WATER SYSTEM IMPROVEMENTS AT VARIOUS LOCATOINS IN THE CITY OF DETROIT
Solicitation number
534156 / WS-741
Issued by
Michigan

About this file

This document is a comprehensive contract specification for Water System Improvements in the City of Detroit, issued by the Detroit Water and Sewerage Department (DWSD) and involving multiple local jurisdictions including the City of Detroit, Wayne County, and Michigan Department of Transportation. The project involves replacing approximately 22,580 linear feet of existing water mains ranging from four to eight inches in diameter, along with 875 existing water services. The work includes installing new gate valves, fire hydrants, and all necessary appurtenances. A critical component of the project is Lead Service Line Replacement, which requires the contractor to coordinate with DWSD's Lead Service Line Team for resident interactions, notice delivery, and providing water filtration pitchers.

The contract specifies detailed requirements for installation, restoration, and coordination, with strict adherence to local jurisdiction standards and permitting agency requirements. The contractor will be responsible for all underground utility work, with no additional compensation allowed for unmarked utilities. Specific technical specifications cover materials, installation methods, testing, and quality control, including precise requirements for concrete work, aggregate base, asphalt and concrete paving, and environmental controls. The contract includes provisions for comprehensive documentation, GPS tracking of installed infrastructure, and detailed testing and inspection protocols. Bidders must demonstrate capability in complex infrastructure replacement, environmental compliance, and community engagement.

View the file

Other files

File Type Posted
Book 3-WS-741 5.1.25.pdf PDF
Bid Schedule WS-741.xlsx XLSX spreadsheet
Book 1-WS-741-5.1.25.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAY 2025

CITY OF DETROIT

Mike Duggan, Mayor

CONTRACT NO. 534156

PROJECT NO. WS-741

TECHNICAL SPECIFICATIONS FOR

WATER SYSTEM IMPROVEMENTS AT VARIOUS

LOCATIONS IN THE CITY OF DETROIT

BOOK 2 OF 3

BOARD OF WATER COMMISSIONERS

Michael Einheuser, Chairperson

Mary E. Blackmon, Vice Chairperson

Lane Coleman

John Henry Davis

Linda Forte

Jane C. Garcia

Jonathan Kinloch

Gary Brown

Director

Mohamad Farhat, P.E.

Chief Engineer

Samuel Smalley, P.E.

Deputy Director

Istakur Rahman Chief Financial Officer

City of Detroit Mike Duggan, Mayor

Detroit City Council

Brenda Jones, President

Mary Sheffield, President Pro Tem

Janee′ Ayers

Scott Benson

Raquel Castaneda-Lopez

Gabe Leland

Roy McCalister Jr.

Andre Spivey

James Tate

CITY OF DETROIT

WATER AND SEWERAGE DEPARTMENT

CONTRACT NO. WS-741

WATER SYSTEM IMPROVEMENTS AT VARIOUS LOCATIONS IN THE CITY OF DETROIT

TABLE OF CONTENTS

SECTION DESCRIPTION

01 11 00

01 14 00

01 20 00

01 30 00

01 31 27

01 32 16

01 33 00

01 35 29

01 40 00

01 51 36

01 52 00

01 55 26

01 57 13

01 57 33

01 58 13

01 70 00

01 78 39

02 01 20

02 22 30

02 31 13.23

02 61 13

03 10 00

03 20 00

03 25 00

03 30 00

Summary of Work

Work Restrictions

Price and Payment Procedures

Administrative Requirements

Project Management Communications

Construction Progress Schedule

GPS Structure Documentation

Submittal Procedures

Safety Program

Quality Requirements

Temporary Water Service

Temporary Facilities

Traffic Control

Erosion Control Sedimentation and Containment of Construction Materials

Temporary Security Measures

Temporary Project Signage

Execution and Closeout Requirements

Electronic Project Record Documentation

Protecting Existing Underground Utilities

Pre-Construction Video and Photographic Record

Utility Line Removal

Excavation and Handling of Contaminated Materials

Concrete Forming

Concrete Reinforcing

Concrete Accessories

Cast-in-Place Concrete

01 32 25

SECTION DESCRIPTION

03 31 00 Construction and Expansion Joints

03 39 00 Concrete Curing

03 60 00 Grouting

26 05 26 Grounding and Bonding

31 10 00 Site Clearing

31 23 23.33 Flowable Fill

31 23 33 Trenching and Backfill

31 41 16 Sheet Piling

31 50 00 Excavation Support Systems

31 62 16 Steel Piles

32 11 23 Aggregate Base Courses

32 12 16 Asphalt Paving

32 13 13 Concrete Paving

32 31 13 Chain Link Fences and Gates

32 31 29 Wood Fences and Gates

32 92 19 Seeding

32 93 00 Plants

33 01 10.58 Disinfection of Water Utility Piping Systems

33 01 15.71 Cured-in-Place Water Main Lining

33 01 30.16 Sanitary Sewer Pipeline Inspection

33 01 30.18 Security Clearances and Communications

33 01 30.24 Water Main Pipe Bursting

33 05 07 Trenchless Installation of Utility Piping

33 05 07.13 Utility Directional Drilling

33 05 61 Concrete Manholes

33 05 63 Precast Concrete Vaults and Chambers

33 14 13 Public Water Utility Distribution Piping

33 14 17 Water Services

33 14 17.81 Lead Service Line Replacement

33 14 19 Valves and Hydrants for Water Utility Service

01 11 00 - 1

SUMMARY OF WORK

DWSD Standard Specification

December 2020

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Contract description.

2. Contractor's use of Site.

3. Work sequence.

4. Permits.

5. Specification conventions.

1.2 CONTRACT DESCRIPTION

A. Perform Work of Contract under unit price Contract with Owner according to Conditions of

Contract.

B. Description of Work included in the Project will be as presented in the Advertisement, Bid

Schedule, and/or Drawings.

1.3 CONTRACTOR'S USE OF SITE

A. Limit use of Site to allow:

1. Owner occupancy.

2. Work by Others, if any, as listed in the Contract Documents.

3. Use of Site by the public within public right of way.

B. Construction Operations: Limited to areas indicated on Drawings.

C. Time Restrictions for Performing Work: Comply with Section 01 14 00 – Work Restrictions.

D. Sound Level Restrictions: Sound pressure level measured at boundary of Site shall not exceed

90 dBA.

1.4 CLEANING OF SITE

A. On a daily basis, following completion of the Work (pipe installation, concreting and asphalting, spreading top soil, or sodding and seeding) and prior to leaving the Site, the

Contractor shall thoroughly clean the roadway and remove the excess material from the roadway so that it is not deposited in the roadway drainage system.

01 11 00 - 2

DWSD Standard Specification

December 2020

B. When directed by the Engineer, but not less than weekly, the Contractor shall sweep the streets with a street sweeper. The sweeper shall have a main broom, conveyor, sprinkler system, and a storage hopper. This requirement shall apply to any streets or roads in the vicinity of the Work which are affected by the Contractor's construction or hauling operations, and as well as to streets or roads in which the Work is located. Should the Contractor neglect his duties in maintaining the proper street or road cleanliness, the Owner has the authority to take necessary steps to perform such cleaning and will charge the Contractor for those costs.

C. The Contractor shall at all times keep the street pavement and right-of-way and any public or private premises temporarily occupied for purposes of Work under this Contract free from accumulations of waste material or rubbish caused by the Contractors employees or the Work.

This requirement shall apply to any streets in vicinity of the Work which are affected by the

Contractor's construction or hauling operations, as well as to streets in which the Work is located. If the Contractor shall fail to keep any street cleaned of debris resulting from their operations, and therefore creating a public nuisance, they shall be notified in writing by the

Engineer to clean the street and remove the nuisance immediately. If, within 24 hours after the receipt of such notice, the Contractor shall have failed to clean such street satisfactorily, the

Engineer shall order the street cleaned by the Department of Public Works or such other agency and all costs of such cleaning shall be paid by the Contractor.

D. Dirt, mud, construction materials or other debris deposited on public sidewalks or streets as the result of spilling, tracking by the wheels of trucks or construction equipment or by other actions of the Contractor, his employees or subcontractors shall be immediately removed by the

Contractor.

E. Unless otherwise stated in the milestones in the Contract Documents, the Contractor shall have all hard surfaces restored within thirty (30) days which shall include all cleaning of the Site and the requirements as listed herein.

1.5 MATERIAL STORAGE

A. Comply with Section 01 52 00 Temporary Facilities for all temporary staging area requirements for material, equipment, and supplies.

B. Materials delivered on the street shall be neatly and compactly stored in such a manner as to cause the least inconvenience to adjacent property owners and the general public.

C. Working and storage areas shall be promptly restored to their original conditions as soon as the required construction work has been completed at the particular location and shall not be used as a storage area for unneeded material or construction equipment.

D. All materials delivered and stored in close proximity to the working area shall be properly barricaded and protected maintaining a safe Site for workers and the general public.

E. Only materials and construction equipment currently being used may be stored at the construction site and within the jurisdictional right of way.

01 11 00 - 3

DWSD Standard Specification

December 2020

1.6 WORK SEQUENCE

A. Construct Work in phases during construction period. Coordinate construction schedule and operations with Owner.

1.7 PERMITS

A. Acquire necessary permits for construction of Work as listed in Book 1 of the Contract

Documents.

1.8 SPECIFICATION CONVENTIONS

A. These Specifications are written in imperative mood and streamlined form. This imperative language is directed to Contractor unless specifically noted otherwise. The words "shall be" are included by inference where a colon (:) is used within sentences or phrases.

1.9 STANDARD SPECIFICATIONS AND DETAILS

A. These Specifications include sections that may or may not be directly relevant to the Work of this Contract as described in the Contract Documents. Some Specifications are included for reference and will only be relevant if the Specification topic is encountered or required over the course of the Work as a result of the Contractor’s performance and Site conditions.

B. All DWSD Standard Specifications as listed on the DWSD website shall be referenced and used as relevant to the performance of the Contract work.

C. DWSD Standard Details may be included for reference in the Drawings or Contract Documents.

All DWSD Standard Details as listed on the DWSD website shall be used and referenced as relevant to the performance of the Contract work.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 11 00

01 14 00 - 1

WORK RESTRICTIONS

DWSD Standard Specification

January 2021

SECTION 01 14 00 - WORK RESTRICTIONS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Requirements.

2. Private Land.

3. Planned Construction Locations.

4. Open Excavations.

5. Test Pits.

6. Cooperation within this Contract.

7. Protection of Construction and Equipment.

8. Precautions during Adverse Weather.

9. Confined Space Entry.

1.2 REQUIREMENTS

A. Coordination:

1. Furnish personnel, equipment and construction aids that will be efficient, appropriate, and sufficient to secure a satisfactory quality of work as defined by the specification and a rate of progress that will ensure the completion of the Work within the time stipulated in the Contract Documents.

2. Coordinate with MISS DIG (811) and other Agencies having jurisdiction over property or structures in and around the construction area and locate all utilities potentially affected by the Work.

3. If at any time, Contractor’s resources appear to the Engineer to be inefficient, inappropriate, or insufficient to achieve the required quality or rate of progress of the

Work, the Engineer may ask the Contractor to increase the efficiency, change the character, or increase the number of personnel and equipment to meet the schedule of the

Contract. Failure of the Engineer to give such direction shall in no way relieve the

Contractor of its obligations to secure the required quality or rate of progress of Work.

B. Hours of Work:

1. Contractor may normally prosecute the Work during the daylight hours, and in no case earlier than 7 AM or later than 7 PM of any weekday, providing that the operations are conducted as to not create a public nuisance or disturb the peace. However, should the

Contractor be stopped, by order of a public authority, from working at times that are contrary to or in violation of any law, ordinance, permit, or license, the Contractor shall not be entitled to an extension of time due to such stoppages.

01 14 00 - 2

2. At the beginning of Work, notify the Engineer in writing, of the days and hours that will constitute a normal work week. Whenever the Contractor intends to depart from the specified work week, the Contractor must request approval in writing so that the Engineer may review the request for approval and make the necessary arrangements to have required inspectors assigned to the Work. The request shall be made at least two (2) calendar days prior to the requested deviation from the specified work week. If an emergency arises that would require work to be performed outside of the normal working hours of the specified work week to save or protect life or property, the requirements of the request for approval would be waived. Notify the Engineer as soon as the Contractor determines that an emergency exists that necessitates a change in or extension of the normal hours of work. However, the Contractor’s determination of the existence of an emergency is subject to review and revision by the Engineer.

C. Shutdowns:

1. A shutdown shall be defined as a portion of the normal operation of a unit or conduit that has to be suspended or taken out of service in order to perform the specified Work. For each shutdown, compile an inventory of labor and materials required to perform tasks, an estimate of the time required, including time for the Owner to take down and start up the unit or conduit, and a written description of steps required to complete all tasks. The inventory, the estimate, and written procedures shall be submitted to the Engineer for review 30 calendar days prior to the proposed start date of the shutdown. Request, in writing from the Engineer, approval for each shutdown a minimum of 14 calendar days prior to the proposed shutdown date. No shutdown shall be initiated until the inventory of materials and labor is verified by the Engineer on site prior to the proposed start date.

2. The Work required herein and any other Work required by the Engineer which may interrupt the normal operations shall be accomplished at such times that will be convenient to the Owner whether during the nighttime hours or during weekend hours.

The Contractor shall include in its bid price all overtime and/or premium time required for performing any work associated with these shutdowns.

3. Have on hand and located in close proximity to the Work area, all tools, equipment, spare parts and materials, both temporary and permanent, necessary to complete each Work category without interruptions. Adequate numbers of personnel shall be scheduled for each shutdown, so that the Work shall be accomplished within the specified time frame.

The Engineer shall be satisfied that Contractor has complied with these requirements, to the fullest extent possible, before shutdowns will be authorized.

4. If Contractor’s procedures cause an unscheduled shutdown of the facilities, perform all

Work necessary to immediately re-establish satisfactory operation. Notify the Engineer, in writing, immediately of any unscheduled shutdown. Permit Owner’s personnel to work with Contractor’s personnel, as deemed necessary by the Owner, to maintain the facilities in continuous satisfactory operation. Unscheduled shutdowns or interruptions of continued safe and satisfactory operation of the facilities that result in fines levied by regulatory agencies shall be the responsibility of Contractor if it is demonstrated that

Contractor was negligent in the Work or did not exercise proper precautions in the conduct of the Work.

01 14 00 - 3

5. Shutdowns of Electrical and Control Systems: Contractor and the Owner shall each lock out and tag circuit breakers and switches operated by the Owner and shall check cables and wires to be sure that they are de-energized to ground potential before Work begins.

Upon completion of the Work, remove the locks and tags and notify the Engineer that the facilities are available for use. The Owner will then remove its locks and place facilities back into use. The Contractor shall supply own locks. Locks shall be checked at the beginning of each shift. Comply with the Owner’s Lockout/Tagout procedure.

Shutdowns for any electrical wiring or I&C cables shall be coordinated with the Owner.

D. General Requirements:

1. Develop a program in cooperation with the Engineer to provide for the construction and putting into service the new work in the most orderly manner possible and in coordination with continued operations of the facilities and all ongoing construction projects at the time of construction of this project.

2. Adhere to such program except as deviations therefrom are expressly permitted in writing by the Engineer.

3. Plan all work of connecting with, cutting into, and reconstructing existing pipes or structures so as not to interfere with the operation and maintenance of the existing facilities. Schedule work that will affect operation of existing facilities for the shortest possible time and when the demands on the facilities best permit such interference, even though it may be necessary to work outside of normal working hours to meet these requirements.

4. For water main work, dewater process and utility pipelines back to the nearest closed valve at the beginning of each piping shutdown.

5. Provide all appropriate means and methods to ensure that water services in the areas and facilities associated with this project are maintained uninterrupted during construction.

6. Make minor modifications in such work relating to existing structures as may be necessary, without additional compensation.

7. Before starting any work which may interfere with the operation of the existing facilities, do all possible preparatory work and see that all tools, materials, and equipment to be installed are made ready and at hand.

8. Conduct construction operations in most orderly manners such that these operations:

a. Interfere as little as possible with the operations of the existing facilities and other ongoing construction contracts.

b. Does not damage existing equipment, structures, etc., or cause disruption to the operations of the existing facilities.

9. Make no claim for additional compensation by reason of delay or inconvenience in adapting construction operations to the need for continuous operations of the existing facilities.

10. Do not begin any portion of Work that will interfere with continued operations of the facilities until such schedule is accepted and approved in writing by the Engineer.

11. Contact the Systems Control Center fourteen (14) days prior to any required ‘Sewer

Shutdown’ or ‘Manned Entry’ required within the sewer. Complete an Equipment

01 14 00 - 4

Shutdown Request form and call 313-267-6000 to inform Systems Control of the planned shutdown and entry. Equipment Shutdown Request form is found attached to this specification.

1.3 PRIVATE LAND

A. Do not enter or occupy private land outside of the designated construction area or property limits, except as specified in the Contract Documents.

B. Provide Owner with copies of any agreements made by the Contractor with private land owners or other government agencies (i.e. Detroit Land Bank) to occupy or use their property.

C. Photographs and/or video shall be taken to document existing private land conditions and post construction conditions. The photographic documentation shall comply with Section 02 22 30

Pre-Construction Video and Photographic Record.

1.4 PLANNED CONSTRUCTION LOCATIONS

A. The work shall be installed substantially as indicated on the Drawings.

B. Where pipe fittings or other items are noted on the Drawings, such notation is for the

Contractor's convenience and does not relieve the Contractor from installing different or additional items where required to complete the work.

1.5 OPEN EXCAVATIONS

A. Comply with all requirements of MISS DIG Public Act 174 including contacting MISS DIG, hand excavation near utilities, and contacting 911 in case of emergency.

B. All open excavations shall be scheduled in advance with the Engineer and shall be coordinated in such a way to minimize disruption and provide full restoration as soon as possible.

C. Excavations shall have sloping, sheeting, shoring, and bracing conforming with 29CFR1926

Subpart P-Excavations, and OSHA requirements. Safeguard all open excavations by providing barricades, caution signs, lights, and other means to prevent accidents to persons or damage to property. Provide suitable and safe bridges and other crossings for accommodating travel by pedestrians and workmen. Bridges provided for access during construction shall be removed when no longer required. The length of an open trench shall always be confined to the limits prescribed by the Engineer. If the excavation becomes a hazard, or if it excessively restricts traffic at any point, the Engineer may require special construction procedures such as limiting the length of the open trench, prohibiting stacking excavated material in the street, and requiring that the trench not remain open overnight.

01 14 00 - 5

D. Take precautions to prevent injury to personnel due to open trenches. All trenches, excavated materials, equipment, or other obstacles that could be dangerous to the public, shall be well lit at night.

1.6 TEST PITS

A. Test pits for the purpose of locating underground pipelines or structures in advance of the construction shall be excavated and backfilled by the Contractor in accordance with project specifications and drawings.

B. Test pits shall be backfilled immediately after their purpose has been satisfied and the surface shall be restored and maintained in accordance with project specifications and drawings.

1.7 COOPERATION WITHIN THIS CONTRACT

A. Contractor and its subcontractors shall assist in incorporating the work of other trades where necessary or required.

B. Cutting, patching, drilling, and fitting shall be carried out by the trade or subcontractors having jurisdiction, unless otherwise indicated herein or directed by the Engineer.

C. Phase the Work so that all chases or openings for the installation of its own or any other

Contractor's or subcontractor’s work are available to prevent delays. All sleeves or forms delivered to the work area shall be properly set in ample time to prevent delays. All chases, openings, and sleeves shall be located accurately and are of proper size and shape. Consult with the Engineer and any Contractors and subcontractors related to this Work.

D. In case of failure to leave or cut all such openings or have all such sleeves provided and set in the proper time, cut them or set them afterwards at no additional expense to the Owner. In so doing, confine the cutting to the smallest extent possible consistent with the Work to be done.

In no case shall piers or structural members be cut without the written consent of the Engineer.

E. Carefully fit around, close up, repair, patch, and point around the Work specified herein to the satisfaction of the Engineer.

F. All of the Work shall be done carefully by workers competent to do such work and with the proper small hand tools. Power tools shall not be used except where, in the opinion of the

Engineer, the type of tool proposed can be used without damage to any Work or structures and without inconvenience or interference to the operation of any facilities. The Engineer's concurrence with the type of tools shall not in any way relieve or diminish the responsibility of the Contractor for such damage, inconvenience, or interference resulting from the use of such tools.

G. Do not alter or permit any worker or subcontractor to alter the Work of any other Contractor or subcontractors working on said job, except with written consent of the Contractor or

01 14 00 - 6 subcontractors whose Work is to be altered or with the written consent of the Engineer. All cutting, patching, or repairing made necessary by the negligence, carelessness, or incompetence of the Contractor or any of its subcontractors, shall be the responsibility of the Contractor and shall be done by or at the expense of the Contractor.

1.8 PROTECTION OF CONSTRUCTION AND EQUIPMENT

A. All newly constructed Work shall be carefully protected from damage in accordance with

Contract Documents. Wheeling, walking or placing of heavy loads will be minimized and the

Contractor, at its own expense, shall reconstruct any portions of the Site damaged.

B. All structures shall be protected in a manner approved by the Engineer. If, in the final inspection of the Work, any defects, faults, or omissions are found, repair or remove and replace utilizing specified materials and workmanship without extra compensation for the materials and labor required. Maintain and repair the construction and other Work undertaken herein, for the warranty period described in the Contract Document, or until the end of the maintenance period, whichever is longer.

C. Take all necessary precautions to prevent damage to any part of the Work due to water pressure during and after construction until such Work is accepted by the Engineer.

1.9 WINTER SHUTDOWN PROVISIONS

A. The winter shutdown requirements as listed below will pertain to water main and sewer Capital

Improvement Plan (CIP) Contracts. All other Contracts shall be excluded from winter shutdown provisions unless otherwise notified by the Owner.

B. Due to the extreme inconvenience to Detroit Water and Sewerage customers and the public in general, and also due to the impossibility of performing prompt, permanent restoration during the winter season, work on water main and sewer CIP Contracts shall be temporarily halted after the second week of November or as authorized by the Engineer. The Contract work shall promptly resume during the third week of April of the following year or as authorized by the

Engineer.

C. All requests to continue Work during the winter season shall be submitted via request for information (RFI) for approval from the Owner at least thirty (30) days prior to winter shutdown. The RFI shall include as a minimum:

1. Anticipated winter work schedule

2. Scope of work

3. Number of crews

D. The following items shall be completed by the Contractor prior to winter shutdown:

1. All Contractor’s equipment shall be removed from the site.

2. All pipe and materials not incorporated in the work shall be removed from the site.

01 14 00 - 7

3. Hard surfaces, where permanent restoration has not been made, shall have stone and cold patch installed subject to approval by the Engineer.

a. All hard surfaces must be restored within 30 days per the Contract unless otherwise stated in the Book 1 milestone dates.

4. All berm areas where mulched seeding has not been placed shall be rough graded and left free of depressions and piles of soil.

5. Repair of all known water main leaks.

6. Pumping out of all hydrants that were used.

7. Cleaning out of catch basins where required.

E. The above list is not inclusive. The site(s) shall be made safe to the general public and to abandoned in a manner to protect the Work. All winter shutdown provisions shall be performed to the satisfaction of the Engineer.

1.10 PRECAUTIONS DURING ADVERSE WEATHER

A. Take all necessary precautions during and against the possibility of adverse weather so that the

Work may be done properly and satisfactory in all respects. Protection shall be provided by use of tarpaulins, wood and building-paper shelters, or other suitable means. All protection during adverse weather must be securely fastened.

B. During cold weather, materials shall be preheated, if required, and the materials and adjacent structure into which they are to be incorporated shall be made and kept sufficiently warm so that a proper bond will occur, and proper curing, aging, or drying will result. Protected spaces shall be artificially heated by suitable means resulting in a moist or a dry atmosphere according to the particular requirements of the Work being protected. Ingredients for concrete and mortar shall be sufficiently heated so that the mixture will be warm throughout when used. Provide suitable means of protection to prevent freezing below slabs and any other Concrete Work to frost heave. This shall include all existing and new facilities. The Contractor shall be responsible for following all cold weather provisions as listed in the DWSD Standard

Specifications should the Contractor decide to continue work in cold weather.

1.11 CONFINED SPACE ENTRY

A. Applicable confined space entry procedures shall be followed.

B. At the preconstruction meeting, submit to the Engineer a copy of the Contractor’s safety plan for confined space entry in accordance with current OSHA and MIOSHA requirements. Prior to entry into any confined space, submit to the Engineer a copy of the daily entry permit in accordance with current OSHA and MIOSHA requirements.

C. Perform all work in accordance with the latest edition of Construction Safety Standards as adopted by the Michigan Department of Labor Construction Safety Standards for Occupational

Health.

01 14 00 - 8

D. Perform all work in accordance with the latest edition of Michigan Department of Environment, Great Lakes, and Energy Occupational Health Standard for Construction.

E. Comply with the latest edition of the requirements, specifications and standards as provided for under the Michigan Occupational Safety and Health Act., as amended, and in force at the date thereof and all other applicable Owner, Federal, State and Local requirements, ordinances, statutes and laws.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Provide materials for construction aids.

B. Materials for construction aids may be new or used provided they are suitable for the intended purpose and do not violate requirements of applicable codes and standards.

C. Maintain facilities and equipment in first-class condition.

2.2 CONSTRUCTION AIDS

A. Provide construction aids and equipment necessary to facilitate the execution of the Work, such as scaffolds, staging, ladders, stairs, ramps, runways, platforms, railings, hoists, cranes, chutes, and other such facilities and equipment. Refer to respective sections for particular requirements for each trade.

B. When permanent stair framing is in place, provide temporary treads, platforms, and railings for use by construction personnel.

PART 3 - EXECUTION

3.1 PREPARATION

A. Consult with the Engineer, review site conditions and factors that will affect construction procedures and identify necessary construction aids.

B. Determine if adjacent properties and public facilities will be affected by execution of the Work and develop strategies to address impacts.

3.2 INSTALLATION

A. Installation: According to OSHA/MIOSHA standards and manufacturer's instructions.

01 14 00 - 9

3.3 REMOVAL

A. Completely remove temporary materials, equipment, and services when construction needs can be met by use of permanent construction and at the completion of the Work. Remove foundations and underground construction aids. Grade areas of the site affected by temporary installations to required elevations and slopes and clear fire area.

B. Clean and repair any damage caused by installation or use of temporary facilities. Restore permanent facilities used for temporary purposes to original condition unless otherwise specified.

END OF SECTION 01 14 00

01 20 00 - 1

PRICE AND PAYMENT PROCEDURES

April 2025

SECTION 01 20 00 - PRICE AND PAYMENT PROCEDURES

PART 1 – GENERAL

1.1 SUMMARY

A. Section Includes:

1. Permit Allowances.

2. Provisional Allowances.

3. Contaminated Material Allowances.

4. Schedule of Values.

5. Application for Payment.

6. Change Procedures.

7. Defect Assessment.

8. Unit Prices.

9. Measurement and Payment General Notes.

10. Unit Price Schedule.

11. Hard and Soft Surface Restoration

1.2 PERMIT ALLOWANCES

A. If required, included in the Contract will be a stipulated sum/price for reimbursement of acquired permits as a permit allowance.

B. Costs Included in Permit Allowances: Cost of permit acquired by Contractor and applicable taxes. Any cost the Contractor deems necessary for overhead, profit, and other expenses on account of a permit allowance should be included elsewhere in the bid in the total Contract price.

C. Contractor Responsibilities:

1. Arrange for and acquire all necessary permits as stated in the Contract Documents.

2. Promptly inspect products upon delivery for completeness, damage, and defects. Submit claims for transportation damage.

D. Payment under permit allowances will be on an actual cost basis. The receipts for permits that have been secured by the Contractor shall be presented to the Owner for reimbursement.

E. At closeout of Contract, funds remaining in the permit allowance will be credited to Owner by Change Order.

1.3 PROVISIONAL ALLOWANCES

A. If required, included in the Contract will be a stipulated sum/price for use upon Owner's instruction as a provisional allowance. The provisional allowances are provided and to be used for additional/extra work authorized in advance of the work by the Owner.

B. Contractor's costs for products, delivery, installation, labor, payroll, taxes, equipment rental, overhead, and profit will be included in Construction Change Authorizations authorizing expenditure of funds from this

01 20 00 - 2 provisional allowance. Insurance and Bond premiums shall be included elsewhere in the bid and are not redeemable in the provisional allowance.

C. Funds will be drawn from provisional allowance only by a Construction Change Authorization.

D. At closeout of Contract, funds remaining in the provisional allowance will be credited to Owner by Change Order.

1.4 CONTAMINATED MATERIAL ALLOWANCES

A. If required, included in the Contract will be a stipulated sum/price for reimbursement of payment associated with the removal of contaminated material via a contaminated material allowance.

B. Requirements for the handling, hauling, disposal, and all associated costs and fees of hazardous waste materials; non-hazardous waste materials; and petroleum contaminated soils will be included in the reimbursement cost of the contaminated material allowance. If chemicals of concern found in groundwater are of a nature and/or concentration that necessitate handling the groundwater as hazardous material, reimbursement of costs will be provided under the contaminated material allowance.

C. Testing of contaminated material shall be responsibility of the contractor including paying for the cost for identifying whether the soil is contaminated or not contaminated. All costs for products, delivery, installation, labor, payroll, taxes, equipment, equipment rental, overhead, profit, field monitoring, on-site testing and laboratory testing for contaminated materials will be included elsewhere in the bid in the total Contract price and will not be included in the reimbursement via contaminated material allowance.

D. Payment under contaminated material allowances will be on an actual cost basis. The receipts for all reimbursement costs for the handling, hauling, disposal, and all associated costs and fees that have been incurred by the Contractor shall be presented to the Owner for reimbursement.

E. At closeout of Contract, funds remaining in contaminated material allowance will be credited to Owner by Change Order.

1.5 SCHEDULE OF VALUES

A. Submit printed schedule on Contractor's standard form or an approved electronic media printout will be considered for this use.

B. The Contractor shall submit a Schedule of Values for review and acceptance in agreement with the deadlines established in the Book 1 Contract Documents.

C. Format: Use Unit Price Schedule of this Specification. Identify each line item with number and title of major bid item followed by a schedule of values for payment including division of all Lump Sum items into a schedule of values for payment.

D. Revise schedule to list approved Change Orders and Construction Change Authorizations with each

Application for Payment.

01 20 00 - 3

1.6 APPLICATION FOR PAYMENT

A. Content and Format: Transmit application for payment using approved electronic procedures and forms. Use Schedule of Values for listing items in Application for Payment.

B. Payment Period: In accordance with the agreement between Owner and Contractor.

C. Substantiating Data: When Engineer requires substantiating information, submit data justifying dollar amounts in question.

D. Include the following as mandatory with each Application for Payment:

1. Contractor and Subcontractor waivers of claim: Partial release of liens from all Subcontractors and vendors.

2. Construction Progress Schedule revised and current as specified in Section 01 32 16 – Construction Progress Schedule.

3. Monthly Safety Reports.

E. Include the following with each Application for Payment if requested by the Engineer:

1. Current construction photographs specified in Section 01 33 00 - Submittal Procedures.

2. Record Documents as specified in Section 01 78 39 – Electronic Project Record Documentation and

Book 1 C-700 7.12, for review by Owner, which will be returned to Contractor.

3. Affidavits attesting to off-Site stored products.

4. Test reports and documentation

5. Updated Schedule of Submittals

6. Application for Payment Bid Items Supporting documentation, submittals, acceptance of work documents, etc.

1.7 CHANGE PROCEDURES

A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.

B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.

C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications.

1. Use e-Builder for requesting interpretations.

2. Engineer will respond with a direct answer on e-Builder or via a Field Order.

D. Engineer will advise of minor changes in the Work not involving adjustment to Contract Sum/Price or

Contract Time by issuing supplemental instructions on a Field Order Form.

E. Contractor shall submit a Change Proposal to propose changes on the Work. The request for change shall be submitted to the Engineer, describing proposed change and its full effect on the Work. Include a statement

01 20 00 - 4 describing reason for the change and the effect on Contract Sum/Price and Contract Time with full documentation and a statement describing effect on the Work by separate or other Contractors.

F. Work Change Directive: Engineer may issue directive, signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work and designate method of determining any change in Contract Sum/Price or Contract Time.

G. Stipulated Sum/Price Change Order: Based on Work Change Directive and Contractor's price quotation or

Contractor's request for Change Order as approved by Engineer.

H. Unit Price Change Order: For Contract Unit Prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, execute Work under Work Change Directive. Changes in Contract Sum/Price or Contract Time will be computed as specified for Time and Material Change Order.

I. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in Conditions of the Contract. Engineer will determine change allowable in Contract Sum/Price and Contract Time as provided in Contract Documents.

J. Maintain detailed records of Work done on time and material basis. Provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work.

K. Document each quotation for change in Project Cost or Time with sufficient data to allow evaluation of quotation.

L. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in Conditions of the Contract.

M. Correlation of Contractor Submittals:

1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Sum/Price.

2. Promptly revise Progress Schedules to reflect change in Contract Time, revise sub-schedules to adjust times for other items of Work affected by the change and resubmit.

3. Promptly enter changes in Record Documents.

1.8 DEFECT ASSESSMENT

A. Replace the Work, or portions of the Work, not conforming to specified requirements.

B. If, in the opinion of the Engineer, it is not practical to remove and replace the Work, the Engineer will direct appropriate remedy or adjust payment.

C. Individual Specification Sections may modify these options or may identify specific formula or percentage sum/price reduction.

D. Authority of the Engineer to assess defects and identify payment adjustments is final.

01 20 00 - 5

E. Non-Payment for Rejected Products: Payment will not be made for rejected products for any of the following reasons:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from transporting vehicle.

4. Products placed beyond lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

1.9 UNIT PRICES

A. Authority: Measurement methods are delineated as indicated below in the unit price schedule.

B. Contractor shall take measurements for installed items and compute quantities. Engineer may verify in place measurements and quantities prior to certifying the measurements, quantities, and invoices. Contractor shall take measurements for installed items and compute quantities. Engineer may verify in place measurements and quantities prior to certifying the measurements, quantities, and invoices. Access pipe lengths resulted from the Directional Drilling operation, Pipe Bursting operation and Water Main Lining Operation including any surplus pipes that is not part of the As Built will not be measured for the payment.

C. Unit Quantities: Quantities and measurements indicated on Bid Schedule are for Contract purposes only.

Actual installed quantities provided by the contractor shall be verified by the Engineer to determine the payment.

1. When actual Work requires more or fewer quantities than those quantities indicated, provide required quantities at contracted unit sum/prices.

2. When the extended price of a particular item of Unit Price Work amounts to 5 percent or more of the Contract Price (based on estimated quantities and Unit Prices in the Bid Schedule) and the variation in the quantity of that particular item of Unit Price Work actually furnished or performed by Contractor differs by more than 25 percent from the estimated quantity of such item indicated in the Bid Schedule, Owner or Contractor may claim a Contract Price adjustment.

D. Unit Quantities (O&M Contracts): Quantities and measurements indicated on Bid Schedule are for Contract purposes only. Actual quantities provided shall determine payment.

1. When actual Work requires more or fewer quantities than those quantities indicated, provide required quantities at contracted unit sum/prices.

2. The unit prices shall remain unchanged for the duration of the Contract regardless of the respective quantities used.

3. The Bidder agrees that the unit prices shall remain unchanged for the duration of the Contract and will not be increased regardless of the quantities used, whether the quantity of a particular item increases or decreases or if the item is not used at all.

E. Payment Includes: Full compensation for required labor, products, tools, equipment, plant and facilities, transportation, services, and incidentals; erection, application, or installation of item of the Work; overhead and profit, payroll, workman compensation and other taxes.

01 20 00 - 6

F. Final payment for Work governed by unit prices will be made on basis of actual measurements and quantities accepted by Engineer multiplied by unit sum/price for Work incorporated in or made necessary by the Work.

G. Measurement of Quantities:

1. Weigh Scales: Inspected, tested, and certified by applicable State weights and measures department within past year.

2. Platform Scales: Of sufficient size and capacity to accommodate conveying vehicle.

3. Metering Devices: Inspected, tested, and certified by applicable State department within past year.

4. Measurement by Weight: Concrete reinforcing steel, rolled or formed steel, or other metal shapes will be measured by handbook weights. Welded assemblies will be measured by handbook or scale weight.

5. Measurement by Volume: Measured by cubic dimension using mean length, width, and height or thickness.

6. Measurement by Area: Measured by square dimension using mean length and width or radius.

7. Linear Measurement: Measured by linear dimension, at item centerline or mean chord of As Built linear measurements.

8. Stipulated Sum/Price Measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as completed item or unit of the Work.

1.10 MEASUREMENT AND PAYMENT GENERAL NOTES

The following items will not be paid for separately. All associated costs for these items shall be included in the total price of the Contract and among the bid items included in the bid schedule.

A. Tree Trimming

B. Shop Drawings

C. Temporary Steel Plating

D. Flow Control and Bypass Pumping

1.11 UNIT PRICE SCHEDULE (CIP CONTRACTS)

The measurement and payment descriptions below are not meant to contain a full listing of all the requirements necessary for the acceptance of work under the Contract. The Work for all items below must be in accordance with all methods, submittals, and requirements as listed within the general conditions and the specifications of the Contract. Application of Wax Tape where specified in this section 01 20 00 Price and Payment Procedures means applying Wax Tape to all buried gate valves, curb valves, mechanical joints, flanges, restraint joint devices, corporations, service saddles, exterior of connections and fittings, steel rods, bolts, lugs, brackets in accordance with AWWA C217 and over-wrapping Wax Tape with one wrap of polyethylene encasement in accordance with AWWA C105. The cost of the Application of wax Tape will not be paid separately but included in respective pay items.

1.12 HARD AND SOFT SURFACE RESTORATION

The restoration of all site work across this project shall be defined to include Hard surface and Soft

01 20 00 - 7 surface restoration. Hard surface and soft surface restoration will not be measured and paid for separately but included in the related unit prices of work items. The hard and soft surface restoration of working area beyond the water main replacement stationing as shown on the WM drawings shall also be included in the unit prices of related watermain replacement work items. The hard surface and soft surface restoration shall include the following:

a. Furnishing materials, labor, equipment, and all other incidental materials necessary for the full restoration and final clean-up of the Site including but not limited to replacement and installation of sidewalks, driveways, curb, curb and gutter, full and/or partial depth HMA pavement, full and/or partial depth concrete pavement of City of Detroit residential and major streets; Wayne County roads and MDOT roads, brick pavers, regrading, placing 4-inch top soil, mulched seeding, sodding, watering and other restoration items.

b. Furnishing materials, labor, and equipment for Work associated with furnishing, placing, and preparation of base materials necessary for the installation of the surface concrete, HMA, brick, items as mentioned.

c. All Work under this item shall be performed to the standards, specifications, and requirements of the local jurisdiction or permitting agency with authority in the right of way where the work is performed.

d. Hard Surface and Soft Surface Restoration shall include and apply to the City of Detroit HMA residential streets, City of Detroit HMA Class C streets, City of Detroit Concrete Paving streets, City of Detroit residential streets with HMA surface over concrete base, City of Detroit Major streets which shall be constructed to the minimum requirements as identified in the cross-section details in the Drawings, per the DPW Standard Specifications for Paving and Related Construction, and the DPW Street and Alley Standard Plans, and the roads under the Wayne County and Michigan Department of Transportation jurisdiction abiding by their standards and permit requirements.

The following non-exhaustive list describes typical work that is included with Hard Surface and Soft Surface Restoration.

Concrete Curb and Concrete Curb and Gutter

The materials, labor, equipment, and all other incidental materials necessary for removal and installation of Concrete Curb and Concrete Curb and Gutter including removals, preparation of subgrade; furnishing reinforcement bars, dowels, tie bars, joint filler, sealant, and accessories;

furnishing, forming, finishing, curing, and sealing concrete curb.

Aggregate Base

The materials, labor, equipment, and all other incidental materials necessary for the removal and furnishing, placing, and compacting of aggregate base.

All aggregate base material and procedures shall be of the type and placed to the standards, specifications, and requirements of the local jurisdiction or permitting agency with authority in

01 20 00 - 8 the right of way where the work is performed.

Concrete Base

The materials, labor, equipment, and all other incidental materials necessary for the removal and installation of concrete base including removal, furnishing reinforcement bars, dowels, tie bars, joint filler, sealant, and accessories; furnishing, forming, finishing, curing, and sealing concrete base. When restoring within Detroit DPW right of way, the concrete base shall be placed per DPW requirements which state that the removal and replacement of concrete base must be from existing joint to joint.

All concrete base material and procedures shall be of the type and placed to the standards, specifications, and requirements of the local jurisdiction or permitting agency with authority in the right of way where the work is performed.

HMA Pavement Milling

The materials, labor, equipment, and all other incidental materials necessary for the removal of HMA pavement materials including milling, hauling, and disposal.

Milling shall be performed in accordance with Detroit DPW requirements which state to mill HMA pavement beyond the area of the trench removal in order to determine location of under-lying concrete base pavement joints and shall be a minimum width of one lane, full roadway, or as shown on the plans.

HMA Pavement

The materials, labor, equipment, and all other incidental materials necessary for the installation of HMA pavement materials including cleaning and preparing concrete base; furnishing and placing tack coat and prime coat; furnishing, placing, compacting HMA pavement.

Permanent pavement markings are to be furnished and installed following the acceptance of HMA Pavement installation and are to be in accordance with Michigan Manual on Uniform Traffic Control Devices and MDOT Pavement and Standard Marking Plans…