C.04.01 Abstract of Bids W912DR23B0015.pdf
PDF 331 KB Posted
- Attached to
- Basin 3 and 4 Flocculation and Sedimentation Improvements at Washington Aqueduct Division
- Solicitation number
- W912DR23C0030
About this file
This abstract of bids summarizes offers received in response to Solicitation Number W912DR23B0015 for the Basin 3 and 4 Flocculation and Sedimentation Improvements project at the Washington Aqueduct Division. Six offers were received for the base bid, ranging from $20.8 million to $28.8 million. The independent government estimate for the base bid was $21.5 million. The project involves modifications to sluice gates, ladders, and inspection flumes; replacement of flocculators, residuals collectors and valves, flush piping, and yard piping; and repairs to handrails, stairs, cracks, spalls, and degraded concrete surfaces. The Department of the Army Corps of Engineers Engineering District Baltimore will award Contract Number W912DR23C0030 for this project.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3. DATE OPENED PAGE
8/10/2023 1 of 1
4. ISSUING OFFICE Name and title of Certifying Official (Type) Ryan Fernandez - Contracting Officer
I CERTIFY that I have opened, read, and recorded on this abstract all offers Signature Date Signed 08/10/2023 received in response to this solicitation.
Contracting Officer: RYAN FERNANDEZ
5. PROJECT TITLE
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F.)
A. HIRED LABOR
B. REASONABLE CONTRACT B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) (Without Profit)
X C. REASONABLE CONTRACT C. Amendment Acknowledged C. Amendment Acknowledged C. Amendment Acknowledged (Including Profit) Yes Yes Yes Yes Yes
7A. 7B. 7C. D. E. F. E. F. E. F. E. F. E. F. E. F.
ITEM DESCRIPTION OF OFFERED ITEM EST. UNIT UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED
No. QUANTITY PRICE AMOUNT IGE PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
All costs in connection with Items 0001AA –
0001AH.
19,304,278.00$ 19,820,300.00$ 25,401,000.00$ 16,746,464.00$ 19,757,618.00$ 17,675,000.00$
0001AA
Basins 3 and 4 sluice gate modifications, ladder replacement, inspection flume replacement and field painting complete as shown on drawings and specified.
1 JOB LS 363,285.00$ 900,000.00$ 50,000.00$ 400,000.00$ 393,000.00$ 60,000.00$
0001AB
Basins 3 and 4 flocculator replacement complete as shown on drawings and specified.
1 JOB LS 10,576,973.00$ 5,000,000.00$ 3,500,000.00$ 3,550,000.00$ 5,115,000.00$ 5,250,000.00$
0001AC
Basins 3 and 4 residuals collector modifications and residuals valve replacement complete as shown on drawings and specified.
1 JOB LS 6,150,963.00$ 5,000,000.00$ 3,300,000.00$ 3,450,000.00$ 4,484,000.00$ 5,150,000.00$
0001AD
Basin 3 and 4 flush piping replacement complete as shown on drawings and specified.
1 JOB LS 1,679,872.00$ 1,000,000.00$ 1,400,000.00$ 645,000.00$ 879,000.00$ 2,265,000.00$
0001AE
Yard piping modifications complete as shown on drawings and specified.
1 JOB LS 379,022.00$ 250,000.00$ 125,000.00$ 500,000.00$ 223,000.00$ 360,000.00$
0001AF
Basins 1 and 2 handrail and stair repairs complete as shown on drawings and specified.
1 JOB LS 19,479.00$ 150,000.00$ 14,000.00$ 50,000.00$ 23,000.00$ 30,000.00$
0001AG
Basin 3 and 4 handrail modifications complete as shown on drawings and specified.
1 JOB LS 19,168.00$ 600,000.00$ 37,000.00$ 105,000.00$ 80,000.00$ 610,000.00$
0001AH
All other costs in connection with the construction of the Basins 3&4 Flocculation/Sedimentation Improvements Project, complete as shown on drawings and specified, but exclusive of work covered under all other CLINs and SubCLINs.
1 JOB LS 115,516.00$ 6,920,300.00$ 16,975,000.00$ 8,046,464.00$ 8,560,618.00$ 3,950,000.00$
Repair of Cracks in Dry Slabs complete as shown on drawings and specified
810 Linear Foot 68.39$ 55,395.90$ 200.00$ 162,000.00$ 193.00$ 156,330.00$ 107.00$ 86,670.00$ 89.00$ 72,090.00$ 165.00$ 133,650.00$
Repair of Cracks in Wet Walls or Slabs complete as shown on drawings and specified
5,410 Linear Foot 68.51$ 370,639.10$ 250.00$ 1,352,500.00$ 261.00$ 1,412,010.00$ 102.00$ 551,820.00$ 85.00$ 459,850.00$ 265.00$ 1,433,650.00$
Repair of Spalls on Top of Slabs complete as shown on drawings and specified
6,154 Square Foot 73.91$ 454,842.14$ 100.00$ 615,400.00$ 93.00$ 572,322.00$ 134.00$ 824,636.00$ 111.00$ 683,094.00$ 200.00$ 1,230,800.00$
BALTIMORE, MD 21201
ABSTRACT OF BIDS - CONSTRUCTION 2. DATE ISSUED1. SOLICITATION NUMBER
6. NUMBER OF AMENDMENTS ISSUED: 2
HPM, Inc. 9781 Meridian Blvd, Suite 120
Englewood,CO 80112
Bid Bond 20% Bid Bond 20% Bid Bond 20% Bid Bond 20% C. Amendment Acknowledged C. Amendment Acknowledged
CPP Construction Company, Inc.
26 North Summit Ave
Gaithersburg, MD 20877
Kokosing Industrial, Inc.
6235 Westerville Road Westerville, OH 43081
W.M. Schlosser Company, Inc.
2400 51st Place
Hyattsville, MD 20781
American Contracting & Evironmental Services, Inc.
10330 Old Columbia Road (Suite 102) Columbia, MD 21046
Bid Bond 20%
6/21/2023W912DR22B0015
Basin 3 & 4 Flocculation and Sedimentation Improvements Washington Aqueduct Division, Washington D.C.
No. 5
BALTIMORE DISTRICT, CORPS OF ENIGNEERS
2 HOPKINS PLAZA
9. OFFERS
No. 1 No. 2 No. 3 No. 4
Repair of Spall on Underside of Slab, Slab Corners or Vertical Surfaces complete as shown on drawings and specified
6,420 Square Foot 134.78$ 865,287.60$ 100.00$ 642,000.00$ 99.00$ 635,580.00$ 156.00$ 1,001,520.00$ 130.00$ 834,600.00$ 255.00$ 1,637,100.00$
Repair of Degraded Concrete Surfaces complete as shown on drawings and specified
3550 Square Foot 45.16$ 160,318.00$ 60.00$ 213,000.00$ 56.00$ 198,800.00$ 59.00$ 209,450.00$ 49.00$ 173,950.00$ 210.00$ 745,500.00$
Remove and Replace Expansion Joints on Dry Side of Walls or Slabs complete as shown on drawings and specified
1035 Linear Foot 37.29$ 38,595.15$ 100.00$ 103,500.00$ 97.00$ 100,395.00$ 36.00$ 37,260.00$ 114.00$ 117,990.00$ 215.00$ 222,525.00$
Remove and Replace Expansion Joints on Wet Side of Walls or Slabs complete as shown on drawings and specified
4963 Linear Foot 48.33$ 239,861.79$ 100.00$ 496,300.00$ 62.00$ 307,706.00$ 260.00$ 1,290,380.00$ 216.00$ 1,072,008.00$ 185.00$ 918,155.00$
Remove and Replace Expansion Joints on Basin 3 & 4 Intermediate Slabs complete as shown on drawings and specified
300 Linear Foot 38.95$ 11,685.00$ 140.00$ 42,000.00$ 139.00$ 41,700.00$ 96.00$ 28,800.00$ 80.00$ 24,000.00$ 115.00$ 34,500.00$
TOTAL ESTIMATED BASE BID AMOUNT 21,500,902.68$ 23,447,000.00$ 28,825,843.00$ 20,777,000.00$ 23,195,200.00$ 24,030,880.00$
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. Prescribed by GSA-FAR(48 CER)53.236-1 OPTIONAL FORM 1419 (11-88)