About this file
The document outlines the Board of Regents' (BOR) Bid Protest Procedures for public works and construction projects procured by the BOR. The procedures cover the right to protest, the form and filing deadline for protests, the evaluation process by the Director of Contracts & Services, available remedies for valid protests, and the process for appealing the Director's decision to the BOR Vice Chancellor for Facilities. Protests can be filed regarding the solicitation process or contract award, and must be submitted within specific timeframes. The Director of Contracts & Services will issue a written response within five working days, or provide a timeframe for completion if further investigation is required. If the protest is deemed valid, the Director may modify the solicitation, cancel the solicitation or contract award, or take other appropriate remedies. The protestor may then appeal the Director's decision to the Vice Chancellor for Facilities within five working days, whose decision is considered the final decision of the BOR.
The document does not provide details on a specific state or local contract opportunity. It only outlines the BOR's general bid protest procedures for public works and construction projects.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Board of Regents Bid Protest Procedures
This section describes the mandatory administrative procedure whereby vendors/bidders/offerors may challenge the solicitation process and/or contract awards for public works and/or public works construction projects procured by the Board of Regents.1
1.0 Right to Protest
Any actual or prospective bidder, proposer, offeror or contractor who is aggrieved in connection with a Board of Regents (“BOR”) solicitation or award of a contract shall have the right to file a protest. All protests shall be filed in the manner prescribed herein.
Protests that do not comply with this procedure shall be deemed invalid and of no effect.
2.0 Form of Protest and Filing Deadline
The protest must be in writing and signed by a company officer authorized to execute agreements on behalf of the bidder or offeror or provided by an authorized legal representative of the protestor. The protest must include, at a minimum, the following information:
name and address of the protestor;
identification of the solicitation or contract by the project name and/or project number;
a concise statement of the reasons(s) for the protest;
any supporting exhibits, evidence or documents to substantiate the claim(s); and desired remedy.
The protest shall be filed with the Director of Contracts & Services via any of the following means:
Mail: Board of Regents of the University System of Georgia Office of Real Estate & Facilities Attention: Director of Contracts & Services 270 Washington Street, SW Atlanta, GA 30333
Email: pwcprotest@usg.edu
Per O.C.G.A. §50-5-72, all public works and public works construction contracts contracted by the Board of
Regents are not required to be procured by the Department of Administrative Services (DOAS).
3.0 Filing Deadline
Protests concerning the solicitation process, including claims related to the specifications, request for proposal, request for qualifications and bid documents, shall be filed no later than three (3) working days prior to the solicitation closing date.
Protests concerning the selection of a vendor or contractor must be filed within five (5) working days from the posting of the award.
Any protest that is filed after these time periods shall be deemed invalid.
4.0 Protest Evaluation by the Director of Contracts & Services
The Director of Contracts & Services shall evaluate and make the initial determination of protest validity.
During this initial evaluation period BOR may, at its discretion, suspend further action on the solicitation or contracting.
The Director of Contracts & Services shall issue a written response to the protest within five
(5) working days of receipt of the protest. If the Director of Contracts & Services is unable to adequately investigate the claim within five (5) working days, a time for completion of the investigation shall be provided within five (5) working days of the protest.
5.0 Response to Valid Protest
If the Director of Contracts & Services determines that the protest is valid, the Director of
Contracts & Services shall determine the appropriate remedy. Available remedies include but are not limited to the following:
Modification of the solicitation document and extension of the solicitation period
Cancellation of the solicitation
Cancellation of the selection or award of contract
6.0 Costs
In no event shall a protesting party be entitled to recover any costs incurred in connection with the protest of a solicitation or contract award, including but not limited to bid or proposal preparation costs, protest preparation costs, or attorneys’ fees.
7.0 Appeal of the Decision of the Director of Contracts & Services
The protestor may appeal a decision of the Director of Contracts & Services. The protesting party shall file a written appeal with the BOR Vice Chancellor for Facilities after the Director of Contracts & Services has issued a written decision and no later than five (5) working days after receipt of the decision from the Director of Contracts & Services. Any appeal filed after that time period shall be deemed invalid.
Any appeal filed with the BOR Vice Chancellor for Facilities shall be sent by any of the following means:
Mail: Board of Regents of the University System of Georgia Office of Real Estate & Facilities Attention: Vice Chancellor for Facilities 270 Washington Street, SW Atlanta, GA 30333
Email: karen.rittler@usg.edu
The Vice Chancellor for Facilities shall review the appeal. The Vice Chancellor for Facilities or his/her designee may further investigate the claim and request additional information from the protestor or any source deemed helpful.
The Vice Chancellor for Facilities shall issue a written determination either confirming or overturning the decision of the Director of Contracts & Services within twenty (20) working days after receipt of the appeal. The decision of the Vice Chancellor for Facilities, either confirming or overturning the decision of the Director of Contracts & Services, shall be deemed to be the final decision of the BOR.