Road Improvements Intersection of Lennon Road and Elms Road
Solicitation number
25000-216323
Issued by
Genesee County, Fruitport Village, Michigan

About this file

This is a bid notice for a local agency infrastructure project in Michigan involving roundabout construction at the intersection of Lennon Road and Elms Road in Genesee County. The project encompasses 0.49 miles of work including hot mix asphalt base crushing, shaping and resurfacing, hot mix asphalt paving, nonreinforced concrete paving, concrete curb and gutter installation, drainage improvements, signing, and pavement markings. The letting is scheduled for August 14, 2026 at 10:30 AM local time at 425 W. Ottawa Street in Lansing, Michigan. The project has an estimated completion date of September 3, 2027, with proposal plans comprising approximately 61 pages available for online examination.

The project requires prime contractor prequalification in classification 1745 or combinations thereof (Ba, Cb, Ea, or J), with subcontractors in subclassifications Ba, Cb, Ea, and J to be designated prior to contract award. The Small Business Program (SBP) participation requirement is set at 4.00%, while no Disadvantaged Business Enterprise (DBE) participation is required. The contract identification number is 25000-216323 with project number 26A0812 and federal project number 25000. The bid notice was advertised on August 14, 2026.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting of: 260904

10:30 AM, Local Time 425 W. OTTAWA ST., LANSING, MI 48933

Call Number Contract ID Control Section Project Number Federal Project Number

027 25000-216323 216323ACRU 25000 26A0812

Description: 0.49 mi of roundabout construction including hot mix asphalt base crushing, shaping and resurfacing, hot mix asphalt paving, nonreinforced concrete paving, concrete curb and gutter, drainage improvements, signing, and pavement markings at the intersection of Lennon Road and Elms Road, Genesee County. This is a Local Agency project.

Required DBE Participation: 0.00%

Required SBP Participation: 4.00%

Net Classification Required For This Project: ** 1745 Ea or Comb/Jt. 1745 Ba, Cb or Comb/Jt. 1745 Ba, J or Comb/Jt. 1745 Cb, J **

Estimated Pages For Plans: 61

Completion Date: 9/3/2027

12:00:00 AM

In addition to the above minimum prequalification requirement for prime contractors this project includes subclassifications of Ba, Cb, Ea and J. If the prime contractor is not prequalified in those subclassifications it must use prequalified subcontractors. Those subcontractors must be designated prior to award of the contract to the confirmed low bidder.

Date Advertised: 8/14/2026

See proposal for bidder guaranty information.

Proposal and plans, if applicable, are available for examination online at <http://mdotcf.state.mi.us/public/eprop/login/index.cfm>

Notice of Advertisement Report v1

AASHTOWare Project™ Version 5.04.04 Revision 047

File details come from the government source that posted it. Updated .