About this file
This document is a comprehensive contract opportunity file for the Biddestone Pump Station Replacement project, issued by the Oakland County Water Resources Commissioner (OCWRC) for the Evergreen Farmington Sanitary Drain Drainage District in Michigan. The project involves rehabilitating an existing lift station, including demolishing the current infrastructure and constructing a new pump station facility. The project encompasses multiple bid items such as demolition, site excavation, piping installation, wet well modifications, pump installation, building construction, electrical and control systems, and site restoration. The bid is scheduled to be opened on September 19, 2025, at 1:30 PM via Microsoft Teams, with a recommended pre-bid meeting on August 26, 2025, at 11:00 AM and a site visit on the same day from 1:00 PM to 2:00 PM. Bidders are required to submit electronic bids through BidNet Direct and must provide various documentation including a bid bond, preliminary schedule, and experience qualifications.
The project has a total contract value that includes various line items and allowances, with specific allocations for permit fees ($6,000), DTE electrical service relocation ($30,000), and programming and SCADA equipment ($206,000). The contract requires the selected contractor to self-perform at least 51% of the construction trade work and provide performance, labor and material, and maintenance bonds. The project will be funded through the Oakland County Water Resources Commissioner, with the final contract award subject to receipt of project funds and easement acquisitions. The contract includes provisions for detailed documentation, quality control, and specific technical requirements for the pump station replacement, with a focus on comprehensive infrastructure rehabilitation and modernization of the existing facility.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 2025-08 Biddestone PS Plans.pdf | ||
| Solicitation Terms and Conditions Rev 11 06 2023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DOCUMENTS AND
TECHNICAL SPECIFICATIONS
FOR
BIDDESTONE PUMP STATION REPLACEMENT
EVERGREEN FARMINGTON SANITARY DRAIN DRAINAGE DISTRICT
OAKLAND COUNTY WATER RESOURCES COMMISSIONER
OAKLAND COUNTY, MICHIGAN
AUGUST 2025
DLZ JOB NO. 2442-7730-00
4494 Elizabeth Lake Road Waterford Township, Michigan 48328
Oakland County Water Resources Commissioner DLZ Job No. 2442-7730-00 Biddestone Pump Station Replacement 08/2025
Biddestone Pump Station Replacement TOC - 1
OAKLAND COUNTY WATER RESOURCES COMMISSIONER CONTRACT DOCUMENTS
DC-116 ADVERTISEMENT
DC-119 INFORMATION FOR BIDDERS
DC-123 BID FORM
DC-118 EXPERIENCE & QUALIFICATION STATEMENT
DC-117 THE AGREEMENT
DC-029 CERTIFICATION FOR SAFETY COMPLIANCE
DC-132 LABOR AND MATERIAL BOND
DC-133 MAINTENACE AND GUARANTEE BOND
DC-134 PERFORMANCE BOND
DC-674 GENERAL CONDITIONS
DC-675 SUPPLEMENTARY CONDITIONS
DC-676 CERTIFICATE OF SUBSTANTIAL COMPLETION
DC-677 FINAL COMPLETION CERTIFICATE FORM
DC-678 FULL UNCONDITIONAL LIEN WAIVER - CONTRACTOR
DC-679 FULL CONDITIONAL LIEN WAIVER - CONTRACTOR
DC-680 PARTIAL UNCONDITIONAL LIEN WAIVER – CONTRACTOR
DC-681 PARTIAL CONDITIONAL LIEN WAIVER - CONTRACTOR
DC-682 FULL UNCONDITIONAL LIEN WAIVER - SUBCONTRACTOR
DC-683 FULL CONDITIONAL LIEN WAIVER - SUBCONTRACTOR
DC-684 PARTIAL UNCONDITIONAL LIEN WAIVER – SUBCONTRACTOR
DC-685 PARTIAL CONDITIONAL LIEN WAIVER - SUBCONTRACTOR
DC-686 CONTRACTOR’S DECLARATION
DC-687 CONTRACTOR’S AFFIDAVIT
DC-688 GENERAL SPECIFICATIONS
DC-689
DC-690
E-VERIFY
VENDOR CERTIFICATION THAT IT IS NOT AN “IRAN LINKED BUSINESS”
Biddestone Pump Station Replacement TOC - 2
DIVISION 01 – GENERAL
01 10 00 SUMMARY
01 20 00 PRICE AND PAYMENT PROCEDURES
01 25 00 SUBSTITUTION PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 21 TEMPORARY BYPASS PUMPING SYSTEMS
01 60 00 PRODUCT REQUIREMENTS
01 70 00 EXECUTION AND CLOSEOUT REQUIREMENTS
DIVISION 02 – EXISTING CONDITIONS
02 22 30 AUDIO VIDEO SPECS (WRC)
02 41 16.00 STRUCTURE DEMOLITION
DIVISION 03 – CONCRETE
03 01 00 MAINTENANCE OF CONCRETE
03 10 00 CONCRETE FORMING AND ACCESSORIES
03 20 00 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 35 00 CONCRETE FINISHING
03 39 00 CONCRETE CURING
DIVISION 04 – MASONRY
04 01 00 MAINTENANCE OF MASONRY
04 05 13 MASONRY MORTARING
04 23 00 GLASS UNIT MASONRY
04 26 00 SINGLE-WYTHE UNIT MASONRY
DIVISION 05 – METALS
05 50 00 METAL FABRICATION
05 52 13 PIPE AND TUBE RAILING
05 54 10 METAL ACCESS HATCHES
DIVISION 06 – WOODS, PLASTICS, COMPONENTS
06 10 00 ROUGH CARPENTRY
06 17 53 SHOP-FABRICATED WOOD TRUSSES
Biddestone Pump Station Replacement TOC - 3
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 19 00 WATER REPELLENTS
07 21 13 BOARD INSULATION
07 26 00 VAPOR RETARDERS
07 41 13 METAL ROOF PANELS
07 46 46 FIBER-CEMENT SIDING
07 62 00 SHEET METAL FLASHING AND TRIM
07 90 00 JOINT PROTECTION
DIVISION 08 – OPENINGS
08 22 20 FIBERGLASS REINFORCED PLASTIC (FRP) DOORS AND FRAMES
08 71 00 DOOR HARDWARE
08 91 00 LOUVERS
DIVISION 09 – FINISHES
09 90 00 PAINTING AND COATING
09 96 00 HIGH-PERFORMANCE COATINGS
DIVISION 22 – PLUMBING
22 05 00 COMMON WORK RESULTS FOR PLUMBING
22 05 23 GENERAL-DUTY VALVES FOR PLUMBING PIPING
22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
22 05 48.13 VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT
22 05 53 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
22 05 93 TESTING, ADJUSTING, AND BALANCING FOR PLUMBING
22 07 19 PLUMBING PIPING INSULATION
22 11 16 DOMESTIC WATER PIPING
22 11 19 DOMESTIC WATER PIPING SPECIALTIES
22 13 16 SANITARY WASTE AND VENT PIPING
22 13 19 SANITARY WASTE PIPING SPECIALTIES
22 13 19.13 SANITARY DRAINS
DIVISION 26 – ELECTRICAL
26 00 01 ELECTRICAL GENERAL REQUIREMENTS
Biddestone Pump Station Replacement TOC - 4
26 32 13 ENGINE GENERATORS
26 36 13 ENCLOSED TRANSFER SWITCHES
DIVISION 31 – EARTHWORK
31 10 00 SITE CLEARING
31 13 00 TREE AND STUMP REMOVAL
31 22 13 ROUGH GRADING
31 23 16 EXCAVATION
31 23 16.13 TRENCHING
31 23 19 DEWATERING
31 23 23 FILL
31 31 19 VEGETATION CONTROL (WRC)
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 23 AGGREGATE BASE COURSES
32 13 13 CONCRETE PAVING
32 91 19 LANDSCAPE GRADING
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 01 12 WET TAPPING HYDRO-STOP
33 01 30.83 SPRAY ON LINING FOR CONCRETE MANHOLES
33 01 30.86 MANHOLE RIM ADJUSTMENT
33 01 35 MANHOLE GROUT SEALING
33 05 61 CONCRETE MANHOLES
33 31 00 WRC OPEN CUT SANITARY SEWERS
WRC MATERIALS – SANITARY SEWER PIPE SPECIFICATIONS
33 31 23 SANITARY SEWERAGE FORCE MAIN PIPING
DIVISION 40 – PROCESS INTERCONNECTION
40 05 06 COUPLINGS, ADAPTERS, AND SPECIALS FOR PROCESS PIPING
40 05 07 HANGERS AND SUPPORTS FOR PROCESS PIPING
40 05 19 DUCTILE IRON PROCESS PIPE
40 05 53 IDENTIFICATION FOR PROCESS PIPING
40 05 61 GATE VALVES
40 05 62 PLUG VALVES
Biddestone Pump Station Replacement TOC - 5
40 05 65.23 SWING CHECK VALVES
40 05 78.23 AIR-VACUUM VALVES FOR WASTEWATER SERVICE
DIVISION 43 – PROCESS EQUIPMENT
43 25 13 OVERHUNG CLOSE-COUPLED SUBMERSIBLE CENTRIFUGAL PUMPS
APPENDICES
APPENDIX A OCWRC ELECTRICAL
13289 HAZARDOUS MATERIAL DISPOSAL
13306 PROCESS CONTROL NARRATIVES
13410 BASIC INSTRUMENTATION REQUIREMENT
13413 OPTICAL FIBER CABLING SYSTEMS
13421 FLOW MEASUREMENT
13423 LEVEL MEASUREMENT
13424 PRESSURE MEASUREMENT
13430 CONTROL PANELS AND CONSOLES
16050 BASIC ELECTRICAL REQUIREMENTS
16050 SPEC SUBMITTAL LOG
16052 COORDINATION STUDY
16060 GROUNDING
16070 SUPPORTING DEVICES
16075 ELECTRICAL IDENTIFICATION
16120 WIRES AND CABLES
16130 RACEWAY
16135 CABINETS, BOXES, AND FITTINGS
16140 WIRING DEVICES
16220 MOTORS
16330 MEDIUM VOLTAGE TRANSFORMERS
16410 CIRCUIT AND MOTOR DISCONNECTS
16421 MOTOR CONTROL CENTERS
16440 PANELBOARDS
16497 FUSES
16510 LIGHTING FIXTURES
APPENDIX B - GEOTECHNICAL REPORT
APPENDIX C – ICS PROPOSAL
APPENDIX D – EGLE CONSTRUCTION PERMIT
APPENDIX E – USACE/EGLE JOINT PERMIT
APPENDIX F – DC-303 OAKLAND COUNTY WRC WATER CONNECTION APPLICATION AND WATER SERVICE
DETAIL
DC-116 ADVERTISEMENT
OAKLAND COUNTY WATER RESOURCES COMMISSIONER
Page ADV-1 of ADV-2 4-23-2024
Biddestone Pump Station Replacement
Electronic sealed Bids will be received by the Owner for the construction of the following project:
Refurbishment of the Biddestone Wastewater Pump Station, including abandonment of the existing steel can dry pit, installation of new pumps in an existing wet well, new piping, new utility building and site work, as well as electrical, generator, and controls replacement and upgrades.
THE BIDS RECEIVED WILL BE PRESENTED PUBLICLY VIA MICROSOFT TEAMS AND READ AT
THE FOLLOWING DATE AND TIME:
FRIDAY SEPTEMBER 19, 2025, at 1:30 P.M. LOCAL TIME
Microsoft Teams https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting Meeting ID: 212 657 272 983 0 Passcode: dv2z3uU7
Bidders shall review and comply with the Information for Bidders, which is incorporated by reference, and carefully review all Bidding Documents. Bids submitted after the exact time specified for receipt will not be considered.
Bidding Documents will be available on the BidNet Direct website. The proposed Contract Documents under which the work will be performed are included in the Bidding Documents. For questions about BidNet Direct, refer to https://www.oakgov.com/government/purchasing/bidder-registration/bid-solicitation-public-search.
A recommended pre-bid meeting is scheduled for August 26, 2025, at 11:00 A.M., local time, virtually via Microsoft Teams for all prospective bidders. The virtual meeting link is shown below.
Microsoft Teams https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting Meeting ID: 292 788 374 100 5 Passcode: KM7h4NB3
A recommended site visit is scheduled for August 26, 2025 from 1:00 P.M. to 2:00 P.M, local time, at the project site located at 26430 Farmington Road, Farmington Hills, MI 48331. Prospective bidders can show up at any time during the hour shown above to view the site.
Bidders will be required to sign-in at the pre-bid meeting and the site tour.
Questions, comments, or concerns of any Bidder regarding the Bidding Documents or the project, must be submitted in writing via the BidNet Direct website by 3 pm on Tuesday, September 9, 2025. No questions received after this time will be given consideration. Questions will be reviewed, and formal responses will be disseminated via addenda on BidNet Direct.
Addenda issued to Bidders prior to the date of receipt of Bids shall become a part of the Contract Documents and all Bids shall include the work described in each addendum issued.
https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting https://www.oakgov.com/government/purchasing/bidder-registration/bid-solicitation-public-search https://www.oakgov.com/government/purchasing/bidder-registration/bid-solicitation-public-search https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting
DC-116 ADVERTISEMENT
Page ADV-2 of ADV-2 4-23-2024
Failure to attend the pre-bid meeting shall not relieve the Bidder from compliance with all applicable federal and state laws and regulations, including without limitation the Equal Employment and Minority, Small, and Women's Business Regulations.
A certified check, cashier's check, or Bid Bond for a sum not less than five percent (5%) of the amount of the Bid will be required.
Owner reserves the right to accept any Bid, to reject any Bid and to waive irregularities in the Bids.
DC–119 INFORMATION FOR BIDDERS
Page IB-1 of IB-10 4-23-2024
1. SCOPE OF WORK
The work under this Contract shall consist of the items listed in the Bidding Documents, including all incidentals necessary to fully complete the project in accordance with the proposed Contract Documents.
2. RECEIPT AND OPENING OF BIDS
A. The Bid shall be submitted as one combined electronic pdf file to the BidNet Direct website as indicated in the Advertisement.
B. The Bids must be submitted only on the forms provided by Owner. All blank spaces for bid prices must be filled in, in ink and scanned as a pdf or typewritten, and the Bid Form must be fully executed when submitted and not modified in any way.
C. The Bids shall be made in full conformity with all the instructions, requirements and conditions set forth in the Bidding Documents. Bids are firm, and no bid may be withdrawn for a period of 120 days after opening of bids. Withdrawal of the Bid will result in the forfeiture of the Bidder’s Bid Bond.
D. Any Bids received after the exact time specified in the Advertisement will not be considered. This material requirement is not subject to waiver by Owner.
3. ESCROW BID DOCUMENTS
The three (3) lowest Bidders will be required to place their Bid Documents in escrow within three
(3) business day of the Bid opening in accordance with the attached Escrow Bid Documents Provision Specification. In addition, Owner reserves the right to require additional Bidders to place their Bid documents in escrow also, as provided in the attached Escrow Bid Documents Specification. Such additional Bidders will be notified within 24 hours of the Bid. Contractors bidding on this project are required to maintain all bid notes, take offs, and other Bidding Documents required for inclusion in the Escrow Bid Documents. Failure to submit the Escrow Bid Documents as required may result in a rejection of the Bid.
4. DEFINITIONS
Certain terms used in the Contract Documents shall have the meanings indicated in the General Conditions and Supplementary Conditions which are part of the Contract Documents.
5. INSPECTION OF SITE, INSPECTION OF CONTRACT DOCUMENTS, PLANNING, AND
ANALYSIS
A. Before submitting a Bid, each Bidder is responsible for inspecting the site of the proposed work, and the surrounding premises, to arrive at a clear understanding of the conditions under which the work is to be performed.
B. Before delivery of its Bid, each Bidder is held to have compared the conditions of the site where work is to be performed with the Contract Documents and to have satisfied itself as to the conditions of the site and surrounding premises, including any obstructions, all excavating, filling in, and quantities, and any other conditions affecting the work, including the weather conditions of the project area. Each Bidder must obtain first-hand
Page IB-2 of IB-10 4-23-2024 information concerning the available facilities for receiving, transporting, handling, and storing construction equipment and materials and concerning other local conditions that may affect its work. Each Bidder must acquaint itself with the character and extent of the operations of Owner and any other contractors in the area of the work, so that the Bidder can plan its work accordingly.
C. Bidders must estimate the quantity of materials, labor and equipment required for the work by examination of the site and a review of the Contract Documents including Addenda, and by carefully considering all other relevant factors. Bidder warrants that by submitting its Bid, it had no misunderstanding concerning the quantities or nature of the work to be performed, and the Bidder will assert no such claim asserting such a misunderstanding.
D. No allowances or extra payment will be made to Contractor because of costs or expenses occasioned by Contractor’s failure to comply with the provisions of this Article, or by reason of error or oversight on the part of the Bidder, or on account of interference by the activities of Owner or any other contractor where those activities are apparent or are made known to the Bidders during the bidding process.
E. For bidding purposes, the Bidder is responsible for evaluating the compatibility of proposed construction methods with the Contract Documents, and soil and site information. Bidders must carefully study and compare all portions of the Contract Documents and must notify the Engineer, in writing, prior to the deadline for pre-bid questions, of any concerns, questions, apparent ambiguities, conflicts, incompatibilities, apparent errors, or other discrepancies evident in the Contract Documents.
F. The successful Bidder must complete the work under whatever conditions it may create by its own actions or inactions, sequence of construction, construction means and methods, or other conditions it may create or cause to be created at no additional cost to Owner.
6. UNDERGROUND CONDITIONS
A. The Engineer performed investigations and issued reports which are available to the Contractor.
B. Bidders may only rely on technical data contained in such reports except were indicated otherwise in the Contract Documents. Evaluations, analyses, recommendations, or conclusions contained in such reports shall not be relied upon in formulating any Bid for the work. This data is offered to the Bidders as information about underground and site conditions only at the locations at which any soil borings, sampling, or other data collection were made. Owner does not represent or warrant that the underground conditions encountered at or near the site during construction will generally or specifically conform to underground conditions described in the data in these borings or any accompanying descriptive report.
C. Each Bidder and the Contractor awarded the project shall draw their own conclusions as to site, underground or soil conditions from their own experience, independent knowledge, and investigation of the site, and they should each secure such other and additional information and data as they consider necessary or desirable to check and supplement the provided underground data for specific locations. The Contractor is
Page IB-3 of IB-10 4-23-2024 required to complete the work under any job or field condition which was present and/or ascertainable prior to Bidding.
D. All Bidders that seek to conduct any additional underground or site exploration or testing must do so at their own expense as necessary. Such Bidders must contact Owner and obtain its written permission before proceeding.
E. Any additional exploration conducted by Bidders must be performed in a manner which precludes unnecessary disruption of the soils, or which impedes construction operations and must be performed in compliance with the Mineral Well Act, Act No. 315 of the Public Acts of 1969, as amended, MCL 319.211, et seq. Any Bidder performing exploration work must restore all areas of exploration to their original condition. By entering the site to conduct such investigation and testing, the Bidder agrees to indemnify, defend, and hold harmless all the persons identified in the indemnity provisions of the General and Supplementary Conditions to the full extent of the indemnity obligation set forth in those Contract Documents.
7. AWARD OF CONTRACT
A. The Contract, if awarded, will be awarded to the lowest, responsive, and responsible bidder, subject to the final approval by the Owner. The Contract will be awarded subject to receipt of funds to finance the project and acquisition of easements, during which time the Bids of the lowest three responsive, responsible Bidders will be held.
B. The party to whom the Contract is awarded will be required to execute the Agreement and obtain the Performance Bond, Labor and Material Bond and Maintenance and Guarantee Bond and shall provide proofs of insurance coverage in accordance with the Contract Documents within ten (10) calendar days of the delivery date of the Notice of Award to the successful Bidder. The necessary Agreement and Bond forms shall accompany the Notice of Award. If the Contractor awarded the project fails to execute the Agreement, submit the Performance Bond, Labor and Material Bond and Maintenance and Guarantee Bond and provide proof of insurance coverage in accordance with the Contract Documents within ten (10) calendar days of the delivery date of the Notice of Award, Owner may declare the Contractor in default, in which case the Bid Bond accompanying the Bid will be forfeited to Owner.
8. INTERPRETATION OF CONTRACT DOCUMENTS
A. Neither Owner nor the Engineer will give verbal instructions prior to the award of the Contract. Any verbal statements regarding the Contract by any person are not authorized and do not constitute representations, warranties, modifications, agreements, or promises, express or implied, and may not be relied upon by Bidders.
B. Bidders seeking explanations regarding the project, or the Contract Documents must submit written requests to the Engineer, and if explanations are necessary, a reply will be made in the form of an Addendum, a copy of which will be forwarded to all parties that have taken out Contract Documents. The determination of the necessity of explanations will be in the sole discretion of the Engineer and Owner and no obligation to provide a reply or addendum will be implied.
Page IB-4 of IB-10 4-23-2024
C. Questions, comments, or concerns of any Bidder regarding bidding or the Contract Documents or the project, must be submitted in writing on the BidNet Direct website and in advance of the opening of bids per the time specified in the Advertisement
D. Addenda issued to Bidders prior to the date of receipt of Bids shall become a part of the
Contract Documents and all Bids shall include the work described in each Addendum issued.
9. NAME AND STATUS OF BIDDER
A. The name and legal status of the Bidder, that is, as a corporation, limited liability company, partnership, limited partnership or individual, must be stated in the Bid form.
B. The place of residence of Bidder, or the office address in the case of a firm or company must be stated in the Bid Form.
C. Unless the legal status of the Bidder is an Individual, the signature(s) of the signing official(s) must be accompanied by the appropriate Resolution or Certificate Form found at the end of the Bid Form, properly executed, authorizing the official(s) to sign both the Bid Form and the Contract. Failure to submit this form is basis for rejecting the Bid.
10. QUALIFICATION OF BIDDERS AND SUBCONTRACTORS
A. Except as otherwise reserved herein, Owner will only award the Contract to a responsible Bidder. A finding that the Contractor is not responsible in connection with the project shall not necessarily preclude the Bidder from bidding and performing work on other projects for Owner.
B. Factors to be considered in determining whether Owner’s standard of responsibility has been met shall include, but not be limited to, whether the Contractor has:
a. The appropriate financial, material, equipment, facilities, and personnel resources and expertise available, or the ability to obtain them, necessary to indicate it can meet all contractual requirements;
b. A satisfactory record of performance;
c. A satisfactory record of integrity;
d. Qualified legally to contract with Owner and has supplied all necessary information in connection with the inquiry concerning responsibility.
e. If Contractor has been deemed non-responsible in the past, provided a detailed explanation of its remedial actions after the determination to address any concerns expressed by the authority making the declaration such that the authority would consider awarding a contract to the Contractor, notwithstanding past concerns about Contractor’s performance.
Page IB-5 of IB-10 4-23-2024
C. The Contractor must supply information requested by Owner concerning the responsibility of the Bidder. If the Bidder fails to supply the requested information, Owner must base the determination of responsibility upon any available information or may find the Bidder non-responsible if such failure is unreasonable. A finding that the Bidder has failed to make a required disclosure or submitted false information may result in immediate disqualification of the Bidder.
D. Within 10 days after bids are received by Owner, the Contractor who has submitted the low bid must, upon request of Owner, complete and submit to Owner the following:
a. MIOSHA Form 300 – “Log of Work-Related Injuries” for the last three (3) years.
b. MIOSHA Form 300A - “Summary of Work-Related Injuries & Illnesses” for the last three (3) years.
E. In addition to meeting the criteria set forth in this Article, and the submission of the required information requested herein, the ability of the Contractor and its identified Subcontractors to proficiently handle technical issues, safety, scheduling, and administrative issues as demonstrated by its past performance on projects for Owner, as well as projects for other public agencies, will be considered in determining whether a Contractor is a responsible contractor for this project. Past performance issues to be considered include, but are not limited to, the following:
a. Failure to adhere to and/or comply with Contractor’s obligations in the Contract
Documents;
b. Failure to follow administrative procedures and provisions in the Contact Documents;
c. Submission of false claims or falsely inflated claims;
d. Failure to prosecute the work in accordance with the Plans and Specifications included in the Contract Documents; and
e. Failure to follow bidding instructions.
F. The Bidder shall promptly submit upon request by Owner any additional information necessary to satisfy Owner that the Bidder is adequately prepared to fulfill the Contract.
G. The existence of any judgment, citation, default, finding of non-responsibility or other negative information disclosed by Contactor in its Experience and Qualification Statement or independently discovered by Owner, or Contractor’s failure to provide the certifications required by this Article, will be considered, among all other factors, in determining whether a Contractor is a responsible Bidder for this project. As part of its response, Contractor may submit an explanation of the facts giving rise to the judgment, citation, default, or negative finding, or reasons why the required certifications cannot be provided, and ask Owner to deem the Contractor both responsive and responsible notwithstanding such facts or omissions.
Page IB-6 of IB-10 4-23-2024
H. The requirements identified above are not an exhaustive or exclusive list of all qualifications required of the Contractor, its Subcontractors, or personnel. The minimum requirements indicated above are in addition to any other requirements contained elsewhere in the Contract Documents and/or typically considered under state or federal procurement law.
I. Owner may, when circumstances warrant, accept any Bidder as a responsible Bidder despite its failure to meet all the minimum standards set out herein. To the extent that special circumstances exist which a Bidder believes render the Bidder a qualified and responsible Bidder for this project, despite the failure to meet one or more of the standards for qualification set out herein, the Bidder may submit a notarized sworn statement explaining the special circumstances and requesting consideration of its Bid.
Notwithstanding the foregoing, Owner has no obligation to consider such special circumstances, or to disregard the requirements set forth in this Article and elsewhere in the Contract Documents and deem the Bidder responsible.
J. Bidder must attend a pre-award conference to satisfy Owner that the Bidder is adequately prepared to fulfill the Contract.
K. If a Bidder who otherwise would have been awarded a contract is found non-responsible, a written determination of non-responsibility setting forth the basis of the finding will be prepared by Owner upon request. A copy of the determination will be sent promptly to the non-responsible Bidder. The final determination will be made part of the bid file.
L. The Contractor must self-perform at least fifty-one percent (51%) of the construction trade work as determined by dollar value. This does not include General Conditions.
11. CONTRACTOR AND SUBCONTRACTOR INFORMATION AND LISTING
A. Bidder must provide a completed Experience and Qualification Statement (DC-118) with its bid. Additional qualification information as requested by Owner shall be submitted within ten (10) calendar days after bids are received by Owner including but not limited to a completed Experience and Qualification Statement (DC-118) for each Subcontractor who will work on the project.
B. Bidders shall submit with their bid a list by name, trade, and scope of work each Subcontractor who will perform Work with a value more than ten percent (10%) of Bid Total.
12. PRELIMINARY SCHEDULE
A. Each Bidder shall submit with its bid a Preliminary Schedule demonstrating the Bidder’s plan to complete the construction work within the time allowed in the Agreement and to achieve the completion of any milestones identified in the Contract Documents. The requirements of the Preliminary Schedule are described in the General Specifications.
B. Failure to provide the requested schedule may result in the Contractor being declared non-responsive.
Page IB-7 of IB-10 4-23-2024
C. The Bidder’s Preliminary Schedule shall be based on the proposed Notice to Proceed date identified in the Bidding Documents by Owner.
13. ADDITIONAL BIDDING INFORMATION
The Advertisement, which precedes the "Information for Bidders" and the Contract Documents as defined in the General Conditions may contain additional bidding information and is considered a part of these instructions.
14. EQUALS AND SUBSTITUTIONS
Anticipated proposed Equals and Substitutions shall not be the basis for any bid pricing. For bidding, Bidders shall base their bid on the design and any specified products. Equals or Substitutions may be submitted for consideration after the award of the Contract. Approval of proposed Equals or Substitutions are discretionary, and Contractor waives the right to make a claim on that basis. Bidders shall not assume that any contemplated Equal or Substitutions will be approved. The Contractor will be responsible for Engineer Fees for review, analysis, tests and/or all other costs necessary to review, analyze and/or implement a proposed Substitution regardless of whether the Bid is approved.
15. BID BOND
A. Each shall be accompanied by a Bid deposit in the form of a certified check, a cashier's check or Bid Bond executed by the Bidder and a qualified, acceptable Surety Company, payable to the Owner, in the amount of five percent (5%) of the accompanying Bid, as guarantee on the part of the Bidder that it will, if called upon to do so, enter into a Contract in the form of the Contract Documents, perform the work required by the Contract Documents, at the prices stated, and furnish acceptable surety for its faithful and entire fulfillment. All cashier’s and certified checks will need to be mailed or hand delivered to the Oakland County Water Resource Commissioner’s office located at One Public Works Drive, Building 95 West, Waterford, MI 48328.
B. The Bid deposits of all, except the three (3) lowest Bidders, will be returned within seventy two (72) hours after the Bids are opened. The Bid deposits of the apparent second and third lowest Bidders that Owner has retained will be returned after the signed Contract has been delivered and the required bonds and insurance of the Contractor have been finally approved by Owner, or after rejection of all Bids.
17. GUARANTEE BONDS
A. In addition to the Bid Bond, the Contractor shall furnish Owner the following bonds prior to the Contract being executed:
a. A Performance Bond in an amount at least equal to one hundred percent (100%) of the Contract Price as security for faithful performance on the Contract.
b. A separate Labor and Material Payment Bond in an amount at least equal to one hundred percent (100%) of the Contract Price as security for payment of all persons performing labor and furnishing materials in connection with the Contract.
Page IB-8 of IB-10 4-23-2024
c. A Maintenance and Guarantee Bond in an amount at least equal to one hundred percent (100%) of the Contract Price.
18. BOND REQUIREMENTS
A. All bonds required of Bidder or Contractor shall meet the following requirements:
a. The Bidder or Contractor shall pay the premiums.
b. The form of the bonds shall be as appended herewith (NOTE: the form of Bid
Bond is NOT incorporated in the Contract Documents).
c. The surety on the bonds shall be a corporate bonding company named on the current list of Surety Companies acceptable on Federal Bonds as published in the U.S. Treasury Department Circular Number 570. If the surety is ever delisted on the cited Circular, Owner may, in Owner’s sole discretion, demand and Contractor shall provide replacement Bonds from a then-listed surety at no additional cost to Owner
d. The surety shall be a corporate bonding company authorized and admitted to transact business in Michigan and subject to service of process and personal jurisdiction in Michigan. A copy of the certificate issued by the State of Michigan evidencing such authorization shall be furnished to Owner.
e. The surety shall be a corporate bonding company, which is otherwise satisfactory to Owner. Without limiting the other factors upon which Owner may determine the acceptability of a surety, Owner specifically reserves the right to reject any surety which has denied, delayed, or obstructed payment or discharge of the sureties’ obligations under a prior bond in favor of Owner.
f. Attorneys-in-Fact who sign bonds must file with each bond a certified copy of a currently effective and dated Power of Attorney.
g. Owner may, but is not obligated to, require the substitution of any of the bonds by
Bidder or Contractor upon the occurrence of any of the events referred to herein and in the General Conditions or Supplementary Conditions.
h. Providing the bonds required hereunder shall not establish that a Bidder is qualified, responsive, or responsible, and shall not limit Owner’s right to review Bidder's qualifications and reject any Bid.
19. PRE-BID MEETING AND SITE TOUR
Bidders shall refer to the Advertisement (ADV-1) found elsewhere in these specifications for pre-bid meeting and site tour requirements.
Page IB-9 of IB-10 4-23-2024
20. REJECTION OF BIDS
Owner reserves the right to reject any or all Bids. Owner further reserves the right to waive any non-material irregularity or informality in the Bids. Owner reserves the right to reject any Bid submitted by any Bidder that Owner determines is not a responsive or responsible Bidder based on information supplied by the Bidder or on any other information that Owner receives or acquires on its own, including the experience of Owner and/or any other public agency owner with the Bidder. Owner’s rights in this regard may be exercised in Owner’s sole discretion and Owner shall not have any obligation to exercise or refrain from exercising these rights.
21. OVERTIME COMPENSATION
Refer to the Labor Standards Provisions, EPA Form 5720-4 and the U.S. Department of Labor Memorandum No. 143 for further information. Labor compensation, including Overtime shall be governed by applicable local, federal, and state law and regulations.
22. WORK WITHIN VARIOUS MUNICIPALITIES, CONSTRUCTION PERMITS, ROAD PERMITS,
ETC.
A. The Contractor shall conform to the various requirements of the municipality within which work is being performed and shall obtain, at its own expense, all permits required.
B. In addition, certain public highways and subdivision roads are under the jurisdiction of the Michigan Department of Transportation, the Road Commission for Oakland County, and/or the local municipality. Contractor shall obtain, at Contractor’s own expense, all permits required by these organizations to use the roads under their jurisdiction.
C. If the scope of the work requires work to be performed within other private properties/easements, Contractor shall comply with the conditions of these easements at its own expense. Applicable easement documents will be made available before work begins.
23. CONTRACT DOCUMENTS
Each Bidder is obligated to carefully review all materials included or referenced in the Contract Documents including, without limitation, the General and Supplementary Conditions. The Contract Documents are defined in the General and Supplementary Conditions and the Bidder must familiarize itself with all provisions, terms, and conditions of all Contract Documents.
24. OWNER’S RESERVATION OF RIGHTS
A. In addition to Owner’s rights in Article 23 [Rejection of Bids], Owner reserves the following rights in connection with this Advertisement:
a. Withdraw the Advertisement at any time, in Owner’s sole discretion.
b. Make an award under the Advertisement in whole or in part.
c. Disqualify any Bidder whose conduct and/or Bid fails to conform to the requirements of the Advertisement.
Page IB-10 of IB-10 4-23-2024
d. Seek clarifications and revisions of Bids.
e. Use Bid information obtained through site visits, management interviews and
Owner’s investigation of a Bidder’s qualifications, experience, ability or financial standing, and any material or information submitted by the Bidder in response to the Owner’s request for clarifying information during evaluation and/or selection under the Advertisement.
f. Prior to the bid opening, direct Bidders to modify their Bid addressing all addenda including addenda that may modify the Bidding Documents.
g. Change any of the scheduled dates.
h. Eliminate any mandatory, non-material specifications that cannot be complied with by all the prospective Bidders.
i. Waive any requirements that are not material.
j. Negotiate with the successful Bidder within the scope of the Bidding Documents in the best interests of the Owner.
k. Conduct contract negotiations with the next responsible Bidder, should the
Owner be unsuccessful in negotiating with the lowest, responsive, responsible Bidder.
l. Utilize all ideas submitted in the Bids received.
Require clarification at any time during the procurement process and/or require correction of arithmetic or other apparent errors for the purpose of assuring a full and complete understanding of a Bidder’s Bid and/or to determine a Bidder’s compliance with the requirements of the solicitation.
DC-123 BID FORM
Page B-1 of B-9 4-23-2024
BIDDESTONE PUMP STATION REPLACEMENT
NAME OF BIDDER:
CONTRACTOR NAME:
ADDRESS:
TELEPHONE NO.:
CONTRACT NAME EMAIL:
The undersigned, as Bidder, hereby declares this Bid is made in good faith without fraud or collusion with any persons bidding or proposing to supply materials or labor, and that it has examined the Bidding Documents, all of which it understands and accepts as sufficient for purposes of constructing the Project, and is familiar with the location of the work described herein and is fully informed as to the nature of the work and the conditions relating to its performance. Further, the undersigned certifies that its proposed construction methods will be compatible with the site conditions described in the above-listed information provided for bidding, as well as its own independent investigation of the field conditions.
The Bidder acknowledges that it has not received or relied upon any representations or warranties of any nature whatsoever from the Owner, its agents, representatives, or employees, as to any conditions to be encountered in accomplishing the work specifically, but not exclusively, including underground conditions, and that its bid is based solely upon the Bidder's own independent judgment.
The following documents listed below shall be compiled into one PDF in the order designated below.
The PDF document shall have the Bidder’s name and the document description in the file name.
Item No. Description
1. Bid Form, completed and signed acknowledging all addenda
2. Certified check/Cashier’s check /Bid Bond (5%)
3. Preliminary Schedule based on the Time noted in the Agreement and an anticipated Notice to Proceed date of: October 6, 2025
4. Completed Form DC-118 Experience and Qualification Statement
5. Signed Vendor Certification that it is not an “Iran Linked Business”
6. Contractor’s OCIP Acknowledgement Form, if applicable
The Bidder declares that it has familiarized itself with the location of the proposed work and the conditions under which it must be constructed. The Bidder shall complete the work under any job or field condition which was present and/or ascertainable prior to bidding. In addition, it shall also complete the work under whatever conditions it may create by its own sequence of construction, construction methods, or other conditions it may create, at no additional cost to the Owner.
The Bidder agrees that it will contract with the Owner to furnish all labor, material, tools, and equipment necessary to do all the work specified and prescribed for the completion of the above-mentioned Contract for the following named unit prices:
Page B-2 of B-9 4-23-2024
BID SHEET
Item No. Description Qty. Unit Unit Price Amount
1. Mobilization, 5% max. 1 LS
2. Color Audio Video Recording of Construction Areas 1 LS
3. Permit Fee Allowance 1 ALLOW $ 6,000.00 $6,000.00
4. Soil Erosion and Sedimentation Control 1 LS
5. DTE Allowance 1 ALLOW $30,000.00 $30,000.00
6. Clearing, Grubbing, and Stump Removal 1 LS
7. Demolition 1 LS
8. Site Excavation, Piping, Valves and Fittings 1 LS
9. Wet Well Modifications 1 LS
10. Submersible Non-Clog Pumps 1 LS
11. Final Force Main Connection 1 LS
12. Water Service 1 LS
13. Bypass Pumping 1 LS
14. Building 1 LS
15. Electrical 1 LS
16. Generator and Transfer Switch 1 LS
17. Controls and SCADA 1 LS
18. Programming and SCADA Equipment Allowance 1 ALLOW $ 206,000.00 $ 206,000.00
19. Site Restoration Work 1 LS
TOTAL CONTRACT PRICE $
Note: In case of discrepancy, unit prices shall be used to determine the total amount of this bid.
Page B-3 of B-9 4-23-2024
TAXES
The foregoing unit prices include all applicable Federal, State and Local taxes.
ADDENDA
This Bid is based on the following Addenda in the table below:
Addendum Number Date Issued
SUBCONTRACTORS AND MAJOR EQUIPMENT MANUFACTURERS/SUPPLIERS
The Bidder agrees, in accordance with the Information for Bidders, that it is concurrently with this Bid, furnishing the Owner the required information relative to the qualifications of Bidder and Subcontractors required to be identified pursuant to the Information for Bidders. Bidder also agrees that Bidder will provide all other information as required with this Bid and/or within the times specified in the Information for Bidders or other Bidding Documents. Bidder acknowledges that this bid may be rejected if Bidder fails to provide any of the required information with this bid and/or within the times outlined in the Information for Bidders or other Contract Documents.
BID GUARANTEE
The Bidder encloses a certified or cashier’s check or Bid Bond in the amount of Five Percent (5%) of the accompanying total bid.
_____ Certified Check _____ Cashier's Check _____ Bid Bond
The Bidder hereby declares that this Bid was prepared by qualified personnel of its employ who inspected the Drawings and Specifications, read, and interpreted the Geotechnical Data and other information furnished by the Owner, and developed the Bidder's intended construction methods.
If this Bid is accepted by the Owner and the undersigned shall fail to contract as aforesaid and to furnish the required surety bonds within ten (10) calendar days of the delivery date of the Notice of Award to the successful Bidder, then the undersigned shall be considered to have abandoned the Contract, and the Certified Check, Cashier’s Check, or Bid Bond accompanying this Bid shall be forfeited to the Owner.
If the Bidder enters the Contract in accordance with this Bid, or if its Bid is rejected, then the accompanying bid guarantee shall be returned to the Bidder.
By submission of the Bid, each Bidder certifies, and in the case of a joint Bid each party thereto certifies as to its own organization, that this Bid has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this Bid with any other Bidder or with any competitor.
Page B-4 of B-9 4-23-2024
In submitting this Bid it is understood that the right is reserved by the Owner to reject all bids, to waive non-material irregularities and/or informalities, and to evaluate the responsiveness and responsibility of each Bidder. The Owner reserves the right to reject any Bid submitted by any Bidder that the Owner determines is not a responsive and responsible Bidder based on information supplied by the Bidder or on any other information that the Owner receives or acquires on its own, including the Owner's experience with the Bidder. The Owner further reserves the right to reject any bid submitted by any bidder in its sole discretion and to exercise any further rights reserved to Owner in the Information for Bidders.
The Bidder shall indicate its legal status as provided herein.
Page B-5 of B-9 4-23-2024
LEGAL STATUS OF BIDDER
The Bidder shall complete the appropriate form below and complete the appropriate Resolution or Certificate.
A Corporation duly organized and doing business under the laws of the State of _________________ for whom ______________________________________ whose signature is affixed to this Bid, is duly authorized to execute Contracts.
A Limited Liability Company duly organized and doing business under the laws of the State of Michigan for whom _______________________________ whose signature(s) is (are) affixed to this Bid, is (are) duly authorized to execute Contracts.
A Partnership or Joint Venture, all members of which, with addresses, are:
Name Address
An Individual, whose signature is affixed to this Bid.
Signed and sealed this _____ day of __________________ ,20____.
WITNESS Bidder Name:
Authorized
Signature of Bidder:
Print Name:
Title:
Page B-6 of B-9 4-23-2024
A. IF BIDDER IS A CORPORATION, COMPLETE THE FOLLOWING:
RESOLUTION OF THE BOARD OF DIRECTORS OF ______________________________________
The undersigned, being all of the members of the Board of Directors of _________________________, a ______________________ (state) Corporation (the “Corporation”) do hereby certify that the following is a true and correct copy of the resolutions duly adopted by the Corporation on the _____ day of ____________, 20 _____, that the same have not been modified or rescinded and are in full force and effect and that the resolutions have been adopted in accordance with the laws of the state of incorporation, the Articles of Incorporation and the Bylaws of the Corporation and either no shareholder consent is required or any necessary shareholder consent has been obtained:
RESOLVED, that any one or more of the officers of the Corporation referred to below be and hereby are authorized and empowered on behalf of the Corporation to transact any and all business with the County of Oakland, State of Michigan, acting by and through its statutory agent, the Owner which the Corporation could, in any way, transact and are further authorized to execute, acknowledge and deliver on behalf of the Corporation and in its name to the Owner.
A Bid for construction of all or part of the Project in form and content as such officer deems necessary and appropriate and as approved by the Owner.
All other agreements, instruments or documents as such officer deems necessary or appropriate in conjunction with the aforementioned project.
RESOLVED FURTHER, that the following are the true and correct names, signatures, and titles of the officers of the Corporation referred to above:
NAMES SIGNATURES TITLES
RESOLVED FURTHER, that the acts of said person(s) or any of them, shall at all times be given full faith and credit without the necessity of inquiry by the Owner as to any of the circumstances attending the same and that the acts and doings of authorized person(s) or any of them in respect to the subject matter hereof are hereby fully ratified, approved, adopted and confirmed; and
RESOLVED FURTHER, that the authorizations herein set forth shall remain in full force and effect until written notice of their modification or discontinuance shall be given to and received by the Owner at its offices.
IN WITNESS WHEREOF, the Board of Directors of __________________________ have executed this Resolution as of the ____ day of ________________, 20___.
Page B-7 of B-9 4-23-2024
B. IF BIDDER IS A LIMITED LIABILITY COMPANY, COMPLETE THE FOLLOWING:
RESOLUTION OF MEMBERS OF ________________________________________________ , L.L.C.
The undersigned, being all of the members of _____________________________________________, L.L.C. a _______________________ (state) limited liability company (the “Company”) do hereby certify that the following is a true and correct copy of the resolutions duly adopted by the Company on the ______ day of _______________, 20_____, that the same have not been modified or rescinded and are in full force and effect and that the resolutions have been adopted in accordance with the laws of the state of incorporation, the Articles of Organization and the Operating Agreement and that no further member consent is required or any necessary member consent has been obtained:
RESOLVED, that any one or more of the members of the Company referred to be and hereby are authorized on behalf of the Company to transact any and all business with the County of Oakland, State of Michigan, acting by and through its statutory agent, the Owner which the Company could, in any way, transact and are further authorized to execute, acknowledge and deliver on behalf of the Company and in its name to the Owner.
A Bid for construction of all or part of the Project in form and content as the members deem necessary and appropriate and as approved by the Owner.
All other agreements, instruments or documents as the members deem necessary or appropriate in conjunction with the aforementioned project.
RESOLVED FURTHER, that the acts of said member(s) or any of them, shall at all times be given full faith and credit without the necessity of inquiry by the Owner as to any of the circumstances attending the same and that the acts and doings of authorized person(s) or any of them in respect to the subject matter hereof are hereby fully ratified, approved, adopted and confirmed; and
RESOLVED FURTHER, that the authorizations herein set forth shall remain in full force and effect until written notice of their modification or discontinuance shall be given to and received by the Owner at its offices.
IN WITNESS WHEREOF, the Members have executed this Resolution of ______________________, L.L.C. as of the _____ day of ________________, 20_____.
Page B-8 of B-9 4-23-2024
C. IF BIDDER IS A LIMITED PARTNERSHIP, COMPLETE THE FOLLOWING:
CERTIFICATE OF GENERAL PARTNER
_______________________________, being the sole General Partner of _______________________ Limited Partnership, a _______________________ limited partnership (the “Partnership”) hereby certifies that the following is a true and correct copy of the resolutions duly adopted by the Partnership on the _____ day of _______________, 20____, that the same have not, in any way, been modified or rescinded and are in full force and effect and that the resolutions have been adopted in accordance with the laws of the state of formation the Certificate of Limited Partnership and that either no further partner consent is required or any necessary partner consent has been obtained:
RESOLVED, that ___________________________________, the sole General Partner, is hereby authorized and empowered on behalf of the Partnership to transact any and all business with the Owner which the Partnership could, in any way, transact and is further authorized to execute, acknowledge and deliver on behalf of the Partnership and in its name to the Owner.
A Bid for construction of all or part of the Project in form and content as such General Partner deems necessary and appropriate and as approved by the Owner.
All other agreements, instruments or documents as such General Partner deems necessary or appropriate in conjunction with the aforementioned project.
RESOLVED FURTHER, that the following are the true and correct names of all general and limited partners of the Partnership:
NAMES PARTNER
General
Limited
Limited
RESOLVED FURTHER, that the acts of General Partner shall always be given full faith and credit without the necessity of inquiry by the Owner as to any of the circumstances attending the same and that the acts and doings of the General Partner in respect to the subject matter hereof are hereby fully ratified, approved, adopted, and confirmed; and
RESOLVED FURTHER, that the authorizations…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .