BSS_SOW_Finishing.docx

DOCX document 32 KB Posted

Attached to
Bearing Support Structure (BSS) Inseperable Assembly Finishing
Solicitation number
Not on record
Issued by

About this file

This document is a Statement of Work (SOW) for the finishing work required on the Bearing Support Structure (BSS) Inseparable Assembly for the Columbia (CLB) Class submarine propulsors. The work includes completing a syntactic fill, final machining, paint, and preservation for each BSS Assembly. Previously, these finishing steps were performed by the Naval Foundry and Propeller Center (NFPC), but this effort aims to complete the work outside of a government facility.

The SOW requires the contractor to develop an Assembly and Manufacturing (A&M) Plan, project schedule, and adhere to program management requirements. The contractor must demonstrate their capability to successfully complete the required manufacturing steps prior to beginning the BSS finishing process. The finished BSS Assemblies must be delivered within 6 months of receiving the BSS Inseparable Assembly. The work is being procured by the Department of the Navy, Naval Sea Systems Command (NAVSEA).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BSS FO

Section C - Descriptions and Specifications

STATEMENT OF WORK

1. SCOPE. The Advanced Propulsor Management Office (Code 808) in the Naval Architecture and Engineering Department (Department 80) of the Naval Surface Warfare Center, Carderock Division (NSWCCD) is responsible for Engineering and Manufacturing Development (EMD) of US Navy COLUMBIA (CLB) Class submarine propulsors. The Bearing Support Structure (BSS) Assembly is a key component. The BSS serves as the main structural interface between the propulsor and submarine. Previously, the finishing of a BSS Inseparable Assembly to the delivered Assembly was completed by the Naval Foundry and Propeller Center (NFPC). This effort looks to complete the Inseparable assembly finishing outside of a government facility.

1. REFERENCES

1. COLUMBIA Class BSS Assembly, DWG C24521100 Rev C

1. COLUMBIA Class BSS Inseparable Assembly, DWG C24521200C

1. DoDI 5230.24, Distribution Statements on Technical Documents, dated August 23, 2012

1. REQUEST FOR DEVIATION/WAIVER (RFD/RFW), DD 1694

1. Propulsor Paint and Preservation Core Manual, P24500000

1. Propulsor Paint and Preservation Manual, Rev S945-A4-TSM-010

1. TECHNICAL REQUIREMENTS

2. ASSEMBLY AND MANUFACTURING (A&M) PLAN DEVELOPMENT. The contractor shall develop and submit to the Government an A&M Plan, CDRL A009 (A&M Plan), reference 2.1 and may be submitted in phases. The A&M plan shall be submitted for information and the Government will concur that the contractor has sufficiently matured their manufacturing plan prior to executing any manufacturing steps.

0. The contractor shall submit a high-level A&M strategy outlining their approach to the BSS finishing, including syntactic fill, final machining, and paint. This plan is to assume a BSS Inseparable Assembly is provided as Government Furnished Material (GFM). This strategy shall include an outline for the detailed A&M plan.

0. The A&M Plan is inclusive of major technical disciplines requiring design development and associated drawings in order to prepare for BSS Assembly fabrication, CDRL A010 (Technical Data Package).

0. The contractor shall deliver the A&M Plan and associated drawings (CDRLs A009 and A010) with Unlimited Data Rights or Government Purpose Rights, as applicable.

2. PROJECT SCHEDULING. Design and develop a graphical report depicting a composite schedule of all planned technical activities and milestones, CDRL A011 (Project Planning Chart). This data item shall be submitted as an appendix to the Monthly Status Report (MSR), SOW paragraph 4.2.

1. Design the logical sequence of activities (also referred to as a “Gantt Chart”) to correlate with the A&M Plan specified in Paragraph 3.1. Reference CDRL A011 Block 16 format and frequency of initial submittals.

1. Gantt chart essential elements shall include discrete tasks and activities consistent with authorized work and relationships for contract completion by identifying items from Contract Award through completion of each Contract Line Item (CLIN). Further, identify the critical path, all major events, and program milestones.

1. Activities shall have a valid total slack or float identified for critical path analysis and impact analysis from delays.

1. Subordinate level elements (3rd thru 5th level or greater activities) shall not exceed 15 work days in duration. The contractor shall propose any exceptions to this parameter to the Contracting Officer’s Representative (COR) for approval in writing. The Contractor may implement any exceptions only upon approval in writing by the COR.

1. Plan and perform schedule risk assessments (SRAs) as required by the Government; determine statistically defensible task and activity results and furnish risk-mitigating recommendations in a briefing format to the Government, CDRL A008 (Presentation Material).

1. The contractor shall participate in Government-led data gathering events (“data calls”) and third party SRAs. However, the Government may elect to participate in the Contractor’s SRA event and will provide advance notice in writing.

2. ASSEMBLY AND MANUFACTURING PLAN EXECUTION.

2. END-ITEM DELIVERABLE.

0. Prior to beginning the BSS finishing process, the vendor shall demonstrate their ability to successfully complete the required manufacturing steps. For the syntactic fill, the vendor must provide OQE that they have previously poured an sealed an equal or greater volume of propulsor syntactic foam (>50 ft3) in a closed cavity. The vendor must also provide OQE of their ability to meet the machining tolerances of reference 2.1 on an active machining center. The vendor shall also maintain an active certification to paint propulsor components per either reference 2.5 or 2.6.

0. Finish each CLB BSS Assembly form a GFM CLB BSS Inseparable Assembly in accordance with the submitted chapters of the A&M Plan, reference 2.1.

0. Observe and report regular updates of planned-to-actual work progress utilizing the graphical report developed in Paragraph 3.2., CDRL A011 (Project Planning Chart). This data item shall be submitted as an appendix to the MSR, SOW paragraph 4.2.

0. Deliver the CLB BSS Assembly in accordance with the specified requirements in reference 2.1.

2. WORK-IN-PROGRESS (WIP) MANAGEMENT.

1. The contractor may deviate from the submitted A&M plan, so long as there is no change to the final conforming component, and no downstream manufacturing steps are impacted. These changes are categorized as minor and the contractor shall inform the government of minor deviations in writing.

1. Process requests for waivers, deviations, or technical specification changes by submitting standard form DD 1694, reference 2.3. The contractor may propose alternative format for processing waivers, deviations or technical specifications for Government approval.

1. PROGRAM MANAGEMENT REQUIREMENTS

3. PROGRAM MANAGEMENT ACTIVITIES. The Contractor shall perform Program Management (PM) services including the organization, planning and interdependencies, schedule, implementation, control, analysis, compliance, and reporting of all contractual elements to achieve technical, schedule and financial objectives. Develop and implement a PM plan to effectively and efficiently execute Delivery Order requirements such as methodology, procedures, and templates, CDRL A001 (PM Plan). Among other PM duties, the contractor shall:

0. Maintain a clear line of authority among all organizational elements, including management of authorized Subcontractors.

0. Designate primary and alternate Contractors’ Points of Contact (CPOCs).

0. Arrange for access to authorized Subcontractor facilities and enable communication at all lower tiers.

0. Investigate and record facts and observations; and communicate any perceived or actual issues related to quality, schedule, cost control, management, utilization of small business, and regulatory compliance that if unresolved, would adversely affect performance and assessment.

0. Contact the COR for guidance or escalation of issues.

3. MONTHLY STATUS REPORTING. The Contractor shall observe and record work progress and status of the program, assigned tasks, costs, and existing or potential problem areas in narrative format, CDRL A002 (MSR). The following activities and resulting data items shall be submitted as appendices to the MSR.

1. MONTHLY EXPENDITURE REPORTING. Observe and record all direct and indirect expenditures for both planned and actual transactions including labor hours against baseline values, and estimates of time and cost at completion, CDRL A003 (MER).

1. LIST OF DELIVERABLES. Draft and maintain a comprehensive list including all data items and all physical deliverables, CDRL A004 (List of Deliverables Report). Substantiating documentation for tangible items shall include a DD Form 1149 (Requisition and Invoice/Shipping Document).

1. PROJECT PLANNING CHART. Furnish these data items in accordance with SOW paragraphs 3.2. and 3.3.1.2.

3. CONTRACT CHANGE PROPOSAL (CCP). The Contractor shall provide the data necessary to propose, control, and approve changes to the Contract by the Contracting Officer (KO), CDRL A005 (CCP). The CCP shall NOT be used for making changes to requirements documentation specified in Section 2 References.

3. TECHNICAL OR ADMINISTRATIVE FORUMS. The Contractor shall participate in meetings in order to provide live or virtual subject-matter expertise and to communicate the status of actions, objectives, and milestones, CDRL A007 (Meeting Minutes).

3. Develop briefing materials such as slideshows or executive summaries and provide documentation for discussion, CDRL A008 (Presentation Material).

3. Participate in the events below.

3. “Kick-off”. At Base Year Award conduct a comprehensive presentation to Government key leadership inclusive of program office stakeholders. Agenda shall include introduction to key personnel and subcontractor leads, workflows, lines of communication, priorities of work, and breakout sessions to review regulatory requirements such as data management and invoicing.

3. “Monthly Status Meeting”. Conduct routine discussions related to emergent issues, planned events and outcomes anticipated to occur within the next 30 calendar days. Agenda shall include discussion points focused on priorities of work and action item status.

3. “Semi-annual Contract Year Review”. Conduct a comprehensive presentation to Government key leadership inclusive of technical and contractual authorities. Agenda shall include review of funded line items by planned-to-actual values and estimates-at-completion, revised workflows, cost, schedule, and performance items.

3. CONTROLLED UNCLASSIFIED INFORMATION (CUI). The Contractor shall identify and safeguard written and visual communications accessed, generated or Government-furnished for reference or development in accordance with DFARS 252.204-7012. Only Unclassified data is going to be handled as part of this effort. A DD254 will not be provided.

4. CUI shall be marked “Controlled Unclassified Information (CUI)” subject to specified exemptions from the Freedom of Information Act (FOIA), as amended.

4. Technical documents are distribution controlled and shall be marked “DISTRIBUTION STATEMENT D” with further specificity contingent upon content at time of generation or development. Reference 2.3 for detailed instructions.

1. DATA MANAGEMENT. A summary of data items is provided below for ease of reference. Section J (List of Attachments) contains each DD Form 1423-2 (Contract Data Requirements List, CDRL) and accompanying Data Item Description (DID).

CDRL
Title
Data Item Description (DID)
A001
Program Management (PM) Plan
DI-MGMT-80004
A002
Monthly Status Report (MSR)
DI-MGMT-80368
A003
Monthly Expenditure Report (MER)
DI-FNCL-81537
A004
List of Deliverables Report
DI-MISC-81920
A005
Contract Change Proposal (CCP)
DI-ADMN-81401
A006
Electronic Data Library (eDL)
DI-MISC-81920
A006
Trip Report
DI-MISC-81943
A007
Meeting Minutes
DI-ADMN-81505
A008
Presentation Material
DI-MGMT-81373
A009
Assembly & Manufacturing (A&M) Plan
DI-MISC-80508
A010
Technical Data Package (TDP)
DI-SESS-80776A
A011
Project Planning Chart
DI-MGMT-80507

1. TRAVEL. The Contractor shall conduct official travel within the Continental United States (CONUS) as necessary to monitor subcontractors and report status to the government.

0. In performance of official travel, the contractor shall document and provide planned and actual itineraries, and deliver CDRL A006 (Trip Report).

0. Specific events conducted within the trip and their outcome shall be recorded in a separate document, CDRL A007 (Meeting Minutes) submitted as an attachment to CDRL A006.