICS):

SMALL BUSINESS

10/07/2026 1700 PT

09/25/2026

802-345-9284MARY BOSCH

(No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

1240LP26Q0199

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 2 OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

DEL NORTE CO 81132

1055 9TH ST

RIO GRANDE NATIONAL FOREST

USDA FOREST SERVICE

15. DELIVER TO

OGDEN UT 84401-2310

324 25TH ST

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FREE ON BOARD

(FOB) DESTINATION UNLESS

BLOCK IS MARKED

11.

SEE SCHEDULE

12. DISCOUNT TERMS THIS CONTRACT IS A RATED

ORDER UNDER THE DEFENSE

PRIORITIES AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

8(A)

USDA-FS CSA INTERMOUNTAIN 4

WOMEN-OWNED SMALL

BUSINESS (WOSB)

ECONOMICALLY DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

0001 Purchase of three commercial vaulted toilets for 3 EA the Rio Grande National Forest Conejos Peak Ranger District. It is a one-time purchase of a standard vaulted toilet of the style routinely used by the Forest Service. The purchase must be designed for these structures to meet ADA compliance and accessibility requirements.

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

X

DATED

SHANE S. GALLES

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Government Use Only)

OFFER

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT: REFERENCE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 11/2021) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

2 2 of

Toilet Purchase Trujillo Meadows

127EAU26Q0199

Rio Grande National Forest

Statement of Requirement

Vaulted toilets placed in a remote outdoor setting; the exact dimensions are less important than the features. Therefore, the following features are requested: Double vault toilet Brown in color Shake shingle roof, Board & batten, barnwood, or lap walls with rock bottom ADA-Compliant construction plastic toilet riser, no urinal, 6-roll toilet paper dispense, Solar vent fan, Chain door strap. The U.S.

Forest Service will excavate and finalize the sites, so the Contractor will only be required to deliver and place the double vault toilets at the designated areas. The Contractor is not responsible for site preparation, excavation, grading, or finishing. Delivery of three accessible concrete double vault toilets to: Trujillo Meadows Campground.

Schedule of Items

Attachment 2 - FS-Schedule of Items Template GAOA Trujillo Meadows

All items must have clear traceability to the Original Equipment Manufacturer (OEM), Traceability means a clear, complete, documented, and auditable paper trail which traces each step from an OEM or distributor to its current location.

Technical Data -

Technical data and supporting documentation associated with this solicitation are available through the following sources:

1. Solicitation Attachments

The following documents are included as attachments to this solicitation and can be accessed via the “Attachments/Links” section of the posting.

• Attachment 1 - SOW GAOA Toilet Replacements Trujillo Meadows

• Attachment 2 - FS-Schedule of Items Template GAOA Trujillo Meadows

Federal Acquisition Regulation (FAR) and United States Department of Agriculture

Acquisition Regulation (AGAR) Clauses and Provisions

The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.

Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The

System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference Feb 1998

This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025)

☐ Alternate I (Nov 2025) of 52.212-4

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(Jan 2017)

52.222-50 Combating Trafficking in Persons (Nov 2025)

☐ Alternate I (Nov 2025) of 52.222-50

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024)

52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023)

52.233-3 Protest After Award (Sep 2025)

52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025)

52.240-91 Security Prohibitions and Exclusions (Nov 2025)

☐ Alternate I (Nov 2025) of 52.240-91

52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)

The following clauses are applicable if checked:

☐ 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) with Alternate I

(Nov 2021) of 52.203-6

☐ 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021)

☐ 52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011

☒ 52.204-13 System for Award Management—Maintenance (Nov 2025)

☐ 52.204-91 Contractor identification (Nov 2025)

☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025)

☐ 52.209-9 Updates of Publicly Available Information Regarding Responsibility

Matters (Sep 2025)

☐ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025)

☐ 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov

2025)

☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025)

☐ Alternate I (Mar 2020).

☐ 52.219-8 Utilization of Small Business Concerns (Nov 2025)

☐ 52.219-9 Small Business Subcontracting Plan (Nov 2025)

☐ Alternate III (Nov 2025) of 52.219-9.

☐ Alternate IV (Nov 2025) of 52.219-9

☐ 52.219-14 Limitations on Subcontracting (Nov 2025)

☐ 52.219-16 Liquidated Damages—Subcontracting Plan (Nov 2025)

☐ 52.219-33 Nonmanufacturer Rule (Nov 2025)

☒ 52.222-3 Convict Labor (June 2003)

☒ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025)

☐ 52.222-35 Equal Opportunity for Veterans (Nov 2025)

☐ Alternate I (Jul 2014) of 52.222-35

☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025)

☐ Alternate I (Jul 2014) of 52.222-36

☐ 52.222-37 Employment Reports on Veterans (Nov 2025)

☐ 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010

☐ 52.222-41 Service Contract Labor Standards (Aug 2018)

☐ 52.222-42 Statement of Equivalent Rates for Federal Hires (May 2014)

This Statement is for Information Only:

It is not a Wage Determination

Employee Class Monetary Wage -- Fringe Benefits

☐ 52.222-43 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment

(Multiple Year and Option Contracts) (Aug 2018)

☐ 52.222-44 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment

(May 2014)

☐ 52.222-51 Exemption from Application of the Service Contract Labor Standards to Contracts for

Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014)

☐ 52.222-53 Exemption from Application of the Service Contract Labor Standards to Contracts for

Certain Services-Requirements (Nov 2025)

☐ 52.222-54 Employment Eligibility Verification (Nov 2025)

☐ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)

☒ 52.222-90 Addressing DEI Discrimination by Federal Contractors (Apr 2026)

☐ 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Nov

2025)

☐ 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items

(May 2008)

☐ Alternate I (May 2008) of 52.223-9

☐ 52.223-11 Ozone-Depleting Substances and High Global Warming Potential

Hydrofluorocarbons (Nov 2025)

☐ 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air

Conditioners (Nov 2025)

☒ 52.223-23 Sustainable Products and Services (Nov 2025)

☐ 52.224-3 Privacy Training (Jan 2017)

☐ Alternate I (Jan 2017) of 52.224-3

☒ 52.225-1 Buy American-Supplies (Nov 2025)

☐ Alternate I (Oct 2022) of 52.225-1

☐ 52.225-3 Buy American--Free Trade Agreements--Israeli Trade Act (Nov 2025)

☐ Alternate II (Nov 2025) of 52.225-3.

☐ Alternate III (Nov 2025) of 52.225-3.

☐ Alternate IV (Oct 2022) of 52.225-3

☐ 52.225-5 Trade Agreements (Nov 2023)

☐ 52.225-19 Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or Consular Mission outside the United States (May 2020)

☐ 52.225-26 Contractors Performing Private Security Functions Outside the United States (Oct

2016)

☐ 52.226-4 Notice of Disaster or Emergency Area Set-Aside (Nov 2007)

☐ 52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area (Aug 2025)

☐ 52.229-12 Tax on Certain Foreign Procurements

☐ 52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services

(Nov 2021)

☐ 52.232-30 Installment Payments for Commercial Products and Commercial Services

(Nov 2021)

☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018)

☐ 52.232-34 Payment by Electronic Funds Transfer—Other Than System for Award Management

(Jul 2013)

☐ 52.232-36 Payment by Third Party (Nov 2025)

☐ 52.237-2 Protection of Government Buildings, Equipment, and Vegetation (Apr 1984)

☐ 52.237-3 Continuity of Services (Jan 1991)

☐ 52.240-92 Security Requirements (Nov 2025)

☐ 52.240-93 Basic Safeguarding of Covered Contractor Information Systems (No 2025)

☐ 52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2025)

☐ Alternate I (Apr 2023) of 52.247-64.

☐ Alternate II (Nov 2021) of 52.247-64

Other Applicable Clauses

52.232-90 Fast Payment Procedures (Nov 2025)

52.247-34 F.O.B. Destination (Jan 1991)

AGAR Clauses

452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (May

2026)

(a) By entering into this contract, the contractor certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.

(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of

1964, or the Equal Protection principles of the U.S. Constitution, and the contractor and any subcontractor or teaming partner will not do so for the duration of the contract.

(b) If the contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil

Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology

Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to contractor’s compliance with the above requirements and/or eligibility for the contract may subject the contractor to liability under the False

Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) The contractor must include the provisions of this clause in all subcontract solicitations.

(g) Failure on the part of the contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.

(End of Clause)

452.204–70 Modification for Contract Closeout (Apr 2026)

(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting

Officer (Contracting Officer) may issue a unilateral modification for de-obligation. The contractor will receive a copy of the modification but is not required to provide a signature. The Contracting

Officer will immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(b) For commercial contracts not exceeding the simplified acquisition procedure threshold under

FAR 12.001(c), if more than $1,000 in unliquidated funds remain at closeout, the Contracting

Officer will issue a bilateral de-obligation modification. Only the modification requires the contractor’s signature, though a Release of Claims may be requested. If the required documents are not returned within 60 days, the Contracting Officer will issue a unilateral modification and proceed with closeout once performance is complete, acceptance is confirmed, and final payment is made.

(c) For all other non-commercial or non–cost‑reimbursement contracts, if more than $1,000 in unliquidated funds remain at closeout, the Contracting Officer will issue a bilateral de-obligation modification and a Release of Claims, both requiring contractor signature. If these documents are not returned within 120 days, the Contracting Officer will issue a unilateral modification u and proceed with closeout upon completion of performance, acceptance, and final payment.

(End of Clause)

Solicitation Information

Award Type

It is anticipated that a firm-fixed price contract will be awarded as a result of this synopsis/solicitation.

The Government intends to make one award from this solicitation. Therefore, to be considered responsive, contractors must submit pricing for all items.

Evaluation and Basis for Award

Evaluation Criteria

Price: Any quantity price discounts and discounts for prompt payment should be included in this section. The offeror shall provide pricing as requested in the attached spreadsheet titled “Attachment

2 - FS-Schedule of Items Template GAOA Trujillo Meadows”.

Total price evaluation for the base period. Failure to quote all items will render the quote non-responsive. The offeror’s quotation will be evaluated in accordance with FAR 12.204, to determine if it is fair and reasonable.

Technical Acceptability: The United States Department of Agriculture (USDA) has a requirement for the following items on a brand name or equal basis.

The Technical capability will be evaluated to determine an overall rating of “acceptable” or

“unacceptable”. To be considered technically acceptable, the quoted product must:

1. Meet or exceed all salient characteristics of the solicitation.

2. Include sufficient descriptive literature or documentation (e.g., product specifications, datasheets, or brochures) to demonstrate how the proposed product meets or exceeds the required salient characteristics.

3. Be available for delivery within the timeframe specified in the solicitation.

Failure to provide adequate documentation or to meet the required salient characteristics will result in a determination of technical unacceptability, and the quotation will not be considered for award.

Past Performance:

The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources or the Contractor Performance Assessment Reporting System

(CPARS) to determine if the Contractor has acceptable or neutral Past Performance. Past

Performance will be evaluated using the following rating system:

• Acceptable: The contractor shows a demonstrated ability to meet contract requirements in prior or current contracts, including quality of work, timeliness, cost control, business relations, and adherence to contract terms.

• Neutral: Offeror does not have a past performance record.

• Unacceptable: The contractor has a documented history of failing to meet contract requirements, including poor quality, missed deadlines, cost overruns, lack of responsiveness, or unethical behavior.

Evaluation Method:

The Government will evaluate quotations based on the lowest price technically acceptable criteria.

Only the lowest priced offer will be evaluated for Technical Acceptability. Should the lowest priced offer not receive an acceptable technical or past performance rating, the process will continue in order of lowest priced offer until the lowest price, technically acceptable offer with acceptable or neutral past performance is identified.

Delivery Information

F.o.b. destination, is requested as the F.O.B. point for all deliverables.

All offers will be considered F.O.B. Destination unless F.O.B. origin is specified AND estimated shipping costs are included.

The USDA requires delivery of all items within 180 days ARO. Early deliveries will be accepted with advanced notice.

Shipping Instructions:

Items shall be shipped to the following address:

See Attachment 1 - SOW GAOA Toilet Replacements Trujillo Meadows for delivery information.

52.252-1 Solicitation Provisions Incorporated by Reference Feb 1998

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Nov

2025)

FAR 52.212-1 is amended as follows:

Period for acceptance of offers.

The Offeror agrees to hold the prices in its offer firm for 90 calendar days from the date specified for receipt of offers.

Questions

Questions shall be submitted via email to Mary.Bosch@usda.gov with Solicitation Number and

Questions in the Subject line, and are due no later than September 30, 2026, at 12:00 PM Pacific

Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email.

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality

Agreements or Statements-Representation (Jan 2017)

52.209-2 Prohibition on Contracting with Inverted Domestic Corporations - Representation

(Sep 2025)

52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony

Conviction under any Federal Law (Sep 2025)

52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025)

The following provisions are applicable if checked:

☐ 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal

Transactions (Sep 2024)

☒ 52.204-7 System for Award Management—Registration (Nov 2025)

☐ Alternate I (Nov 2025) to 52.204-7

☐ 52.204-90 Offeror Identification (Nov 2025)

☐ 52.207-6 Solicitation of Offers from Small Business Concerns and Small Business Teaming

Arrangements or Joint Ventures (Multiple-Award Contracts) (Aug 2024)

☐ 52.209-12 Certification Regarding Tax Matters (Oct 2025)

☐ 52.219-2 Equal Low Bids (Nov 2025)

☒ 52.222-18 Certification Regarding Knowledge of Child Labor for Listed End Products (Feb

2021)

☐ 52.222-48 Exemption from Application of the Service Contract Labor Standards for

Maintenance, Calibration, or Repair of Certain Equipment–Certification (Nov 2025)

☐ 52.222-52 Exemption from Application of the Service Contract Labor Standards for Certain

Services-Certification (Nov 2025)

☐ 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Oct 2020)

☐ 52.223-4 Recovered Material Certification (May 2008)

☒ 52.225-2 Buy American Certificate (Oct 2022)

☐ 52.225-4 Buy American-Free Trade Agreements-Israeli Trade Act Certificate (Nov 2025)

☐ 52.225-6 Trade Agreements-Certificate (Feb 2021)

☐ 52.226-3 Disaster or Emergency Area Representation (Nov 2007)

☐ 52.229-11 Tax on Certain Foreign Procurements—Notice and Representation (Jul 2025)

Other Applicable FAR Provisions

52.225-18 Place of Manufacture (Aug 2018)

AGAR Provisions

452.203-70 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Certification (Dec

2025)

(a) By submission of its offer, the offeror certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution.

(2) Neither it nor any proposed subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of

1964, or the Equal Protection principles of the U.S. Constitution.

(b) If the offeror participates in, facilitates, or funds programs that implicate Title VI of the Civil

Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, by submission of its offer, the offeror certifies that it is compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from

Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and

Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The offeror affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the offeror will not be eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to offeror’s compliance with the above requirements and/or eligibility for the contract may subject the offeror to liability under the False

Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) Failure on the part of the offeror or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate the contract for default.

(End of Provision)

NOTICE FOR FILING AGENCY PROTESTS

United States Department of Agriculture (USDA) Protest Procedures

The United States Department of Agriculture (USDA) is committed to fair, transparent, and efficient acquisitions. Interested parties with concerns about this solicitation are encouraged to seek resolution through the following USDA procedures.

Tier 1: Contracting Officer Concern Resolution

Submission: Interested parties with concerns about either the solicitation or subsequent award should first submit their concern directly to the Contracting Officer, providing sufficient detail to allow the Contracting Officer to understand and assess the issue.

Process: The Contracting Officer will review the concern, seek clarification as needed, and engage with the interested party to attempt prompt resolution.

Review Timeline: The Contracting Officer will make every effort to provide a response or resolution within 10 business days of receiving the concern.

Effect on Award or Performance: Tier 1 engagement is not considered an official notification of filing an agency protest and does not pause solicitation deadlines, delay award decisions, or suspend contract performance.

Next Steps: If the matter cannot be resolved at Tier 1, the interested party may file a written agency protest under Tier 2.

USDA encourages all parties to seek resolution with the Contracting Officer before filing an agency protest.

Tier 2: Agency Protest

If concerns cannot be resolved at Tier 1, an interested party may file a written agency protest with either the Contracting Officer or the USDA Independent Review Authority. The decision by the

USDA Independent Review Authority is an alternative to a decision by the Contracting Officer. The

USDA Independent Review Authority will not consider an appeal of the Contracting Officer’s decision on an agency protest.

The protest must state whether the protester elects review by the Contracting Officer, by the UDSA

Independent Review Authority. If no election is stated, the Contracting Officer will decide the protest.

Required Information: Protests shall include the information set forth in FAR 33.104-4 (a)(3).

Failure to submit the required information may result in a delay or dismissal of the protest.

Submission: Agency protests should be submitted electronically to SPE.inquiry@usda.gov and the

Contracting Officer.

Timeliness: Protests must be filed within the timeframes specified in FAR 33.104.

Effect on Award or Performance: Contract awards or performance will be suspended during the protest period unless justified in writing for urgent and compelling reasons or determined to be in the best interest of the Government.

Review Timeline: USDA strives to resolve agency-level protests within 35 business days of receipt.

Election of Forum: By filing a protest with USDA, the protesters agree not to file a protest on the same matter with the Government Accountability Office (GAO) or any other external forum while the agency protest is pending. If such a protest is filed externally, the USDA agency protest will be dismissed.

mailto:SPE.inquiry@usda.gov

Questions: Questions regarding this notice or protest procedures should be directed to the

Contracting Officer identified in this solicitation.

Quote Due Date: Quotes are due to PPS.Proposals@usda.gov by the date and time specified on the SF-1449.

mailto:PPS.Proposals@usda.gov

File details come from the government source that posted it. Updated .