Brisbon Road Rehab and Sidewalk Addendum 2.pdf
PDF 10 MB Posted
- Attached to
- Brisbon Road Rehab and Sidewalk
- Solicitation number
- PE-77523-NONST-2024-000000033
- Issued by
- Brooks County, Georgia
About this file
This document is an addendum to the Brisbon Road Rehab and Sidewalk contract opportunity issued by the state of Georgia for Bryan County. The project consists of roadway rehabilitation, including full-depth reclamation and pavement, as well as the installation of a 5-foot sidewalk on one side of the Brisbon corridor. The work also includes updating signage and striping, and installing conduit for lighting along the corridor.
The addendum provides clarification and additional details related to the project. It does not appear to contain any information about pricing, set-asides, incumbents, funding requirements, or other salient commercial terms.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
\\thomas-hutton.local\dfs\Projects\27691\27691.0068\Documents\Construction\Bid\Addenda\Addendum 2 Addendum # 2
August 20, 2024
BRISBON ROAD REHAB AND SIDEWALK
PREPARED FOR:
BRYAN COUNTY BOARD OF COMMISSIONERS
T&H PROJECT NO.
J–27691.0068
ADDENDUM NO. 2 August 20, 2024
GENERAL
This Addendum has been issued on behalf of Bryan County Board of Commissioners. The following information should be considered by prospective bidders in preparation of their proposals and is hereby incorporated into the Proposal Documents. Bidders shall be responsible for acknowledging receipt of this addendum in the Bid Form, Document 00313. Failure to do so will result in the proposal being considered non–responsive.
PART I – QUESTIONS AND CLARIFICATIONS:
A. QUESTIONS:
Question 1: There is no Pay Item for SD Structure’s #7B (Std MH) or 1-B2 (D-4 Grate Inlet).
Answer: Items updated with addendum.
Question 2: Could you please add a Pay Item for Aggregate Surface Crs for use at driveways and Brisbon Rd storm drain crossings?
Answer: Driveway pavement structure specified in plan General Notes with the addendum.
Question 3: Could you please add a Pay Item for Class B Concrete (Pvmt Widening)?
Answer: Class B Conc Widening added to typical sections in addendum 2. The price for using Class B Conc Widening should be included in the cost of Grading Complete.
Question 4: There is a Pay Item for Portland Cement. However, the Pay Item for FDR states
“includes material”. Please clarify that the unit price for FDR does not include the cement.
Answer: See GDOT Spec 315 as mentioned in the General Notes, specifically section 5
“payment”.
Question 5: Since there is no summary of surfacing quantities. Could you please clarify where the 4” GABC is to be used?
Answer: Item updated. Driveway structure is specified in the General Notes with the addendum.
Question 6: What is the intent for the existing side drain pipes? Removal or fill with flowable fill? There is no note on the plans indicating removal.
Answer: Those shown as new pipe will be replaced. Those shown as existing will be retained.
\\thomas-hutton.local\dfs\Projects\27691\27691.0068\Documents\Construction\Bid\Addenda\Addendum 2 Addendum # 2
August 20, 2024
Question 7: There are no notes on the plans. What is the intent for the existing driveways? Full removal and reconstruction, partial removal for pipe installation, if so what is the patching detail for trench patching? In some areas the new Side Drain pipes are beyond the end line of the proposed driveways.
Answer: All driveways are being reconstructed, except those specifically noted, as shown in the plans and in accordance with the General Notes in the addendum.
Question 8: Since there is going to be FDR, can the Storm Drain Crossing on Brisbon be backfilled with stone and no concrete patch?
Answer: Backfill according to GDOT standards.
Question 9: Can Town Centre road be close to through traffic during construction?
Answer: Any proposed road closures should be coordinated with the City of Richmond Hill and Bryan County.
Question 10: In our opinion the contract time of 120 calendar days is not achievable. Would you consider extending that to 210 days?
Answer: The contract time is 270 calendar days.
Question 11: The plan shows power poles in the sidewalk and adjacent to the timber bridge. Pile installation equipment will be in conflict with the power lines. Can steel, segmented, low overhead piles be installed instead of long timber piles?
Answer: The timber boardwalk has been eliminated from the project.
PART II – CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS:
The Proposal Documents shall be changed in the following respects:
SECTION 00313 – BID FORM
1. Section 00313 has been revised to include new pay items.
2. Delete and replace with the attached Section 00313 – “Bid Form”.
3. Bidders must use the enclosed form. NO OTHER FORM SHALL BE ACCEPTED.
PART III – DRAWINGS:
1. The attached plan sheets have been revised. Delete and replace corresponding plan sheets with the attached. The 18 series has been removed from the plan set. Delete the 18 series accordingly.
THOMAS & HUTTON
Doyle Kelley, PE
Project Manager
End of ADDENDUM NO. 2
Doyle D. Kelley, Jr., P.E.
Project Manager
00313 – 1
Z:\27691\27691.0068\Documents\Construction\Bid\Specifications \00313 – Bid Form.DOC
DOCUMENT 00313
BID FORM
PROJECT IDENTIFICATION: BRISBON ROAD REHAB AND SIDEWALK
CONTRACT IDENTIFICATION
AND NUMBER: J –27691.0068
THIS BID IS SUBMITTED TO: Thomas & Hutton
1. The undersigned BIDDER proposes and agrees, if this Bid is accepted, to enter into an agreement with OWNER in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the Bid Times indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.
2. BIDDER accepts all of the terms and conditions of the Advertisement or Invitation to Bid and Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 90 days after the day of Bid opening, or for such longer period of time BIDDER may agree to in writing upon request of OWNER.
3. In submitting this Bid, BIDDER represents, as more fully set forth in the Agreement, that:
a. BIDDER has examined and carefully studied the Plans and Specifications for the work and contractual documents relative thereto, and has read all Technical
Provisions, Supplementary Conditions, and General Conditions, furnished prior to the opening of Bids, and can fulfill the requirements of the work to be performed.
b. BIDDER further acknowledges hereby receipt of the following Addenda:
ADDENDUM NO. DATE
1 July 23, 2024
2 August 20, 2024
c. BIDDER has visited the site and become familiar with and is satisfied as to the general, local and site conditions possibly affecting cost, progress, performance and furnishing of the Work;
d. BIDDER is familiar with and is satisfied as to all federal, state, and local Laws and
Regulations possibly affecting cost, progress, performance and furnishing of the
Work.
e. BIDDER has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structure at or contiguous to the site
(except underground Facilities) have been identified in the Supplementary
Conditions. BIDDER acknowledges such reports and drawings are not Contract
Documents and may not be complete for BIDDER’s purposes. BIDDER
00313 – 2 acknowledges OWNER and Engineer do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the
Bidding Documents with respect to Underground Facilities at or contiguous to the site. BIDDER has obtained and carefully studied (or assumes responsibility for having done so) all such additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions
(surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost progress, performance or furnishing of the work or which relate to any aspect of the means, methods, techniques, sequences and procedures of construction to be employed by BIDDER and safety precautions and programs incident thereto. BIDDER does not consider any additional examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance and furnishing of the
Work in accordance with the times, price and other terms and conditions of the
Bidding Documents.
f. BIDDER is aware of the general nature of Work to be performed by Owner and others at the site relating to Work for which this Bid is submitted as indicated in the
Bidding Documents.
g. BIDDER has correlated the information known to BIDDER, information and observations obtained from visits to the site, reports and drawings identified in the
Bidding Documents and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.
h. BIDDER has given ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies BIDDER has discovered in the Bidding Documents and the written resolution thereof by ENGINEER is acceptable to BIDDER. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work for which this Bid is submitted.
i. This bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; BIDDER has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; BIDDER has not solicited or induced any person, firm or corporation to refrain from bidding; and BIDDER has not sought by collusion to obtain for itself any advantage over any other Bidder or over OWNER.
4. BIDDER will complete the Work in accordance with the Contract Documents for the following price(s):
00313 – 3
BRISBON ROAD REHAB AND SIDEWALK
ITEM DESCRIPTION
QUANTITY COST
UNITS MEASURE
PER
UNIT
TOTAL COST
ROADWAY CONSTRUCTION
150-1000 Traffic Control 1 ls $ –
151-1000 Mobilization 1 ls $ –
163-0232 Temporary Grassing 28 ac $ –
163-0240 Mulch 250 tn $ –
163-0301 Construct and Remove Construction
Exits 2 ea $ –
163-0528 Construct and Remove Fabric Check
Dam- Type C Silt Fence 858 lf $ –
163-0550 Construct and Remove Inlet Sediment
Trap 29 ea $ –
165-0010 Maintenance of Temporary Silt Fence, Type A 11,670 lf $ –
165-0030 Maintenance of Temporary Silt Fence, Type C 860 lf $ –
165-0041 Maintenance of Check Dams - All Types 1 lf $ –
165-0101 Maintenance of Construction Exits 2 ea $ –
165-0105 Maintenance of Inlet Sediment Traps 29 ea $ –
167-1000 Water Quality Monitoring and Sampling 8 ea $ –
167-1500 Water Quality Inspections 9 mo $ –
171-0010 Temporary Silt Fence, Type A 11,670 lf $ –
171-0030 Temporary Silt Fence, Type C 860 lf $ –
207-0203 Found Bkfill Matl, Tp 2 360 cy $ –
210-0100 Grading Complete 1 ls $ –
310-5060 Gr Aggr Base Crs, 6 Inch, Incl Material 1,200 sy $ –
310-5080 Gr Aggr Base Crs, 8 Inch, Incl Material 3,000 sy $ –
315-1000 Portland Cement 400 tn $ –
315-1080 Cement Stabilized Reclaimed base course 8 In, Incl Material 14,800 sy $ –
402-1812 Recycled Asph Conc Leveling, Inc
Bitum Matl & H Lime 1,200 tn $ –
402-3130
Recycled Asph Conc 12.5 mm
Superpave, GP 2 Only, Incl Bitum Matl &
H Lime (1.5")
1,800 tn $ –
402-3190
Recycled Asph Conc 19 mm
Superpave, GP 1 or 2, Incl Bitum Matl &
H Lime (2")
2,400 tn $ –
413-0750 Tack Coat 1,800 gl $ –
429-1000 Rumble Strips 6.00 ea $ –
432-5010 Mill Asph Conc Pvmt, Variable Depth 200 sy $ –
441-0016 Driveway Concrete, 6 In Tk 700 sy $ –
441-0104 Conc Sidewalk, 4 In 3,700 sy $ –
00313 – 4
BRISBON ROAD REHAB AND SIDEWALK
ITEM DESCRIPTION
QUANTITY COST
UNITS MEASURE
PER
UNIT
TOTAL COST
441-6222 Conc Curb & Gutter 8"x30, TP2 5,400 lf $ –
446-1100 Pvmt Reinf Fabric Strips, TP2, 18 Inch
Width 6,100 lf $ –
550-3618 Safety End Section 18 In, Storm Drain, 6:1
Slope 4 ea $ –
550-33624 Safety End Section 24 In, Storm Drain, 6:1
Slope 4 ea $ –
550-4118 Flared End Section 18 In Side Drain 36 ea $ –
550-4218 Flared End Section 18 In Storm Drain 10 ea $ –
550-5180 Storm Drain Pipe, 18 In, Class III 1,800 lf $ –
550-5183 Storm Drain Pipe, 18 In, Class V 200 lf $ –
603-2181 Stn Dumped Rip Rap, TP3, 18 In 230 sy $ –
603-7000 Plastic Filter Fabric 230 sy $ –
636-1033 Highway Signs, TP1 Matl, Refl Sheeting, TP9
30 sf $ –
636-1036 Highway Signs, TP1 Matl, Refl Sheeting, TP11
210 sf $ –
636-2070 Galv Steel Posts, TP7 330 lf $ –
636-2080 Galv Steel Posts, TP8 25 lf $ –
636-2090 Galv Steel Posts, TP9 70 lf $ –
643-8200 Barrier Fence (Orange), 4 FT. 270 lf $ –
653-1501 Thermoplastic Solid Traf Stripe, 5 In, White 13,300 lf $ –
653-1502 Thermoplastic Solid Traf Stripe, 5 In, Yellow 6,000 lf $ –
653-1704 Thermoplastic Solid Traf Stripe, 24 In, White 150 lf $ –
653-1804 Thermoplastic Solid Traf Stripe, 8 In, White 880 lf $ –
653-3502 Thermoplastic Skip Traf Stripe, 5 In, Yellow 5,500 lf $ –
654-1001 Raised Pavement Markers, TP 1 300 ea $ –
668-2100 Drop Inlet, GP 1 29 ea $ –
668-4300 Storm Sewer Manhole, TP 1 1 ea $ –
668-7018 Drain Inlet, 18 IN 3 ea $ –
700-6910 Permanent Grassing 10.00 ac $ –
700-7000 Agricultural Lime 42.00 tn $ –
700-8000 Fertilizer Mixed Grade 13.00 tn $ –
700-8100 Fertilizer Nitrogen Content 500 lb $ –
TOTAL PROJECT $
00313 – 5
TOTAL BID:
Dollars
Unit Prices have been computed in accordance with paragraph 11.03.C of the General
Conditions.
BIDDER acknowledges estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities determined as provided, determined as provided in the Contract Documents.
5. BIDDER agrees the Work will be substantially complete within 240 calendar days after the date when the Contract Times commence to run as provided in paragraph 2.03 of the
General Conditions and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within 270 calendar days after the date when the Contract Times commence to run.
6. BIDDER accepts provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within times specified in the Agreement.
7. The following documents are attached to and made a condition of this Bid:
a. Required Bid Security in the form of 10 percent of the Bid Total Price.
8. The undersigned further agrees in case of failure on his/her part to execute the said contract and the Bond within 30 consecutive calendar days after written notice being given of the award of the contract, the check or bid bond accompanying this bid, and the monies payable thereon shall be paid into the funds of the Owner as liquidated damages for such failure, otherwise, the check or bid bond accompanying this proposal shall be returned to the undersigned.
9. Communications concerning this Bid shall be addressed to:
Doyle D. Kelley, P.E.
Thomas & Hutton
50 Park of Commerce Way
Savannah, GA 31405
(912)721–4160
Kelley.d@tandh.com
10. Terms used in this Bid which are defined in the General Conditions or Instructions will have the meanings indicated in the General Conditions of Instructions.
SUBMITTED 2024.
CONTRACTOR'S NAME
ADDRESS:
00313 – 6
BY:
State Contractor License No.
BRI
SBON
ROAD
H A R R I S
T R A I L
B R Y A N
N E C K
R O A D
T I
M B E
R
T
R A I L
STERLI
NG
LI
NKS
WAY
BRIS
BON R
OAD
S R
H A
R R I S
T
R A I L
99+91.74
BRISBON ROAD REHAB
BEGIN CONSTRUCTION
STA 160+49.13
BRISBON ROAD REHAB
END CONSTRUCTION
C A
N T
L E
D R
K E
E P
L
O
O P
S M
O K
I
S
T O
W N
C
N T
R S
H E
L T
O N
S
T
B R I S
B
T
MILES
PLANS COMPLETED
REVISIONS
1.147
PLAN AND PROFILE OF PROPOSED
NET LENGTH OF EXCEPTIONS
GROSS LENGTH OF PROJECT
NET LENGTH OF ROADWAY
NET LENGTH OF BRIDGES
NET LENGTH OF PROJECT
LENGTH OF PROJECT
APPROVAL BY:
RECOMMENDED FOR
TRAFFIC A.D.T.:
TRAFFIC A.D.T.:
SPEED DESIGN:
% TRUCKS:
DESIGN DATA:
PROJECT DESIGNATION: EXEMPT
029 No.
BRYAN COUNTY
SPECIFICALLY DIRECTED TO SUBSECTIONS 102.04, 102.05, AND 104.03 OF THE SPECIFICATIONS.
BIND THE DEPARTMENT OF TRANSPORTATION IN ANY WAY. THE ATTENTION OF BIDDER IS
HOWEVER, THE SAME ARE SHOWN AS INFORMATION ONLY, ARE NOT GUARANTEED, AND DO NOT
UPON FIELD INVESTIGATIONS AND ARE BELIEVED TO BE INDICATIVE OF ACTUAL CONDITIONS.
INDICATED THEREBY, WHETHER BY DRAWINGS OR NOTES, OR IN ANY OTHER MANNER, ARE BASED
THE DATA, TOGETHER WITH ALL OTHER INFORMATION SHOWN ON THESE PLANS OR IN ANYWAY
LOCAL STREET
FUNCTIONAL CLASS:
100% IN CONG. DIST. NO. 1.
BRYAN COUNTY AND IS
THIS PROJECT IS 100% IN
OF 1988.
AMERICAN VERTICAL DATUM (NAVD)
1983)/94 WEST ZONE, AND THE NORTH
COORDINATE SYSTEM OF 1984 (NAD
USING THE HORIZONTAL GEORGIA
THIS PROJECT HAS BEEN PREPARED
BY:
PLANS PREPARED Thomas and Hutton
BRYAN COUNTY ENGINEER
0001 01-
LOCATION SKETCH
REHAB AND SIDEWALK
BRISBON ROAD
0 1
0 1
500 1000
SCALE IN FEET
0 250
RO
E
G
G
IA
.DEL
Y
O D
KELL
E Y
SIGE
R
TERED
IGNE
NEER
No. 031048
PROFESSIONAL
11/05/2020 arce.r
8/20/2024 GPLOT-ORD
gplotborder-ORD.tbl
2769168_01.dgn
CONCOV
DRAWING No.
CONCOV-CE
www.thomasandhutton.com
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
IO
DRAWING NO. DESCRIPTION REVISION DATE REVISION DATEDESCRIPTIONDRAWING NO.
Erosion Control Watershed Map-Sire Monitoring55-0001
BMP Location Details54-0001 - 54-0044
ESPC Drainage Area Map53-0001
ESPC General Notes Drawing51-0001 - 51-0009
Erosion Control Cover Drawing50-0001
Erosion Control Plans
Signing and Marking Plans and Details - Plan Drawings26-0001 - 26-0012
Utility Plans24-0001 - 24-0012
Cross Sections23-0001 - 23-0026
Drainage Structure Tables22-0001
Drainage Area Map21-0001
Driveway Profiles17-0001 - 17-0005
Crossroad, Side Street, and Frontage Road Profile Drawings16-0001
Mainline Roadway Profile Drawings15-0001 - 15-0012
Construction Plan13-0001 - 13-0012
Construction Layout Drawing (Stakeout Drawing)11-0001 - 11-0005
Typical Sections05-0001 - 05-0003
General Notes/Project Notes04-0001 - 04-0003
Index Drawing02-0001
Cover Drawing01-0001
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024 arce.r
GPLOT-ORD
gplotborder-ORD.tbl
2769168_02.dgn
11:46:22 AM
GPLN-CE
0001-02
BRISBON ROAD REHAB
AND SIDEWALK
INDEX
www.thomasandhutton.com
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
DURING THE CONSTRUCTION.
CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION WITH UTILITIES
ARE BASED ON INFORMATION OBTAINED FROM UTILITY COMPANIES.
13. THIS IS NOT A SUE UTILITY LOCATION PROJECT. UTILITIES SHOWN
THAT WILL BE REMOVED OR DESTROYED TO ALLOW FOR CONSTRUCTION.
TREES WITHIN THE CONSTRUCTION LIMITS OR LIMITS OF DISTURBANCE
TREES TO REMAIN IN THE RIGHT OF WAY. THIS DOES NOT APPLY TO
TRAILER PLACEMENT, ETC.) OCCUR UNDER THE DRIP LINE OF EXISTING
VEHICULAR USE, BORROW OR WASTE ACTIVITIES, SEDIMENT BASINS,
ACTIVITIES (SUCH AS THE USE OF EASEMENTS, STAGING,CONSTRUCTION,
12. THE CONTRACTOR SHALL ENSURE THAT NO CONSTRUCTION-RELATED
FOREST SERVICE SOUTHERN RESEARCH STATION FOR REFERENCE.
PLANTS IN SOUTHERN FORESTS' GTR SRS-131, PRODUCED BY THE USDA
TREE - PAULOWNIA TMENTOSA SEE 'A MANAGEMENT GUIDE FOR INVASIVE
BROUSSONETIA PAYRIFERA CHINABERRY - MELIA AZEDARACH PRINCESS
ALTISSIMA WHITE MULBERRY - MORUS ALBA PAPER MULBERRY -
MIMOSA- ALBIZIA JULIBRISSIN TREE OF HEAVEN - AILANTHUS
PROTECTION AND SHOULD BE REMOVED IF POSSIBLE. THESE INCLUDE:
11. INVASIVE OR UNDESIRABLE SPECIES DO NOT QUALIFY FOR ANY
INVASIVE PEST PLANTS.
SERVICE SOUTHERN RESEARCH STATION FOR REFERENCE ON SPECIFIC
SOUTHERN FORESTS' GTR SRS-131, PRODUCED BY THE USDA FOREST
201.3.05.A. SEE 'A MANAGEMENT GUIDE FOR INVASIVE PLANTS IN
SPECIFICATION SECTION 201-CLEARING AND GRUBBING RIGHT OF WAY,
10. INCLUDE ERADICATION OF INVASIVE SPECIES IF ENCOUTERED PER
ITEMS. COST WILL BE INCLUDED IN OVERALL BID SUBMITTED.
9. NO SEPARATE PAYMENT WILL BE MADE FOR TEMPORARY DRAINAGE
DRAINS AND BOX CULVERTS.
8. FOUNDATION BACKFILL MATERIAL TP II WILL BE USED AT ALL CROSS
CONSTRUCTION DEBRIS AT NO ADDITIONAL COST TO THE PROJECT.
SHOWN IN GA. SPECIFICATION 201 TO DISPOSE OF EXISTING BRIDGE /
CONTRACTOR SHALL PROVIDE AN ENVIRONMETALLY APPROVED SITE AS
CONSTRUCTION DEBRIS WITHIN THE PROJECT'S LIMITS. THE
7. THERE IS NO KNOWN SUTIBLE PLACE TO BURY EXISTING BRIDGE/
INCLUDED IN THE PRICE BID FOR GRADING COMPLETE.
EXISTING PAVEMENT REMOVAL AND PREPARATION, SHALL ALSO BE
JOINTS ASSOCIATED WITH SHOULDER REMOVAL, AS WELL AS ALL OTHER
IN THE PRICE BID FOR GRADING COMPLETE. SAWED LONGITUDINAL
TO BE CONSTRUCTED SHALL BE REMOVED. REMOVAL SHALL BE INCLUDED
6. EXISTING PAVED SHOULDERS WHERE NEW TRAVEL OR TURN LANES ARE
RECLAIMED BASE.
IT SHALL BE INCLUDED IN THE COST FOR CEMENT STABILIZED
ADDITIONAL GEOTECHNICAL WORK IS NEEDED FOR THE FDR MIX DESIGN
PROVIDED FOR USE BY THE CONTRACTOR IN THEIR MIX DESIGN.IF
SPECIFICATICATION 315. THE GEOTECHNICAL REPORT HAS BEEN
FOR FULL DEPTH RECLAMATION THAT MEETS GDOT STANDARD
5. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING A MIX DESIGN
INFORMATION.
STANDARD SPECIFICATION AND SUPPLEMENTS THERETO FOR ADDITIONAL
LANDFILL OR IN AN ENGINEERED FILL. SEE SECTION 201 OF THE
PERMITTED SOLID WASTE FACILITY, A PERMITTED INERT WASTE
OUTSIDE THE PROJECT RIGHT OF WAY SHALL BE PLACED IN EITHER A
OCCURRING IN THEM. ALL COMMON FILL OR EXCESS MATERIAL DISPOSED
ENVIRONMENTALLY APPROVED PRIOR TO CONSTRUCTION ACTIVITIES
4. ALL BORROW AND WASTE SITES FOR THIS PROJECT SHALL BE
FOR PIPE ON THE PROJECT.
WRAPPING PIPE JOINTS SHALL BE INCLUDED IN THE OVERALL COST
MINIMUM OVERLAP. EQUIVALENT TO MIRAFI 14ON. THE COST FOR
OF FILTER FABRIC, 4'-0" WIDE. CENTERED ON JOINT WITH A 1'-0"
3. ALL CONCRETE PIPE JOINTS SHALL BE WRAPPED WITH TWO LAYERS
THE COST FOR PIPE ON THE PROJECT.
TO THE COST OF THE PROJECT AND THE COST SHALL BE INCLUDED IN
(EXISTING AND PROPOSED) SHALL BE CONSIDERED INCIDENTAL
THE FLUSHING AND CLEANING OF DROP INLETS, CULVERTS AND PIPES
COMPLETION OF CONSTRUCTION TO REMOVE ANY SILT AND DEBRIS.
2. CONTRACTOR IS TO FLUSH ALL RETAINED INLETS AND PIPE AT THE
FOR THIS PROJECT.
PROJECT IS MORE THAN 1.0 ACRE, A NOTICE OF INTENT IS REQUIRED
1. SINCE THE PROJECT DISTURBED AREA ASSOCIATED WITH THIS
CROSSING ARE NECESSARY.
AND THE TOPS OF PROPOSED RELOCATED WATER MAINS WHERE VERTICAL
CLEARANCE SEPARATION BETWEEN THE BOTTOM OF PROPOSED STORM PIPES
30. CONTRACTOR TO MAINTAIN A MINIMUM OF 18" OF VERTICAL
PRIOR TO CONSTRUCTION.
UTILITIES. AND SHALL COORDINATE WITH THE LOCAL UTILITY COMPANY
UTILITIES ONLY IF NECESSARY FOR THE PROTECTION OF THE
AND SEWER MAINS, CONTRACTPR TO REMOVE AND REPLACE EXISTING
EXISTING UTILITIES. INCLUDING EXISTING WATER MAINS, GAS LINES,
29. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROTECTION OF ALL
28. THIS PROJECT WILL NOT INCLUDE ASPHALT INDEXING.
PRIOR TO CONSTRUCTION.
COORDINATE WITH BRYAN COUNTY AND UTILITY OWNER A MINIMUM OF 72
27. ALL EXISTING GAS LINES ARE ACTIVE. CONTRACTOR TO
A MINIMUM IF 72 HOURS PRIOR TO CONSTRUCTION.
DOWN OF SECTIONS OF EXISTING WATER MAINS USING EXISTING VALVES
TO COORDINATE WITH THE CITY OF RICHMOND HILL TO SCHEDULE SHUT
26. ALL EXISTING WATER AND SEWER MAINS ARE ACTIVE. CONTRACTOR
DISTRICT'S FIELD MANUAL (THE GREEN BOOK).
WITH THE STATE OF GEORGIA SOIL AND WATER CONSERVATION
EROSION CONTROL PRACTICES SHALL BE IMPLEMENTED IN ACCORDANCE
EROSION CONTROL PRACTICES ONCE CONSTRUCTION IS COMPLETE. ALL
CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING AND REMOVING
UNPAVED AREAS, CONSTRUCTION ACCESS AND STORM WATER MONITORING.
PROTECTION, SILT FENCE INSTALLATION AS NEEDED, GRASSING IN
PRACTICES. THIS SHALL INCLUDE, BUT NOT BE LIMITED TO, INLET
25. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL EROSION CONTROL
BRYAN COUNTY ON ANY PROPOSED DISTURBANCE TO ACCESS.
TIMES DURING CONSTRUCTION. COORDINATE WITH PROPERTY OWNERS AND
24. MAINTAIN ACCESS TO THE PROPERTIES AND BRISBON ROAD AT ALL
IN EASEMENTS.
23. CONTRACTOR IS RESPONSIBLE FOR REPLACEMENT OF DAMAGED ITEMS
BETTER AFTER CONSTRUCTION IS COMPLETED.
22. RESTORE TEMPORARY EASEMENTS AREA TO EXISTING CONDITIONS OR
THE PLANS.
21. UTILIZE CLASS V REINFORCED CONCRETE PIPE WHERE NOTED IN
INSTALLCONDUIT/EQUIPMENT.
PRIOR TO ANY NEW PAVING. NO NEW PAVING SHALL BE CUT TO
20. ALL CONDUIT WHICH IS RUN UNDER ROADWAY SHALL BE INSTALLED
ITEM IS TO BE INCLUDED WITH THE COST OF THE CONDUIT.
GALVANIZED PULL WIRE IN EACH EMPTY CONDUIT. THE COST OF THIS
19. THE CONTRACTOR SHALL INSTALL A NYLON PULL CORD OR
WITHIN THE RIGHT OF WAY.
ON THE DRAWING ARE DIAGRAMMATIC. CONTRACTOR SHALL INSTALL THEM
18. ALL CONDUIT AND ELECTRICAL JUNCTION BOXES (EJB) PLACEMENT
EARTH AT A DEPTH OF NOT LESS THAN 24".
INSTALLED UNDERNEATH ROADWAYS AND DRIVES SHALL BE BURIED IN
17. ALL UNDERGROUND CONDUIT SHALL BE SCH 40 PVC. CONDUIT
PROCEDURES SHALL FOLLOW GDOT STANDARD SPECIFICATIONS.
BE PAID FOR IN OVERALL COST OF BID. TESTING FREQUENCY AND
OF ALL REQUIRED QUALITY TESTING SERVICES. COST OF TESTING SHALL
16. CONTRACTOR SHALL BE RESPONSIBLE FOR EMPLOYMENT AND PAYMENT
WITH EXISTING GROUND.
LIMITS. ALL STUMPS OUTSIDE CUT/FILL LIMITS WILL BE CUT FLUSH
BRISBON ROAD. NO GRUBBING WILL BE ALLOWED OUTSIDE OF CUT/FILL
15. CONTRACTOR SHALL CLEAR AND GRUB ENTIRE RIGHT OF WAY ALONG
COMPLETE.
SPECIFICATIONS AND WILL BE INCLUDED IN PRICE BID FOR GRADING
ACCORDANCE WITH SECTION 411 OF THE GEORGIA STANDARD
REQUIRED, SAW CUT OF EXISTING PAVEMENT WILL BE REQUIRED IN
14. IN AREAS WHERE NEW PAVEMENT OR PAVEMENT WIDENING IS
BE INCLUDED IN THE BID ITEM GRADING COMPLETE.
IS TWO FEET WIDE OR LESS. THE PRICE FOR CLASS B CONCRETE IS TO
40. CLASS B CONCRETE BASE TO BE USED FOR AREAS WHERE WIDENING
CONCRETE - DRIVEWAY CONCRETE, 6IN THICK
RESIDENTIAL:
6" GRADED AGGREGATE ON FILTER FABRIC
2" 19mm SUPERPAVE
39. ASPHALT DRIVES 1 1/2" 12.5mm SUPERPAVE
DURING CONSTRUCTION.
CONTRACTOR SHALL COORDINATE WITH COASTAL ELECTRIC COOPERATIVE
38. LIGHTING TO BE INSTALLED BY COASTAL ELECTRIC COOPERATIVE.
REPRESENTATIVE.
THIS BID ITEM IS ONLY TO BE USED AFTER APPROVAL FROM OWNER
UNSUITABLE MATERIALS THAT MAY BE ENCOUNTERED ON THE PROJECT.
THIS ITEM IS TO COVER THE REMOVAL AND REPLACEMENT OF
37. PAY ITEM "UNCLASSIFIED EXCAVATION" INCLUDED IN BID FORM.
REPORT.CONTRACTOR MAY EVALUATE NATIVE SOIL FOR CONFORMITY.
CONFORMITY TO TESTING AND SPECIFICATIONS IN GEOTECHNICAL
INFORMATIONAL PURPOSES. CONTRACTOR SHALL BE RESPONSIBLE FOR
36. GEOTECHNICAL REPORT PROVIDED TO CONTRACTOR FOR
4:30 P.M. TO 6 P.M.
35. LANE CLOSURES ARE PROHIBITED BETWEEN 7 A.M.TO 8:30 A.M.AND
TRAFFIC CONTROL.
PAVEMENT REQUIRED TO STAGE THE JOB IN THE LUMP SUM BID FOR
TRAFFIC CONTROL. THE CONTRACTOR SHALL INCLUDE ANY TEMPORARY
POTENTIAL ROAD DETOURS) SHALL BE INCLUDED IN LUMP SUM BID FOR
CONSTRUCTION. ALL SIGNS AND NECESSARY MATERIALS (INCLUDING
TO BRYAN COUNTY AND THE ENGINEER FOR APPROVAL PRIOR TO
34. CONSTRACTOR SHALL SUBMIT TRAFFIC CONTROL AND STAGING PLANS
COUNTY AND THE ENGINEER IMMEDIATELY.
SHOWN ON THE CONSTRUCTION PLANS, CONTRACTOR SHALL NOTIFY BRYAN
33. IF ANY UTILITIES ARE LOCATED IN THE FIELD THAT ARE NOT
CONTROL.
OF THE JOB SHALL BE INCLUDED IN THE LUMP SUM BID FOR TRAFFIC
32. ANY TEMORARY PAVING REQUIRED TO FACILITATE THE CONSTRUCTION
CONSTRUCTION.
ANY POTENTIAL UNSUITABLE MATERIAL BE ENCOUNTERED DURING
31. CONTRACTOR SHALL NOTIFY BRYAN COUNTY AND ENGINEER SHOULD
UTILITY OWNER SERVICE
CITY OF RICHMOND HILL WATER
CITY OF RICHMOND HILL SEWER
COASTAL ELECTRIC
COMCAST FIBER
CLEARWAVE FIBER
POWER
FIBER
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024 cook.c
GPLOT-ORD
gplotborder-ORD.tbl
2769168_04.dgn
3:16:28 PM
0001-04
GENERAL NOTES
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
IN THE CENTER OF THE SIGN AND FLUSH WITH THE BACK OF THE SIGN.
½ INCH x (WIDTH OF SIGN) ALUMINUM OR GALVANIZED STEEL STRAP LOCATED
6. EACH 42 OR 48 INCH WIDE x 18 OR 24 INCH HIGH SIGN REQUIRES ONE 2 INCH x
INCH DIAMETER, DRILLED OR PUNCHED, AS SHOWN ON THE SIGN PLATE DETAILS.
WIDTH FROM THE EDGE OF THE SIGN. SIGN PLATE BOLT HOLES SHALL BE ⅜
THE SIGN. THE CENTERLINE OF EACH POST SHALL BE INSET 1/6TH OF THE SIGN
WITH THE BACK OF THE SIGN WITH ONE EACH ACROSS THE TOP AND BOTTOM OF
SIGN) ALUMINUM OR GALVANIZED STEEL STRAPS. THE STRAPS SHALL BE FLUSH
SHALL BE MOUNTED ON TWO POSTS WITH 2 EACH 2 INCH x ½ INCH x (WIDTH OF
5. SINGLE PLATE, HORIZONTAL RECTANGULAR SIGNS OVER 48 INCHES IN WIDTH
UNSTIPULATED DISTANCE BEHIND GUARDRAIL.
4c. WHEN GUARDRAIL IS PRESENT OR BEING PROPOSED, SIGNS SHALL BE POSTED AN
BE AT LEAST 2 FEET FROM THE CURB FACE TO THE NEARER EDGE OF THE SIGN(S).
GREATER. THE HORIZONTAL CLEARANCE IN NON-MOUNTABLE CURB SECTIONS SHALL
NORMAL EDGE OF PAVEMENT TO THE NEARER EDGE OF THE SIGN(S), WHICHEVER IS
SHALL BE 6 FEET FROM THE EDGE OF THE PAVED SHOULDER OR 12 FEET FROM THE
4b. HORIZONTAL CLEARANCE FOR STANDARD HIGHWAY SIGNS ON ALL OTHER ROADWAYS
NORMAL EDGE OF PAVED SHOULDER, OR EDGE OF GRADED SHOULDER WHEN PRESENT.
CLEARANCE FOR STANDARD HIGHWAY SIGNS ON RAMPS SHALL BE 2 FEET FROM THE
THE SIGN(S), UNLESS SPECIFIED OTHERWISE IN THE PLANS. HORIZONTAL
SHALL BE 32 FEET FROM THE NORMAL EDGE OF PAVEMENT TO THE NEARER EDGE OF
4a. HORIZONTAL CLEARANCE FOR STANDARD HIGHWAY SIGNS ON INTERSTATE HIGHWAYS
OF 7 FEET ABOVE THE SIDEWALK.
SIDEWALK IS PROPOSED OR EXISTING, THE SIGNS SHALL BE ERECTED AT A HEIGHT
THE NORMAL EDGE OF PAVEMENT TO THE BOTTOM OF THE SIGN OR ASSEMBLY. IF
3. ALL STANDARD HIGHWAY SIGNS SHALL BE ERECTED AT A HEIGHT OF 7 FEET ABOVE
OPERATIONS.
PROJECT ENGINEER WITHOUT PRIOR APPROVAL FROM THE OFFICE OF TRAFFIC
EDITION. NO SIGN LOCATION SHALL BE CHANGED BY THE CONTRACTOR OR BY THE
SET FORTH IN THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES, CURRENT
FIELD CONDITIONS WHERE NECESSARY, BUT SHALL BE WITHIN THE LIMITATIONS
2. SIGN ERECTION STATIONS ARE APPROXIMATE AND MAY BE ADJUSTED TO MEET
SUPPLEMENTAL SPECIFICATIONS, AND/OR SPECIAL PROVISIONS.
TRAFFIC CONTROL DEVICES, CURRENT EDITION, AND THE GEORGIA SPECIFICATIONS,
ACCORDANCE WITH THE DETAILS SHOWN IN THE PLANS, THE MANUAL ON UNIFORM
1. ALL STANDARD HIGHWAY SIGNS SHALL BE FABRICATED AND ERECTED IN
OR ARE CONTRARY TO THESE SIGN PLANS.
ENGINEER, BE REQUIRED TO REMOVE ANY EXISTING SIGNS THAT ARE DUPLICATED
17. THE CONTRACTOR WILL, AS REQUESTED BY THE DISTRICT TRAFFIC OPERATIONS
BE SHOWN ON ALL R552-1 (LIMITED ACCESS) SIGNS IN THIS PROJECT, IF ANY.
16. REFER TO PLAN SHEETS FOR LOCATION OF THE DISTRICT ENGINEERS OFFICE TO
MISCELLANEOUS SIGNS.
15. FOR DETAILS OF SPECIAL DESIGN HIGHWAY SIGNS, SEE DETAILS OF
UNIFORM TRAFFIC CONTROL DEVICES, CURRENT EDITION, FOR DETAILS.
OR SPUR SHALL USE 4 INCH SERIES "D" LETTERS. REFER TO THE MANUAL ON
14. ALL INTERSTATE, U.S., AND GEORGIA SHIELDS REQUIRING ALT, BUS, CONN, LOOP,
PUNCHED, SHALL BE REQUIRED TO PROPERLY MOUNT THE ASSEMBLY.
ON THE POST(S), ADDITIONAL⅜INCH DIAMETER HOLE(S), DRILLED OR
13. WHERE SIGNS WITHIN AN ASSEMBLY EXTEND BELOW THE STANDARD MOUNTING HOLES
WITHIN AN ASSEMBLY.
12. A ½ INCH MINIMUM AIR SPACE SHALL BE REQUIRED BETWEEN ALL SIGN PLATES
SIGNING SHALL HAVE TYPE 9 (VERY HIGH INTENSITY) REFLECTIVE SHEETING.
PORTION OF THE S5-1) SIGNS. ALL REGULATORY SIGNS WITHIN THE SCHOOL ZONE
SHALL BE USED FOR SCHOOL ZONE (S1-1, S2-1, S3-1, S4-3, AND THE TOP
11. TYPE 11 (VERY HIGH INTENSITY) FLUORESCENT YELLOW GREEN REFLECTIVE SHEETING
BE USED FOR ALL WARNING SIGNS.
10. TYPE 11 (VERY HIGH INTENSITY) FLUORESCENT YELLOW REFLECTIVE SHEETING SHALL
RED SERIES SIGNS (R1-1, R1-2, R1-3P, R5-1, R5-1A, R5-1B).
9. TYPE 11 (VERY HIGH INTENSITY) REFLECTIVE SHEETING SHALL BE USED FOR ALL
OR CLASS 2 ADHESIVE BACKING IS PERMISSIBLE.
AS SPECIFIED BELOW OR SPECIFIED OTHERWISE IN THE PLANS. EITHER CLASS 1
ALL STANDARD HIGHWAY SIGNS REQUIRING REFLECTORIZED BACKGROUNDS EXCEPT
8. TYPE 9 (VERY HIGH INTENSITY) REFLECTIVE SHEETING SHALL BE USED FOR
TYPICAL FRAMING DETAILS.
FRAMES. FOR DETAILS AND STRAP SPECIFICATIONS REFER TO SIGN ASSEMBLY-
7. SIGN ASSEMBLIES SHALL BE MOUNTED ON ALUMINUM OR GALVANIZED STEEL STRAP
GENERAL NOTES - STANDARD SIGNS
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
gplotborder-ORD-PO.tbl
9:51:57 AM
0002-04
Savannah, GA 31405 • 912.234.5300
50 Park of Commerce Way •
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
Traffic Control Detail for Lane Closure on Two-Lane Highway - 3/30/20069102
Traffic Control General Notes, Standard Legend, and Miscellaneous Details - 3/30/20069100
Concrete Curb and Gutter, Concrete Curbs, Concrete Medians - 7/01/20229032b
Delineators & Object Markers and Alternate Post - 7/01/20229030c
Concrete Spillways9013
Federal Aid and State Project Markers; Right of Way Markers; County Line Marker - 4/10/20069003
1401 Pavement Patching Details (Storm Drain or Utility Installations by Open cut Across Existing Pavement) - 8/01/1999
1122-1 Safety End Section (Concrete) (for Side Drain Pipe-or Storm Drain Pipe Parallel to Mainline) (Sheet 3 of 3) - 1/28/2005
1122-2 Safety End Section (Metal) (for Side Drain Pipe-or Storm Drain Pipe Parallel to Mainline) (Sheet 2 of 3) - 1/01/2005
1122-1 Safety End Section (Metal) (for Side Drain Pipe-or Storm Drain Pipe Parallel to Mainline) (Sheet 1 of 3) - 1/28/2005
Flared End Sections for Pipes. - 6/09/20061120
1035 Drain Inlet (Elbow type) - 11/01/1999
Concrete and Metal Pipe Culverts Sheet 3 of 3 - 9/26/20011030d3
Concrete and Metal Pipe Culverts Sheet 2 of 3 - 9/26/20011030d2
Concrete and Metal Pipe Culverts Sheet 1 of 3 - 9/01/20011030d1
1019ap Precast Drop Inlets - 8/01/1999
1019a Drop Inlets - 8/01/1999
GEORGIA STANDARDS
T-19 Rumble Strips: Roundabouts and Stop Controlled Intersections - 11/04/2020
Details of Raised Pavement Markers - 9/22/2011T-15c
Details of Raised Pavement Marker Location Non-Limited Access Roadway - 9/15/2016T-15a
- 11/21/2008 Details of Pavement Marking HatchingT-14
T-13a Pavement Markings: Words (Sheet 1 of 2) - 11/04/2020
- 11/04/2020 Details of Pavement Marking - ArrowsT-12b
- 1/1/2000 Details of Pavement Marking Arrow LocationT-12a
Details of Pavement Marking Placement on Non-Limited Access Roadway - 9/15/2016T-11a
T-05b Details of Regulatory Signs (Sheet 2 of 2) - 1/01/2000
T-05a Details of Regulatory Signs (Sheet 1 of 2) - 1/01/2003
T-04 Details of Cardinal Direction Signs - 1/01/2000
T-03a Type 7,8 and 9 Square Tube Post Installation Detail - 7/1/2002
Details For Typical Framing - 3/1/2000T-02
Sign Plates - 1/1/2000T-01
Concrete Flumes Type "A" & "B"D-9
Pavement Edge Treatment Asphalt and Concrete Pavement - 11/17/2011P-7
D-6 Fabrication Details for Safety Grates - 10/01/1972
D-5 Safety Inlets with Grates - 6-21-1995
D-4 Ditch Drop Inlet With Fabricated Safety Grate and Weir Openings
A-4 Detectable Warning Surface Truncated Dome Size, Spacing and Alignment Requirements - 6/18/2009
A-3 Concrete Sidewalk Details Curb Cut (Wheelchair) Ramps - 9/15/2016
A-2 Concrete Valley Gutter at Street Intersection 6 - 7/21/2011
A-1 Driveways With Tapered Entrances Concrete Valley Gutters - 7/21/2011
CONSTRUCTION DETAILS
PAYMENT WILL BE MADE FOR BENCHING.
AND NO ADDITIONAL MEASUREMENT OF QUANTITY OR
GRADING COMPLETE IN CONSTRUCTION OF THE EBANKMENT
THE ITEM OF UNCLASSIFIED EXCAVATION AND BORROW OR
3. THE PROCESS OF BENCHING IS CONSIDERED INCIDENTAL TO
THE HORIZONTAL DISTANCE TO VARY.
PART REACHES A MAXIMUM OF 4 FEET ALLOWING
THEN THE ACTUAL CUT STOPS WHEN THE VERTICAL
4 FEET IF A 8 FEET HORIZONTAL CUT IS MADE,
THE VERTICAL PART OF THE STEP WILL EXCEED
LAYERS ARE AGAIN PLACED. IF IT IS ANTICIPATED THAT
CUT 8 FEET INTO THE SLOPE AND SUCCESSIVE
BEFORE LAYER "E" IS PLACED, THE SECOND STEP IS
SUCCESSIVE LAYERS B, C, AND D ARE THEN PLACED
THE WIDTH OF THE TYPICAL D-8 BULDOZER BLADE).
A MAXIMUM DISTANCE OF ABOUT 8 FEET (ABOUT¾
PLACED THE FIRST STEP IS TO (1) CUT INTO THE SLOPE
2. THE DIAGRAM SHOWS THAT BEFORE LAYER "A" IS
(SEE DIAGRAM AT LEFT.)
BEING MADE.
MUST BE BENCHED WHILE THE EMBANKMENT IS
A SLOPE OF 3 TO 1 OR STEEPER. THE FOUNDATION
HILLSIDE OR ANOTHER EXISTING EMBANKMENT HAVING
1. WHERE THE EMBANKMENT IS TO BE PLACED ON A
4' MAX.
STEP 3
STEP 2
STEP 1
8' MAX. 8' MAX.
F
E
D
C
B
A
4' MAX.
4' MAX.
BENCHING DETAIL
4.5.28 NO SCALERevised 9/29/08
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
9:51:57 AM
0003-04
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
GADOT
LOWNDES
F
A
B
C
D
E
F
G
H
I
J
K
L
M
N FULL DEPTH RECLAMATION WITH CEMENT TREATMENT, 8 IN
MILLING ASPH. CONC. PVMT - VARIABLE DEPTH
SAFETY EDGE (GA CONSTRUCTION DETAIL P-7)
PVMT REINF FABRIC STRIPS, TP 2, 18 INCH WIDTH
RECYCLED ASPH. CONC 19 MM SUPER PAVE,GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
PLAIN PC CONC PVMT, CL 3 CONC, 9 INCH THK
PLAIN PC CONC PVMT, CL 3 CONC, 9 IN THK (COLORED INSIGNIA RED # 31136 AND STAMPED)
CONC CURB & GUTTER, 8 IN X 30 IN, TP 1-4"
CONC SIDEWALK, 4 IN
RECYCLED ASPHALT CONC LEVELING, INCL BITUM & H LIME
GRADED AGGREGATE BASE COURSE - 8 IN
RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
RECYCLED ASPH CONC 19 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 220 LB/SY
RECYCLED ASPH CONC 12.5 MM SUPERPAVE, GP 2 ONLY, INCL BITUM & H LIME - 165 LB/SY
REQUIRED PAVEMENT
BRISBON ROAD
FULL DEPTH RECLAMATION AND WIDENING
TYPICAL SECTION #1
STA. 158+40.06 to STA. 159+83.61
STA. 119+38.98 to STA. 133+63.40
STA.110+18.16 to STA. 118+15.16
STA. 103+64.49 to STA. 109+62.48
THE EXISTING PAVEMENT.
MILLING WILL BE REQUIRED TO CREATE A SMOOTH TIE TO 4.
SEE ROADWAY PLANS FOR LOCATION OF GUARDRAIL.3.
OF NORMAL CROWN AND S.E. SECTIONS.
SUPERELEVATION RATES AND TRANSITIONS, AND LOCATIONS
SEE ROADWAY PLANS FOR METHOD OF SUPERELEVATION, 2.
EACH.
PLANS FOR LOCATION, DIRECTION AND COMPLETE DETAILS OF
TURN LANES ALSO APPLY TO OPPOSITE-HAND SECTIONS. SEE
TYPICAL SECTIONS ILLUSTRATING SUPERELEVATION AND 1.
NOTES:
Existing LaneExisting Lane 2:
MAX
4:1
6%2%
4:1
DES.
Profile Grade
2% 2%
12'-0" 11'-0"
Travel Lane Travel Lane
11'-0" 8'-0" 10'-0"
2'-0" 2'-0"
TANGENT SECTION
CL
2:1 MAX
5'-0"
Sidewalk
B
K
D
N
NO SCALE
CLASS "B" CONCRETE BASE FOR PAVEMENT WIDENING
Item Code 500-9999 - CY Unit of Measure
CLASS "B" CONCRETE BASE FOR WIDENING DETAIL
be placed in lieu of the paving between the GAB and surface courses specified by the typical section.
top of the GAB and the bottom of the surface course is 5 inches or greater, Class B concrete shall Where GAB is required under the new Curb and Gutter and the depth of proposed paving between the Case 1:
whichever is greater.
base course, the bottom of the Base specified by the typical section, or to a depth of 6 inches:
be placed beneath the proposed surface course to the depth of either the bottom of the existing the top of the Base and the bottom of the surface course is less than 5 inches, Class B concrete shall Where GAB is not required under the new Curb and Gutter and/or the depth of proposed paving between Case 2:
new Curb and Gutter <= 5.0' 0.0' < Width of excavation to
Case 2 Case 1
Case 2 Case 1
Pavement Existing
Course Surface
6" minimum
5" minimum
Base existing Bottom of
Concrete Class B
Class B Concrete by Typical Section when required Proposed GAB
5'-0"
2'-0"
2:1
MAX.
AND MAX
2% TYP
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
2769168_05.dgn
9:54:51 AM
0001-05
TYPICAL SECTIONS
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
SCALE IN FEET
0 10 20
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
A
B
C
D
E
F
G
H
I
J
K
L
M
N FULL DEPTH RECLAMATION WITH CEMENT TREATMENT, 8 IN
MILLING ASPH. CONC. PVMT - VARIABLE DEPTH
SAFETY EDGE (GA CONSTRUCTION DETAIL P-7)
PVMT REINF FABRIC STRIPS, TP 2, 18 INCH WIDTH
RECYCLED ASPH. CONC 19 MM SUPER PAVE,GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
PLAIN PC CONC PVMT, CL 3 CONC, 9 INCH THK
PLAIN PC CONC PVMT, CL 3 CONC, 9 IN THK (COLORED INSIGNIA RED # 31136 AND STAMPED)
CONC CURB & GUTTER, 8 IN X 30 IN, TP 2-6"
CONC SIDEWALK, 4 IN
RECYCLED ASPHALT CONC LEVELING, INCL BITUM & H LIME
GRADED AGGREGATE BASE COURSE - 8 IN
RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
RECYCLED ASPH CONC 19 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 220 LB/SY
RECYCLED ASPH CONC 12.5 MM SUPERPAVE, GP 2 ONLY, INCL BITUM & H LIME - 165 LB/SY
REQUIRED PAVEMENT
GADOT
LOWNDES
2% MAX
1% TYP
4:1
DES.
9'-0" TO 12'-0"
VARIES
2'-6"0'-0"
2'-0" TO
F
5'-0"
Sidewalk
2'-6"
2:1
MAX.
Existing LaneExisting Lane
4:1 DES.
6%
Profile Grade
2% 2%
11'-0"
Travel Lane Travel Lane
11'-0" 8'-0"
2'-6"
TANGENT SECTION
CL
B
D
BRISBON ROAD
FULL DEPTH RECLAMATION AND WIDENING
TYPICAL SECTION #2
STA. 134+00.00 to STA. 158+40.05
K
N
5'-5"
2:1 MAX.
2:
MAX.4:
DE
S.
G
VARIES
4:1 DES.2:1 MAX.
THE EXISTING PAVEMENT.
MILLING WILL BE REQUIRED TO CREATE A SMOOTH TIE TO 4.
SEE ROADWAY PLANS FOR LOCATION OF GUARDRAIL.3.
OF NORMAL CROWN AND S.E. SECTIONS.
SUPERELEVATION RATES AND TRANSITIONS, AND LOCATIONS
SEE ROADWAY PLANS FOR METHOD OF SUPERELEVATION, 2.
EACH.
PLANS FOR LOCATION, DIRECTION AND COMPLETE DETAILS OF
G
NO SCALE
CLASS "B" CONCRETE BASE FOR PAVEMENT WIDENING
Item Code 500-9999 - CY Unit of Measure
CLASS "B" CONCRETE BASE FOR WIDENING DETAIL
be placed in lieu of the paving between the GAB and surface courses specified by the typical section.
top of the GAB and the bottom of the surface course is 5 inches or greater, Class B concrete shall Where GAB is required under the new Curb and Gutter and the depth of proposed paving between the Case 1:
whichever is greater.
base course, the bottom of the Base specified by the typical section, or to a depth of 6 inches:
be placed beneath the proposed surface course to the depth of either the bottom of the existing the top of the Base and the bottom of the surface course is less than 5 inches, Class B concrete shall Where GAB is not required under the new Curb and Gutter and/or the depth of proposed paving between Case 2:
new Curb and Gutter <= 5.0' 0.0' < Width of excavation to
Case 2 Case 1
Case 2 Case 1
Pavement Existing
Course Surface
6" minimum
5" minimum
Base existing Bottom of
Concrete Class B
Class B Concrete by Typical Section when required Proposed GAB
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
9:54:51 AM
0002-05
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
SCALE IN FEET
0 10 20
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
C
D
E
F
G
H
I
J
K
L
M
N FULL DEPTH RECLAMATION WITH CEMENT TREATMENT, 8 IN
MILLING ASPH. CONC. PVMT - VARIABLE DEPTH
SAFETY EDGE (GA CONSTRUCTION DETAIL P-7)
PVMT REINF FABRIC STRIPS, TP 2, 18 INCH WIDTH
RECYCLED ASPH. CONC 19 MM SUPER PAVE,GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
PLAIN PC CONC PVMT, CL 3 CONC, 9 INCH THK
PLAIN PC CONC PVMT, CL 3 CONC, 9 IN THK (COLORED INSIGNIA RED # 31136 AND STAMPED)
CONC CURB & GUTTER, 8 IN X 30 IN, TP 2-6"
CONC SIDEWALK, 4 IN
RECYCLED ASPHALT CONC LEVELING, INCL BITUM & H LIME
GRADED AGGREGATE BASE COURSE - 8 IN
RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
RECYCLED ASPH CONC 19 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 220 LB/SY
RECYCLED ASPH CONC 12.5 MM SUPERPAVE, GP 2 ONLY, INCL BITUM & H LIME - 165 LB/SY
REQUIRED PAVEMENT
GADOT
LOWNDES
THE EXISTING PAVEMENT.
MILLING WILL BE REQUIRED TO CREATE A SMOOTH TIE TO 4.
SEE ROADWAY PLANS FOR LOCATION OF GUARDRAIL.3.
OF NORMAL CROWN AND S.E. SECTIONS.
SUPERELEVATION RATES AND TRANSITIONS, AND LOCATIONS
SEE ROADWAY PLANS FOR METHOD OF SUPERELEVATION, 2.
EACH.
PLANS FOR LOCATION, DIRECTION AND COMPLETE DETAILS OF
NO SCALE
CLASS "B" CONCRETE BASE FOR PAVEMENT WIDENING
Item Code 500-9999 - CY Unit of Measure
CLASS "B" CONCRETE BASE FOR WIDENING DETAIL
be placed in lieu of the paving between the GAB and surface courses specified by the typical section.
top of the GAB and the bottom of the surface course is 5 inches or greater, Class B concrete shall Where GAB is required under the new Curb and Gutter and the depth of proposed paving between the Case 1:
whichever is greater.
base course, the bottom of the Base specified by the typical section, or to a depth of 6 inches:
be placed beneath the proposed surface course to the depth of either the bottom of the existing the top of the Base and the bottom of the surface course is less than 5 inches, Class B concrete shall Where GAB is not required under the new Curb and Gutter and/or the depth of proposed paving between Case 2:
new Curb and Gutter <= 5.0' 0.0' < Width of excavation to
Case 2 Case 1
Case 2 Case 1
Pavement Existing
Course Surface
6" minimum
5" minimum
Base existing Bottom of
Concrete Class B
Class B Concrete by Typical Section when required Proposed GAB
6%
Profile Grade
Travel Lane
11'-0" 8'-0" 10'-0"
2'-0"
TANGENT SECTION B
K
D
N
2%
CL
Existing Lane
2% MAX
1% TYP
4:1
DES.
11'-6"
2'-6"2'-0"5'-0"
Sidewalk
2'-0"
2:1
MAX.
Existing Lane
11'-0"
Travel Lane
G
4:1 DES.2:1 MAX.
F
2%
BRISBON ROAD
FULL DEPTH RECLAMATION AND WIDENING
TYPICAL SECTION #3
STA. 118+15.17 to STA. 119+38.95
STA. 109+62.78 to STA. 110+19.00
STA.100+76.53 to STA. 103+64.16
2:1 MAX.
4:1 DES. 2:
MAX.4:
DE
S.
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
9:54:52 AM
0003-05
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
SCALE IN FEET
0 10 20
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
C
D
E
F
G
H
I
J
K
L
M
N FULL DEPTH RECLAMATION WITH CEMENT TREATMENT, 8 IN
MILLING ASPH. CONC. PVMT - VARIABLE DEPTH
SAFETY EDGE (GA CONSTRUCTION DETAIL P-7)
PVMT REINF FABRIC STRIPS, TP 2, 18 INCH WIDTH
RECYCLED ASPH. CONC 19 MM SUPER PAVE,GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
PLAIN PC CONC PVMT, CL 3 CONC, 9 INCH THK
PLAIN PC CONC PVMT, CL 3 CONC, 9 IN THK (COLORED INSIGNIA RED # 31136 AND STAMPED)
CONC CURB & GUTTER, 8 IN X 30 IN, TP 2-6"
CONC SIDEWALK, 4 IN
RECYCLED ASPHALT CONC LEVELING, INCL BITUM & H LIME
GRADED AGGREGATE BASE COURSE - 8 IN
RECYCLED ASPH CONC 25 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 330 LB/SY
RECYCLED ASPH CONC 19 MM SUPERPAVE, GP 1 OR 2, INCL BITUM & H LIME - 220 LB/SY
RECYCLED ASPH CONC 12.5 MM SUPERPAVE, GP 2 ONLY, INCL BITUM & H LIME - 165 LB/SY
REQUIRED PAVEMENT
GADOT
LOWNDES
4:1
DES.
9'-6" TO 11'-6"
VARIES
2'-6"0'-0"
2'-0" TO
F
5'-0"
Sidewalk
2'-0"
2:1
MAX.
Existing LaneExisting Lane
4:1 DES.
6%
Profile Grade
2% 2%
11'-0"
Travel Lane Travel Lane
11'-0" 8'-0"
2'-6"
TANGENT SECTION
CL
B
D
BRISBON ROAD
FULL DEPTH RECLAMATION AND WIDENING
TYPICAL SECTION #4
STA. 159+84.70 to 160+42.80
STA. 100+11.80 to STA. 100+93.17
K
5'-5"
2:1 MAX.
2:
MAX.4:
DE
S.
G
VARIES
4:1 DES.2:1 MAX.
THE EXISTING PAVEMENT.
MILLING WILL BE REQUIRED TO CREATE A SMOOTH TIE TO 4.
SEE ROADWAY PLANS FOR LOCATION OF GUARDRAIL.3.
OF NORMAL CROWN AND S.E. SECTIONS.
SUPERELEVATION RATES AND TRANSITIONS, AND LOCATIONS
SEE ROADWAY PLANS FOR METHOD OF SUPERELEVATION, 2.
EACH.
PLANS FOR LOCATION, DIRECTION AND COMPLETE DETAILS OF
NO SCALE
CLASS "B" CONCRETE BASE FOR PAVEMENT WIDENING
Item Code 500-9999 - CY Unit of Measure
CLASS "B" CONCRETE BASE FOR WIDENING DETAIL
be placed in lieu of the paving between the GAB and surface courses specified by the typical section.
top of the GAB and the bottom of the surface course is 5 inches or greater, Class B concrete shall Where GAB is required under the new Curb and Gutter and the depth of proposed paving between the Case 1:
whichever is greater.
base course, the bottom of the Base specified by the typical section, or to a depth of 6 inches:
be placed beneath the proposed surface course to the depth of either the bottom of the existing the top of the Base and the bottom of the surface course is less than 5 inches, Class B concrete shall Where GAB is not required under the new Curb and Gutter and/or the depth of proposed paving between Case 2:
new Curb and Gutter <= 5.0' 0.0' < Width of excavation to
Case 2 Case 1
Case 2 Case 1
Pavement Existing
Course Surface
6" minimum
5" minimum
Base existing Bottom of
Concrete Class B
Class B Concrete by Typical Section when required Proposed GAB
E
2% MAX
1% TYP
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
9:54:52 AM
0004-05
BRISBON ROAD
REHAB AND SIDEWALK
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
SCALE IN FEET
0 10 20
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
BRISBON ROADBRISBON ROAD
CURVE# 1
PI 102+64.59
N 698,466.3692
E 923,279.7066
¬ 02°15'22.8" (RT)
D 00°35'59.84"
T 188.06'
L 376.08'
R 9550.00'
E 1.85' ed 2.0%
D.S. 35 mph
N85°02'39.5"E
P C
PT
.6
PC
.3
CURVE# 2
PI 112+19.40
N 698,511.3385
E 924,233.4962
¬ 03°51'40.9" (RT)
D 00°34'22.65"
T 337.09'
L 673.93'
R 10000.00'
E 5.68' ed 2.0%
D.S. 35 mph
P I
P I
P O
B
CURVE #2CURVE #1
N87°18'02.2"E
ELEV.: 10.30'
923022.6462E
698373.9183N
POWER POLE
BENCH TIE IN WOOD
BENCHMARK "X"
STA 99+91.74
BEGIN CONSTRUCTION
BEGIN PROJECT
H A R R I S
T R
A I L
M A
T
H
A
A W I o
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
2769168_11.dgn
9:57:39 AM
0001-11
CONSTRUCTION LAYOUT
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
100 200
SCALE IN FEET
0 50
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
CURVE# 3
PI 118+89.15
N 698,497.7516
E 924,903.3643
¬ 10°47'19.0" (LT)
D 02°41'23.79"
T 201.13'
L 401.07'
R 2130.00'
E 9.48' ed 2.6%
D.S. 35 mph
N80°22'24 .1"E
P T
P C
P T
P I
CURVE #3
CURVE #2
S88°50'16.9"E
C A
N T
K E P L E
R
L
O O P
BRISBON ROAD
M A
T
A
A W I
M A
T
A
A W I
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
9:57:40 AM
0002-11
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
100 200
SCALE IN FEET
0 50
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
CURVE# 4
PI 136+75.91
N 698,796.7456
E 926,666.1375
¬ 09°09'52.9" (LT)
D 01°56'32.03"
T 236.44'
L 471.86'
R 2950.00'
E 9.46' ed 2.0%
D.S. 35 mphP C
P T
P I
CURVE #4
N80°22'24.1"E N71°12 '31.2"
E
ELEV.: 17.58'
E 926366.6386
N 698707.6414
PK & WASHER
BENCHMARK
T O
N T
S M
O
BRISBON ROAD
M A
T
A
A W I
M A
T
A
A W I
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
0003-11
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
100 200
SCALE IN FEET
0 50
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
PC
.6
N71°12'31.2"E
ELEV.: 15.09'
E 927374.4799
N 699009.4980
IN (SE) CORNER TOP STORM BOX
BENCHMARK "X"
S H
E L
T O
N S
T
B R
IS
B
O N
C T
M A
T C
H L
I N
E S
T A
.0
D
R A
W I N
G N o
M A
T
A
A W I
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
0004-11
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
100 200
SCALE IN FEET
0 50
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
P T
CURVE# 5
PI 157+17.21
N 699,454.6191
E 928,599.5871
¬ 18°15'25.2" (LT)
D 07°09'43.10"
T 128.55'
L 254.92'
R 800.00'
E 10.26' ed 3.4%
D.S. 25 mph
P I
P O
E
CURVE #5 N52°57'06.0"E
ELEV.: 18.29'
E 928682.4625
N 699476.3903
NAIL FOUND IN POWER POLE
BENCHMARK 1021
STA 160+49.13
END CONSTRUCTION
END PROJECT
S R
M A
T
A
A W I
DRAWING No.CHECKED:
BACKCHECKED:
CORRECTED:
VERIFIED:
DATE:
DATE:
DATE:
DATE:
11/05/2020
REVISION DATES
8/20/2024
Umberg.a
GPLOT-ORD
9:57:41 AM
0005-11
Savannah, GA 31405 • 912.234.5300 50 Park of Commerce Way •
100 200
SCALE IN FEET
0 50
B
ID
S E
T
N O
T F
O R
C O
N S
T R
U C
T
IV
E
A S
P H
A L T
ASPHALT PAVEMENT
DRIVE
ASPHALT
A S
P H
A L T
P
A V
E M
E N
T
WOODLINE
WOODLINEWOODLINE
W O
O D L
IN
E
WOODLIN
E
BOX
RETURN
BOOK
F.F .E.
=11.
93BLOCK1-
STORY
GEORGIA TRANSMISSION CORP
HONNOR ENTERPRISES LLC
CHURCH BRISBAIN
BARRY WASHINGTON
ALFONSO WALKER
DSP-13 DEVELOPERS INC
DATA SHEET 14
DATA SHEET 14
DE4
DE5
DE26
DE96
SEE HARRIS TRAIL
PEDESTRIAN IMPROVEMENT PLANS
FOR R/W AQUISITION DATA
CURVE# 1
PI 102+64.59
N 698,466.3692
E 923,279.7066
¬ 02°15'22.8" (RT)
D 00°35'59.84"
T 188.06'
L 376.08'
R 9550.00'
E 1.85' ed 2.0%
D.S. 35 mph
P C
P T
P
.5
N85°02'39.5"E
P O
B
CURVE #1
BRISBON ROAD
H A R R I S
T R
A I L
BEGIN PROJECT
BEGIN CONSTRUCTION
STA 99+91.74
CONST CL
923084.1785E
698449.4150N
STA 100+68.33
BEGIN R/W ACQUISTION
18"
YARD INLET
INSTALL 18"
1-B2
1-C
1-B1
1-A1
1-A2
1-A3
CURVE #1
65.06' Lt.OFF:
100+50.99STA:
BRISBON ROAD
BEGIN 5' CONCRETE SIDEWALK
BEGIN MILL AND INLAY
TIE TO EXISTING EDGE OF PAVEMENT
ST…