bidnotice.pdf
PDF 114 KB Posted
- Attached to
- Road Improvement US-131 from I-96 to Post Drive
- Solicitation number
- 41132-204378
- Issued by
- Kent County, West Branch City, Michigan
About this file
This is a Bid Notice issued by the Michigan Department of Transportation for a road improvement project in Walker, Kent County. The project involves 6.40 miles of concrete shoulder widening, concrete curb and gutter installation, sidewalk construction, culvert and drainage improvements, sewer work, and rehabilitation of four structures including steel sheet piling and steel piles on US-131 from I-96 to Post Drive. The project includes approach work and pavement markings, along with warranty provisions comprising a 5-year materials and workmanship pavement warranty, a 2-year concrete surface coating warranty, and a 2-year bridge coating warranty. The letting is scheduled for September 25, 2026 at 10:30 AM local time at 425 W. Ottawa Street, Lansing, Michigan 48933. The project completion date is June 9, 2029, with proposal and plans available online for examination.
The project requires prequalified contractors classified under Comb/Jt. 64196 B, Ea or Comb/Jt. 64196 B, Fa or Comb/Jt. 64196 Ea, Fa designations, with subclassifications B, Ea, and Fa required. Prime contractors not prequalified in these subclassifications must utilize prequalified subcontractors designated prior to contract award. The project specifies a 3.00 percent Disadvantaged Business Enterprise (DBE) participation requirement and 0.00 percent Small Business Program (SBP) participation requirement. The estimated proposal plans comprise 589 pages. Bidders are required to provide bidder guaranty information as specified in the proposal documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Letting of: 261106
10:30 AM, Local Time 425 W. OTTAWA ST., LANSING, MI 48933
Call Number Contract ID Control Section Project Number Federal Project Number
011 41132-204378 204378ABFP 41132 26A1158
211694ANHFP 41132 26A1174
221439ANH 41132 26A1161
225218AHSIP 41132 26A1165
Description: 6.40 mi of concrete shoulder widening, concrete curb and gutter, sidewalk, culverts, drainage, sewer, rehabilitation of 4 structures to include steel sheet piling, steel piles, approach work and pavement markings on US-131 from I-96 to Post drive in the city of Walker, Kent County. This project includes a 5 year materials and workmanship pavement warranty, a 2 year concrete surface coating warranty and a 2 year bridge coating warranty.
Required DBE Participation: 3.00%
Required SBP Participation: 0.00%
Net Classification Required For This Project: ** Comb/Jt. 64196 B, Ea or Comb/Jt. 64196 B, Fa or Comb/Jt.
64196 Ea, Fa **
Estimated Pages For Plans: 589
Completion Date: 6/9/2029
12:00:00 AM
In addition to the above minimum prequalification requirement for prime contractors this project includes subclassifications of B, Ea and Fa. If the prime contractor is not prequalified in those subclassifications it must use prequalified subcontractors. Those subcontractors must be designated prior to award of the contract to the confirmed low bidder.
Date Advertised: 9/25/2026
See proposal for bidder guaranty information.
Proposal and plans, if applicable, are available for examination online at <http://mdotcf.state.mi.us/public/eprop/login/index.cfm>
Notice of Advertisement Report v1
AASHTOWare Project™ Version 5.04.04 Revision 047
File details come from the government source that posted it. Updated .