Hot mix asphalt crack treatment and overband crack filling on various routes
Solicitation number
23051-221957
Issued by
Eaton County, Michigan

About this file

This is a bid notice from the State of Michigan for a highway pavement maintenance contract. The project involves hot mix asphalt crack treatment and overband crack filling on various routes spanning Delta, Dickinson, Gogebic, Iron, and Menominee Counties. The scope encompasses up to 280.28 linear miles of crack treatment work. The contract will be constructed using an innovative contracting method with fixed price variable scope and includes a 2-year pavement performance warranty. The project is scheduled for completion by October 9, 2026. The letting is advertised for April 3, 2026, with a scheduled bid opening on that date at 10:30 AM local time at 425 W. Ottawa Street, Lansing, Michigan 48933. The contract is identified as Call Number 602, Contract ID 36000-225241, with Project Number 26A0517.

The project requires prime contractors to be prequalified in Net Classification 570 N9-3E or 570 N9-3F. If the prime contractor lacks prequalification in these subclassifications, prequalified subcontractors must be designated prior to contract award. No Disadvantaged Business Enterprise (DBE) participation or Small Business Program (SBP) participation is required for this project. Proposal and construction plans are available for online examination. Bidders should consult the proposal documents for guaranty requirements and additional contractual terms.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting of: 260506

10:30 AM, Local Time 425 W. OTTAWA ST., LANSING, MI 48933

Call Number Contract ID Control Section Project Number Federal Project Number

602 36000-225241 225241ANH 36000 26A0517

Description: Up to 280.28 lnmi of hot mix asphalt crack treatment and overband crack filling on various routes, Delta, Dickinson, Gogebic, Iron and Menominee Counties. This project will be constructed with an innovative contracting method, fixed price variable scope. This project includes a 2 year pavement performance warranty.

Required DBE Participation: 0.00%

Required SBP Participation: 0.00%

Net Classification Required For This Project: ** 570 N9-3E or 570 N9-3F **

Estimated Pages For Plans: 0

Completion Date: 10/9/2026

12:00:00 AM

In addition to the above minimum prequalification requirement for prime contractors this project includes subclassifications of N9-3E and N9-3F. If the prime contractor is not prequalified in those subclassifications it must use prequalified subcontractors. Those subcontractors must be designated prior to award of the contract to the confirmed low bidder.

Date Advertised: 4/3/2026

See proposal for bidder guaranty information.

Proposal and plans, if applicable, are available for examination online at <http://mdotcf.state.mi.us/public/eprop/login/index.cfm>

Notice of Advertisement Report v1

AASHTOWare Project™ Version 5.04 Revision 037

File details come from the government source that posted it. Updated .