This is a bid notice for a Local Agency road construction project in Norton Shores, Muskegon County, Michigan. The project involves 0.53 miles of hot mix asphalt reconstruction, storm sewer installation, water main work, curb ramps, signing, and pavement marking on McCracken Street from Norton Avenue northerly to Bonneville Drive. The letting was scheduled for October 26, 2026, at 10:30 AM local time at 425 W. Ottawa Street, Lansing, Michigan 48933. The project has an estimated completion date of October 15, 2027, with proposal plans comprising approximately 50 pages available for online examination. Prime contractors must maintain prequalification in Net Classification 3217 Ea or 3217 K, and if not prequalified in subclassifications Cb, Ea, and K, they must designate prequalified subcontractors prior to contract award.
The project requires 5.00% Disadvantaged Business Enterprise (DBE) participation and 0.00% Small Business Program (SBP) participation. The contract is identified by Call Number 062, Contract ID 61000-215762, Control Section 215762ASTUL, Project Number 61000, and Federal Project Number 26A1050. Bidder guaranty information is specified in the proposal documentation. The project was advertised on October 16, 2026, and bidders are required to submit proposals in accordance with the terms outlined in the bid notice and associated contract documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Letting of: 261106
10:30 AM, Local Time 425 W. OTTAWA ST., LANSING, MI 48933
Call Number Contract ID Control Section Project Number Federal Project Number
062 61000-215762 215762ASTUL 61000 26A1050
Description: 0.53 mi of hot mix asphalt reconstruction, storm sewer, water main, curb ramps, signing and pavement marking on McCracken Street from Norton Avenue northerly to Bonneville Drive in the city of Norton Shores, Muskegon County. This is a Local Agency project.
Required DBE Participation: 5.00%
Required SBP Participation: 0.00%
Net Classification Required For This Project: ** 3217 Ea or 3217 K **
Estimated Pages For Plans: 50
Completion Date: 10/15/2027
12:00:00 AM
In addition to the above minimum prequalification requirement for prime contractors this project includes subclassifications of Cb, Ea and K. If the prime contractor is not prequalified in those subclassifications it must use prequalified subcontractors. Those subcontractors must be designated prior to award of the contract to the confirmed low bidder.
Date Advertised: 10/16/2026
See proposal for bidder guaranty information.
Proposal and plans, if applicable, are available for examination online at <http://mdotcf.state.mi.us/public/eprop/login/index.cfm>
Notice of Advertisement Report v1
AASHTOWare Project™ Version 5.04.04 Revision 047
File details come from the government source that posted it. Updated .