biddoc.pdf
PDF 2 MB Posted
- Solicitation number
- #131-26
- Issued by
- Grand County, Colorado
About this file
This is a Project Manual and Request for Bids issued by the City of Canon City, Colorado for the 2A Griffin Avenue Reconstruction Project (Bid #131-26, Project #59052). The project involves reconstructing approximately five city blocks along Griffin Avenue between South 4th and South 9th Streets, including construction of a new storm sewer system to separate stormwater and irrigation systems, irrigation system improvements, replacement of the existing water main and water services, and full roadway reconstruction. The scope includes approximately 2,500 linear feet of new storm sewer pipe with associated inlets and manholes, 2,800 linear feet of new irrigation piping with cleanout structures, 2,400 linear feet of 8-inch water main with service replacements and an HDD bore under existing railroad tracks, 9,000 square yards of hot-mix asphalt pavement, 4,800 linear feet of concrete curb and gutter, and 3,500 square yards of miscellaneous concrete paving. Electronic bid submission is required through BidNet Direct, with bids due December 30, 2026. A non-mandatory pre-bid meeting is scheduled for December 1, 2026 at 11:00 AM in Canon City, Colorado, with virtual attendance available. The contract duration is 259 consecutive calendar days from the Notice to Proceed, with award to the lowest responsible and responsive bidder. The bid schedules are divided into four categories: Roadway (Schedule A), Water (Schedule B), Storm (Schedule C), and Irrigation (Schedule D).
The project is funded through the Colorado State Revolving Fund (SRF) loan program administered by the Colorado Department of Public Health and Environment (CDPHE), making it subject to Davis-Bacon prevailing wage requirements, Build America Buy America (BABA) requirements, American Iron and Steel (AIS) requirements, and Disadvantaged Business Enterprise (DBE) requirements. Certified DBEs or consortiums of certified DBEs are encouraged to bid. A five percent bid bond is required, with the full payment and performance bond required upon award. A local bidders' preference applies to Fremont County bidders when the total bid difference is within five percent up to $10,000. The contract includes a two-year general warranty on all work, and the City reserves the right to reject any or all bids. The contractor must comply with all SRF requirements including certified payroll documentation, stormwater management and permit compliance, utility coordination with Atmos Energy and Black Hills Energy for gas and electrical relocations, and coordination with South Canon Ditch Company regarding irrigation operations. The contractor is responsible for all costs associated with construction phasing, property access maintenance, traffic control, staging within the active construction zone, emergency services access coordination, stormwater permit compliance, and subgrade preparation and protection.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
FOR
2A GRIFFIN AVE RECONSTRUCTION PROJECT- 4TH STREET TO 9TH STREET
BID # 131-26
(PROJECT #59052)
CITY OF CAÑON CITY
PREPARED BY CITY OF CAÑON CITY,
ENGINEERING DEPARTMENT
November 13th, 2026
TOC
TABLE OF CONTENTS
CONTRACT DOCUMENTS
BID INFORMATION
PAGE
SECTION
PART 1 REQUEST FOR BIDS 1-1
PART 2 INSTRUCTIONS TO BIDDERS 2-1
PART 3 PROJECT NARRATIVE 3-1
PROJECT DOCUMENTS
A. BID FORM (INCLUDING BID SUMMARY) A-1
B. BID SCHEDULES B-1
C. BIDDER’S QUALIFICATION STATEMENT C-1
D. BIDDER’S CERTIFICATION D-1
E. BID BOND E-1
F. CONSTRUCTION CONTRACT F-1
G. PAYMENT AND PERFORMANCE BOND G-1
H. NOTICE OF AWARD/ AUTHORIZED
REPRESENTATIVE DESIGNATION
H-1
I. NOTICE TO PROCEED I-1
J. CHANGE ORDER J-1
K. CERTIFICATE OF SUBSTANTIAL
COMPLETION
K-1
L. PUNCH LIST L-1
M. CERTIFICATE OF FINAL PAYMENT M-1
N. CERTIFICATE OF FINAL ACCEPTANCE N-1
O. GENERAL PROVISIONS O-1
P. SPECIAL PROVISIONS P-1
Q. TECHNICAL SPECIFICATIONS Q-1
R. CONSTRUCTION DRAWINGS R-1
S. COLORADO STATE REVOLVING FUND
REQUIRED SPECIFICATIONS
S-1
T. DAVIS BACON MINIMUM WAGES,
COLORADO, U.S. DEPARTMENT OF LABOR
- GENERAL DECISION NUMBER:
CO20260003, HEAVY CONSTRUCTION
T-1
U. ADDENDUM ## DOCUMENTS (FUTURE) U-1
1-1
PART 1 – REQUEST FOR BIDS
PROJECT: 2A GRIFFIN AVE RECONSTRUCTION PROJECT; 4TH ST. to 9TH ST.
PROJECT #59052
BID NO.: #131-26
SUBMITTAL DATE AND LOCATION:
Date of Request: November 18th, 2026
Due Date for Bids: December 30th, 2026
Bid Documents can be found at: https://www.bidnetdirect.com/colorado/cityofcanoncity
Electronic bid submission only at: https://www.bidnetdirect.com/colorado/cityofcanoncity
NON-MANDATORY PRE-BID MEETING:
Date & Time: December 1st, 2026 at 11:00 AM
Location ( In-Person): Room A002 South
128 Main Street
Cañon City, CO 81212
Virtual Attendance
Join: https://teams.microsoft.com/meet/2431362456153951?p=r1NzdAH95SJVly5c0Z
Meeting ID: 243 136 245 615 395 1
Passcode: f3PL9Ui6
Attendance at the pre-bid meeting is recommended. A tour of the worksite may follow the meeting for those interested. See BidNet posting for virtual meeting details.
The City of Cañon City requests Bids for:
This project will reconstruct approximately five city blocks along Griffin Avenue between South 4th Street and South 9th Street. The project will include construction of a new storm sewer system to separate the existing stormwater and irrigation systems along the corridor, irrigation system improvements, replacement of the existing water main and water services, and full reconstruction of the roadway corridor.
Any questions concerning this Request for Bids shall be directed IN WRITING ONLY to the
Public Works Director, Leo Evans at laevans@canoncity.org.
FIRST PUBLICATION November 18th, 2026
SECOND PUBLICATION November 21st, 2026
/s/ Tammy Nordyke
Finance Director
PUBLISHED IN Cañon City Daily Record Line item #27-430-0399-59052 http://www.bidnetdirect.com/colorado/cityofcanoncity http://www.bidnetdirect.com/colorado/cityofcanoncity https://teams.microsoft.com/meet/2431362456153951?p=r1NzdAH95SJVly5c0Z mailto:laevans@canoncity.org.
2-4
PART 2 - INSTRUCTIONS TO BIDDERS
2.1 A "Bid" is a responsive, conforming, unconditional, complete, legible, and properly executed offer by a Bidder on the form supplied by the City to provide the work specified in the Request for Bids for the compensation specified.
2.2 Bids shall be submitted electronically through BidNet. No paper bid submission will be accepted. Any document required in original form shall be delivered to the City before the bid deadline. The solicitation shall identify the required delivery method and deadline for each such document. A bid will be considered timely only if all required electronic and physical submissions are received by the applicable deadlines. .
2.3 The City will not accept bids received after the deadline. Late electronic submissions will be rejected by the City and retained or disposed of in accordance with applicable records-retention requirements.
2.4 The City may correct or waive a minor informality or irregularity only where the correction or waiver does not prejudice other bidders or materially alter the bid as determined in the City's sole discretion. Material errors or omissions may result in rejection of the bid. The City shall document its determination.
2.5 In the event of a discrepancy between a unit price and the corresponding extended amount, the unit price shall control and the extended amount shall be corrected. In the event of a discrepancy between a price stated in words and a price stated in figures, the price stated in words shall control, subject to applicable procurement requirements. The City may reject a bid if the discrepancy is material or cannot be resolved under these rules.
2.6 The City shall not reimburse any Bidder for any cost incurred in preparing a Bid or attending equipment demonstrations, inspections, pre-bid conferences, or interviews.
2.7 All addenda will be issued through BidNet. Each bidder is responsible for monitoring the solicitation and acknowledging all addenda as required by the bid forms. Only written addenda issued by the City shall modify the solicitation or Contract Documents.
2.8 A bid submitted by a corporation shall be signed by an officer or other authorized representative with authority to bind the corporation. A bid submitted by a partnership shall be signed by a partner or authorized representative. A bid submitted by a limited liability company shall be signed by a member, manager, or other authorized representative. The City may request evidence of signing authority.
2.9 The following information shall be submitted with the Bid:
2.9.1 The names and addresses of any subcontractors who will be retained for the project.
2.9.2 A list of the Bidder's previous experience on construction of similar projects.
2.10 By submitting a bid, the bidder acknowledges that it has reviewed the Contract
Documents, made reasonable inquiry concerning the Project, and considered information made available by the City regarding the site and the Work. This acknowledgment does
2-5 not waive the Contractor’s rights or remedies under the Contract Documents or applicable law, including rights relating to differing site conditions, concealed conditions, errors or omissions in the Contract Documents, or written clarifications and addenda issued by the
City.
2.11 The Contract will be awarded, if at all, to the lowest responsible and responsive Bidder whose Bid complies with the Contract Documents. In determining whether a Bidder is responsible, the City may consider the Bidder's experience, qualifications, past performance, financial capability, proposed subcontractors and suppliers, references, ability to complete the Work within the required time, and any other information reasonably related to the Bidder's ability to perform the Contract. The City may meet with the lowest responsible and responsive Bidder before award to discuss the proposed construction schedule, project phasing, and the Bidder's understanding of the Work. The
City reserves the right to reject any or all Bids and to waive informalities or irregularities as stated herein.
2.12. The City reserves the right to conduct such investigations as it deems necessary to assist in the evaluation of any Bid to establish the experience, responsibility, reliability, references, reputation, qualifications, or financial ability of any Bidder, manufacturer or supplier. The purpose of such investigation is to satisfy the City that the Bidder has the experience, resources, and commercial reputation necessary to supply the specified equipment and to perform the necessary warranty and product support in accordance with the Contract Documents in the prescribed manner and time.
2.13. The City reserves the right, if it deems such action to be in its best interests, to reject any and all Bids or to waive any irregularities or informalities therein. Any incomplete, inaccurate, false, or misleading information provided by any Bidder shall be grounds for rejection of the Bid. Any reproduction or use of a third party’s work product, in part or whole, without the written consent of the third party, shall also be grounds for rejection of the Bid. If Bids are rejected, the City further reserves the right to investigate and accept the next best Bid in order of ranking, or to reject all Bids and re-solicit for additional Bids.
2.14. The bidder shall not separately include taxes for which the City is legally exempt. The
Contractor remains responsible for all taxes, fees, and assessments imposed on the
Contractor or its operations, employees, equipment, materials, or purchases, except to the extent the City provides a valid exemption. .
2.15. In the event of any claim, suit, or demand which may result from any Bid, or the award of any contract as a result of submission of a Bid, Fremont County, Colorado shall be the venue and Colorado law shall govern any such claim, suit, or demand and the rights and duties of the parties.
2.16. The Bid, including all required documents, shall be submitted using the enclosed forms.
The Summary and Bid Schedule shall be used for submitting the fees, and the completed forms shall be submitted in separate envelopes. Total Base Price/Bid Amount shall be the aggregate total of all bid schedules.
2-6
2.17. Copies of the Contract Documents are available at:
https://www.bidnetdirect.com/colorado/cityofcanoncity
2.18. All parts not specifically mentioned which are necessary in order to provide a complete unit shall be included in the Bid. Any item listed as "Standard" in the manufacturer's published specification, furnished by the Bidder, is assumed to be included in the Bid.
Any variations shall be outlined in writing, noting cost factors where applicable.
2.19. Bids shall be in accordance with the specifications contained in the Contract Documents.
Should any requirement in the specifications not be included in the manufacturer’s specification sheets, the Bidder shall include with its Bid a statement of compliance.
Failure to do so shall be grounds for disqualification of the Bid.
2.20 The City requires a Bid Bond in the form of a corporate surety bond in the amount of five percent (5%) of the total Bid amount before the City can accept and consider any Bid.
Bids with the required bid bond shall be submitted with the fee schedule, bid schedule, and bid as required through the electronic bid submission process. Upon award, such bid bonds shall be returned to the unsuccessful Bidder(s). For the successful Bidder, the Bid bond will be returned upon receipt of the required payment and performance bond, in the full amount of the contract price
2.20. Any Bid received as a result of this request is prepared at the Bidder’s expense and becomes City property and is therefore a public record upon opening by the City. No Bid may be withdrawn for a period of sixty (60) days after the deadline for Bids.
2.21. All questions related to the bid shall be communicated IN WRITING ONLY via the
BidNet application. Submitted questions will be answered collectively and once posted, are identified by BidNet as addendums and must be acknowledged on the bid forms appropriately.
2.22. Bidders shall include all costs associated with each individual line-item quantity, including mobilization/demobilization, signage and traffic control, profit, etc.
2.23. The Project is to be fully complete within 259 (two hundred fifty-nine) consecutive calendar days total duration after Notice to Proceed Date.
2.24. There is a local bidders’ preference on this Project. Fremont County Bidders shall be given priority consideration if the total bid difference is within five percent up to $10,000.
2.25. Bid Award Information:
• The award will not be split and shall be awarded to only one contractor.
- end of section -https://www.bidnetdirect.com/colorado/cityofcanoncity
3-1
PART 3 – PROJECT NARRATIVE
PROJECT SUMMARY:
This project will reconstruct approximately five city blocks along Griffin Avenue between South
4th Street and South 9th Street. The project will include construction of a new storm sewer system to separate the existing stormwater and irrigation systems along the corridor, irrigation system improvements, replacement of the existing water main and water services, and full reconstruction of the roadway corridor.
The storm sewer improvements will include approximately 2,500 linear feet (LF) of new storm sewer pipe, along with all associated inlets, manholes, and appurtenant structures necessary to complete the system. Storm sewer infrastructure will be installed in Griffin Ave and along South
8th Street.
Irrigation improvements will include approximately 2,800 LF of new irrigation piping and construction of multiple cleanout structures and associated appurtenances.
The water main improvements will consist of installation of approximately 2400 LF of 8” watermain, replacement of all services and meter pits including meters, backflows, and shut-offs, and an HDD bore under the existing Rock and Rail tracks.
The roadway improvements will include approximately 9,000 square yards (SY) of hot-mix asphalt (HMA) pavement, 4,800 LF of concrete curb and gutter, 3,500 SY of miscellaneous concrete paving, and other related improvements necessary to complete the reconstruction of the
Griffin Avenue corridor.
This project intends to utilize funding from the Colorado State Revolving Fund (SRF) loan program administered by the Colorado Department of Public Health and Environment (CDPHE).
Bidder’s attention is called to the SRF requirements in the bid package, and all requirements therein are expressly incorporated in this Bid. Bidders are advised that this Project is subject to applicable SRF requirements, including Davis-Bacon prevailing wage requirements, Build
America, Buy America (BABA) and applicable American Iron and Steel (AIS) requirements, Disadvantaged Business Enterprise (DBE) requirements, and other applicable federal and state funding conditions. Also, certified DBEs or a consortium of certified DBEs are encouraged to bid. SRF Specifications are included in Section U-1.
Bidders must carefully review the SRF requirements included in the Contract Documents.
Failure to submit required certifications or documentation may result in rejection of a bid. No construction activity, including mobilization, site preparation, installation, excavation, or physical placement of materials or equipment, shall commence until the City has received written confirmation that all required environmental clearances and final engineering design approvals have been issued by CDPHE.
The project shall be fully complete within 259 consecutive calendar days total duration after
Notice to Proceed is issued. The allotted days for the project schedule include thirty (30) days for adverse weather as indicated in General Provisions section 2.04 plus five (5) days designated for Holidays. Project Substantial Completion will be issued in accordance with GP 1.13 at such time when the elements of the project are completed and put into service for it intended use as a whole.
PROJECT MANAGEMENT:
The construction management/project management team (Engineer) for this project will be comprised of City personnel and third-party Engineering Firm. City of Canon City personnel will perform day-to-day inspections, complete daily inspection reports, verify quantities for pay applications, and direct work in the field in accordance with project plans and specifications.
The third-party engineering firm, under contract with the City, will be responsible for comprehensive project tracking, administration, and compliance throughout the duration of the project.
Construction management will be provided by City staff in coordination with the third-party engineering firm. Together, they will provide overall construction oversight to ensure the project is completed in accordance with the approved plans, specifications, and contract documents.
Responsibilities include providing field direction, coordinating inspections and documentation, monitoring construction progress and quality, addressing construction issues, and coordinating project activities with the Contractor.
City Water Distribution staff, or an authorized representative, will be onsite when water distribution work is being performed. Water Distribution will inspect water-related work, including water mains, services, shutdowns, tie-ins, capping, testing, and related activities. Water
Distribution will coordinate with the Contractor and Engineer to document work and quantities, identify deficiencies, oversee bacteriological and pressure testing, provide direction for correcting water-related work, and review completed water work for acceptance based on the plans, specifications, and applicable standards. Water Distribution will also verify water-related quantities for payment.
City oversight and inspection do not relieve the Contractor of responsibility for the means and methods of construction, sequencing, safety, quality, or proper completion of the work.
COLORADO STATE REVOLVING FUND (SRF) REQUIREMENTS:
This project is being funded, in part, through the State Revolving Fund (SRF) program administered by the Colorado Department of Public Health and Environment (CDPHE). As a result of the SRF funding, the project will be subject to additional state and federal requirements beyond the City's standard construction and contract administration requirements. These requirements will be incorporated into the project plans, specifications, contract documents, and construction administration procedures.
Bidder’s attention is called to the SRF requirements in the bid package. Disadvantaged Business
Enterprise (DBE) requirements and goals are included. Certified DBEs or a consortium of certified DBEs are encouraged to bid. SRF Specifications are included in Section U-1, project wage determination is included in Section T-1. The decision number will be verified by the City
10 day prior to bid opening. If a new decision has been published, an addendum will be published including the updated wage decision.
The project will be administered in coordination with CDPHE and the assigned CDPHE Grant and Loan Specialist. The City's third-party engineering firm will be responsible for coordinating the project's SRF compliance requirements and maintaining the documentation necessary to support project reimbursement and program compliance. The PM will coordinate with City staff, the Contractor, and CDPHE to ensure that required documentation is submitted, reviewed, and maintained throughout the project.
SRF-related requirements will include, as applicable, compliance with federal labor requirements, certified payroll requirements, Build America, Buy America (BABA) requirements, applicable environmental requirements, disadvantaged business enterprise or equivalent program requirements, and other conditions established by the SRF funding agreement. Materials, payroll documentation, construction records, and other required project documentation will be reviewed throughout construction to verify compliance with these requirements.
The Contractor will be responsible for complying with all SRF requirements applicable to its work and for providing the documentation necessary to demonstrate compliance. The Contractor will also be responsible for ensuring that its subcontractors and suppliers comply with applicable
SRF requirements. Failure to provide required documentation or comply with applicable funding requirements may affect the City's ability to obtain reimbursement and may result in corrective action or other contractual remedies.
The PM and City Engineering staff will coordinate the review of contractor pay applications, change orders, certified payrolls, material documentation, and other project records to ensure that costs submitted for payment are eligible under the project contract and applicable SRF requirements. Project records will be maintained throughout construction and compiled as necessary for project closeout and final reimbursement.
The use of SRF funding is intended to support the construction of the project while ensuring that the project is administered in accordance with the requirements of the funding program. The
City, PM, and Contractor will work cooperatively throughout construction to maintain compliance, document eligible project costs, address deficiencies in a timely manner, and complete the project in accordance with both the City's contract requirements and the applicable
SRF funding requirements.
STORMWATER MANAGEMENT AND SWMP REQUIREMENTS:
The Contractor shall be responsible for implementing, managing, maintaining, and enforcing the
Stormwater Management Plan (SWMP) in accordance with the approved plans and specifications and all applicable local, state, and federal laws, regulations, permits, and requirements. The Contractor shall obtain and maintain all permits and approvals required for the project, including, but not limited to, the State Stormwater Construction Permit, any required dewatering permit, and the City of Cañon City Grading, Erosion, and Sediment Control (GESC)
Permit. The City GESC Permit shall be provided at no charge to the Contractor.
The Contractor shall designate a qualified Stormwater Administrator for the project. The
Contractor shall be the primary operator and responsible party for the State Stormwater
Construction Permit and shall designate a qualified Stormwater Administrator as the individual responsible for day-to-day administration of the SWMP. The Stormwater Administrator shall be responsible for implementing, maintaining, inspecting, documenting, and revising the SWMP as necessary to maintain compliance throughout construction. Responsibilities shall include, but are not limited to:
• Implementing and maintaining all stormwater, erosion, and sediment control measures identified in the approved SWMP, plans, specifications, and applicable permits.
• Conducting required site inspections at the frequency and under the conditions established by the applicable permit and SWMP.
• Identifying deficiencies, unauthorized discharges, inadequate control measures, or other conditions that may result in noncompliance.
• Promptly implementing corrective measures for deficiencies identified during inspections or otherwise observed on the project.
• Documenting inspections, deficiencies, corrective actions, maintenance activities, and other SWMP-related activities as required by the applicable permit.
• Maintaining all SWMP and permit documentation onsite and readily available for review by the City and applicable regulatory agencies.
• Revising the SWMP when required by changes in construction activities, site conditions, or permit requirements.
• Coordinating with the City Stormwater Coordinator or designated City representative regarding SWMP implementation and periodic City compliance inspections.
• Coordinating with the City and regulatory agencies regarding stormwater compliance issues, corrective actions, and permit requirements.
The Contractor shall remain responsible for stormwater compliance throughout the project, including periods when construction activities are suspended or the project is otherwise inactive.
The Contractor shall maintain all required temporary and permanent erosion and sediment control measures until such measures are no longer required under the applicable permit or have been accepted by the City.
The Contractor will be required to provide copies of the inspection reports and corrective actions taken within 10 days of the inspection.
The City’s Stormwater Coordinator, or designated representative, will perform periodic compliance inspections of the project site and review the Contractor’s stormwater permit compliance documentation.
Project Closeout and Permit Transfer
Prior to final acceptance of the project by the City, the Contractor shall provide the City
Stormwater Coordinator or designated representative with complete copies of all SWMP and stormwater-related project documentation required by the applicable permits, including inspection reports, corrective action documentation, maintenance records, SWMP revisions, and other required records.
The Contractor shall be responsible for completing all requirements necessary to close the State
Stormwater Construction Permit upon completion of the project, including achievement and documentation of final stabilization, when required. The State permit shall be closed in accordance with applicable Colorado Department of Public Health and Environment (CDPHE) requirements once all permit conditions have been satisfied.
If the State Stormwater Construction Permit cannot be closed prior to final project acceptance solely because final stabilization or other post-construction requirements remain outstanding, the permit may be transferred to the City for continued administration, subject to the requirements and approval of the applicable regulatory agency and prior approval by City personnel. Transfer of the permit to the City shall not relieve the Contractor of any contractual obligations, including requirements for final stabilization, correction of deficient work, maintenance of stormwater controls, or warranty obligations associated with work performed by the Contractor.
The Contractor shall coordinate with the City prior to any permit transfer and shall provide all documentation and information necessary for the City to assume administration of the permit.
SITE ACCESS AND STAGING:
The project site consists primarily of residential neighborhoods along Griffin Avenue, with commercial and light-industrial properties along South 8th Street. The project limits terminate at the Colorado Department of Transportation (CDOT) right-of-way at SH 115 (South 9th Street) to the east and South 4th Street to the west.
There are no adjacent side streets or alleys behind the properties that can be utilized to provide alternate or temporary access during construction. Accordingly, the Contractor shall carefully consider access requirements and construction phasing when preparing its bid and developing its means and methods.
Griffin Avenue may be closed to through traffic in accordance with the Phasing Plan provided in the Contract Documents. However, local access to residences, businesses, and other properties within the project limits shall be maintained to the maximum extent practicable throughout construction. South 5th and south 6th Streets are currently used by parents to access Lincoln
School, located 1 block south on Myrtle Ave., for pick-up and drop-off. The Contractor shall coordinate its operations and phasing to minimize disruptions to property access.
South 8th Street has its only vehicular access from Griffin Avenue. Access to South 8th Street shall be maintained throughout the project. The Contractor shall sequence its work and maintain appropriate temporary access as necessary to prevent South 8th Street from being isolated from the existing street network.
The Contractor shall be responsible for incorporating the requirements of the Phasing Plan, property access, traffic control, and construction staging into its bid. No additional compensation will be provided for costs associated with complying with the required construction phasing, maintaining property access, or sequencing construction activities as necessary to meet these requirements, unless specifically authorized elsewhere in the Contract Documents.
The City does not have nearby property available for Contractor staging. Therefore, the
Contractor should anticipate that construction staging, including materials, equipment, and other necessary construction operations, will generally need to be accommodated within the active construction zone. The contractor is encouraged to work with suppliers and coordinate delivery of materials in stages to attempt to limit the amount of materials being staged. Should the contractor opt for offsite storage, no additional compensation will be paid for handling the materials multiple times or transportation. Chain of custody for BABA material tracking must include off-site storage if this option is selected.
Staging of materials, equipment, or other construction-related activities shall not block or unreasonably restrict access to residences or businesses. Staging or extended construction closures will not be permitted within the intersecting streets south of Griffin Avenue between
South 4th Street and South 8th Street. The Contractor shall maintain these streets available for local access and shall coordinate construction activities to minimize impacts to adjacent properties.
Access for emergency services shall be maintained at all times. The Contractor shall coordinate with emergency service providers as necessary to ensure emergency access is continuously available throughout construction.
The Contractor shall be solely responsible for planning and coordinating its construction operations, sequencing, staging, and traffic control in a manner that satisfies these requirements and the approved Phasing Plan.
PROJECT PHASING AND TRAFFIC COORDINATION:
To minimize disruption to residents and businesses, construction is being executed in carefully scheduled phases that prioritize public safety and continuous property access.
PHASING OVERVIEW AND TRAFFIC CONTROL:
The initial construction phases will impact South 8th Street north of Griffin Avenue for storm sewer installation and then will extend west along Griffin Avenue from South 8th Street to South
4th Street to facilitate storm sewer, water, and irrigation utility improvements, as well as construction of the proposed roadway section. Water main installation will begin at 4th Street and work east towards 9th Street. The project will likely involve multiple construction operations occurring concurrently and may require coordination among multiple crews and subcontractors.
Traffic control and construction operations shall be carefully planned and executed to maintain access to adjacent properties and residents to the maximum extent practicable throughout construction. The Contractor shall coordinate the sequencing of work, traffic control, utility operations, and access requirements to minimize disruptions and maintain safe and reasonable access to residences and businesses within the project limits.
South 8th Street, north of Griffin Avenue, serves as the sole access point for adjacent properties.
Consequently, this intersection must remain open at all times to provide necessary vehicular and pedestrian access. Any work elements that directly impact this intersection must be planned and coordinated in advance. Implementation of targeted strategies as needed, including the use of flaggers, off-peak night operations, or weekend work schedules are potential options.
Griffin Avenue between S. 8th Street (East) and S. 9th Street is designated as the final phase of road construction. To maintain safe traffic flow throughout the project, this final section of roadway will not be closed until Griffin Avenue between 4th and 8th Streets has been fully paved, pavement markings installed if applicable, and verified as safe for the traveling public.
Once opened, that newly completed section will serve as the primary detour route to guide traffic around the final work zone. The only exception will be temporary, short-term closures with supporting detours to facilitate work at the 8th and Griffin intersections. The Contractor must obtain a CDOT Special Use Permit for the closure of the Griffin Ave intersection at 9th St (State
Highway 115
CONSTRUCTION PHASE 0:
0A. Submittal approval process and secure materials in accordance with project specifications. Priority should be given to critical path items due to anticipated lead times for BABA/AIS deliveries.
0B. Other project administration coordination, permitting, and preliminary construction survey work.
0C. Begin utility potholing along south 8th Street for storm sewer installation. Continue activity as needed.
0D. Coordinate utility relocations.
CONSTRUCTION PHASE 1:
1A. Install storm sewer improvements along South 8th Street to Griffin Intersection
▪ Patch storm trench as soon as practical to reduce maintenance and impact to the area. Likely Spring 2027 unless weather allows earlier.
1B. Install planned storm and irrigation around the intersection of 8th and Giffin.
Continue installation of storm west to 7th Street.
1C. Identify and install any additional irrigation improvements that can be completed ahead of ditch turn on.
▪ Potentially complete multiple irrigation crossing near STA 1+75.00 prior to ditch turn on
1D. Utility potholing in along Griffing Ave ahead of project utility and irrigation work.
CONSTRUCTION PHASE 2:
2A. Continue storm installation from 7th to 6th
2B. Identify and install any additional irrigation improvements that can be completed ahead of ditch turn on.
2C. Complete Water phase W-1
CONSTRUCTION PHASE 3:
3A. Complete storm installation from 6th to west end of system
3B. Complete irrigation improvements
3C. Complete Water phases W-2 and W-3
CONSTRUCTION PHASE 4:
4A. Complete Water phase W-4 to 8th St intersection
4B. Begin construction of road section at 4th Street working east
CONSTRUCTION PHASE 5:
5A. Construct all ROW improvements between 4th and 8th.
5B. Complete HMA paving between 4th and 8th including tie-ins at 5th , 6th , and 7th
CONSTRUCTION PHASE 6:
6A. Close roadway from 8th to 9th
6B. Complete irrigation improvements
6C. Complete water phases W-5, W-6, and W-7
6D. Construct all ROW improvements, road sections, and complete HMA paving
WATER MAIN PHASING:
The water main design has been phased to allow for segmented construction and to minimize disruption to existing water service. The new water main will be installed in the segments identified in the plan set, with each segment being tested and accepted prior to completing the associated service connections and tie-ins to the new main. Installation of the subsequent water main segment may proceed while services and tie-ins are being completed within the preceding segment, provided adequate City inspection staffing is available to support the required inspection and testing activities.
Water Phasing has been broken down into the following segments and shall be completed in sequence and properly phased with the overall project phasing plan.
Water- Phase 1 (W-1) 4th Street to 5th St
Water- Phase 2 (W-2) 5th Street to 6th St
Water- Phase 3 (W-3) 6th Street to 7th St
Water- Phase 4 (W-4) 7th Street to 8th St
Water- Phase 5 (W-5) 8th to RR
Water- Phase 6 (W-6) HDD Install; RR Crossing
Water- Phase 7 (W-7) RR to 9th St
The existing water main serving South 8th Street is a dead-end main, making coordination and sequencing construction activities particularly important to minimize impacts to the system users. Work that requires interruption of water service will be coordinated with the City in advance and scheduled to minimize the duration and extent of service disruptions. Where practical, critical shutdowns, tie-ins, and service transfers may be scheduled during nighttime or weekend hours to reduce impacts to customers and maintain continuity of service to the greatest extent possible. The Contractor will be responsible for coordinating its construction activities, crews, and subcontractors to efficiently complete these critical operations and restore service as quickly as practicable.
Flushing of new water mains shall be conducted at a minimum flow velocity of 500 GPM for a sufficient duration to fully flush the main in accordance with project specifications and AWWA standards incorporated by reference. The Contractor shall be responsible for managing and controlling all discharge water generated during flushing operations to prevent property damage, flooding, erosion, damage to existing facilities or other improvements, and adverse impacts to adjacent properties or the public. The Contractor shall provide and maintain all necessary hoses, fittings, temporary discharge piping, erosion control measures, energy dissipation devices, and other equipment required to safely convey and discharge flushing water. The Contractor shall coordinate the discharge location and flushing operations with the City prior to beginning flushing activities.
SUBGRADE PREPARATION AND PROTECTION
The Contractor shall prepare and protect the pavement subgrade in accordance with the geotechnical recommendations. Prior to placing the aggregate base course (ABC), the
Contractor shall scarify and blend the upper 8 inches of subgrade, adjust moisture content as necessary, and compact the material to the specified requirements. The Contractor shall then proof-roll the prepared subgrade.
The Contractor shall minimize construction traffic and heavy equipment operations on the exposed subgrade to prevent disturbance or deterioration. The Contractor shall sequence the work and manage construction activities to prevent unnecessary or prolonged operation of heavy equipment and truck traffic on the exposed subgrade. The Contractor shall take all necessary measures to protect the subgrade from rutting, disturbance, pumping, moisture-related damage, or other deterioration.
Any subgrade failure, damage, or deterioration resulting from the actions or operations of the
Contractor or its subcontractors shall be the sole responsibility of the Contractor. The Contractor shall, at its sole expense, repair or replace the affected subgrade as directed by the Geotechnical
Engineer and to the satisfaction of the City. No additional compensation or extension of contract time will be provided for repairs required because of the Contractor's or subcontractors' operations.
UTILITY COORDINATION AND IRRIGATION REQUIREMENTS:
ATMOS ENERGY
Atmos Energy will relocate the existing gas main and replace existing gas services to mitigate conflicts with the proposed improvements. This work is anticipated to begin in early October
2026 and is expected to be completed prior to December 31, 2026.
The limits of the Atmos Energy work will extend from South 4th Street to the east side of South
8th Street. The new gas main will generally be installed beneath the proposed sidewalk along the north side of Griffin Avenue. New gas services will be installed to properties along both the north and south sides of Griffin Avenue.
The Contractor shall coordinate its construction activities with Atmos Energy and the City to accommodate the gas main relocation and service replacement work. The Contractor shall consider the anticipated schedule and sequencing of the Atmos Energy work when developing its bid, construction schedule, phasing plan, and means and methods.
BLACK HILLS ENERGY
Black Hills Energy will relocate existing utility poles along the north side of Griffin Avenue between South 4th Street and South 7th Street. The pole relocations are being performed at the
City's request.
The Contractor shall coordinate its construction activities with Black Hills Energy and the City to accommodate the pole relocation work. The Contractor shall account for the anticipated pole relocation work and associated coordination requirements when developing its bid, schedule, and construction phasing.
SOUTH CAÑON DITCH COMPANY AND IRRIGATION
The South Cañon Ditch Company operates the irrigation system serving the project area. The project includes multiple irrigation crossings that will be replaced, as well as improvements to existing irrigation laterals and associated structures.
The South Cañon Ditch Company is scheduled to discontinue irrigation deliveries for the 2026 season no later than November 1, 2026, with irrigation service scheduled to resume March 1, 2027. The Contractor shall plan its work to complete as much of the irrigation-related construction as practicable during the irrigation shutdown period and shall prioritize the critical-path irrigation improvements identified in the Phasing Plan for completion prior to March 1, 2027.
Irrigation work, storm sewer work, and water main work that cannot be completed prior to March
1, 2027, shall require the Contractor to coordinate directly with the South Cañon Ditch Company and the City to develop an acceptable construction approach. Depending on the location and nature of the work, the Contractor may be required to:
• Coordinate temporary shutdowns of individual irrigation laterals on a case-by-case basis;
• Develop and implement alternate irrigation delivery methods, including pump-around systems or similar measures;
• Develop construction techniques that allow work to proceed while maintaining irrigation flows; and
• Provide temporary measures necessary to protect existing irrigation facilities and maintain service to affected shareholders.
At no time shall the Contractor interrupt or prevent delivery of irrigation water to a shareholder without prior authorization from the affected shareholder and concurrence from the South Cañon
Ditch Company.
The Contractor shall include in its bid all anticipated costs associated with coordinating irrigation operations and maintaining irrigation service, including temporary bypasses, pump-around systems, temporary piping, access, protection of existing facilities, and other measures reasonably necessary to complete the work while maintaining required irrigation deliveries.
The Contractor should also anticipate encountering groundwater during excavation and construction activities. The Contractor shall be responsible for providing and maintaining all necessary dewatering, groundwater management, excavation support, temporary drainage, and other measures necessary to safely and properly perform the work. These conditions shall be considered incidental to the work unless otherwise specifically identified for payment in the
Contract Documents.
Irrigation cleanout boxes that are significantly modified or installed with this project shall have grates constructed to allow installation of pumps where necessary and be hinged to allow access for cleaning and access to diversion structures/mechanisms. Additionally, some boxes act as diversion structures and that function must be preserved and incorporated into the design of the box. The design and operation of the grating shall be at the contractor’s discretion and must be approved by the Engineer prior to construction of the structure.
OTHER EXISTING UTILITIES
The Contractor shall be responsible for potholing and field-verifying the horizontal and vertical location and elevation of existing utilities that may be affected by the proposed improvements.
Utility locations shown in the Contract Documents are provided for reference and shall not relieve the Contractor of its responsibility to independently verify existing utility locations prior to excavation.
If a conflict between an existing utility and the proposed improvements is identified through potholing or other field verification, the Contractor shall immediately notify the Engineer. The
Contractor shall not proceed with work that would impact or conflict with the utility until the conflict has been reviewed and direction has been provided by the Engineer.
An RFI initiated by the Contractor regarding an existing utility conflict shall include sufficient documentation to clearly identify the conflict, including, as applicable, pothole locations, measured horizontal and vertical locations, elevations, photographs, utility information, and the proposed work that creates the conflict. The Contractor shall provide this information with the
RFI to facilitate timely review and resolution.
BID FORM
The undersigned offers and agrees to furnish all items, upon which the prices are quoted, at the price set opposite each item, if this Bid is accepted within sixty (60) days of the due date. The undersigned also agrees to execute the Contract and satisfy the Performance and Payment Bond and Insurance requirements within ten (10) calendar days from the date when Notice of Award is delivered to the Bidder. The undersigned certifies that no federal, state, or local tax is included in the quoted prices and that none will be added.
PROJECT NAME: 2A GRIFFIN AVE RECON PROJECT- 4TH- 9TH STREETS
(PROJECT # 59052)
BID #: 131-26
Bidder acknowledges receipt of the following Addenda:
Name of Bidder:
Address:
Telephone Number:
BID SUMMARY
Total Base Price: $
(in words)
BIDDER:
By:
Name:
(SEAL)
ATTEST:
Title:
A-1
C-1
BID SCHEDULES
PROJECT: 2A GRIFFIN AVE RECON PROJECT- 4TH- 9TH STREETS
BID NO.: #131-26 PROJECT NO.: #59052
BID: Pursuant to the request for bids for the above-named Project and being familiar with all contractual requirements, therefore, the undersigned Bidder hereby proposes to furnish all labor, materials, tools, supplies, equipment, plant, transportation, services, and all other things necessary for the completion of the Project. All other work to complete the Project but not specifically itemized shall also be included as incidental to the Project’s cost. Contractor also agrees to pay all taxes and patent documents, within the time of completion of the Project and pay all taxes and patent costs, and complete the Project in accordance with the time of completion set forth herein, for and in consideration of the following unit and lump sum prices:
BID 131-26 - 2A GRIFFIN AVE RECON (59052)
BID SCHEDULE A- ROADWAY
ITEM
CODE
ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
000-00001 EROSION CONTROL LS 1.0
201-00001 CLEARING AND GRUBBING LS 2.0
202-00203 REMOVAL OF CURB AND GUTTER LF 197.0
202-00210 REMOVAL OF CONCRETE
PAVEMENT
SY 2133.0
202-00220 REMOVAL OF ASPHALT MAT SY 8161.0
202-00240 REMOVAL OF ASPHALT MAT
(PLANING 2 INCH)
SY 110.0
203-00010 UNCLASSIFIED EXCAVATION
(COMPLETE IN PLACE)
(ROADWAY)
CY 2130.0
203-00001 UTILITY POTHOLING (UP-1)(0-4FT
DEPTH)
EA 76.0
203-00002 UTILITY POTHOLING (UP-2)(4-6FT
DEPTH)
EA 62.0
203-00003 UTILITY POTHOLING (UP-3)(6-8FT
DEPTH)
EA 30.0
203-00004 UTILITY POTHOLING (UP-4)(8-
10FT DEPTH)
EA 20.0
203-00005 UTILITY POTHOLING (UP-5)(OVER
10FT DEPTH)
EA 10.0
210-01000 RESET FENCE LF 230.0
210-00810 RESET GROUND SIGN EA 4.0
C-2
BID SCHEDULE A- ROADWAY
ITEM
CODE
ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
210-04010 ADJUST MANHOLE EA 5.0
212-00000 LANDSCAPE RESTORATION
(PARKING)
SY 2500.0
304-06004 AGGREGATE BASE COURSE
(CLASS 6)(ROAD SECTION)
SY 7945.0
403-34742 HOT MIX ASPHALT (GRADING
SX)(75)(PG 64-22)( 2 INCH
OVERLAY)
SY 110.0
403-34743 HOT MIX ASPHALT (GRADING
SX)(75)
(PG 64-22)(FULL DEPTH)
SY 8826.0
412-00600 CONCRETE PAVEMENT (6 INCH) SY 1425.0
412-00615 CONCRETE PAVEMENT (6 INCH)
(REINFORCED)
SY 57.0
412-00815 CONCRETE PAVEMENT (8 INCH)
(REINFORCED)
SY 152.0
420-00300 GEOTEXTILE (REINFORCEMENT) SY 7945.0
608-00000 CONCRETE SIDEWALK (4 INCH) SY 1856.0
608-00010 CONCRETE CURB RAMP SY 430.0
609-21010 CURB AND GUTTER TYPE 1A LF 5077.0
609-21020 CURB AND GUTTER TYPE 2 LF 267.0
610-00024 MEDIAN COVER- PATTERNED (4
INCH THICK)
SY 45.0
625-00000 CONSTRUCTION SURVEY AND
STAKING
LS 1.0
626-00000 MOBILIZATION LS 1.0
627-30210 THERMOPLASTIC PAVEMENT
MARKING (XWALK-STOPLINE)
SF 88.0
630-00016 TRAFFIC CONTROL (SPECIAL) LS 1.0
SCHEDULE A TOTAL
C-3
BID SCHEDULE B- WATER
ITEM
CODE
ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
202-04001 1-1/2” CAP EA 1.0
202-04006 6" CAP EA 4.0
202-04008 8” CAP EA 3.0
202-04076 6” PLUG EA 2.0
603-50004 PVC PIPE- 4 INCH (C900)(DR14) LF 5.0
603-50006 PVC PIPE- 6 INCH (C900)(DR14) LF 97.0
603-50008 PVC PIPE- 8 INCH (C900)(DR14) LF 2435.0
603-50012 PVC PIPE- 12 INCH (C900)(DR14) LF 5.0
603-50018 HDPE- 8 INCH (C906) LF 48.0
603-60000 8”45o TRANSITION COUPLING
(HDPE TO PVC) MEGA LUG
EA 2.0
619-00000 METER PIT ASSEMBLY EA 55.0
619-00008 12" X 12" X 8" MJ TEE EA 2.0
619-06060 6" X 4" REDUCER EA 1.0
619-40060 3/4" COPPER PIPE LF 1718.0
619-50482 6” 45° MJ ELBOW EA 4.0
619-50641 8”X6” REDUCER EA 3.0
619-50642 8” 45° MJ ELBOW EA 10.0
619-50643 8” 22.5° MJ ELBOW EA 3.0
619-50646 8”X 6”X 8” MJ SWIVEL TEE EA 5.0
619-50648 8"X 8"X 8" MJ TEE EA 4.0
619-75046 6” GATE VALVE EA 4.0
619-75068 8” GATE VALVE EA 12.0
619-75096 12” GATE VALVE EA 1.0
619-77200 3/4” SADDLE TAP EA 55.0
619-77204 4” TRANSITIONAL COUPLING
ADAPTER
EA
1.0
619-77206 6” TRANSITIONAL COUPLING
ADAPTER
EA
2.0
619-77208 8” TRANSITIONAL COUPLING
ADAPTER
EA
2.0
619-78048 FIRE HYDRANT ASSEMBLY EA 4.0
SCHEDULE B TOTAL
C-4
BID SCHEDULE C- STORM
ITEM
CODE
ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
202-00019 REMOVAL OF INLET EA 20.0
202-00035 REMOVAL OF PIPE LF 2108.0
506-00209
RIP RAP (9 IN) - OUTLET
PROTECTION
CY 5.0
603-01180 REINFORCED CONCRETE PIPE, 18" LF 1376.0
603-01240 REINFORCED CONCRETE PIPE, 24" LF 1031.0
603-01305 REINFORCED CONCRETE PIPE, 30" LF 69.0
603-77001
CULVERT HEADWALL (3 SIDED
CULVERT)(TYPE 1)
EA 1.0
604-13005 INLET TYPE 13 (5 FOOT) EA 1.0
604-16005 INLET TYPE 16 (5 FOOT) EA 9.0
604-19105 INLET TYPE R (5 FOOT) EA 11.0
604-39004 MANHOLE - 4FT EA 4.0
SCHEDULE C TOTAL
C-5
BID SCHEDULE D- IRRIGATION
ITEM
CODE
ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE
619-50608 PVC PIPE- 8" (MIN SDR 26) LF 2243.0
619-50610 PVC PIPE- 10" (MIN SDR 26) LF 20.0
619-50800 PVC PIPE- 12" (MIN SDR 26) LF 546.0
619-65000 11.25o PVC ELBOW- 10” (MIN SDR
26)
EA 1.0
615-65000 PRECAST IRRIGATION
STRUCTURE
EA 28.0
SCHEDULE D TOTAL
C-6
2A GRIFFIN AVE RECON PROJECT- 4TH- 9TH STREETS
BID 131-26
TOTAL PRICE: BID SCHEDULE A $
TOTAL PRICE: BID SCHEDULE B $
TOTAL PRICE: BID SCHEDULE C $
TOTAL PRICE: BID SCHEDULE D $
TOTAL PRICE: SUM OF SCHEDULES A -D $
(SEAL) ATTEST:
C-7
BIDDER’S QUALIFICATION STATEMENT
A Statement showing the qualifications of Bidder shall be a prerequisite to the Bidder being awarded the Contract. The qualification statement is intended to assure the City that a high degree of overall workmanship can be expected, and that the Project will be completed within the time limits contained in the Contract Documents.
All items on the statement must be answered in full and submitted with the Bid. The qualification statement will be reviewed by the City after all Bids have been received and opened and prior to award.
The Bidder shall answer and furnish the following items for review:
1. Name of Bidder.
2. Permanent address and phone number of Bidder.
3. Date Company was organized.
4. If a corporation, where incorporated.
5. Number of years engaged in contracting business under present firm or trade name.
6. Please give references who can speak to your financial condition (Financial Officer, Banker, or CPA):
7. List…
This is the start of the file's text. The full file is on GovTribe.