C02_01_Pre-Solicitation_Synopsis_with_PWS_1.pdf
PDF 740 KB Posted
- Attached to
- UFO Pump Relocate Project
- Solicitation number
- 140R1726Q0046
About this file
This is a Presolicitation Notice and Draft Performance Work Statement for the UFO Pump Relocation Project issued by the U.S. Bureau of Reclamation, Umatilla Field Office.
The requirement involves relocating a Fairbanks Morse Model 36XHC6927UW250 three-stage vertical pump (31 feet long, 30,000 lbs) approximately 10 feet from its current position at the Columbia River Pumping Plant near Hermiston, Oregon, and installing a new 2,500-HP inverter-duty VFD motor. The scope includes disconnecting the current synchronous motor and pump, providing a new flange gasket, relocating equipment, reinstalling the pump to the manifold and pump base, ensuring proper motor-to-pump alignment and coupler adjustments, and conducting trim balancing. The contractor must provide all equipment, labor, and materials necessary for completion. The period of performance is two weeks from contract award, with work to be performed in Hermiston, Oregon (coordinates: 45.922865, -119.122338). The requirement is set aside for small businesses and is classified under PSC N043 (Installation of Equipment – Pumps and Compressors) and NAICS 811310 (Commercial and Industrial Machinery and Equipment Repair). Four deliverables are required: a Lift & Rigging Plan (due minimum 5 business days prior to lifting), an Alignment Report (due within 3 business days after alignment completion), a Trim Balance Report (due within 3 business days of completion), and an Installation Verification Report (due within 5 business days of installation completion). The Contracting Officer is Jeri L. Wahl, and the Contract Specialist is Brendan Koop (brendan_koop@ios.doi.gov).
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Presolicitation Notice
Purchase Request Number: 44049589, UFO Pump Relocation Project
This Presolicitation Notice is drafted in accordance with FAR 5.101(c).
1. Point of Contact
a. Name: Brendan Koop, Contract Specialist.
b. Email: brendan_koop@ios.doi.gov.
c. Address: 1150 N Curtis Road, Boise, Idaho, 83706.
d. Contracting Officer: Jeri L. Wahl (Lynn); jeri_wahl@ios.doi.gov.
2. Set-Aside
a. This requirement will be set aside for a total small business.
3. Codes for Services
a. PSC: N043; Installation of Equipment – Pumps and Compressors
b. NAICS: 811310; Commercial and Industrial Machinery and Equipment (except
Automotive and Electronic) Repair.
4. See attached Draft Performance Work Statement (PWS) for the scope of this requirement.
5. Place of Performance
a. Hermiston, Oregon.
6. Period of Performance
a. Two weeks from contract award.
All responsible sources may submit a quotation which will be considered for award.
PERFORMANCE WORK STATEMENT (PWS)
U.S. Bureau of Reclamation – Umatilla Field Office
UFO Pump Relocation Project
1. Background The Bureau of Reclamation, Umatilla Field Office located in Hermiston Oregon, has a requirement to move the #2 Fairbanks Morse 3 stage vertical pump which is currently in the Government’s possession and in operation, located approximately 10 feet from the location it needs to be installed. The contractor will also be responsible for having it brought to operational capacity.
Description of the Government furnished components
• Pump: Fairbanks Morse, Model# 36XHC6927UW250, and is Approximately 31 feet long. Weight:
30,000 lbs.
• Motor: U.S. Motor, Inverter Duty Weight: 20,600 lbs.
2. Scope
The contractor shall provide all equipment, labor, and materials necessary to complete the scope of this requirement. This requirement is to disconnect Pump #2 (Fairbanks Morse Model 36XHC6927UW250) from its current operation and reinstall the pump in a new position approximately 10 feet away, disconnect the currently operational synchronous motor and relocate it to a position where it will not be operational, install a 2,500‑HP inverter‑duty VFD motor, align and couple it, and conduct motor trim balancing.
3. Period of Performance
Two weeks from contract award.
4. Place of Performance
The pump is located at the Columbia River Pumping Plant near Hermiston Oregon off HWY 730 (next to Sand Station Park). The coordinates are latitude: 45.922865, longitude: -119.122338.
5. Tasks
a) Pump and Motor Relocation.
Contractor will be responsible for:
• Unbolting and removing the current motor from the pump, a spare motor pedestal will be provided, the spare motor pedestal is 60 feet from current pump location. The pump motor will have electrical, RTD’s and vibration probes disconnected by Reclamation personnel.
• Unbolting and removing the pump from the manifold and pump base.
• Supplying a new flange gasket for the pump to manifold flange.
• Relocate pump and motors in accordance with Section 2 of this document.
b) Installation After relocating the pump and motor the contractor will:
• Secure the pump to the manifold and pump base with the new flange gasket.
• Re-install the VFD motor ensuring proper alignment and coupler adjustments.
Draft
• Trim balance the motor. Reclamation personnel will complete electrical hook up, reconnect the RTD, and vibration probes.
6. Deliverables
Deliverable
Description / Required Content
Due Date Acceptance Criteria
Lift & Rigging Plan
Contractor’s plan detailing crane configuration, rigging method, equipment load ratings, safety controls, and sequencing for pump/motor removal and installation.
Minimum 5 business days prior to lifting operations
Meets OSHA/ASME standards; includes all required load calculations and safety controls.
Alignment Report
Documentation of final motor-to-pump alignment, including pre-alignment readings, final readings, tolerances, and verification that OEM specifications were met.
Within 3 business days after alignment completion
Alignment readings fall within OEM tolerances;
complete dataset provided.
Trim Balance Report
Vibration/trim balancing data including baseline vibration values, corrective actions/weights added, final vibration levels, and confirmation of OEM compliance.
Within 3 business days of trim balancing
Final vibration readings meet OEM specifications;
report includes all required measurements.
Installation Verification Report
Confirmation that pump and motor were installed correctly, including torque verification, gasket installation, coupler fit, and visual inspection of mechanical connections.
Within 5 business days of installation
All required checkpoints completed and documented; no deficiencies noted.
7. Performance Requirement Summary
Performance Requirement Summary Performance Requirement
Method of Surveillance
Acceptable Quality Level
(AQL)
Performance Standards (PRS) Performance Measurement
Services necessary to install pump and motor
COR
Inspection After Task Completion
Successful testing and operation of pump and motor;
contractor also submits all deliverables within the timeframes stated in section 6 of this PWS.
Fully operational prior to two (2) weeks after award
COR inspection that 100% of the task has been achieved