STATEMENT OF WORK 7274
This work is being done to upgrade Ellsworth Air Force Base’s Energy Management Control System (EMCS) at Building 7274. The Honeywell controls shall be upgraded from C-Bus protocol to BACnet protocol and the building HVAC (Heating, Ventilation, and Air Conditioning) controllers, thermostats, and bus wire will all be replaced. This is a purchase for labor and parts to complete job.
HONEYWELL contractor shall:
1. Install new BACnet bus communication wire (approximately 2500’) in a polarity sensitive daisy chain pattern to all the thermostats, VAV controllers and Comfort Point Open controllers.
2. Replace the existing (2) Zone Manager controllers, (2) Honeywell XL500 controller, (1) Honeywell XL 100, (1) Honeywell XL 50, (65) VAV controllers with thermostats and (1) BNA (Building Network Adapter) with (4) CPO-PC410 controllers, (2) CPO-RL5 controllers and (65) CPO-VAV2A controllers with thermostats. All field controllers must be Comfort Point Open style controllers programmed with Comfort Point Open Studio. Comfort Point Jace and all other Jace controllers are not allowed on the Ellsworth base network.
3. Rewrite the HVAC building program with Honeywell Comfort Point Open Studio version 230 software and at the completion of the project install, the Comfort Point Open software program shall become the property of Ellsworth AFB.
4. Contractor must complete a 100% VAV and building data point commission to insure all wires are terminated correctly and all dampers/actuators are moving in the right direction.
5. Integrate the Comfort Point Open BACnet data points into the Honeywell EBI R500 front end server. Delete all of the existing Excel 5000 data points associated with building 7274. Build graphics using HMI web Builder on the Honeywell EBI R500 server for all new BACnet data points within the new graphics.
6. The contract shall provide a new Honeywell EBI R500 server license to account for the new BACnet data points gained in order in integrate into the Honeywell EBI R500 server.
Period of Performance: As mutually agreed to by both parties but, not more than 180 days.