Bid Worksheet.pdf
PDF 71 KB Posted
- Attached to
- 23WHM-SGL 440 Robbs Fording Road project
- Solicitation number
- 6100055213
- Issued by
- Armstrong County, Harveys Lake Borough, Pennsylvania
About this file
This document is a Bid Worksheet for the Robbs Fording Road Project, PGC-440-21-01, issued by the Commonwealth of Pennsylvania Pennsylvania Game Commission. The project involves maintenance work on 0.39 miles of road at Crooked Creek Lake in Burrell Township, Armstrong County. The principal items of work include clearing, earthwork, pipe installation, drainage ditch work, and road base and surface material. The bid is due on March 2, 2022 at 2:00 P.M.
The estimated quantities for the various work items are provided, including the lengths and diameters of corrugated plastic pipes, volumes of bedding and backfill material, and areas of geogrid, geotextile, and seeding. Contractors are required to furnish all necessary materials, labor, and equipment to complete the project in a timely and workmanlike manner.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Drawing 3.pdf | ||
| BOP-2201 EO 2021-06 Worker Protection Form BOP 02072022 FINAL.pdf | ||
| Electronic Bid Notice.pdf | ||
| Drawing 1.pdf | ||
| Specifications.pdf | ||
| Drawing 2.pdf | ||
| Terms_and_Conditions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF PENNSYLVANIA
PENNSYLVANIA GAME COMMISSION
DESCRIPTION: Robbs Fording Road Project
PROJECT NO.: PGC-440-21-01
LOCATION OF WORK: SGL #440, Burrell Township, Armstrong County
DATE DUE: March 2, 2022 TIME: 2:00 P.M.
This project shall be known as PGC-440-21-01
The contractor agrees to furnish, deliver to the site, and use materials, water, tools, equipment, light, power, and to perform all labor, superintendence, and all means of demolition necessary to execute, construct and finish in an expeditious, substantial and workmanlike manner all the work necessary for maintenance of 0.39-miles of road at Crooked Creek Lake in
Burrell Township, Armstrong County. The principal items of work under this contract and estimated quantities are as follows:
1. Contract Bonds – Job
2. Clearing - Job
3. Earthwork – 1,233 Sy
4. Remove Existing Pipes – 6 Each
5. 18-inch Corrugated Plastic Pipe – 20 LF
6. 24-inch Corrugated Plastic Pipe – 160 LF
7. 30-inch Corrugated Plastic Pipe – 60 LF
8. Pipe Bedding and Backfill – 158 CY
9. 18” Precast Concrete Headwalls – 2 Each
10. 24” Precast Concrete Headwalls – 10 Each
11. 30” Precast Concrete Headwalls – 4 Each
12. Drainage Ditch – 129 LF
13. Geogrid – 358 SY
14. Geotextile 358 SY
15. AASHTO #1 Stone – 96 CY
16. Road Base Material – 911 CY
17. #2A Coarse Aggregate – 596 CY
18. Seeding - Job