SOIL Lab & Community Schoolyard Construction - General Contracting Services RFP
This Request for Proposals is issued by Durango School District 9-R in Colorado for general contracting services to manage construction of the SOIL Outdoor Learning Lab & Ecological Learning Park at Riverview Elementary School, located at 2900 Mesa Avenue in Durango. The project converts an underutilized hillside, playground area, and school bus turnaround into an outdoor learning laboratory, agricultural park, and public gathering space. The scope includes master site scheduling, active campus safety, civil earthworks, utility connections, structural installation, and coordination with District-recommended specialty subcontractors and local trade specialists. Attendance at the mandatory pre-bid site walk on November 17, 2026, from 2:00 PM to 3:00 PM MT is required for all prime contractors submitting proposals. The deadline for written questions is December 2, 2026, at 4:00 PM MT, with a final addendum issued by December 7, 2026. Proposals are due by December 16, 2026, at 2:00 PM MT via BidNet. The District anticipates contract award and execution by January 14, 2027, with notice to proceed issued January 15, 2027. The project has a target completion date of December 31, 2027, for core construction and February 2028 for exhibit finishes and final punch-list work.
The contract employs a Target-Cost Guaranteed Maximum Price (GMP) model with prioritized scope bidding within a $795,000 GMP ceiling against a total project budget of $1,142,635. Bidders submit line-item pricing for an ordered, prioritized menu of construction tasks (Priorities 1-11) with evaluation based on the total depth of scope items guaranteed within the fixed ceiling. The District retains 5% statutory retainage from monthly progress payments, released upon final completion and inspector sign-off. One hundred percent pass-through applies to all trade discounts, vendor rebates, and material price reductions, with no overhead or profit markups on donated materials or volunteer labor. The General Contractor's standard overhead and profit percentage applies to all District-recommended specialty subcontractor agreements. Bid guaranty bonds of 5% of bid amount and 100% performance and payment bonds are required. A bid bond is mandatory, with surety ratings of A- or better in Best's Insurance Guide. The project is funded under DOLA Community Schoolyard Grant #YARD-26-004 and is not subject to prevailing wage or Davis-Bacon requirements. General Contractors must comply with District Master Insurance standards as outlined in Attachment D, or submit a formal Insurance Waiver Request for review. Four additive alternates are available for funding through realized cost savings, trade discounts, donated materials, or supplemental capital funds.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS (RFP)
General Contracting Services: SOIL Lab & Community Schoolyard Construction
Grant Identification: DOLA Community Schoolyard Grant #YARD-26-004
Issuing Entity: Durango School District 9-R (“District”)
Project Location: Riverview Elementary School Campus (2900 Mesa Avenue, Durango, CO)
Target Completion: Core Construction: December 31, 2027; Exhibit Finishes & Final Punch-List: February 2028
1. INTRODUCTION & PROJECT PURPOSE
Durango School District 9-R is soliciting competitive proposals from qualified General Contracting firms to manage construction of the SOIL Outdoor Learning Lab & Ecological Learning Park at Riverview Elementary School. The project converts an underutilized hillside, playground area, and school bus turnaround into a vibrant outdoor learning laboratory, agricultural park, and public gathering space.
The District seeks a collaborative Prime General Contractor to oversee master site scheduling, active campus safety, civil earthworks, utility connections, and structural installation. To maintain project momentum and specialized craftsmanship, the selected General Contractor will collaborate with established site partners, local trade specialists, and design teams familiar with the SOIL Lab's physical layout, custom structures, and educational vision.
2. CONTRACT STRUCTURE & FINANCIAL TERMS
Contract Model: Target-Cost Guaranteed Maximum Price (GMP) with Prioritized Scope Bidding.
Total Project Budget $1,142,635
● General Contract Guaranteed Maximum Price Ceiling: $795,000
● Owner-Direct Budget (outside of General Contract Scope: $347,635)
○ Planning, Design, Engineering, Consulting: $160,000
○ Infrastructure, Exhibit Construction, Furnishings and Finishes: $87,635
○ Contingency Fund: $100,000
Prioritized Scope Bidding Model: Bidders shall submit line-item pricing for an ordered, prioritized menu of construction tasks (Attachment C) within the $795,000 budget ceiling.
Bidders will be evaluated on the total depth of prioritized scope items (P-1 through P-11) they guarantee to complete within the fixed ceiling.
Open-Book Accounting & Pass-Through Savings:
● 100% Pass-Through: All trade discounts, vendor rebates, and material price reductions secured by the District or SOIL team shall pass through 100% to the project budget without GC percentage markup.
● Donated Materials & Volunteer Labor: No overhead or profit markups shall apply to donated materials, volunteer labor, or equipment ($0 direct cost). Supervisory staff time during community build days is billable under standard contract hourly rates.
District Recommended Specialty Subcontractors: Durango School District 9-R may recommend pre-qualified local trade partners, craftspeople, and community artisans for specific specialized line items within the project scope (e.g., mass timber framing, adobe flooring, specialized civil earthworks, etc.). Bidders are encouraged to evaluate and engage these recommended local partners to preserve project momentum and specialized craftsmanship.
When the General Contractor elects to subcontract with a District-recommended specialty partner, the GC shall execute a standard subcontract with that partner at the negotiated scope amount and integrate them into the master site schedule and GC liability/safety umbrella. The General Contractor’s standard Overhead & Profit markup percentage (specified on Attachment C) shall apply to all such subcontractor agreements.
Permitting & Agency Coordination:
● General Building Permit: Durango School District 9-R will organize, submit, and pay for the primary Building Permits through the Colorado Division of Fire Prevention and Control (CDFPC).
● Trade Permits: The General Contractor shall secure, pull, and manage all required state trade permits, specifically DORA (Colorado Department of Regulatory Agencies) permits for electrical and plumbing work.
● Special Inspections & Materials Testing: The District directly contracts 3rd-party special inspections and materials testing (soils, concrete, structural connections) as required by CDFPC. The GC is responsible for site scheduling and providing 24- to 48-hour advance notice to inspectors.
Bonds & Financial Security:
● BID GUARANTY (BID BOND): Bid Guaranty (Bid Bond) is required on all bids. The bid shall be accompanied by a bid guaranty bond (bid bond), by a guaranty company authorized to carry on business in the State of Colorado, for payment to Durango School District in the sum of at least five percent (5%) of the total amount of the bid. A bid bond form which provides further payment of attorney's fees or which contains a termination date will not be considered. The amount payable to Durango School District under the guaranty bond, shall be forfeited to Durango School District as liquidated damages in case of a failure or neglect of the Bidder to furnish, execute and deliver the required performance and payment bonds, evidence of insurance, and to enter into, execute and deliver to Durango School District the contract on the form provided herewith, after being notified in writing by Durango School District that the award has been made and the agreement is ready for execution. All bonds shall have a power of attorney authorizing the signature of the person authorized to sign on behalf of the Surety attached to the bond. The power of attorney signature and the principal's signature shall each (both) be notarized. The bid bond shall name Durango School District as beneficiary and shall specify that the bond is valid for the bid opening of this project as scheduled in the Invitation for Bid.
● PERFORMANCE AND PAYMENT BONDS: The successful Bidder will be required, as a condition to granting a contract award, to furnish the District both Performance and Labor and Material Payment Bonds or other acceptable security on all bids in excess of $50,000. Such bonds shall be in the amount of one hundred percent (100%) of the contract price, covering the faithful performance of the contract and the payment of all obligations arising thereunder. The cost of the bonds shall be included in the bid. Bonds shall be fully executed and notarized and delivered to the District’s purchasing Manager prior to execution of the contract on forms acceptable to said District representative and before commencement of any work.
○ Contract Execution. The Contractor shall furnish to the District, prior to beginning any Work at the construction site, bonds in the full amount of the estimated Cost of the Work plus the Construction Phase Fee or, if established, the Guaranteed Maximum Price less the Design Phase Fee, whichever is greater, covering both the faithful performance of the Owner-Contractor Agreement and payment of all obligations for labor and materials arising thereunder. Bonds shall be on such forms as the District may find acceptable (in compliance with AIA Document A311) and shall be issued by a surety legally authorized in the State of Colorado and rated in Best’s Insurance Guide (latest edition) not lower than A- or having a Best’s Financial Rating of at least A-VII. Such bonds shall be duly executed by a qualified surety, conditioned upon the true and faithful performance of the Contract, and shall provide that if the Contractor or its Subcontractors fail to duly pay for any labor, materials or other supplies used or consumed by such Contractor or its Subcontractors in the performance of the work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, together with interest at the rate of twelve percent (12%) per annum.
The Performance Bond shall additionally guarantee that the Contractor shall remedy any omissions; correct any and all defects; and adjust and make operable all component parts of the work falling under the requirements of its Contract which may be called to its attention within a period of twelve (12) months following the date of the Letter of Acceptance.
○ The premium for all bonds shall be paid by the Contractor and included in all estimates and the Guaranteed Maximum Price. The District will accept and approve bonds written by sureties legally authorized to write such bonds in the State of Colorado, provided such surety companies are rated in Best’s Insurance Guide (latest edition), not lower than A- and have a Best’s Financial Rating of at least VII. If at any time a surety on such a bond becomes irresponsible or loses its right to do business in the State of Colorado, the District may require another surety acceptable to the District, which the Contractor shall furnish within ten (10) calendar days after receipt of written notice to do so.
○ Subcontractors pre-qualified with concurrence by the District prior to bidding, who enter into a Subcontract agreement with the Contractor for any portion of the work, shall provide the Contractor with Performance and Payment Bonds in accordance with the Contract Documents on the basis of their subcontract scope of work to the Contractor.
○ The Contractor shall require the attorney-in-fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of the power of attorney.
Payments & Statutory Retainage: Monthly pay applications using standard AIA Form G702 and Form G703 with open-book backup documentation. Pursuant to C.R.S. § 24-91-103, the District will withhold 5.0% statutory retainage from each progress payment, released upon final completion and inspector sign-off.
Insurance & Exception Process: General Contractors must meet District Master Insurance standards (Attachment D). Contractors who carry lower limits may submit a formal Insurance Waiver Request (Section 6 of proposal) for case-by-case review by the District Chief Operations Officer.
Labor Standards & Wage Rates:
● State and federal prevailing wage requirements (including Davis-Bacon) do not apply to this project under DOLA Grant #YARD-26-004.
● Bidders and subcontractors shall calculate all labor estimates using standard open-market rates. Certified payroll reporting is not required for monthly pay applications.
3. DETAILED PRIORITIZED SCOPE OF WORK
Bidders must submit line-item pricing for the following prioritized menu of construction tasks.
Scope items are listed in strict order of priority, ensuring Phase 3 core gathering space and exhibit infrastructure are completed before advancing into Phase 4 components.
PHASE 3 PRIORITIES (Core Bus Circle Infrastructure, Hub & Exhibits)
● Priority 1 (P-1): The Hub Site Prep, Civil Grading & Main Electrical/Water Utilities
General site grading, excavation, and clearing inside the bus circle turnaround. Install and feed a main electrical service subpanel inside the bus circle utilizing existing buried conduit; install a secondary electrical subpanel on the existing Horizon Stage pavilion;
install weather-rated electrical outlets on existing light posts. Expose buried water line in the bus circle to install a seasonal, frost-resistant exterior drinking fountain, bottle-filling station, and hose bib.
● Priority 2 (P-2): Campus Access, Crosswalks & Traffic Safety Controls Supply and application of painted pedestrian crosswalk striping connecting school, exhibits, features, and phases. Supply and installation of prominent bus circle safety signage: “DO NOT ENTER – SCHOOL BUS TRAFFIC ONLY” and “CAUTION:
PEDESTRIAN CROSSING / 5 MPH”.
● *Priority 3 (P-3): Horizon Stage Pavilion & Gathering Space Assembly Construction of terraced Horizon Gathering Space seating utilizing rock retaining walls, gravel backfill, stone steps, and artificial grass terracing. Installation of overhead protective shade sails (pending engineering), stage lighting/sound systems, and sustainable adobe floor integration beneath the pavilion. (The pavilion structure is already built.)
● Priority 4 (P-4): Pervious Pathways & Stormwater Management Infrastructure Construction of pervious, ADA-compliant walking pathways connecting all Phase 3 exhibits. Installation of rain gardens and rainwater/snowmelt catch systems demonstrating localized stormwater management off pavilion roofs and roadways.
● *Priority 5 (P-5): Living Soils Subterranean Zone & Phase 3 Exhibits Integration Full construction and site integration of the subterranean viewing bunker within the Living Soils Lab exhibit (excavation, earth-retention framing, structural viewing walls, utility rough-ins per conceptual plans). Site integration, structural mounting, and utility hookups for Animas Valley Rocks, Nature Art Garden & Studio, and Inspiration Hill play area. (Note: Animas Watershed Flowscape fabrication is contracted owner-direct with Iron Mesa Studios).
PHASE 4 PRIORITIES (Core Living Landscape Infrastructure, Fencing & Guilds)
● Priority 6 (P-6): Custom Perimeter Safety Fencing
Installation of heavy-duty perimeter safety fencing defining Phase 4 boundaries, securing campus access during school hours, and isolating active K–5 play areas.
● Priority 7 (P-7): Farm Market Stand Structure (120 sq ft) Structure construction, electrical conductors run from the main subpanel, electrical stub-up into the building, and interior/exterior electrical finishes.
● Priority 8 (P-8): Interpretive Feature Mounting & Agriculture Timeline Framing Structural post installation and heavy-duty framing for the History of Local Agriculture Timeline along the perimeter fence line. Mounting posts for interpretive signage throughout The Hub, Living Landscape, and self-guided nature yoga circuit installation (approx. 50-60 signs total).
● **Priority 9 (P-9): Landscape Regenerative Agriculture Guilds Soil preparation, irrigation distribution piping, planting beds for permaculture food forest demonstration guilds, and surrounding pathways.
● Priority 10 (P-10): Buffers, Screening & Site Aesthetics Planting shade trees, screening shrubs, and perennials throughout the site. Strategic placement of boulders, gravel, mulch, and wood sponges for physical boundaries, erosion control, and aesthetics.
* Defined GC and owner responsibilities for exhibit/feature installations (priorities 3,5,9):
Exhibit / Feature GC Responsible Scope Owner-Directed / Excluded Scope
Horizon Stage & Amphitheater
Complete excavation, retaining walls, stone steps, gravel backfill, artificial turf terracing, shade sail supports, and adobe floor.
Timber frame pavilion structure is already built.
Audio/visual equipment, stage lighting fixtures, and loose performance furniture.
Inspiration Hill Play Area
Civil grading, safety surfacing/mulch base, boulder placement, and installation of all permanent play feature structures.
Loose play props.
Nature Art Garden & Studio
Utility rough-ins, garden perimeter fencing, garden beds, and installation of small timber shade structures.
Garden soil, plants,outdoor easels, art tables, art supplies, and art supply storage.
Living Soils Lab Civil excavation, subterranean concrete bunker, structural viewing walls and roof assembly, earth-retention framing, and electrical rough-in.
"Soils Petals" and equipment installation, soil media filling, scientific display exhibits, and interactive game elements.
Animas Watershed Flowscape
Supervision of subcontractor Custom stream sculpture fabrication and installation, artistic details and interpretive sign graphics.
History of Local Agriculture Timeline
Installation of structural mounting posts, top/bottom framing rails along the perimeter fence line, and ground prep.
High-resolution graphic design, weatherproof panel printing, painted timeline, and 3-D content fabrication.
Permaculture Food Forest Guilds
Four multi-tiered food forest guilds: site preparation, earthworks for hügelkultur beds, planting, and irrigation.
Protective perimeter fence.
Heritage Fruit Tree Orchard: site prep, tree sourcing and planting, irrigation, and mulching
**Technical specification note: Wildlife and Predator Hardening (Priority 8 & 10) Because the SOIL Lab campus is located in an active urban-wildlife corridor, all livestock structures, feed storage, and agricultural enclosures built under Priority 8 and Priority 10 must meet the following physical hardening specifications:
● Physical Enclosures & Digging Barriers (Mini-Barn & Chicken Run):
○ Hardware Cloth: All coop openings, run walls, and ventilation gaps must be fully enclosed with minimum 1/2-inch, 19-gauge hot-dipped galvanized hardware cloth.
○ Dig-Proof Apron: Install a 24-inch horizontal underground wire apron (or 12-inch vertical burial) of 1/2-inch hardware cloth extending outward around the entire perimeter of the coop and run foundation to prevent predator digging.
● Feed Storage & Secure Access:
○ Dedicated Feed Room: The internal feed storage area within the Mini-Barn must be fully enclosed with solid 3/4-inch exterior-grade plywood or CLT panels, ceiling included, leaving no exposed gaps.
● Bear-Resistant Latching: All exterior doors to the Mini-Barn, coop, and feed storage room must utilize heavy-duty, two-stage commercial mechanical latches (e.g., deadbolts, heavy-duty drop-bars, or spring-loaded carabiner latches) mounted at minimum 48 inches above finished grade.
● Elevated Beehive Mounting Platform: Per Drawing A-101, beehive structures must be structurally anchored to an elevated mounting surface (minimum 8 feet above grade or integrated into the structural roof/wall plane of the Mini-Barn) to prevent direct physical access by larger mammals.
ADDITIVE ALTERNATES
Evaluation & Funding Structure for Additive Alternates (Alternates 1–3):
● Priced Outside Baseline GMP: Additive Alternates represent independent scope items and shall be priced OUTSIDE the baseline $795,000.00 GMP contract ceiling.
● Activation Mechanisms: If realized cost savings, trade discounts, or donated materials/volunteer labor are unlocked during construction (facilitated by the Owner or GC), those savings may be reallocated to fund Additive Alternates. Additionally, uncommitted Owner contingency funds or supplemental capital funds secured outside the baseline DOLA grant may be utilized by the District to authorize these scope items.
● Selection & Award: The District reserves the right to incorporate one or more Additive Alternates into the final contract value at award or via change order during construction as funding mechanisms are activated.
Additive Alternate Priorities
● Additive Alternate 1: Forest Trail Rehabilitation & ADA Upgrades — Erosion control, grading, interpretive sign posts, and ADA surface improvements along 500 linear feet of rim trail.
● Additive Alternate 2: "The Nest" Observation Deck — Cantilevered, ADA-accessible observation deck overlooking the forest hillside and Animas Valley.
● Additive Alternate 3: Neighborhood Forest Access Trail — Durable forest trail establishing winter pedestrian access connecting Riverview School/SOIL Lab to western neighborhood.
● Additive Alternate 4: Mini-Barn (240 sf), Livestock Enclosures, Sanitation Station – Mini-Barn structure construction, livestock enclosures, observation beehives (built into wall), 20-ft water and electrical extensions, conductor runs, electrical finishes, and interior handwashing station / utility sink.
SCOPE EXCLUSIONS (Owner-Direct) General building permit fees (CDFPC), architectural/engineering design services (Interface Architecture), graphic design and sign panel fabrication (Gaia Creative / El Matador), scientific consulting (MSI), Flowscape exhibit fabrication and install (Iron Mesa Studios), specialized exhibit fabrications as outlined in table above (contractors TBD) and moveable loose furnishings and site items (direct purchase) are excluded from the General Contract Scope.
4. PROCUREMENT SCHEDULE & SUBMISSION INSTRUCTIONS
4.1 Procurement Schedule
● RFP Issuance & Contractor Outreach: November 10, 2026
● Mandatory Pre-Bid Site Walk: November 17, 2026 from 2:00 PM – 3:00 PM MT, start at SOIL Community Garden entrance
○ Attendance at the Pre-Bid Site Walk is mandatory for any prime contractor submitting a proposal. Attendance by a designated representative, project manager, estimator, or proxy fulfills this requirement, provided the individual signs in on behalf of the bidding prime contractor firm.
● Deadline for Written Questions: December 2, 2026 at 4:00 PM MT
● Final Addendum Issued: December 7, 2026 at 4:00 PM MT
● Proposal Submission Deadline: December 16, 2026 at 2:00 PM MT
● Selection Committee Scoring & Award: January 7, 2026 at 2:00 PM MT
● Contract Execution: January 14, 2027 at 4:00 PM MT
● Notice to Proceed: January 15, 2027 at 10:00 AM MT
4.2 Standardized Proposal Outline
Proposals must be submitted as a single PDF document in the exact order below:
● Section 1: Cover Letter & Executive Summary
● Section 2: Master Site Management, Safety & Specialty Integration (25 Points)
● Section 3: Fee Structure, Prioritized Scope & Transparency- Attachment C (25 Points)
● Section 4: Community Experience & References (20 Points)
● Section 5: Phasing, Seasonal Sequencing & Schedule (15 Points)
● Section 6: Insurance Compliance / Waiver Request (15 Points)
4.3 Submission of Questions and Proposals
All questions must be submitted in writing via BidNet by 4:00 PM MT, December 2, 2026.
All questions shall then be answered in the form of an addendum, to be issued no later than December 7, 2026.
Proposals are to be submitted via BidNet by 2:00 PM MT, December 16, 2026. Proposals shall be submitted in a single PDF file displaying the firm’s name, the RFP #: 27-GC SOIL and the date.
5. EVALUATION RUBRIC & SCORING MATRIX
Evaluation Criteria Description / Focus Areas Max Points
1. Master Site Management & Safety
Track record in civil site work, utility distribution, active public safety isolation, and traffic management.
Points
2. Fee Structure & Scope Maximization
Total depth of prioritized scope items guaranteed within the $795,000 ceiling, competitiveness of GC fee, and pass-through transparency.
Points
3. Community & Partner Collaboration
Track record of collaborating with local craftspeople, managing volunteer build days, and strong references.
Points
4. Phasing, Sequencing & Logistics
Schedule feasibility for substantial completion by December 31, 2027, and total completion by December 2028 with clear seasonal and winter weather planning.
Points
5. Insurance & Commercial Reliability
Compliance with District Master Insurance requirements (or approved Waiver Request) and prompt subcontractor payment history.
Points
TOTAL EVALUATION
SCORE
Points
Attachment A- Site Plan and Conceptual Drawings- Link to: Preliminary Architectural Plans for DOLA Community Schoolyard Grant
Attachment B- Site Renderings & Feature Descriptions Link to: Master Site Vision document
Attachment C- PRIORITIZED SCOPE & BID PRICING FORM (Mandatory - Submit in Section 3 of Proposal) Link to: Bid Pricing Form- Opens as a fillable spreadsheet. Attach completed form as a PDF in Section 3 of Submission Package.
Attachment D- Durango School District Master Insurance Requirements and Waiver Process Link to: Overview of DSD Insurance Policies
Attachment E- Durango School District Vendor Contract Template Link to: Contract template- For review only. Must be completed & signed, after contract is awarded, by all parties, before work commences.
Attachment F- Durango School District Vendor Contract Template Link to: Contract template- For review only. Must be completed & signed, after contract is awarded, by all parties, before work commences.
https://drive.google.com/file/d/1fCx95FVVDSHoQH5pVPt14a1PcqKm4-K9/view?usp=sharing https://docs.google.com/document/d/11SQzfvS17-bbiCS9gM2CHDAKJKDOzJLy/edit?usp=sharing&ouid=107835780325437520149&rtpof=true&sd=true https://docs.google.com/spreadsheets/d/1MfUjz9YAXedWBfYZdxt0vj0abqe0m9Hd/copy https://docs.google.com/document/d/1tTDW9nbyPNrzv04ZoD2cPrZ3GVxvNQsHP8EAWet8uPg/edit?usp=sharing https://docs.google.com/document/d/1bIGYi16J5afwMmvUgGp-GTVHI1ewxz43/edit?usp=sharing&ouid=107835780325437520149&rtpof=true&sd=true https://docs.google.com/document/d/1bIGYi16J5afwMmvUgGp-GTVHI1ewxz43/edit?usp=sharing&ouid=107835780325437520149&rtpof=true&sd=true
| REQUEST FOR PROPOSALS (RFP) |
| General Contracting Services: SOIL Lab & Community Schoolyard Construction |
| 1. INTRODUCTION & PROJECT PURPOSE |
| 2. CONTRACT STRUCTURE & FINANCIAL TERMS |
| 3. DETAILED PRIORITIZED SCOPE OF WORK |
| PHASE 3 PRIORITIES (Core Bus Circle Infrastructure, Hub & Exhibits) |
| PHASE 4 PRIORITIES (Core Living Landscape Infrastructure, Fencing & Guilds) |
| SCOPE EXCLUSIONS (Owner-Direct) |
| 4.1 Procurement Schedule |
| 4.2 Standardized Proposal Outline |
| 4.3 Submission of Questions and Proposals |