BL097_26 INV.pdf
PDF 1 MB Posted
- Solicitation number
- PE-77023-NONST-2026-000000635
- Issued by
- Gwinnett County, Georgia
About this file
This is a Notice of Bid (BL097-26) issued by the Gwinnett County Board of Commissioners for the Bethesda Park Aquatic Center Wall Tile and Floor Tile Replacement project, soliciting competitive sealed bids from qualified contractors for the Gwinnett County Department of Parks and Recreation. The scope of work includes removing and replacing tile floors and walls in the locker rooms and restrooms at Bethesda Park Aquatic Center, located at 225 Bethesda Church Road, Lawrenceville, Georgia 30044. The project encompasses both base bid and alternate bid components, with the base bid covering wall tile and floor tile replacement using 12" x 24" large format ceramic wall tiles and 1" x 1" or 2" x 2" small format ceramic floor tiles, along with associated materials such as epoxy grout and polymer-modified thinset. A pre-bid conference is scheduled for 10:00 a.m. on June 16, 2026, at the Bethesda Park Aquatic Center. Sealed bids must be received by 2:50 p.m. on July 9, 2026, at the Gwinnett County Purchasing Division, 75 Langley Drive, Lawrenceville, Georgia 30046. The bid opening will be held virtually via Microsoft Teams on July 9, 2026, at 3:00 p.m. The project must be completed between September 14, 2026, and October 16, 2026, during facility closure for other construction. The alternate scope of work includes removal and reinstallation of restroom and locker room fixtures, including lockers, stall partitions, shower equipment, toilets, urinals, and sinks.
All contractors must submit a bid bond, certified check, or cashier's check equal to five percent (5%) of the total bid amount and must demonstrate at least five years of commercial flooring experience with three references from similar projects completed within the past five years. The successful contractor shall provide a 100% performance bond and 100% payment bond, with all bonds and insurance from companies rated A-7 or higher by A.M. Best and licensed to do business in Georgia. Pricing must be submitted as lump sum fees for both the base bid and alternate components and must include all charges associated with labor, materials, installation, and travel. The contractor shall provide warranty for a minimum of one year from the date of completion. Work hours shall typically be 7:00 a.m. to 3:30 p.m., Monday through Friday, with specific hours to be agreed upon with the county representative. Questions regarding the bid should be directed to Jake Scarpone, Purchasing Associate II, at jake.scarpone@gwinnettcounty.com or 770-822-8722, no later than 3:00 p.m. on June 22, 2026. The county reserves the right to reject any or all bids, waive technicalities, and negotiate terms and conditions with the lowest responsive and responsible bidder at its discretion.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
June 10, 2026
NOTICE OF BID
BL097-26
Bethesda Park Aquatic Center Wall Tile and Floor Tile Replacement
The Gwinnett County Board of Commissioners is soliciting competitive sealed bids from qualified contractors for Bethesda Park Aquatic Center Wall Tile and Floor Tile Replacement for the Gwinnett County Department of Parks and Recreation.
Bid submittal date and location Bids should be typed or submitted in ink and returned in a sealed container marked on the outside with the BL# and Company Name. Bids will be received until 2:50 P.M. local time on July 9, 2026 at the Gwinnett County Purchasing Division, 75 Langley Drive, Lawrenceville, Georgia 30046. Any bid received after this date and time will not be accepted. The bid opening will be held VIRTUALLY ONLY. To access the bid opening, use the following link (https://teams.microsoft.com/meet/229678536420349?p=R4uVQBHHC46DfrQDbr) and use Meeting ID 229 678 536 420 349 and Passcode Py2wM22N. Bids will be publicly opened and read at 3:00 P.M. Apparent bid results will be available the following business day on our website www.gwinnettcounty.com.
Pre-Bid Conference A pre-bid conference is scheduled for 10:00 a.m. on June 16, 2026 at the Gwinnett County Bethesda Park Aquatic Center, located at 225 Bethesda Church Rd., Lawrenceville, GA 30044. All contractors are urged to attend.
Project Description The successful contractor shall furnish all labor and materials required to remove and replace tile floors and walls in the locker rooms and restrooms at Bethesda Park Aquatic Center.
Instructions on Submitting Questions Questions regarding bids should be directed to Jake Scarpone, Purchasing Associate II, at jake.scarpone@gwinnettcounty.com or by calling 770-822-8722, no later than 3:00 P.M. on June 22, 2026. Bids are legal and binding upon the bidder when submitted.
Bonding and Insurance All contractors must submit with bid, a bid bond, certified check or cashier's check in the amount of five percent (5%) of the total bid. Failure to submit a bid bond with the proper rating will result in the bid being deemed non-responsive. Successful contractor will be required to meet insurance requirements, submit a one hundred percent (100%) performance bond and a one hundred percent (100%) payment bond. Insurance and Bonding Company should be licensed to do business by the Georgia Secretary of State, authorized to do business in Georgia by The Georgia Insurance Department, listed in the Department of Treasury's Publication of Companies holding Certificates of Authority as Acceptable Surety on Federal Bonds and as acceptable reinsuring companies. The bid bond, payment bond, and performance bond must have an A.M. Best rating of A-7 or higher.
Facility Access Gwinnett County does not discriminate on the basis of disability in the admission or access to its programs or activities. Any requests for reasonable accommodations required by individuals to fully participate in any open meeting, program or activity of Gwinnett County Government should https://teams.microsoft.com/meet/229678536420349?p=R4uVQBHHC46DfrQDbr http://www.gwinnettcounty.com/
Gwinnett County, Georgia Page 2 Bethesda Park Aquatic Center Wall Tile and Floor Tile Replacement BL097-26 be directed to the ADA Coordinator, Gwinnett County Justice and Administration Center, 770-822- 8165.
The written bid documents supersede any verbal or written prior communications between the parties.
Award will be made to the contractors submitting the lowest responsive and responsible bid. Gwinnett County reserves the right to reject any or all bids to waive technicalities and to make an award deemed in its best interest. Bids may be split or awarded in entirety. Gwinnett County reserves the option to negotiate terms, conditions and pricing with the lowest responsive, responsible bidder(s) at its discretion.
Award notification will be posted after award on the County website, www.gwinnettcounty.com and companies submitting a bid will be notified via email.
We look forward to your bid and appreciate your interest in Gwinnett County.
Jake Scarpone, CPPB Purchasing Associate III http://www.gwinnettcounty.com/
Gwinnett County, Georgia Page 3
BETHESDA PARK AQUATIC CENTER WALL TILE AND FLOOR TILE REPLACEMENT
SPECIFICATIONS
Bethesda Park Aquatic Center
225 Bethesda Church Road Lawrenceville, GA 30044
I. SCOPE OF WORK – BASE BID
Gwinnett County Department of Parks and Recreation is soliciting competitive bids from qualified contractors for the removal and replacement tile floors and walls at Bethesda Park Aquatic Center. The successful contractor shall furnish all labor and materials required to remove and replace tile floors and walls at Bethesda Park Aquatic Center.
II. DESCRIPTION OF WORK
1. Contractor shall provide samples of both floor and wall tiles with a mockup board prior to beginning work. Tile color and texture must be approved by the County Representative.
2. Contractor shall remove all existing wall tiles.
3. Contractor shall remove all existing floor tiles and mud bed.
4. Contractor shall clean and prepare all surfaces for new tile.
5. Contractor shall install new mud bed and ensure all floors slope towards drains.
6. Contractor shall install new County-approved large format 12” x 24” tile one walls.
7. Contractor shall install new County-approved small format tile 1” x 1” or 2” x 2” on floors.
8. Contractor shall install grout, sealer and thresholds.
III. QUALITY ASSURANCE
1. Contractor must have at least 5 years of commercial flooring experience.
2. All work must meet ANSI A108/A118/A136.1:2024-08 standards.
3. Contractor must test and confirm all floors slope towards drains to ensure there is no puddling.
IV. STORAGE
1. The successful contractor shall be responsible for storing all materials in accordance with the manufacturer’s specifications.
2. Gwinnett County is not responsible for the storage of materials.
3. All materials should be stored in areas that are not accessible to the public.
V. WORK CONSTRAINTS
1. The affected area will be closed to the public, but the remainder of the facility and park will be open to the public. The successful contractor shall take proper precautions to block off, barricade, and cover in-process work areas to protect the floor.
2. Hours of work shall be agreed upon by the successful contractor and the County representative. Typical work hours are from 7:00 AM until 3:230 PM, Monday through Friday.
3. Project must be completed between September 14, 2026 and October 16, 2026 while the facility is closed for other construction.
Gwinnett County, Georgia Page 4
VI. MATERIALS
The successful contractor must submit samples of flooring materials to the Gwinnett County Representative for final approval of color and texture before beginning installation.
1. Thinset shall be of the polymer-modified variety and be approved for use in commercial bathrooms and showers.
2. Grout shall be of the epoxy grout variety and be approved for use in commercial bathrooms and showers.
i. Final grout color sample will be required for approval by the County Representative.
We will be looking for a darker color grout.
ii. Grout will require sealers as required by manufacturer specifications.
3. Floor tile shall be ceramic 2” x 2” or 1” x 1” and be rated for use in commercial showers and bathrooms. It should meet all non-slip standards.
i. Final tile samples will be required for final approval from the County Representative.
4. Will tile shall be ceramic and of the large format style 12” x 24” or County-approved alternates.
i. Final tile samples will be required for final approval from the County Representative.
VII. PREPARATION
The successful contractor shall exercise care during surface preparation and system installation to protect surrounding finishes, substrates, and surfaces, as well as in-place equipment, floor drains, cleanouts, etc.
1. The successful contractor shall cover and secure all HVAC grills, vents, drains, etc. with heavy-duty plastic sheeting before beginning surface preparation. Contractor shall provide dust control during surface preparation. All dust and debris from surface preparation work shall be removed before uncovering and operating HVAC systems.
2. The successful contractor must remove all existing wall tiles then legally dispose of all materials off site, according to EPA regulations. The existing flooring may be removed by sanding, chipping, grinding or any other method as long as old wall tile is completely removed from substrate.
3. The successful contractor must remove existing tile flooring and mud bed. Then legally dispose of all materials off site, according to EPA regulations. The existing flooring may be removed by sanding, chipping, grinding or any other method as long as old floor is completely removed from substrate.
4. The successful contractor shall prepare the substrate. Fully clean and remove any laitance, dust, debris, oils and any other chemicals that may be present. Contractor may need to open or roughen the surface in accordance with Flooring System or coating manufacturer’s instructions.
5. The successful contractor must treat cracks, control joints and isolation/expansion joints in accordance with the manufacturer’s recommendations. Where necessary, the installer shall saw cut existing control joints, clean out joint materials and fill joints with the crack filler.
6. Contractor shall clean all prepped surfaces and ensure they are dry, and free of grease or debris.
Gwinnett County, Georgia Page 5
7. Contractor must notify the owner’s representative when surface preparation is completed and must obtain approval of surface preparation before proceeding with installation of the flooring system.
VIII. INSTALLATION
Apply each component of the flooring system and/or coatings in compliance with manufacturer’s written installation instructions and strictly adhere to mixing and installation methods, re-coat windows, cure times and environmental restrictions.
1. Contractor shall install new mud beds and ensure all floors slope towards drains.
2. Contractor shall install new wall tile:
i. Tile industry standards require minimum mortar coverage of 80% in dry areas and 95% in wet or exterior areas.
ii. Use finished one edge tile at all edges.
3. Contractor shall install new floor tile:
i. Tile industry standards require minimum mortar coverage of 80% in dry areas and 95% in wet or exterior areas.
ii. Use finished one edge tile at all edges.
4. Contractor shall ensure there is no pooling of water and all water flows towards drains.
IX. CURING, CLEANING, AND PROTECTION
1. Contractor shall cure the flooring system materials and coatings in compliance with the manufacturer's directions, taking care to prevent contamination during the stages of the installation and prior to completion of the curing process. Do not leave the room(s) unlocked or unattended during the curing process. Do not allow public access on the floors until curing is complete and approval has been given by the County Representative.
2. Contractor must perform cleaning during installation of the work and upon completion of the work. Clean the flooring system just prior to final inspection, using only materials and procedures recommended by the manufacturer.
3. Contractor shall remove from the site all debris and equipment, clean flooring material and preparation work debris from adjacent surfaces and repair all damage resulting from work under this contract.
4. Contractor shall inspect the site daily and must not leave the site without correcting any conditions caused by this work which would be hazardous to the public. Contractor(s) must provide barricades, warning tape and other means necessary to protect the public from hazardous conditions while work is in progress.
X. GENERAL REQUIREMENTS
1. References: The selected contractor must have demonstrated successful performance on projects on projects of a similar size and scope. A minimum of three (3) references shall be provided on the “References” form included herein. References must clearly demonstrate the successful completion of similar projects within the past five (5) years.
2. Contractor Qualifications: The selected contractor shall comply with state and local codes and regulations, Contractor shall have and maintain all appropriate state, local, and federal licensing.
3. Safety and Damages: The contractor shall adequately protect County property and take necessary precautions during the work process to protect all persons/property from damage or loss. Reports of any damage to County property must be submitted by the
Gwinnett County, Georgia Page 6 contractor to the designated County representative. Damage to public and/or private property shall be the sole responsibility of the contractor and shall be repaired and/or replaced at no additional cost to Gwinnett County.
4. Clean Up: The contractor shall be responsible for proper removal and disposal of all construction debris and materials according to Environmental Protection Agency (EPA) regulations
5. Warranty: The contractor shall warrant all work for a minimum of one (1) year from the date of completion.
XI. SCOPE OF WORK – ALTERNATE
The successful contractor shall furnish all labor and materials required to remove and reinstall restroom and locker room fixtures, including lockers, stall partitions, shower equipment, toilets, urinals and sinks in the locker rooms and restrooms.
1. Contractor shall remove all lockers and stall partitions.
2. Contractor shall remove all shower valves, shower heads, hand dryers, toilets, urinals and sinks.
3. Contractor shall reinstall all lockers and stall partitions.
4. Contractor shall reinstall all shower valves, shower heads, hand dryers, toilets, urinals, and sinks.
XII. LOCATION
Bethesda Park Aquatic Center 225 Bethesda Church Rd.
Lawrenceville, GA 30044
1. Men’s Locker Room
2. Women’s Locker Room
3. Family Restroom 1
4. Family Restroom 2
Gwinnett County, Georgia Page 7
FAILURE TO RETURN THIS PAGE AS PART OF YOUR BID DOCUMENT MAY RESULT IN REJECTION.
BID SCHEDULE
BASE BID LUMP SUM
LUMP SUM FEE FOR BETHESDA PARK AQUATIC CENTER WALL TILE AND FLOOR TILE
REPLACEMENT, PER ABOVE SPECIFICATIONS $
ALTERNATE LUMP SUM
LUMP SUM FEE TO REMOVE AND REINSTALL RESTROOM AND LOCKER ROOM FIXTURES, PER
ABOVE SPECIFICATIONS $
TOTAL BID PRICE (BASE BID + ALTERNATE) $
NOTE: Pricing MUST contain ALL charges associated with service including installation, materials, and travel.
State number of days to begin work once the bid has been awarded: ___________________
State number of days to complete work once the project has started: __________________
Company Name _______________________________________________________________________________________
Gwinnett County, Georgia Page 8
FAILURE TO RETURN THIS PAGE AS PART OF YOUR BID DOCUMENT MAY RESULT IN
REJECTION.
CONTRACTOR INFORMATION
The undersigned acknowledges receipt of the following addenda, listed by number and date appearing on each:
Addendum No. Date Addendum No. Date
Certification Of Non-Collusion in Bid Preparation
(Signature) (Date)
The County requires that all who enter into a contract for the physical performance of services with the County must satisfy O.C.G.A. § 13-10-91 and Rule 300-10-1-.02, in all manner, and such are conditions of the contract.
In compliance with the attached specifications and O.C.G.A. §36-91-50, the undersigned offers and agrees, if this bid is accepted by the Board of Commissioners within sixty (60) days of the date of bid opening, to furnish any or all of the items upon which prices are quoted, at the price set opposite each item, delivered to the designated point(s) within the time specified in the bid schedule. By submission of this bid, I understand that Gwinnett County uses Electronic Payments for remittance of goods and services.
Vendors should select their preferred method of electronic payment upon notice of award. For more information on electronic payments, please refer to the Electronic Payment information in the instructions to bidders.
Legal Business Name
Address
Does your company currently have a location within Gwinnett County? Yes No
Representative Signature
Print Authorized Representative's Name
Telephone Number Fax Number
E-Mail Address
Contact Person (if someone other than the authorized representative listed above)
Telephone Number Fax Number
E-Mail Address
Gwinnett County, Georgia Page 9
FAILURE TO RETURN THIS PAGE AS PART OF YOUR BID MAY RESULT IN BID BEING REJECTED.
NON-COLLUSION AFFIDAVIT
Now here appeared before the undersigned officer duly authorized by the State of Georgia to administer oaths______________________________________________and after being first duly sworn, depose and say that, they are all the officers, agents, persons or employees who have acted for (Company Name) on the West Gwinnett Aquatic Center Pool Renovations and that said has not by (himself, themselves) or through any persons, officers, agents or employees prevented or attempted to prevent by any means whatsoever, competition in such bidding; or by any means whatever prevented or endeavored to prevent anyone from making a bid therefore, or induced or attempted to induce another to withdraw bid from said work.
BY:______________________________________
Signature of Affiant
Name – Typed or printed
Title
Sworn to and subscribed before me this _______ day of ______________, 20 .
Notary Public
(Seal)
Note: See OCGA § 36-91-21 (e)
Gwinnett County, Georgia Page 10
CORPORATION INFORMATION
CORPORATE NAME
CORPORATE ADDRESS
MAILING ADDRESS (IF DIFFERENT)
DOING BUSINESS AS (IF DIFFERENT THAN CORPORATE NAME)
CORPORATE OFFICERS: PRESIDENT
SECRETARY
TREASURER
VICE PRESIDENT
REGISTERED AGENT ADDRESS
POWER OF ATTORNEY ADDRESS
DATE OF INCORPORATION
NUMBER OF FULL DAYTIME EMPLOYEES (M-F/8-5)
HAS THE CORPORATION OR ANY OF ITS OFFICERS/AGENTS BEEN INVOLVED IN ANY
LITIGATION IN THE PAST FIVE YEARS? IF SO, PROVIDE DATE AND EXPLANATION
Company Name
Gwinnett County, Georgia Page 11
REFERENCES
Gwinnett County requests a minimum of three (3) references where work of a similar size and scope has been completed within the past five (5) years.
Note: References should be customized for each project, rather than submitting the same set of references for every project bid. The references listed should be of similar size and scope of the project being bid on. Do not submit a project list in lieu of this form.
1. Company Name
Brief Description of Project
Completion Date
Contract Amount $ Start Date
Contact Person Telephone
2. Company Name
3. Company Name
Gwinnett County, Georgia Page 12
LIST OF SUBCONTRACTORS
I do , do not , propose to subcontract some of the work on this project. I propose to Subcontract work to the following subcontractors:
NAME AND ADDRESS
TYPE OF WORK
Gwinnett County, Georgia Page 13
BID BOND
KNOW ALL MEN BY THESE PRESENTS: that
(Name of Contractor)
(Address of Contractor) a (Corporation, Partnership or Individual) hereinafter called Principal, and
(Name of Surety)
(Address of Surety) a Corporation of the State of , and a surety authorized by law to do business in the State of Georgia, hereinafter called Surety, are held and firmly bound unto
Gwinnett County Board of Commissioners (Name of Obligee)
75 Langley Drive, Lawrenceville, Georgia 30046 (Address of Obligee)
Thereinafter referred to as Obligee: in the penal sum of
Dollars
($ ) in lawful money of the United States, for the payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.
WHEREAS, the Principal is about to submit, or has submitted, to Gwinnett County, Georgia, a proposal for furnishing materials, labor, and equipment for:
WHEREAS, the Principal desires to file this Bond in accordance with law in lieu of a certified Bidder's check otherwise required to accompany this Proposal.
NOW, THEREFORE, the conditions of this obligation are such that if the proposal be accepted, the Principal shall within ten days after receipt of notification of the acceptance, execute a Contract in accordance with the Proposal and upon the terms, conditions, and prices set forth in the form and manner required by Gwinnett County, Georgia, and execute a sufficient and satisfactory Performance Bond and Payment Bond payable to Gwinnett County, Georgia, each in the amount of 100% of the total Contract Price, in form and with security satisfactory to said Gwinnett County, Georgia, and otherwise, to be and remain in full force and virtue in law, and the Surety shall, upon failure of the Principal to comply with any or all of the foregoing requirements within the time specified above, immediately pay to Gwinnett County, Georgia, upon demand, the amount hereof in good and lawful money of the United States of America, not as a penalty, but as liquidated damages.
Gwinnett County, Georgia Page 14
PROVIDED, FURTHER, that Principal and Surety agree and represent that this bond is executed pursuant to and in accordance with the applicable provisions of the Official Code of Georgia Annotated, as Amended, including, but not limited to, O.C.G.A. § 36-91- 1 et seq., and is intended to be and shall be constructed as a bond in compliance with the requirements thereof.
Signed, sealed and dated this day of , A.D., 20 .
ATTEST:
(Principal)
(Principal Secretary)
By:
(SEAL)
(Address)
(Witness as to Principal)
(Surety)
ATTEST: By:
(Attorney-in-Fact)
Resident or Nonresident Agent
(SEAL)
(Witness as to Surety)
NOTE: If Contractor is Partnership, all partners should execute Bond. Surety Companies executing Bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State where the Project is located.
Principal Secretary, Principal and Witness as to Principal signature lines must be signed by three different individuals. Additionally, Resident or Nonresident Agent, Witness as to Surety, and Attorney-in-fact must be signed by three different individuals.
Gwinnett County, Georgia Page 15
GENERAL CONDITIONS
FOR GWINNETT COUNTY CONSTRUCTION CONTRACTS
GC-1 FAMILIARITY WITH SITE
Execution of this agreement by the Contractor is a representation that the Contractor has visited the site, has become familiar with the local conditions under which the work is to be performed, and has correlated personal observations with the requirements of this agreement.
GC-2 CONTRACT DOCUMENTS
This agreement consists of Gwinnett County's request for proposals, instructions to bidders, Contractor's proposal, construction contract, Performance Bond, Payment Bond, general conditions, special provisions, specifications, plans, drawings, addenda, and written change orders.
GC-3 DEFINITIONS
The following terms as used in this agreement are defined as follows:
Change Order - a written order to the Contractor, prepared by the Engineer and issued by the County for changes in the work within the general scope of the contract documents, adjustment of the contract price, extension of the contract time, or reservation of determination of a time extension.
County - Gwinnett County, Georgia, a political subdivision of the State of Georgia, acting by and through the Chairman of its Board of Commissioners.
Day - a calendar day of twenty-four hours lasting from midnight of one day to midnight the next day.
Notice to Proceed - written communication issued by the County to the Contractor authorizing it to proceed with the work and establishing the date of commencement and completion of the work.
Substantial Completion - the date certified by the engineer when all or a part of the work, identified in the engineer's certification, is sufficiently completed in accordance with the requirements of the contract documents so that the identified portion of the work can be utilized for the purposes for which it is intended.
Work - all of the services specified, indicated, shown or contemplated by the contract documents, and furnishing by the Contractor of all materials, equipment, labor, methods, processes, construction and manufacturing materials and equipment, tools, plans, supplies, power, water, transportation and other things necessary to complete such services in accordance with the contract documents to ensure a functional and complete facility.
GC-4 CODES
All codes, specifications, and standards referenced in the contract documents shall be the latest additions, amendments and revisions of such referenced standards in effect as of the date of the request for proposals for this contract.
GC-5 REVIEW OF CONTRACT DOCUMENTS
Before making its proposal to the County, and continuously after the execution of the agreement, the Contractor shall carefully study and compare the contract documents and shall at once report to the engineer any error, ambiguity, inconsistency or omission that may be discovered, including
Gwinnett County, Georgia Page 16 any requirement which may be contrary to any law, ordinance, rule, or regulation of any public authority bearing on the performance of the work. By submitting its proposal, the Contractor agrees that the contract documents, along with any supplementary written instructions issued by or through the engineer that have become a part of the contract documents appear accurate, consistent and complete insofar as can be reasonably determined. If the Contractor has reported in writing any error, inconsistency, or omission to the County, has properly stopped the effected work until instructed to proceed, and has otherwise followed the instructions of the engineer, the Contractor shall not be liable to the County for any damage resulting from any such error, inconsistency, or omission in the contract documents. The Contractor shall not perform any portion of the work without the contract documents, approved plans, specifications, products and data, or samples for such portion of the work.
GC-6 STRICT COMPLIANCE
No observation, inspection, test or approval of the County or engineer shall relieve the Contractor from its obligation to perform the work in strict conformity with the contract documents.
GC-7 APPLICABLE LAW
All applicable State laws, County ordinances, and rules and regulations of all authorities having jurisdiction over the construction of the project shall apply to this agreement. All work performed within the right of way of the Georgia Department of Transportation shall be in accordance with DOT regulations, policies and procedures. The Contractor shall comply with all laws, ordinances, rules and regulations bearing on the conduct of the work as specified and the Contractor agrees to indemnify and hold harmless the County, its officers, agents and employees, as well as the engineer, against any claim or liability arising from or based on the violation of any law, ordinance, regulation, order or decree affecting the conduct of the work, whether occasioned by the Contractor, his agents or employees.
GC-8 PERMITS & LICENSES
All permits and licenses necessary for the work shall be secured and paid for by the Contractor.
If any permit, license or certificate expires or is revoked, terminated, or suspended as a result of any action on the part of the Contractor, the Contractor shall not be entitled to additional compensation or time.
GC-9 TAXES
The Contractor shall pay all sales, retail, occupational, service, excise, old age benefit and unemployment compensation taxes, consumer, use and other similar taxes, as well as any other taxes or duties on the materials, equipment, and labor for the work provided by the Contractor which are legally enacted by any municipal, county, state or federal authority, department or agency at the time bids are received, whether or not yet effective. The Contractor shall maintain records pertaining to such taxes and levies as well as payment thereof and shall make the same available to the County at all reasonable times for inspection and copying.
GC-10 DELINQUENT CONTRACTORS
The County shall not pay any claim, debt, demand or account whatsoever to any person firm or corporation who is in arrears to the County for taxes. The County shall be entitled to a counterclaim and offset for any such debt in the amount of taxes in arrears, and no assignment or transfer of such debt after the taxes become due shall affect the right of the County to offset any taxes owed against said debt.
GC-11 LIEN WAIVERS
The Contractor shall furnish the County with evidence that all persons who have performed work or furnished materials pursuant to this agreement have been paid in full prior to submitting its
Gwinnett County, Georgia Page 17 demand for final payment pursuant to this agreement. In the event that such evidence is not furnished, the County may retain sufficient sums necessary to meet all lawful claims of such laborers and materialmen. The County assumes no obligation nor in any way undertakes to pay such lawful claims from any funds due or that may become due to the Contractor.
GC-12 MEASUREMENT
All items of work to be paid for per unit of measurement shall be measured and certified by the Engineer.
GC-13 ASSIGNMENT
The Contractor shall not assign any portion of this agreement or moneys due therefrom without the prior written consent of the County. The Contractor shall retain personal control and shall provide personal attention to the fulfillment of its obligations pursuant to this agreement.
GC-14 FOREIGN CONTRACTORS
In the event that the Contractor is a foreign corporation, partnership, or sole proprietorship, the Contractor hereby irrevocably appoints the Secretary of State of Georgia as its agent for service of all legal process for the purpose of this contract only.
GC-15 INDEMNIFICATION
To the fullest extent permitted by law, the Contractor shall, at his sole cost and expense, indemnify, defend, satisfy all judgments, and hold harmless the County, the engineer, and their agents and employees from and against all claims, damages, actions, judgments, costs, penalties, liabilities, losses and expenses, including, but not limited to, attorney's fees arising out of or resulting from the performance of the work, provided that any such claim, damage, action, judgment, cost, penalty, liability, loss or expense (1) is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property (other than the work itself) including the loss of use resulting therefrom, and (2) is caused in whole or in part by any act or omission of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless whether such claim is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge or otherwise reduce any of the rights or obligations of indemnity which would otherwise exist as to any party or person described in this agreement. In any and all claims against the County, the engineer, or any of their agents or employees by any employee of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation contained herein shall not be limited in any way by any limitation on the amount or type of damages, compensation, or benefits payable by or for the Contractor or any subcontractor under Worker's Compensation Acts, disability benefit acts, or other employee benefit acts.
GC-16 SUPERVISION OF WORK
The Contractor shall supervise and direct the work using the Contractor's best skill and attention.
The Contractor shall be solely responsible for all construction methods and procedures and shall coordinate all portions of the work pursuant to the contract subject to the overall coordination of the engineer. All work pursuant to this agreement shall be performed in a skillful and workmanlike manner.
GC-17 RESPONSIBILITY FOR WORK
The Contractor shall not be relieved from the Contractor's obligations to perform the work in accordance with the contract documents by the activities or duties of the engineer, including inspections, tests or approvals required or performed pursuant to this agreement.
Gwinnett County, Georgia Page 18
GC-18 RESPONSIBILITY FOR ACTS OF EMPLOYEES
The Contractor shall be responsible to the County for the acts and omissions of its employees, subcontractors, and agents as well as any other persons performing work pursuant to this agreement. All areas within the limits of the Project which are determined by the Engineer to be unnecessarily damaged, due either directly or indirectly to the process of construction, shall be responsibility of the Contractor to correct and repair. This is not a payment item and shall be done without additional compensation.
GC-19 PAYMENT FOR LABOR AND MATERIALS
Unless otherwise provided in this agreement, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the execution and completion of the work.
GC-20 DISCIPLINE ON WORK SITE
The Contractor shall enforce strict discipline and good order among its employees and subcontractors at all times during the performance of the work. The Contractor shall not employ any subcontractor who is not skilled in the task assigned to it. The engineer may, by written notice, require the Contractor to remove from the work any subcontractor or employee deemed by the engineer to be incompetent.
GC-21 HOURS OF OPERATION
All work at the construction site shall be performed during regular business hours, except upon the engineer's prior written consent to other work hours.
GC-22 FAMILIARITY WITH WORK CONDITIONS
The Contractor shall take all steps necessary to ascertain the nature and location of the work and the general and local conditions, which may affect the work or the cost thereof. The Contractor's failure to fully acquaint itself with the conditions which may affect the work, including, but not limited to conditions relating to transportation, handling, storage of materials, availability of labor, water, roads, weather, topographic and subsurface conditions, other separate contracts to be entered into by the County relating to the project which may affect the work of the Contractor, applicable provisions of law, and the character and availability of equipment and facilities necessary prior to and during the performance of the work shall not relieve the Contractor of its responsibilities pursuant to this agreement and shall not constitute a basis for an equitable adjustment of the contract terms. The County assumes no responsibility for any understandings or representations concerning conditions of the work made by any of its officers, agents, or employees prior to the execution of this agreement.
GC-23 RIGHT OF ENTRY
The County reserves the right to enter the site of the work by such agent as it may elect for the purpose of inspecting the work or installing such collateral work as the County may desire.
GC-24 NOTICES
Any notice, order, instruction, claim or other written communication required pursuant to this agreement shall be deemed to have been delivered or received as follows:
(1) Upon personal delivery to the Contractor, it’s authorized representative, or the engineer on behalf of the County. Personal delivery may be accomplished by in-person hand delivery or bona fide overnight express service.
(2) Three days after depositing in the United States mail a certified letter addressed to the Contractor, the County, or the engineer. For purposes of mailed notices, the County's mailing address shall be 75 Langley Drive, Lawrenceville, Georgia 30046. The Contractor's mailing address shall be the address stated in its proposal, and the engineer's mailing address shall
Gwinnett County, Georgia Page 19 be its address listed in the Notice to Begin Work.
GC-25 SAFETY
The Contractor shall take all reasonable precautions for the safety of all persons and property associated with the work, and the Contractor shall erect and maintain, as required by existing conditions and the progress of the work, all reasonable safeguards for the safety and protection of persons in the vicinity of the project.
GC-26 BLASTING AND EXCAVATION
The Contractor acknowledges that it is fully aware of the contents and requirements of O.C.G.A.
§ 25-9-1 through 25-9-12 concerning blasting and excavation near underground gas pipes and facilities and shall fully comply therewith.
GC-27 HIGH VOLTAGE LINES
The Contractor acknowledges that it is fully aware of the contents and requirements O.C.G.A. § 46-3-30 through 46-3-39 concerning safeguards against contact with high voltage lines, and the Contractor shall fully comply with said provisions.
GC-28 SCAFFOLDING AND STAGING
The Contractor acknowledges that it is the person responsible for employing and directing others to perform labor within the meaning of O.C.G.A. § 34-1-1 and agrees to comply with said provisions.
GC-29 CLEAN-UP
The Contractor shall clean up all refuse, rubbish, scrap materials, and debris caused by its operations to the end that the site of the work shall present a neat, orderly and workmanlike appearance at all times.
GC-30 PROTECTION OF WORK
The Contractor shall be responsible for maintenance and protection of the work until final completion of this agreement and acceptance of the work as defined herein. Any portion of the work suffering injury, damage or loss shall be considered defective and shall be corrected or replaced by the Contractor without additional cost to the County.
GC-31 REJECTED WORK
The Contractor shall promptly remove from the project all work rejected by the engineer for failure to comply with the contract documents and the Contractor shall promptly replace and re-execute the work in accordance with the contract documents and without expense to the County. The Contractor shall also bear the expense of making good all work of other Contractors destroyed or damaged by such removal or replacement.
GC-32 DEFECTIVE WORK
If the Contractor defaults or neglects to carry out any portion of the work in accordance with the contract documents, and fails within three days after receipt of written notice from the County or the engineer to commence and continue correction of such default or neglect with diligence and promptness, the County or the engineer may, after three days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy the County may have, make good such deficiencies and complete all or any portion of any work through such means as the County may select, including the use of a new Contractor. In such case, an appropriate change order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies. In the event the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the County on demand.
Gwinnett County, Georgia Page 20
GC-33 NEW MATERIALS
The Contractor warrants to the County that all materials and equipment furnished under this contract will be new unless otherwise specified, and the Contractor further warrants that all work will be of good quality, free from faults and defects, and in conformance with the contract documents. The warranty set forth in this paragraph shall survive final acceptance of the work.
GC-34 CONTRACTOR'S WARRANTY
If within one year after the date of substantial completion and final acceptance of the work by the County, or within such longer period of time as may be prescribed by law or by the term of any applicable special warranty required by the contract documents, any of the work is found to be defective or not in accordance with the contract documents, the Contractor shall correct such work promptly after receipt of written notice from the County to do so. This obligation shall survive both final payment for the work and termination of the contract.
GC-35 ASSIGNMENT OF MANUFACTURERS' WARRANTIES
Without limiting the responsibility or liability of the Contractor pursuant to this agreement, all warranties given by manufacturers on materials or equipment incorporated in the work are hereby assigned by the Contractor to the County. If requested, the Contractor shall execute formal assignments of said manufacturer's warranties to the County. All such warranties shall be directly enforceable by the County.
GC-36 WARRANTIES IMPLIED BY LAW
The warranties contained in this agreement, as well as those warranties implied by law, shall be deemed cumulative and shall not be deemed alternative or exclusive. No one or more of the warranties contained herein shall be deemed to alter or limit any other.
GC-37 STOP WORK ORDERS
In the event that the Contractor fails to correct defective work as required by the contract documents or fails to carry out the work in accordance with contract documents, the County, or the engineer, in writing, may order the Contractor to stop work until the cause for such order has been eliminated. This right of the County or engineer to stop work shall not give rise to any duty on the part of the County or the engineer to execute this right for the benefit of the Contractor or for any other person or entity.
GC-38 TERMINATION FOR CAUSE
If the Contractor is adjudged bankrupt, makes a general assignment for the benefit of creditors, suffers the appointment of a receiver on account of its insolvency, or fails to supply sufficient properly skilled workers, materials, fails to make prompt payment to subcontractors or materialmen, disregards laws, ordinances, rules, regulations, or orders of any public authority having jurisdiction, or is otherwise guilty of a material violation of this agreement and fails within seven days after receipt of written notice to commence and continue correction of such default, neglect, or violation with diligence and promptness, the County may, after ten days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy the County may have, terminate the employment of the Contractor and take possession of the site as well as all materials, equipment, tools, construction equipment and machinery thereon.
The County may finish the work by whatever methods the County deems expedient. In such case, the Contractor shall not be entitled to receive any further payment until the work is completed. If the unpaid balance of the contract price exceeds the cost of completing the work, such excess shall be paid to the Contractor. If such costs exceed the unpaid balance, the Contractor shall pay the difference to the County on demand. This obligation for payment shall survive the termination of the contract. Termination of this agreement pursuant to this paragraph may result in
Gwinnett County, Georgia Page 21 disqualification of the Contractor from bidding on future County contracts.
GC-39 TERMINATION FOR CONVENIENCE
The County may, at any time upon 30 days written notice to the Contractor, terminate the whole or any portion of the work for the convenience of the County. Said termination shall be without prejudice to any right or remedy of the County provided herein. In addition, in the event this agreement has been terminated due to the default of the Contractor, and if it is later determined that the Contractor was not in default pursuant to the provisions of this agreement at the time of termination, then such termination shall be considered a termination for convenience pursuant to this paragraph.
GC-40 TERMINATION FOR CONVENIENCE - PAYMENT
In the event that the County terminates this agreement for the convenience of the County, the County shall only be liable to the Contractor for those costs reimbursable to the Contractor plus a mark-up of ten percent on the actual fully accounted cost recovered pursuant to this paragraph.
In the event that it appears that the Contractor would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed hereunder and an appropriate adjustment shall be made reducing the amount of settlement to reflect the indicated rate of loss.
In the event of termination for the convenience of the County, the County shall pay the Contractor the following amounts determined by the engineer:
A. An amount for supplies, services, or property accepted by the County for which payment has not previously been made. The price to be paid for these items shall be equivalent to the aggregate price for such supplies or services computed in accordance with the price specified in this agreement appropriately adjusted for any saving of freight or other charges; and
B. The total of:
(1) The costs incurred in the performance of the work terminated, including initial costs and preparatory expenses allocable thereto, but exclusive of any costs attributable to supplies or services previously paid;
(2) The costs of settling and paying claims arising pursuant to the termination of the work under said contracts or orders which are properly chargeable to the terminated portion of the contract (exclusive of the amounts paid or payable on account of completed items or equipment delivered or services furnished by a subcontractor or vendor prior to the effective date of the notice of termination, which amounts shall be included in the costs payable pursuant to (A); and
(3) The reasonable costs of settlement, including accounting, legal, clerical, and other expenses reasonable and necessary for the preparation of settlement claims and supporting data with respect to the terminated portion of the contract and for the termination and settlement of subcontracts thereunder, together with reasonable storage, transportation, and other costs incurred in connection with the protection or disposition of property allocable to this agreement.
GC-41 TERMINATION FOR CONVENIENCE - PAYMENT LIMITATIONS
In the event of termination for the convenience of the County, the total sum to be paid to the Contractor shall not exceed the contract price as reduced by the amount of payments otherwise made, by the contract price for work not terminated, and as otherwise permitted by the contract.
Except for normal spoilage, and except to the extent that the County shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the
Gwinnett County, Georgia Page 22
Contractor the fair value, as determined by the engineer, of property which is destroyed, lost, stolen or damaged so as to become undeliverable to the County or to another buyer.
GC-42 COST TO CURE
If the County terminates the whole or any part of the work pursuant to this agreement, then the County may procure upon such terms and in such manner as the engineer may deem appropriate, supplies or services similar to those so terminated, and the Contractor shall be liable to the County for any excess costs for such similar supplies or services. The Contractor shall continue the performance of this agreement to the extent not terminated hereunder.
GC-43 ATTORNEY'S FEES
Should the Contractor default pursuant to any of the provisions of this agreement, the Contractor and its surety shall pay to the County such reasonable attorney's fees as the County may expend as a result thereof and all costs, expenses, and filing fees incidental thereto.
GC-44 CONTRACTOR'S RESPONSIBILITIES UPON TERMINATION
After receipt of a notice of termination from the County, and except as otherwise directed by the engineer, the Contractor shall:
1. Stop work under the contract on the date and to the extent specified in the notice of termination;
2. Place no further orders or subcontracts for materials, services or facilities, except as may be necessary for completion of such portion of the work under the agreement as is not terminated;
3. Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the notice of termination;
4. Assign to the County in the manner, at the times, and to the extent directed by the engineer, all of the rights, title and interest of the Contractor under the orders and subcontracts so terminated, in which case the County shall have the right, at its discretion, to settle or pay any and all claims arising out of the termination of such orders or subcontracts;
5. Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, with the approval or ratification of the engineer, to the extent the engineer may require, which approval or ratification shall be final for all purposes;
6. Transfer title and deliver to the entity or entities designated by the County, in the manner, at the times, and to the extent, if any, directed by the engineer, and to the extent specifically produced or specifically acquired by the Contractor for the performance of such portion of the work as has been terminated:
(a) The fabricated or unfabricated parts, work, and progress, partially completed supplies, and equipment, materials, parts, tools, dyes, jigs, and other fixtures, completed work, supplies, and other material produced as a part of or acquired in connection with the performance of the work terminated by the notice of termination; and
(b) The completed or partially completed plans, drawings, information, and other property to the work.
Gwinnett County, Georgia Page 23
7. Use its best efforts to sell in the manner, at the times, to the extent, and at the prices directed or authorized by the engineer, any property described in Section 6 of this paragraph, provided, however, that the Contractor shall not be required to extend credit to any buyer and further provided that the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the County to the Contractor pursuant to this agreement.
8. Complete performance of such part of the work as shall not have been terminated by the notice of termination; and
9. Take such action as may be necessary, or as the engineer may direct, for the protection and preservation of the property related to the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .