This is a Request for Bids (RFB) issued by the Maryland Department of Health's Clifton T. Perkins Hospital Center (CTPHC) for mold abatement and remediation services at the facility. CTPHC, a maximum-security psychiatric hospital with approximately 285 average daily inpatients, seeks a contractor to inspect and remediate mold throughout the building in accordance with industry standards including ASTM D7338-14 and IICRC standards. The scope of work encompasses visual inspection of wet areas, establishment of containment barriers with negative air pressure, removal of visible fungal growth and contaminated materials, proper disposal of contaminated waste, and restoration or replacement of damaged building materials. Written questions from prospective bidders must be submitted by September 18, 2026, at 12:00 p.m. local time, and bids are due September 24, 2026, at 2:00 p.m. local time via eMMA (eMaryland MarketPlace Advantage). Site visits may be requested by contacting the Procurement Officer by September 22, 2026. A public bid opening is scheduled for September 25, 2026, at 9:00 a.m. via Google Meet. The contract will commence upon Notice to Proceed and continue for approximately three to six months with no option periods.
This is a Small Business Reserve procurement limited to certified small businesses meeting requirements under State Finance and Procurement Article 14-501-14-505. Bidders must hold a Maryland General Contractor's License and possess relevant mold inspection and remediation certifications such as IICRC's Applied Microbial Remediation Technician or Mold Remediation Specialist, ACAC's Council Certified Microbial Remediator, or equivalent credentials. The contract will be awarded to the lowest responsive bid from a responsible bidder under the Small Procurement method. The total contract cost shall not exceed $50,000. Contractors must maintain Commercial General Liability insurance of $500,000 combined single limit per occurrence and $1,500,000 annual aggregate, and Workers' Compensation insurance of at least $1,000,000 per occurrence. The State shall be listed as an additional insured on all liability policies. No federal funding is involved, and contractors must comply with all State, Federal, and OSHA safety standards, facility security requirements, and Maryland's environmentally preferable purchasing commitments. All work must be approved and coordinated with an assigned facility Contract Monitor prior to performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Bids for
Mold Abatement and Remediation at Clifton T. Perkins Hospital Center
Solicitation #BPM058784
Issue Date: September 9, 2026
A Prospective Bidder that has received this document from a source other than eMarylandMarketplace
Advantage (eMMA) https://procurement.maryland.gov should register on eMMA https://emma.maryland.gov/
NOTICE TO BIDDERS
SMALL BUSINESS RESERVE PROCUREMENT
This is a Small Business Reserve Procurement for which the award will be limited to certified small business vendors. Only businesses that meet the statutory requirements set forth in State Finance and
Procurement Article, §§14-501—14-505, Annotated Code of Maryland, and that are certified by the
Governor’s Office of Small, Minority & Women Business Affairs (GOSBA) Small Business Reserve
Program are eligible for award of a contract. Before awarding a contract under a procurement designated as a small business reserve procurement, the Procurement Officer shall verify that the apparent awardee is certified by the GOSBA as a small business through eMMA. However, if small businesses do not show interest in this solicitation, the Procurement Officer has the right to remove the SBR designation via an
Amendment on eMMA.
MINORITY BUSINESS ENTERPRISES ARE ENCOURAGED TO RESPOND TO THIS
SOLICITATION.
https://procurement.maryland.gov/ https://emma.maryland.gov/ https://gomdsmallbiz.maryland.gov/Pages/sbr-program.aspx https://gomdsmallbiz.maryland.gov/Pages/sbr-program.aspx
KEY INFORMATION SUMMARY SHEET (KISS)
Request for Bids Maintenance – Mold Abatement and Remediation at Clifton T. Perkins
Hospital Center
Solicitation
Number:
BPM058784
RFB Issue Date: September 9, 2026
RFB Issuing
Office:
Maryland Department of Health (MDH), Clifton T. Perkins Hospital
Center (CTPHC)
Procurement
Officer:
Victoria F. Bell, Director of Procurement
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd., Jessup, MD 20794
Email:
Phone Number:
Victoria.bell1@maryland.gov
410-724-3104
Bids are to be sent to:
Submit on emma.maryland.gov under Solicitation Number BPM058784
To submit a bid, bidders must first register on emma.maryland.gov. We recommend registering in advance to become acquainted with the site.
No Bid Notice
Feedback Form
If you are not submitting a bid for this solicitation, submit Attachment 1 with your reasons why. No Bid/Proposal Notice
Pre-Bid
Conference:
No conference will be held.
Scheduled Site
Visit
If requesting a site visit, please contact the Procurement officer via email no later than September 22, 2026.
Questions Due
Date and Time:
September 18, 2026, by 12:00 pm Local Time
Bid Due (Closing)
Date and Time:
September 24, 2026, by 2:00 pm Local Time
Bidders are reminded that a completed Feedback Form is requested if a no-bid decision is made: No Bid/Proposal Notice mailto:Victoria.bell1@maryland.gov https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-1.-No-Bid_Proposal-Notice_Vendor-Feedback-Form-1-1.docx https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-1.-No-Bid_Proposal-Notice_Vendor-Feedback-Form-1-1.docx
Public Bid Opening
Date, Time, and
Location
BPM058784 Mold Abatement & Remediation: Bid Opening
Friday, September 25 · 9:00 – 9:30am
Time zone: America/New York
Google Meet joining info
Video call link: https://meet.google.com/grn-otqs-jva
Or dial: 0076-459-(US) +1 567 PIN: 618 701 014#
More phone numbers: https://tel.meet/grn-otqs-jva?pin=8687622466785
MBE
Subcontracting
Goal:
N/A
VSBE
Subcontracting
Goal:
N/A
Procurement
Method:
A Contract will be awarded in accordance with the Small Procurement method under COMAR 21.05.07.
Multiple or
Alternate Bids:
Multiple or alternate Bids will not be accepted.
Contract Type: Indefinite Quantity with Firm Fixed Prices
Contract Duration: Approximately 3-6 Month base period with No option periods.
Primary Place of
Performance:
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd., Jessup, MD 20794
SBR Designation: Yes
Federal Funding: No
The remainder of this page is intentionally left blank.
https://meet.google.com/grn-otqs-jva https://tel.meet/grn-otqs-jva?pin=8687622466785
1. Summary Statement and Background
A. This Request for Bids (RFB) is issued to procure the goods or services, as specified in this section 4, from a contract between the successful bidder(s) and Clifton T. Perkins
Hospital Center (CTPHC) a part of the Maryland Department of Health (MDH).
B. CTPHC is a maximum-security psychiatric hospital that provides a comprehensive program for the evaluation and treatment of mental illness, with emphasis on assessment, treatment and recovery. The hospital program is structured to facilitate recovery through a graduated release process that begins in maximum security and culminates in release into the community.
C. CTPHC has an average daily inpatient population of approximately 285 patients and is accredited by the Joint Commission on Hospital Accreditation Standards (JC).
D. CTPHC is seeking a Contractor to inspect and remediate mold in the building.
2. Minimum Requirements
As part of the determination to be considered responsive, the Bidder must submit documentation in its Bid that satisfies the following Minimum Qualifications:
A. The Bidder or its subcontractors shall be licensed in the State of Maryland as a General
Contractor to perform work as defined in the Scope of Work; as proof of this requirement, the Bidder shall submit the following:
1) A copy of their Maryland General Contractor’s License.
2) A copy of their state or county Business License where they perform business.
B. The Bidder or its subcontractors shall be certified to perform all Industrial Hygiene
Indoor Air Quality and Mold Inspection as related to the Scope of Work; as proof of this requirement Bidder must include one of the following documentations of licensing, certification and applicable experience as follows:
• Institute of Inspection, Cleaning and Restitution Certification (IICRC) – for Applied Microbial Remediation Technician (AMRT) and Mold
Remediation Specialist (MRS): shall provide a copy of the certification.
• American Council for Accredited Certification (ACAC) – Council certified Microbial Remediator (CMR).
• Professional Mold Inspection Institute – proof of courses and certifications for remediator and inspection.
• NORMI, CHE, HPE, CJH, as applicable.
C. The Bidder or its subcontractors shall provide at least 3 references that attest to their capabilities and general experience (corroboration of at least 3 years of experience total) in providing services as applicable to the Scope of Work.
3. The identity of the Procurement Officer Victoria F. Bell, MBA, CMPO
Director of Procurement
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd.
Jessup, MD 20794
410-724-3104
Email: victoria.bell1@maryland.gov
4. Deliverables / Scope of Work The Contractor shall perform the following services:
A. Inspection of Areas
Upon receipt of a work order designating an area requiring abatement and remediation, perform a visual Inspection of all wet areas for the potential presence of fungal growth in accordance with industry standards, including but not limited to: ASTM D7338-14
Standard Guide for Assessment of Fungal Growth in Buildings.
B. Containment of Areas
Establish containment barriers and negative air pressure to prevent the spread of spores during the remediation process.
C. Mold Abatement
Remove all visible fungal growth or contaminated materials, including drywall, insulation, ceiling tiles, and flooring. Clean and disinfect all surfaces in affected areas in accordance with industry standards, including but not limited to: Institute of Inspection, Cleaning and Restoration Certification (IICRC), ANSI/IICRC S520-2015 (or current edition), “Standard for Professional Mold Remediation”.
D. Waste Disposal
Properly dispose of all contaminated materials in accordance with local regulations.
E. Restoration and Replacement
Repair or replace damaged building materials, including drywall, insulation, ceiling tiles, and flooring in accordance with industry standards, including but not limited to: Institute of Inspection, Cleaning and Restoration Certification (IICRC), ANSI/IICRC S500-2021
(or current edition), “Standard and Reference Guide for Professional Water Damage
Restoration”
F. The Contractor shall furnish all labor, materials, and equipment to perform operations required to complete the total work in accordance to federal, state, and local regulations.
G. All work shall be approved and coordinated with an assigned and authorized facility
Contract Monitor prior to any work being performed. All work shall be performed to the complete satisfaction of the facility and until the job is completed. The Contractor shall not perform additional work not stated in specifications that may lead to additional costs without written approval from the Procurement Office before any modifications or alterations are made.
mailto:vbell1@maryland.gov
H. Reports-
1) The Contractor shall provide a written report of findings within 72 hours of testing with recommendations.
2) The Contractor shall provide documentation verifying that conditions are clear to normal based on successfully certified mold testing report with acceptable and safe air quality level.
3) When conditions represent a potential health hazard, the Contractor shall immediately inform the Department. The method of communication shall be established at the start of the contract.
G. Project Schedule
Work to begin upon Notice to Proceed and continue without interruption through completion. The Contractor shall work with the Contract Monitor to develop a written project schedule that meets the patient needs of the facility and does not interfere with patient programming.
H. The Contractor must comply with all facility security requirements to work at the facility, including but not limited to access and escorting, tool inventory, contraband compliance, and all requirements for contractors.
I. The Contractor shall meet all State, Federal and OSHA (Occupational Safety and Health
Administration) safety standards for the workplace.
J. The State of Maryland’s Commitment to Purchasing Environmentally Preferred Products and Services (EPPs)
Maryland’s State Finance & Procurement Article §14-410 defines environmentally preferable purchasing as “the procurement or acquisition of goods and services that have a lesser or reduced effect on human health and the environment when compared with competing goods or services that serve the same purpose.” Accordingly, Bidders are strongly encouraged to offer EPPs to fulfill this contract, to the greatest extent practicable.
5. State Staff and Roles
A. Contract Monitor
1) The State will provide a Contract Monitor, who may select a designee, with responsibility for providing authorization for work to be performed and validation of completed work under this solicitation and subsequent contract.
2) The Contract Monitor will designate additional personnel and will provide associated contact information as needed.
3) The Contract Monitor or their designee shall provide access to work areas required to complete assigned tasks pursuant to this solicitation and subsequent contract.
https://trackbill.com/bill/maryland-house-bill-629-environmentally-preferable-procurement-maryland-green-purchasing-committee/647077/
6. Contract term
A. The contract resulting from this solicitation shall commence upon the Notice to Proceed and continue for a period of approximately three to six months, with no option periods.
B. The total cost of work shall not exceed $50,000.00 for the term of the contract.
7. Procurement method This Contract will be awarded in accordance with the Small Procurement method under COMAR
21.05.07.
8. Bid/Proposal submission information
A. The Bid/Proposal is due on September 24, 2026, at 2:00 p.m. Local Time (Key
Information Sheet)
B. Bids may only be submitted via eMMA (eMaryland Market Place Advantage.
Bidders shall provide their Bids in one submission through eMMA following the
Quick Reference Guides (QRG). Please DO NOT hand deliver any replies to the facility.
C. What must be submitted.
1) The bid form with appropriate pricing.
2) A transmittal letter prepared on the Bidder’s business stationery MUST accompany the bid. The purpose of this letter is to transmit the bid and references; therefore, it should be brief. The letter shall be signed by an individual or corporate officer who is authorized to bind his firm to all statements, including services, material availability, timeliness and prices contained in the bid.
3) At least three (3) references that can attest to the Contractor’s experience in providing services for a similar business entity of this nature.
4) With the transmittal letter, each Contractor is to provide a list of all contracts with any entity of the State of Maryland that it is currently performing, or which have been completed within the last five (5) years. For each identified contract the Contractor is to provide:
a) The State contracting entity.
b) A brief description of the services/goods provided.
c) The dollar value of the contract.
d) The term of the contract.
e) The State employee contact person (name, title, telephone number and e-mail address).
f) Whether the contract was terminated before the end of the term specified in the original contract, including whether any available renewal option was not exercised.
5) Qualifications documentation that may be required, as set forth in RFB Section
2. Minimum Qualifications. Failure to submit the bid form or documentation as stated in Section 2 will result in the Contractor's offer being deemed ineligible for consideration.
6) Additional required attachments listed in Section 17.
7) Any Addendum posted after this solicitation with required signatures.
D. Inquiries Statement:
1) Written questions from prospective Bidders will be accepted by the
Procurement Officer and shall be submitted via eMMA to the Procurement
Officer indicated in Section 3 of this document. Questions should be submitted no later than September 18, 2026, by 12:00 p.m. Local Time, (Key
Information Summary Sheet)
2) The Procurement Officer, based on the availability of time to research and communicate an answer, shall decide whether an answer can be given before the Bid due date.
9. Award Determination
A. The Contract to result from this solicitation will be awarded to the Bidder submitting the
Most Favorable Bid Price (“Most favorable” is defined in COMAR 21.01.02.01.B. (57).
B. The Most Favorable Bid Price, will be determined by the “lowest responsive bid from a responsible bidder”.
10. Payment
The Contractor shall bill the Department on a monthly basis for the work performed the previous month. The total cost of work may not exceed $50,000.00 for the term of the contract.
A. To be considered for payment, submission of a proper invoice must include the following information, without error:
1) Contractor name and address;
2) Remittance address;
3) Federal taxpayer identification (FEIN) number, social security number, appropriate;
4) Invoice period (i.e. time period during which services covered by invoice were performed);
5) Invoice date;
6) Invoice number;
7) State assigned Contract number;
8) State assigned (Blanket) Purchase Order number(s);
9) Goods or services provided;
10) Amount due; and
11) Any additional documentation required by regulation or the Contract.
B. The State reserves the right to reduce or withhold Contract payment in the event the
Contractor does not provide all required deliverables within the time frame specified in the Contract or otherwise breaches the terms and conditions of the Contract until such time as the Contractor brings itself into full compliance with the Contract.
C. The State is generally exempt from federal excise taxes, Maryland sales and use taxes, District of Columbia sales taxes and transportation taxes. The Contractor, however, is not exempt from such sales and use taxes and may be liable for the same. Invoices for final payment shall be clearly marked as “Final” and submitted when all work requirements have been completed, and no further charges are to be incurred under the Contract. In no event shall any invoice be submitted later than sixty (60) calendar days from the Contract termination date. The Contractor shall submit invoices by the 15th of the month in which services were delivered. Invoices must be addressed to:
Chief Financial Officer
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd.
Jessup, MD 20794
Invoices may be mailed to the address above or electronically submitted to:
dlctphcfiscalservices_MDH@maryland.gov
11. Contractor’s Responsibilities Upon Award A. Man/Person-hours paid under this contract shall be only for productive hours at the job site. Time spent for idle time, breaks and lunch is not directly chargeable but is overhead and shall be included in the hourly rate bid for basic labor.
B. All parts and materials used by the contractor shall be billed to CTPHC at actual cost to the Contractor. No mark-up cost in addition to the cost to the Contractor will be accepted
C. Upon completion of the service, the Contractor must obtain signed verification from the contract monitor or designee that the service has been performed. All inspections shall be coordinated with the contract monitor or designee and any problems which require attention shall be reported to the contract monitor or designee.
D. Any failure by the Contractor to become acquainted with available information shall not relieve the Contractor from the responsibility for estimating properly the difficulty or cost of successfully performing the work. Clifton T. Perkins Hospital Center assumes no responsibility for any conclusions or interpretations made by the Contractor on the basis of the information made available by Clifton T. Perkins Hospital Center.
E. Travel time for service calls shall be the sole responsibility of the Contractor, and the
Contractor shall bear the cost as part of the Contractor’s base bid proposal.
12. Department Obligations
The department agrees to:
A. Provide guidance concerning contract activities, as needed;
B. Evaluation and acceptance when appropriate of deliverable
C. Review and approval for payment of invoices.
13. Small Business Reserve Requirements A. This is a Small Business Reserve Procurement for which award will be limited to certified small business Contractors. Only businesses that meet the statutory requirements mailto:dlctphcfiscalservices_MDH@maryland.gov set forth in State Finance and Procurement Article, §§14-501 —14-505, Annotated Code of Maryland, and that are certified by the Governor’s Office of Small, Minority &
Women Business Affairs (GOSBA) Small Business Reserve Program are eligible for award of a contract.
14. Insurance Requirements The Contractor shall maintain, at a minimum, the insurance coverages outlined below, or any minimum requirements established by law if higher, for the duration of the Contract:
A. Commercial General Liability – Five hundred thousand dollars ($500,000) combined single limit per occurrence for bodily injury, property damage, and personal and advertising injury and 1.5 million dollars ($1,500,000) annual aggregate. The minimum limits required herein may be satisfied through any combination of primary and umbrella/excess liability policies.
B. Worker’s Compensation - The Contractor shall maintain such insurance as necessary or as required under Workers’ Compensation Acts, the Longshore and Harbor Workers’
Compensation Act, and the Federal Employers’ Liability Act, to not be less than. one million dollars ($1,000,000) per occurrence (unless a state’s law requires a greater amount of coverage). Coverage must be valid in all states where work is performed.
C. The State shall be listed as an additional insured on the faces of the certificates associated with the coverages listed above, including umbrella policies, excluding
Workers’ Compensation Insurance and professional liability.
D. All insurance policies shall be endorsed to include a clause requiring the insurance carrier to provide the Procurement Officer, by certified mail, not less than 30 days’ advance notice of any non-renewal, cancellation, or expiration. The Contractor shall notify the
Procurement Officer in writing, if policies are canceled or not renewed within five (5) days of learning of such cancellation or nonrenewal. The Contractor shall provide evidence of replacement insurance coverage to the Procurement Officer at least 15 days prior to the expiration of the insurance policy then in effect.
E. Any insurance furnished as a condition of the Contract shall be issued by a company authorized to do business in the State.
F. The recommended awardee must provide current certificate(s) of insurance with the prescribed coverages, limits and requirements set forth in this section within five (5)
Business Days from the notice of the recommended award. During the period of performance for multi-year contracts, the Contractor shall provide certificates of insurance annually, or as otherwise directed by the Contract Monitor.
G. Subcontractor Insurance
The Contractor shall require any subcontractors to obtain and maintain comparable levels of coverage and shall provide the Contract Monitor with the same documentation as is required of the Contractor.
15. Security Requirements The following requirements are applicable to the Contract upon award:
A. Employee Identification:
1) Contractor Personnel shall display his or her company ID badge in a visible location at all times while on State premises. Upon request of authorized State personnel, each Contractor Personnel shall provide additional photo identification.
2) Contractor Personnel shall cooperate with State site requirements, including but not limited to, being prepared to be escorted at all times, and providing information for State badge issuance.
3) Contractor shall remove any Contractor Personnel from working on the Contract where the State determines, in its sole discretion, that Contractor Personnel has not adhered to the Security requirements specified herein.
4) The State reserves the right to request that the Contractor submit proof of employment authorization of non-United States Citizens, prior to commencement of work under the Contract.
B. Persons with a criminal record may not perform services under the Contract unless prior written approval is obtained from the Contract Monitor. The Contract Monitor reserves the right to reject any individual based upon the results of the background check.
Decisions of the Contract Monitor as to acceptability of a candidate are final. The State reserves the right to refuse any individual Contractor Personnel to work on State premises, based upon certain specified criminal convictions, as specified by the State.
16. Verification of Registration and Tax Payment A. Before a business entity can do business in the State, it must be registered with the State
Department of Assessments and Taxation (SDAT). SDAT is located at State Office
Building, Room 803, 301 West Preston Street, Baltimore, Maryland 21201. For registration information, visit https://egov.maryland.gov/BusinessExpress/.
B. It is strongly recommended that any potential Bidder complete registration prior to the
Bid due date and time. The Bidder’s failure to complete registration with SDAT may disqualify an otherwise responsive successful Bidder from final consideration and recommendation for Contract award.
17. Attachments A. Exhibit A-Contractor Construction Guidelines
B. Exhibit B-1 Bid Form
C. Exhibit C-Small Procurement Contract (Example)
D. Exhibit D-Contractor Daily Report
E. Exhibit E-Acknowledgement of Confidentiality Form
F. Exhibit F-Contractor Safety Reference Sheet
G. Exhibit G-Outside Vendor Tool Inventory Form
H. State Links for Bid Attachments to Include:
Bid/Proposal Affidavit
Bidder/Offer Information Sheet
Conflict of Interest Affidavit
Reference Checks
List of Current or Prior State Contracts
Legal Action Summary
List of All Subcontractors
Non-Disclosure Agreement (Contractor)
Contract Affidavit https://egov.maryland.gov/BusinessExpress/ https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-F.-Bidder-Offeror-Information-Sheet.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-M.-List-of-Current-or-Prior-State-Contracts.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-N.-Legal-Action-Summary.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-P.-Prime-Contractor-List-of-ALL-Subcontractors.xlsx https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-S.-Non-Disclosure-Agreement-Contractor.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf
File details come from the government source that posted it. Updated .